Glass kiln flue gas treatment system and method

By designing a combination of storage box and scheduling baffle in the glass kiln flue gas treatment system, the problem of flue gas treatment interruption in the fault is solved, and the stable operation of the system and the continuous production of the production are achieved.

CN119492271APending Publication Date: 2025-02-21XINJIANG GUANGYAO GLASS TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411614396.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-13
Publication Date
2025-02-21

AI Technical Summary

Technical Problem

When the existing glass kiln flue gas treatment system fails or the purification capacity decreases, it needs to stop the system urgently to avoid gas leakage that does not meet the standards, resulting in interruption of the processing system or shutdown of production.

Method used

A glass kiln flue gas treatment system is designed, including a storage box, a dispatch baffle, a connection control component and a control component, which can temporarily store flue gas when a fault occurs, provide maintenance time, and avoid minor problems affecting normal processing.

Benefits of technology

By temporarily storing flue gas, the processing system interruption caused by failure is avoided, and a maintenance time window is provided, ensuring the continuity and stability of production.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119492271A_ABST
    Figure CN119492271A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of flue gas treatment, in particular to a glass kiln flue gas treatment system and method.The glass kiln flue gas treatment system comprises a cooling tower, a flue gas treatment module, a guide pipe and an induction mechanism and further comprises a strain assembly; the strain assembly comprises a storage box, a dispatching baffle, a connection control component and a regulation and control component. Connection control components are arranged on the two sides of the storage box, the two sets of connection control components are connected with the cooling tower and the flue gas treatment module through guide pipes correspondingly, then control over guiding-in and guiding-out of flue gas of the storage box is completed, the dispatching baffle is installed in the storage box, and the regulation and control component is installed in the storage box and used for driving the dispatching baffle according to the actual situation. When an emergency occurs or a treatment system cannot operate normally through arranged components, exhausted smoke can be temporarily stored, time is provided for maintenance personnel and workers to conduct treatment, and the situation that small problems affect the whole normal machining process is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of flue gas treatment, and in particular to a glass kiln flue gas treatment system and method. Background Art

[0002] Glass kilns usually use natural gas, petroleum coke powder, heavy oil and other fuels for combustion to generate high temperature to heat the glass furnace. These fuels will produce a large amount of flue gas during the combustion process, which contains a variety of components, such as CO2, H2O, CO and pollutants such as smoke particles, sulfur oxides (SOx) and nitrogen oxides (NOx). These pollutants will seriously deteriorate the air quality and pose a threat to human health when discharged into the atmosphere. Therefore, most of them need to be treated by a flue gas treatment system to effectively reduce the emission of these pollutants, thereby reducing the degree of air pollution and protecting human health. The existing glass kiln flue gas treatment system usually includes multiple links such as pretreatment, core treatment, deep purification, emission and control system. During the treatment, the flue gas is first cooled and preliminarily dusted through the treatment system, and then the harmful substances in the flue gas are removed and converted through the desulfurization device, denitrification device, defluorination device and other treatment devices in the core treatment system. Finally, the treated flue gas is secondary purified through the deep purification system, so that the final discharged gas is cleaner; In the process of treating flue gas, when the purification capacity of the existing glass kiln flue gas treatment system decreases due to damage to internal components of the device or long-term operation of the device, resulting in various indexes of the exhausted gas not meeting the standards, the existing treatment system will mostly use emergency stop and other treatment methods to stop the operation of the entire system, thereby avoiding a large amount of gas that does not meet the standards from leaking. The system can only be used normally after maintenance personnel have repaired and repaired it. When the entire treatment system cannot work normally, the normal operation of the entire processing system will also be affected because the generated gas cannot flow, be purified and discharged normally, resulting in some special situations that can be quickly resolved and situations that can be quickly maintained and handled. The entire normal processing will be affected, resulting in processing interruptions or even short-term shutdowns. Summary of the invention

[0003] The purpose of the present invention is to provide a glass kiln flue gas treatment system and method, which can temporarily store the exhausted flue gas through the provided components when an emergency occurs or the treatment system cannot operate normally, providing time for maintenance personnel and staff to handle it, thereby avoiding small problems from affecting the entire normal processing.

