Construction method of heavy-weight window based on heat preservation integrated windowsill

By using embedded parts and anchors on the integrated AAC panel insulation window sill, and combining the use of thin insulation mortar and waterproof coating, the problem of insufficient bearing capacity of the window sill is solved, and higher bearing capacity and insulation performance are achieved. At the same time, the risk of leakage is reduced.

CN119507772APending Publication Date: 2025-02-25SHANGHAI BAOYE GRP CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411321481.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2025-02-25

AI Technical Summary

Technical Problem

When installing heavy windows in the prior art, the load bearing capacity of the AAC board insulation integrated window sill is insufficient, which is prone to risk of cracking and leakage of the window sill, resulting in a reduction in user experience.

Method used

The embedded parts and pressure bearing plates are used instead of the traditional window sill top pressure process. The upper pressure is transmitted to the integrated insulation window sill through the anchors and the carrier, which increases the overall bearing capacity of the window sill, and uses thin insulation mortar and acrylic waterproof coating at the window. Reduce cold bridge phenomenon and leakage risks.

Benefits of technology

It effectively improves the bearing capacity of the window sill, avoids problems such as window sinking and wall cracking, and at the same time improves the indoor insulation performance and waterproofing effect, enhancing the user experience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119507772A_ABST
    Figure CN119507772A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a heavy-weight window based on a heat-preservation integrated windowsill. The heavy-weight window comprises an interior facing layer, an AAC plate and anchoring steel bars. According to the construction method of the heavy-weight window based on the heat preservation integrated windowsill, compared with a traditional technology, an embedded part and a bearing plate are adopted to replace a traditional windowsill coping technology, upper pressure is transmitted to the heat preservation integrated windowsill through a bearing part and an anchoring part, the integrality of the windowsill is improved, and the construction efficiency is improved. In addition, the heat preservation performance of the window part is improved in the aspects of energy conservation and heat preservation, cold bridges at the window part are reduced in a thin heat preservation mortar plastering mode, the indoor heat preservation performance is greatly improved, and the heat preservation effect is good. The acrylic acid waterproof coating is adopted for conducting anti-seepage strengthening treatment on the window auxiliary frame, and the hidden danger of seepage of the window part is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of window construction, and in particular to a construction method for a heavy-weight window based on a thermal insulation integrated window sill. Background Art

[0002] At present, the quality of residential projects is constantly upgraded, the indoor lighting effect continues to expand, and the types and weights of windows are also increasing accordingly. At present, thermal insulation integration is also an advanced practice promoted by construction owners. For installing heavy windows on the thermal insulation integrated window sills of the exterior wall AAC boards, the middle part of the structural method of the thermal insulation integrated window sills of the AAC boards is thermal insulation material, which lacks bearing capacity. The bearing capacity of the window sill cannot meet the requirements or the window sill cracks, etc., and there is a risk of leakage, thereby reducing the user experience. The present invention takes effective measures to increase the bearing capacity of the window sill, and at the same time uses the sealing method of the junction of different materials to reduce leakage. Summary of the invention

[0003] The purpose of the present invention is to provide a construction method for heavy-weight windows based on thermal insulation integrated window sills, so as to solve the problem proposed in the above background technology that the current practice is only to add a concrete slab on the AAC thermal insulation integrated window sill, and to improve the bearing capacity of the window sill by the concrete itself. In this case, a cold bridge phenomenon will occur at the position of the concrete slab due to the lack of thermal insulation material, thereby reducing the user experience.

[0004] To achieve the above object, the present invention provides the following technical scheme: a construction method for heavy-weight windows based on thermal insulation integrated window sills, comprising an interior surface layer, an AAC board, anchoring steel bars, a 5 mm thick waterproof mortar leveling, an 8 mm thick steel plate, a silicone weather-resistant sealing board, polyurethane foam filling, dry hard waterproof mortar caulking, 30 thick thermal insulation mortar, 1.5 thick acrylic waterproof coating, 6 thick waterproof mortar leveling, a two-component waterproof sealant, a sandwich insulation layer, and an exterior surface layer; comprising the following steps: Step 1: Install AAC thermal insulation integrated window sill; Step 2: Drill holes and install embedded parts; Step 3: Install the fixed bearing member; Step 4: Install the attached frame; Step 5: Waterproofing and closing of exterior windows; Step 6: Install the main frame glass; Step 7: Glue treatment.