[0004] To achieve the above-mentioned object, the present invention provides a glass kiln flue gas treatment system and method, including a cooling tower, a flue gas treatment module, a conduit and a sensing mechanism, and also includes a strain assembly; The strain assembly includes a storage box, a dispatching baffle, a connection control component and a regulating component; The connection control components are provided on both sides of the storage box, and two groups of the connection control components are respectively connected to the cooling tower and the flue gas treatment module through the conduit, thereby completing the control of the flue gas import and export of the storage box. The scheduling baffle is installed in the storage box, and the regulating component is installed in the storage box, and is used to drive the scheduling baffle according to actual conditions.

[0005] Among them, the connection control component includes a connecting frame, a guide bracket, a control slide and an adjusting component. The two connecting frames are respectively fixedly installed on both sides of the storage box, and the two connecting frames are respectively connected to the cooling tower and the flue gas treatment module through the conduit; the two guide brackets are respectively fixedly installed on the sides of the corresponding two connecting frames; the two control slides are respectively slidably installed on the corresponding two guide brackets and inserted into the corresponding two connecting frames; the two groups of adjusting components are respectively installed on the two guide brackets for driving the control slides.

[0006] Wherein, the regulating component includes a limiting bracket, a base plate, a pressure sensor and a pulling component, the limiting bracket is fixedly mounted on the bottom of the scheduling baffle; the base plate is mounted on the limiting bracket; the pressure sensor is mounted on a side of the scheduling baffle close to the base plate; the pulling component is mounted in the storage box for driving the base plate.

[0007] Wherein, the adjusting component includes a control screw and a control motor, the control screw is threadedly connected to the control slide and rotatably mounted on the guide bracket; the output shaft of the control motor is connected to the control screw, and the control motor is fixedly mounted on one side of the guide bracket.

[0008] Among them, the pulling component includes a sliding bracket, a sliding plate, a driving member, a sliding screw and a sliding motor, the sliding bracket is fixedly installed on the inner bottom wall of the storage box; the sliding plate is slidably installed on the sliding bracket; the two sides of the driving member are rotatably connected with the sliding plate and the bottom plate respectively; the sliding screw is threadedly connected to the sliding bracket and rotatably installed in the storage box; the output shaft of the sliding motor is connected to the sliding screw, and the sliding motor is fixedly installed on one side of the storage box.

[0009] Among them, the strain assembly also includes a side wall scraper ring, a bottom scraper and a rotating component. The side wall scraper ring is fixedly installed on the top of the scheduling baffle; the bottom scraper is rotatably installed on the bottom surface of the scheduling baffle; the rotating component is connected to the scheduling baffle to facilitate driving the bottom scraper.

[0010] Wherein, the rotating component includes a driving gear disc, a driving gear disc and a driving component, the driving gear disc is fixedly installed at the bottom of the bottom scraper; the driving gear disc is meshed with the driving gear disc and is rotatably installed in the scheduling baffle through the driving component; the driving component is connected to the bottom plate for driving the driving gear disc.

[0011] Among them, the driving component includes a cross-slot rotating column, a cross rotating shaft and a driving motor, the cross-slot rotating column is fixedly connected to the driving gear plate and is rotatably installed in the scheduling baffle; the cross rotating shaft cooperates with the cross slot provided on the cross-slot rotating column and is rotatably installed on the base plate; the output shaft of the driving motor is connected to the cross rotating shaft, and the driving motor is fixedly installed at the bottom of the base plate.

[0012] The present invention provides a glass kiln flue gas treatment system and method, wherein the storage box is arranged between the cooling tower and the flue gas treatment module through the connecting control component and the duct, and the scheduling baffle is arranged in the storage box. The user can change the size of the gas storage space on the top of the storage box by driving the scheduling baffle, so that when a problem occurs in one of the functional modules, the flue gas can be stored in the storage box first, and when the problem of the designated functional module is repaired, the flue gas in the storage box can be discharged to avoid the situation where the processing system cannot work normally due to the failure of the functional module. It should be noted that the storage box and the corresponding mechanism can be arranged between any two functional modules to facilitate the buffering between the two functional modules. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0014] Figure 1 It is a schematic diagram of the overall structure of the glass kiln fume treatment system of the present invention.

[0015] Figure 2 The present invention Figure 1 Enlarged view of point A.

[0016] Figure 3 It is a schematic diagram of the structure of a storage box of the present invention when it is cut open.

[0017] Figure 4 It is a schematic structural diagram of the rotating component of the present invention.

[0018] Figure 5 It is a schematic diagram of the installation structure of the cross shaft of the present invention.

[0019] Figure 6 The present invention Figure 5 Enlarged view of point B.

[0020] Figure 7 It is a flow chart of the glass kiln fume treatment method of the present invention.

[0021] In the figure: 1-cooling tower, 2-flue gas treatment module, 3-duct, 4-sensing mechanism, 5-storage box, 6-scheduling baffle, 7-connection control component, 8-regulating component, 9-side wall scraper ring, 10-bottom scraper, 11-rotating component, 71-connecting frame, 72-guide bracket, 73-control slide plate, 74-adjusting component, 81-limiting bracket, 82-bottom plate, 83-pressure sensor, 84-pulling component, 111-driving gear disc, 112-driving gear disc, 113-driving component, 741-control screw, 742-control motor, 841-sliding bracket, 842-sliding plate, 843-driving member, 844-sliding screw, 845-sliding motor, 1131-cross groove rotating column, 1132-cross rotating shaft, 1133-driving motor. DETAILED DESCRIPTION

[0022] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0023] In the description of the present invention, it should be understood that “plurality” means two or more than two, unless otherwise clearly and specifically defined.

[0024] See also Figures 1 to 6The present invention provides a glass kiln flue gas treatment system: comprising a cooling tower 1, a flue gas treatment module 2, a duct 3, a sensing mechanism 4 and a strain assembly, wherein the strain assembly comprises a storage box 5, a scheduling baffle 6, a connection control component 7 and a regulating component 8, wherein the connection control component 7 comprises a connection frame 71, a guide bracket 72, a control slide plate 73 and an adjusting component 74, wherein the regulating component 8 comprises a limiting bracket 81, a bottom plate 82, a pressure sensor 83 and a pulling component 84, wherein the adjusting component 74 comprises a control screw 741 and a control motor 742, wherein the pulling component 84 comprises a sliding bracket 841, a sliding plate 842, a driving member 843, a sliding screw 844 and a sliding motor 845, and the above-mentioned solution solves the existing glass kiln flue gas treatment system In the process of flue gas treatment, when the purification capacity decreases due to damage to internal components of the device or the device works for a long time, so that various indexes of the exhausted gas do not meet the standards, the existing treatment systems will mostly use emergency stop and other treatment methods to stop the operation of the entire system, so as to avoid a large amount of gas that does not meet the standards from leaking. The system can only be used normally after maintenance personnel have repaired and maintained it. When the entire treatment system cannot work normally, the normal operation of the entire processing system will also be affected because the generated gas cannot flow, purify and discharge normally, resulting in some special situations that can be quickly resolved and situations that can be quickly maintained and handled. The normal processing will be affected, resulting in processing interruptions or even short-term shutdowns.

[0025] Furthermore, the connection control components 7 are provided on both sides of the storage box 5, and the two groups of the connection control components 7 are respectively connected to the cooling tower 1 and the flue gas treatment module 2 through the conduit 3, thereby completing the control of the flue gas import and export of the storage box 5, and the scheduling baffle 6 is installed in the storage box 5, and the regulating component 8 is installed in the storage box 5, and is used to drive the scheduling baffle 6 according to actual conditions.