[0005] Preferably, the precise position and size of the windowsill are determined by marking the size and position of the protruding part of the exterior wall, a special adhesive is evenly applied behind the deepened AAC board, the position of the anchor is marked on the insulation board, and holes are drilled to install the anchor to ensure firmness. After installation, the gaps between the boards are filled with a special adhesive and compacted with force.

[0006] Preferably, according to the design requirements and the actual window sill position, the drilling position is accurately marked, the measurement and marking should be precise, and an electric drill is used to drill holes at the marked positions. The hole diameter and depth should be determined according to the size requirements of the embedded reinforcement. The speed and force should be controlled when drilling to prevent the plate from cracking. After drilling, the dust and debris in the hole should be removed to ensure that the hole is dry and clean. Then the embedded reinforcement is inserted into the hole to ensure that there is enough friction between the reinforcement and the hole wall. If necessary, a special adhesive can be used to fix the embedded reinforcement to increase its stability. Slowly pour the prepared cement slurry into the holes around the embedded reinforcement. Be careful not to generate bubbles. The grouting should be uniform to ensure that the slurry can fully fill the holes and surround the embedded reinforcement. After grouting, necessary maintenance is required to ensure the normal curing of the slurry.

[0007] Preferably, carefully check the flatness and strength of the base surface to ensure that there are no loose objects and pollutants, use waterproof mortar to level the base, ensure that the ground is flat and has good waterproof performance, calculate the corresponding steel plate bearing capacity according to the weight of the window, use steel plate bearing parts that meet the bearing capacity requirements, place the pre-prepared steel plate on the leveled base, ensure that the position and direction of the steel plate meet the requirements, and perform welding operations to firmly connect the embedded reinforcement and the steel plate through welding. The weld should be uniform and free of slag inclusions and cracks.

[0008] Preferably, a suitable fixing method is selected according to the wall material. For example, expansion screws may be used on concrete walls, while special plugs and cement nails may be required for brick walls. The auxiliary frame is aligned according to the pre-marked position, and holes are drilled at the marked points with an electric drill. The auxiliary frame is then fixed to the wall with screws or nails to ensure that each fixing point is firm and stable without any looseness. The part where the auxiliary frame contacts the wall is sealed with dry and hard waterproof mortar to seal the secret room. The auxiliary frame and the steel plate bearing member are sealed with waterproof sealant to ensure that the sealing performance of the entire auxiliary frame is good.

[0009] Preferably, before waterproofing construction, the outer window area is leveled with waterproof mortar to make the steel plate bearing part, the attached frame and the base layer solid and flat. During the waterproofing painting process, acrylic waterproof coating is evenly applied with a brush or roller. The coating thickness should be controlled at 1.5 mm to ensure that the coating covers every area that needs waterproofing, including the sides and upper mouth of the window. After the first coat of paint is dry, a second coat is cross-coated, which helps to close tiny pores and enhance the waterproofing effect. For window treatment, a trowel is used to evenly apply the thermal insulation mortar around the window that has been painted with waterproof coating to ensure that the mortar layer is smooth and has no hollows. This layer not only enhances the waterproofing effect, but also has a thermal insulation effect.

[0010] Preferably, place the main frame at the location of the window, use a screwdriver and hammer to fix it to the wall, make sure the main frame is level and vertical, carefully place the glass into the main frame, make sure the glass is fully inserted into the main frame, and then use rubber pads or other materials to fix it in place.