[0026] Specifically, the cooling tower 1 and the flue gas treatment module 2 are connected to the corresponding processing device flue gas exhaust system and the purified flue gas exhaust system through the provided conduit 3. The cooling tower 1 is mainly used to cool the flue gas exhausted by the processing device, and the flue gas treatment module 2 is used to purify the cooled flue gas. The cooling tower 1 and the conduits 3 on both sides of the flue gas treatment module 2 are provided with the sensing mechanism 4. The sensing mechanism 4 is composed of various sensors. The operator can select a designated sensor for detection according to the function of a specific module. For example, the conduits 3 on both sides of the cooling tower 1 can be detected by using a temperature sensor to monitor the actual cooling effect of the cooling tower. Sensors for detecting air quality can be provided on both sides of the flue gas treatment module 2 to monitor the processing quality of the flue gas treatment module 2, so that when a problem occurs, the problem module can be quickly locked by the corresponding sensing mechanism 4. The storage box 5 is arranged between the cooling tower 1 and the flue gas treatment module 2 in cooperation with the conduit 3 through the connection control component 7. The scheduling baffle 6 is arranged in the storage box 5. The user can change the size of the gas storage space on the top of the storage box 5 by driving the scheduling baffle 6, so that when a problem occurs in one of the functional modules, the flue gas can be stored in the storage box 5 first. When the problem of the designated functional module is repaired, the flue gas in the storage box 5 can be discharged to avoid the situation where the processing system cannot work normally due to the failure of the functional module. It should be noted that the storage box 5 and the corresponding mechanism can be arranged between any two functional modules to facilitate the buffering between the two functional modules.

[0027] Furthermore, the two connecting frames 71 are respectively fixedly installed on both sides of the storage box 5, and the two connecting frames 71 are respectively connected to the cooling tower 1 and the flue gas treatment module 2 through the conduit 3; the two guide brackets 72 are respectively fixedly installed on the sides of the corresponding two connecting frames 71; the two control slides 73 are respectively slidably installed on the corresponding two guide brackets 72 and inserted into the corresponding two connecting frames 71; the two groups of adjustment components 74 are respectively installed on the two guide brackets 72, and are used to drive the control slides 73.

[0028] Furthermore, the control screw 741 is threadedly connected to the control slide plate 73 and is rotatably mounted on the guide bracket 72 ; the output shaft of the control motor 742 is connected to the control screw 741 , and the control motor 742 is fixedly mounted on one side of the guide bracket 72 .

[0029] When this embodiment is in use, the storage box 5 is connected to the corresponding module through the connecting frame 71 and the conduit 3 provided on both sides. The connecting frame 71 is provided with the guide bracket 72 and the control slide 73. The control slide 73 slides accordingly by cooperating with the guide bracket 72. The control slide 73 is provided with a threaded hole adapted to the control screw 741. The control screw 741 is fixed to the output shaft of the control motor 742, so that the user can drive the control slide 73 through the control motor 742 in cooperation with the control screw 741, and then adjust the air guide range of the connecting frame 71 by moving the control slide 73.

[0030] Furthermore, the limiting bracket 81 is fixedly mounted at the bottom of the scheduling baffle 6; the bottom plate 82 is mounted on the limiting bracket 81; the pressure sensor 83 is mounted on the side of the scheduling baffle 6 close to the bottom plate 82; the pulling component 84 is installed in the storage box 5 for driving the bottom plate 82.

[0031] Furthermore, the sliding bracket 841 is fixedly installed on the inner bottom wall of the storage box 5; the sliding plate 842 is slidably installed on the sliding bracket 841; the two sides of the driving member 843 are rotatably connected to the sliding plate 842 and the bottom plate 82 respectively; the sliding screw 844 is threadedly connected to the sliding bracket 841 and rotatably installed in the storage box 5; the output shaft of the sliding motor 845 is connected to the sliding screw 844, and the sliding motor 845 is fixedly installed on one side of the storage box 5.