[0011] Preferably, the windows and gaps should be thoroughly cleaned before applying glue to remove dust and impurities to ensure that the sealant can adhere well. Use detergent and rag to clean the windows, and ensure that the gaps are dry and free of water marks. Use a glue gun to evenly apply the sealant to ensure that the glue layer is continuous without breakpoints. When fixing the window frame to the wall, fix the upper frame first and then the frame to improve the sealing effect. After applying the glue, use a scraper to level the sealant to ensure that its surface is smooth and beautiful, without bubbles and protrusions.

[0012] Compared with the prior art, the beneficial effects of the present invention are as follows: compared with the traditional process, the present invention adopts embedded parts and pressure plates to replace the traditional window sill pressing process, and transmits the upper pressure to the thermal insulation integrated window sill in the form of bearing parts and anchoring parts, thereby improving the integrity of the window sill and avoiding problems such as window sinking and wall cracking due to insufficient bearing capacity of the thermal insulation part. In addition, the present invention also increases the thermal insulation performance of the window part in terms of energy saving and thermal insulation, reduces the occurrence of cold bridges in the window part by adopting thin thermal insulation mortar plastering, and greatly increases the indoor thermal insulation performance. The present invention adopts acrylic waterproof coating to strengthen the anti-leakage treatment of the window frame part, thereby reducing the leakage risk of the window part. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the construction model structure of the present invention. DETAILED DESCRIPTION

[0014] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0015] See also Figure 1 The present invention provides a technical solution: a construction method for a heavy-weight window based on an integrated thermal insulation window sill, comprising an interior surface layer 1, an AAC board 2, anchoring steel bars 3, a 5 mm thick waterproof mortar leveling 4, an 8 mm thick steel plate 5, a silicone weatherproof sealing board 6, a polyurethane foam filling 7, a dry hard waterproof mortar caulking 8, a 30 mm thick thermal insulation mortar 9, a 1.5 mm thick acrylic waterproof coating 10, a 6 mm thick waterproof mortar leveling 11, a two-component waterproof sealing paste 12, a sandwich thermal insulation layer 13, and an exterior finishing layer 14; comprising the following steps: Step 1: Install AAC thermal insulation integrated window sill; Step 2: Drill holes and install embedded parts; Step 3: Install the fixed bearing member; Step 4: Install the attached frame; Step 5: Waterproofing and closing of exterior windows; Step 6: Install the main frame glass; Step 7: Gluing Draw lines according to the size and position of the protruding part of the exterior wall, determine the exact position and size of the window sill, evenly apply special adhesive behind the deepened AAC board 2, mark the position of the anchor on the insulation board, and drill holes to install the anchor to ensure firmness. After installation, use special adhesive to fill the gap between the boards and compact them. According to the design requirements and the actual window sill position, accurately mark the drilling position. The measurement and marking should be accurate. Use an electric drill to drill holes at the marked position. The hole diameter and depth should be determined according to the size requirements of the embedded reinforcement. The speed and strength should be controlled when drilling holes to prevent To prevent the plate from cracking, dust and debris in the hole should be removed after drilling, and the hole should be kept dry and clean. Then the embedded reinforcement should be inserted into the hole to ensure that there is enough friction between the reinforcement and the hole wall. If necessary, special adhesives can be used to fix the embedded reinforcement to increase its stability. Slowly pour the prepared cement slurry into the holes around the embedded reinforcement. Be careful not to generate bubbles. The grouting should be uniform to ensure that the slurry can fully fill the holes and surround the embedded reinforcement. After grouting, necessary maintenance should be carried out to ensure the normal solidification of the slurry. Carefully check the flatness and strength of the base surface to ensure that there are no loose objects and pollutants. Use anti- Use water mortar to level the base to ensure that the ground is flat and has good waterproof performance. Calculate the corresponding steel plate bearing capacity according to the weight of the window, use steel plate bearing parts that meet the bearing capacity requirements, and place the pre-prepared steel plate on the leveled base to ensure that the position and direction of the steel plate meet the requirements. Welding operation: firmly connect the embedded reinforcement and the steel plate through welding. The weld should be uniform, without slag inclusions and cracks. Choose a suitable fixing method according to the wall material. For example, expansion screws can be used on concrete walls, and special plugs and cement nails may be required for brick walls. Install the attached frame according to the pre-marked Align the position, use an electric drill to drill holes at the marked points, and then use screws or nails to fix the auxiliary frame to the wall, ensuring that each fixing point is firm and stable without looseness. Use dry hard waterproof mortar to seal the part where the auxiliary frame contacts the wall, seal the secret room, and use waterproof sealant to seal the auxiliary frame and steel plate bearing parts to ensure good sealing performance of the entire auxiliary frame. Before waterproof construction, use waterproof mortar to level the outer window part to make the steel plate bearing parts, auxiliary frame and base layer solid and flat. Use a brush or roller to evenly apply acrylic waterproof paint during waterproof painting. The coating thickness should be controlled at 1.5 thick, make sure the paint covers every area that needs waterproofing, including the sides and upper mouth of the window. After the first coat of paint is dry, apply the second coat crosswise, which helps to close the tiny pores and enhance the waterproofing effect. Window treatment Use a trowel to evenly apply the thermal insulation mortar around the window that has been painted with waterproof paint, and ensure that the mortar layer is smooth and has no hollows. This layer not only enhances the waterproofing effect, but also has a heat preservation effect. Place the main frame at the position of the window and use a screwdriver and hammer to fix it to the wall. Make sure the main frame is horizontal and vertical. Carefully place the glass Put it into the main frame, make sure the glass is fully inserted into the main frame, and then use rubber pads or other materials to fix it in place. Before applying glue, the window and gaps should be thoroughly cleaned to remove dust and impurities to ensure that the sealant can stick well. Use detergent and rags to clean the windows and make sure the gaps are dry and free of water marks. Use a glue gun to evenly apply the sealant to ensure that the glue layer is continuous without breakpoints. When fixing the window frame to the wall, fix the upper frame first and then the frame to improve the sealing effect. After applying the glue, use a scraper to level the sealant to ensure that its surface is smooth and beautiful without bubbles and protrusions. .