[0032] When the present embodiment is in use, the bottom plate 82 is arranged at the bottom of the dispatching baffle 6 through the limiting bracket 81, and the pressure sensor 83 is arranged between the bottom plate 82 and the dispatching baffle 6. The pressure sensor 83 can monitor the pressure between the bottom plate 82 and the dispatching baffle 6 in real time, and a connecting platform for connecting two driving members 843 is arranged at the bottom of the bottom plate 82. The sliding plate 842 is connected to the bottom plate 82 through the driving member 843, and both sides of the driving member 843 can rotate normally. The sliding plate 842 is driven by the sliding screw 844 and the sliding motor 845, so that when the sliding plate 842 slides under the guidance of the sliding bracket 841, the driving member 843 can drive the bottom plate 82 to move through the movement of the sliding plate 842, thereby changing the gas storage space at the top of the storage box 5; In actual operation, when the sensing mechanism 4 detects that a problem occurs in the corresponding module, the storage box 5 connected to the designated module can drive the control slide plate 73 through the control motor 742 and the control screw 741 on the corresponding side, so as to stop the generated smoke from being transported to the module with the problem. After that, due to the continuous filling of smoke, the pressure sensed by the pressure sensor 83 will gradually increase. At this time, the sliding motor 845 will cooperate with the sliding screw 844 to drive the sliding plate 842, and then drive the bottom plate 82 downward through the driving member 843, so that the pressure between the scheduling baffle 6 and the bottom plate 82 can be maintained within the normal working range, thereby avoiding the situation where the internal air pressure of the storage box 5 continues to increase due to the continuous filling of smoke, and then the smoke backflow occurs; At the same time, when the smoke is charged into the storage box 5, the user can adjust the air intake efficiency of the connecting frame 71 at the end of the storage box 5 charged with smoke according to the actual maintenance time and operation conditions. The specific adjustment means is to drive the control slide plate 73 through the control motor 742 on the connecting frame 71 in cooperation with the control screw 741, and then change the size of the air intake port of the connecting frame 71 through the movement of the control slide plate 73 to adjust the smoke entry efficiency; Secondly, based on the pressure sensing changes of the pressure sensor combined with the moving speed of the sliding plate 842, the descending speed of the scheduling baffle 6 when the smoke is normally introduced into the storage box 5 can be inferred, and then the buffering time inside the storage box 5 can be determined based on the descending speed of the scheduling baffle combined with the maximum descending distance of the scheduling baffle 6, so that the user can deploy and predict the work in more detail and specifically according to the actual buffering time before performing repairs and maintenance.

[0033] Preferably, the strain assembly further includes a side wall scraper ring 9, a bottom scraper 10 and a rotating member 11, wherein the rotating member 11 includes a driving gear disc 111, a driving gear disc 112 and a driving component 113, and the driving component 113 includes a cross groove rotating column 1131, a cross rotating shaft 1132 and a driving motor 1133.

[0034] Specifically, the side wall scraper ring 9 is fixedly mounted on the top of the scheduling baffle 6; the bottom scraper 10 is rotatably mounted on the bottom surface of the scheduling baffle 6; the rotating member 11 is connected to the scheduling baffle 6 to facilitate driving the bottom scraper 10.

[0035] Furthermore, the driving toothed disc 111 is fixedly installed at the bottom of the bottom scraper 10; the driving toothed disc 112 is engaged with the driving toothed disc 111, and is rotatably installed in the scheduling baffle 6 through the driving component 113; the driving component 113 is connected to the bottom plate 82 for driving the driving toothed disc 112.

[0036] Furthermore, the cross groove rotating column 1131 is fixedly connected to the driving gear disc 112 and is rotatably installed in the scheduling baffle 6; the cross rotating shaft 1132 cooperates with the cross groove provided on the cross groove rotating column 1131 and is rotatably installed on the base plate 82; the output shaft of the driving motor 1133 is connected to the cross rotating shaft 1132, and the driving motor 1133 is fixedly installed at the bottom of the base plate 82.

[0037] When the present embodiment is in use, the side wall scraper ring 9 is fixedly mounted on the dispatching baffle 6, the dispatching baffle 6 is disc-shaped, and the gas storage space provided inside the storage box 5 is cylindrical, so that the dispatching baffle 6 can be closely matched with the storage box 5, the side wall scraper ring 9 provided on the top of the dispatching baffle 6 is mainly used to clean the impurities attached to the inner wall of the storage box 5, and the bottom scraper 10 provided on the bottom surface of the dispatching baffle 6 is used to process the impurities on the bottom surface of the dispatching baffle 6; When the storage box 5 temporarily stores the flue gas, since the flue gas stored in the storage box 5 is most likely not subjected to evolution treatment, the smoke dust impurities mixed in the flue gas are easily attached to the side wall of the storage box 5 and the bottom surface of the scheduling baffle 6. Therefore, the side wall scraper ring 9 and the bottom scraper 10 can be used to clean the impurities and dust on the side wall of the storage box 5 and the bottom surface of the scheduling baffle 6 when the normal flue gas conduction is performed after the module maintenance is completed, and then the cleaned impurities can follow the flue gas into the subsequent module for processing; The bottom of the bottom scraper 10 is connected to the dispatching baffle 6 through a cylinder provided thereunder, and the driving toothed disc 111 is fixed on the cylinder below the bottom scraper 10. At the same time, the driving toothed disc 111 is also engaged with the driving toothed disc 112 arranged inside the dispatching baffle 6. The driving toothed disc 112 is driven by the cross groove rotating column 1131, and the cross groove rotating column 1131 is driven by the cross rotating shaft 1132 in cooperation with the driving motor 1133. 2 is driven mainly because there is no direct and stable connection between the scheduling baffle 6 and the bottom plate 82, the bottom plate 82 is arranged below the scheduling baffle 6 through the limiting bracket 81, and there may be a slight relative movement between the bottom plate 82 and the scheduling baffle 6 when the pressure sensor 83 performs pressure sensing. Therefore, the driving by using the cooperation of the cross groove rotating column 1131 and the cross rotating shaft 1132 can avoid the movement between the bottom plate 82 and the scheduling baffle 6 affecting the overall normal driving.

[0038] See also Figure 7 A glass kiln fume treatment system and method are provided, wherein the glass kiln fume treatment system and method are provided, and the following steps are included: S1: The storage box 5 is arranged between the cooling tower 1 and the flue gas treatment module 2 through the connection control member 7 and the conduit 3, and the cooling tower 1 and the flue gas treatment module 2 are monitored in real time through the provided sensing mechanism 4; S2: When the sensing mechanism 4 detects that a problem occurs in the corresponding module, the connection control component 7 that connects the storage box 5 with the corresponding module with the problem can cut off the connection between the storage box 5 and the module with the problem, so that the smoke is temporarily stored in the storage box 5; S3: When the smoke is continuously charged into the storage box 5, the dispatching baffle 6 can be moved in the storage box 5 through the regulating member 8, so as to ensure the stability of the air pressure in the storage space of the storage box 5, so that the smoke can be continuously and stably charged into the storage box 5; S4: When the smoke is collected by the storage box 5, the operator can perform maintenance and repair on the module with the problem. After the maintenance is completed, the smoke temporarily stored in the storage box 5 is introduced into the subsequent module for processing through the corresponding connection control component 7.

[0039] What is disclosed above is only one or more preferred embodiments of the present application, and cannot be used to limit the scope of rights of the present application. Ordinary technicians in this field can understand that all or part of the processes of implementing the above embodiments and equivalent changes made according to the claims of the present application are still within the scope covered by the present application.

Claims

1. A glass kiln flue gas treatment system, comprising a cooling tower, a flue gas treatment module, a duct and a sensing mechanism, characterized in that: Also included are strain components; The strain assembly includes a storage box, a dispatching baffle, a connection control component and a regulating component; The connection control components are provided on both sides of the storage box, and two groups of the connection control components are respectively connected to the cooling tower and the flue gas treatment module through the conduit, thereby completing the control of the flue gas import and export of the storage box. The scheduling baffle is installed in the storage box, and the regulating component is installed in the storage box, and is used to drive the scheduling baffle according to actual conditions.