[0016] Finally, it should be noted that the above content is only used to illustrate the technical solution of the present invention, rather than to limit the scope of protection of the present invention. Simple modifications or equivalent substitutions of the technical solution of the present invention by ordinary technicians in this field do not deviate from the essence and scope of the technical solution of the present invention.

Claims

1. A construction method for a heavy-weight window based on an integrated thermal insulation window sill, comprising an interior surface layer (1), an AAC board (2), anchoring steel bars (3), a 5 mm thick waterproof mortar leveling layer (4), an 8 mm thick steel plate (5), a silicone weatherproof sealing plate (6), a polyurethane foam filling (7), a dry hard waterproof mortar caulking layer (8), a 30 mm thick thermal insulation mortar (9), a 1.5 mm thick acrylic waterproof coating (10), a 6 mm thick waterproof mortar leveling layer (11), a two-component waterproof sealing paste (12), a sandwich thermal insulation layer (13), and an exterior surface layer (14); characterized in that: The steps include: Step 1: Install AAC thermal insulation integrated window sill; Step 2: Drill holes and install embedded parts; Step 3: Install the fixed bearing member; Step 4: Install the attached frame; Step 5: Waterproofing and closing of exterior windows; Step 6: Install the main frame glass; Step 7: Glue treatment.

2. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 1, characterized in that: Mark the size and position of the protruding part of the exterior wall to determine the exact position and size of the window sill. Apply a special adhesive evenly behind the deepened AAC board (2). Mark the position of the anchor on the insulation board and drill holes to install the anchor to ensure firmness. After installation, fill the gap between the boards with a special adhesive and compact them firmly.

3. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 2, characterized in that: According to the design requirements and the actual window sill position, accurately mark the drilling position. The measurement and marking should be precise. Use an electric drill to drill holes at the marked positions. The hole diameter and depth should be determined according to the size requirements of the embedded reinforcement. The speed and strength should be controlled when drilling to prevent the plate from cracking. After drilling, the dust and debris in the hole should be removed to ensure that the hole is dry and clean. Then insert the embedded reinforcement into the hole to ensure that there is enough friction between the reinforcement and the hole wall. If necessary, use a special adhesive to fix the embedded reinforcement to increase its stability. Slowly pour the prepared cement slurry into the holes around the embedded reinforcement. The grouting should be uniform to ensure that the slurry can fully fill the holes and surround the embedded reinforcement. After grouting, necessary maintenance is required to ensure the normal curing of the slurry.

4. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 3, characterized in that: Carefully check the flatness and strength of the base surface to ensure that there are no loose objects and pollutants. Use waterproof mortar to level the base to ensure that the ground is flat and has good waterproof performance. Calculate the corresponding steel plate bearing capacity based on the weight of the window. Use steel plate bearing parts that meet the bearing capacity requirements. Place the pre-prepared steel plate on the leveled base to ensure that the position and direction of the steel plate meet the requirements. Perform welding operations to firmly connect the embedded reinforcement and the steel plate. The weld should be uniform and free of slag inclusions and cracks.

5. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 4, characterized in that: Choose the appropriate fixing method according to the wall material. For example, expansion screws may be used on concrete walls, while special plugs and cement nails may be needed for brick walls. Align the auxiliary frame according to the pre-marked position, use an electric drill to drill holes at the marked points, and then use screws or nails to fix the auxiliary frame to the wall. Make sure that each fixing point is firm and stable. Use dry and hard waterproof mortar to seal the part where the auxiliary frame contacts the wall to seal the secret room. Use waterproof sealant to seal the auxiliary frame and the steel plate bearing to ensure good sealing performance of the entire auxiliary frame.

6. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 5, characterized in that: Before waterproofing construction, the outer window area is leveled with waterproof mortar to make the steel plate bearing parts, the attached frame and the base layer solid and flat. During the waterproofing painting process, use a brush or roller to evenly apply acrylic waterproof paint. The coating thickness should be controlled at 1.5 mm to ensure that the paint covers every area that needs waterproofing, including the sides and upper mouth of the window. After the first coat of paint is dry, apply the second coat crosswise, which helps to close tiny pores and enhance the waterproofing effect. For window treatment, use a trowel to evenly apply the thermal insulation mortar around the window that has been painted with waterproof paint to ensure that the mortar layer is smooth and has no hollows. This layer not only enhances the waterproofing effect, but also has a thermal insulation effect.

7. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 6, characterized in that: Place the main frame at the location of the window, use a screwdriver and hammer to secure it to the wall, make sure the main frame is level and plumb, put the glass into the main frame, make sure the glass is fully inserted into the main frame, and then use the rubber pads to secure it in place.

8. A construction method for heavy-weight windows based on thermal insulation integrated window sills according to claim 7, characterized in that: Before applying glue, the windows and gaps should be thoroughly cleaned to remove dust and impurities to ensure that the sealant can adhere well. Use detergent and rags to clean the windows, and ensure that the gaps are dry and free of water marks. Use a glue gun to evenly apply the sealant to ensure that the glue layer is continuous without breakpoints. When fixing the window frame to the wall, fix the upper frame first and then the frame to improve the sealing effect. After applying the glue, use a scraper to smooth the sealant.

Citation Information

Patent Citations

  • Construction method for shell nosing of bridge-cutoff aluminum alloy external window

    CN107255007A

  • Ultralow-energy-consumption building enclosure wall for high-rise building and construction method

    CN116971505A

  • Near-zero-energy-consumption building window heat preservation node structure

    CN217420043U

  • Environment-friendly energy-saving lightweight wall window frame on-wall mounting node structure

    CN217735244U

  • Sealing structure for fixed observation window of masonry wall

    CN221346691U