2. The glass kiln fume treatment system according to claim 1, characterized in that: The connection control component includes a connecting frame, a guide bracket, a control slide and an adjusting component. The two connecting frames are respectively fixedly installed on both sides of the storage box, and the two connecting frames are respectively connected to the cooling tower and the flue gas treatment module through the conduit; the two guide brackets are respectively fixedly installed on the sides of the corresponding two connecting frames; the two control slides are respectively slidably installed on the corresponding two guide brackets and inserted into the corresponding two connecting frames; the two groups of adjusting components are respectively installed on the two guide brackets for driving the control slides.

3. The glass furnace fume treatment system according to claim 1, characterized in that: The regulating component includes a limiting bracket, a base plate, a pressure sensor and a pulling component, wherein the limiting bracket is fixedly mounted on the bottom of the scheduling baffle; the base plate is mounted on the limiting bracket; the pressure sensor is mounted on a side of the scheduling baffle close to the base plate; and the pulling component is mounted in the storage box for driving the base plate.

4. The glass kiln fume treatment system according to claim 2, characterized in that: The adjusting component includes a control screw and a control motor. The control screw is threadedly connected to the control slide and is rotatably mounted on the guide bracket. The output shaft of the control motor is connected to the control screw, and the control motor is fixedly mounted on one side of the guide bracket.

5. The glass kiln fume treatment system according to claim 3, characterized in that: The pulling component includes a sliding bracket, a sliding plate, a driving member, a sliding screw and a sliding motor. The sliding bracket is fixedly mounted on the inner bottom wall of the storage box; the sliding plate is slidably mounted on the sliding bracket; the two sides of the driving member are rotatably connected to the sliding plate and the bottom plate respectively; the sliding screw is threadedly connected to the sliding bracket and rotatably mounted in the storage box; the output shaft of the sliding motor is connected to the sliding screw, and the sliding motor is fixedly mounted on one side of the storage box.

6. The glass furnace fume treatment system according to claim 3, characterized in that: The strain assembly also includes a side wall scraper ring, a bottom scraper and a rotating component. The side wall scraper ring is fixedly installed on the top of the scheduling baffle; the bottom scraper is rotatably installed on the bottom surface of the scheduling baffle; the rotating component is connected to the scheduling baffle to facilitate driving the bottom scraper.

7. The glass furnace fume treatment system according to claim 6, characterized in that: The rotating component includes a driving gear disc, a driving gear disc and a driving component. The driving gear disc is fixedly installed at the bottom of the bottom scraper; the driving gear disc is meshed with the driving gear disc and is rotatably installed in the scheduling baffle through the driving component; the driving component is connected to the bottom plate for driving the driving gear disc.

8. The glass furnace fume treatment system according to claim 7, characterized in that: The driving component includes a cross-slotted rotating column, a cross-rotating shaft and a driving motor. The cross-slotted rotating column is fixedly connected to the driving gear disk and is rotatably installed in the scheduling baffle; the cross-rotating shaft cooperates with the cross-slotted rotating column and is rotatably installed on the base plate; the output shaft of the driving motor is connected to the cross-rotating shaft, and the driving motor is fixedly installed at the bottom of the base plate.

9. A glass kiln fume treatment method, using the glass kiln fume treatment system according to claim 1, characterized in that: The following steps are included: The storage box is arranged between the cooling tower and the flue gas treatment module through a connection control member and a conduit, and the cooling tower and the flue gas treatment module are monitored in real time through a sensing mechanism provided; When the sensing mechanism detects that a problem occurs in the corresponding module, the connection control component that connects the storage box with the corresponding problematic module can cut off the connection between the storage box and the problematic module, so that the smoke is temporarily stored in the storage box; When smoke is continuously charged into the storage box, the dispatching baffle can be moved in the storage box through the regulating member, so as to ensure the stability of the air pressure in the storage space of the storage box, so that smoke can be continuously and stably charged into the storage box; When the smoke is collected by the storage box, the operator can perform maintenance and repair on the module with the problem. After the maintenance is completed, the smoke temporarily stored in the storage box is introduced into the subsequent module for processing through the corresponding connection control component.