Intelligent weekly progress visual display system and method based on BIM (Building Information Modeling)

By adopting an intelligent BIM-based weekly progress visual display system in engineering projects, the weekly progress data and building information model are automatically linked, which solves the problem that the project cannot manage progress in a refined manner, and achieves efficient progress management and construction period guarantee.

CN119513975APending Publication Date: 2025-02-25CHINA CONSTR SCI & IND CORP LTD

Patent Information

Application Number
CN202411519600.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-29
Publication Date
2025-02-25

AI Technical Summary

Technical Problem

The progress cannot be managed in a refined manner during the construction of the project, which may delay the construction period and cause losses.

Method used

An intelligent weekly progress visual display system based on BIM is adopted, which includes weekly report management module, model management module, model association module, coloring module and display window module. By automatically correlating weekly report progress data and building information model, the construction progress three-dimensional model is dynamically updated in real time.

Benefits of technology

It improves the refinement of the progress management of the project, reduces manual operations, improves work efficiency, and ensures the timely fulfillment of the project construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119513975A_ABST
    Figure CN119513975A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of data processing, and discloses a BIM-based intelligent weekly progress visual display system and method, and the system comprises a weekly report management module which is used for uploading and storing weekly report progress data of a target project; the model management module is used for uploading and storing the building information model of the target project; the model association module is used for associating the weekly report progress data with the building information model; the coloring module is used for setting colors of different components in the building information model according to the construction progress in the weekly report progress data to obtain a construction progress three-dimensional model; and the display window module is used for displaying the building information model and the construction progress three-dimensional model. According to the method, the weekly report progress data and the building information model are automatically associated and dynamically updated in real time, the weekly progress of the target project is visualized, fine management of the project construction progress is assisted, the project management level is improved, predictable management and control correction is achieved, and it is guaranteed that the project construction period is achieved as much as possible.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data processing, and in particular to a BIM-based intelligent weekly progress visualization display system and method. Background Art

[0002] During the construction process of a project, regular supervision meetings are usually held every week to report the progress of the project and the next work arrangements to the owner and the supervisor, and to jointly control and correct the construction progress.

[0003] With the in-depth use of Building Information Modeling (BIM) technology, frontier cities have begun to use BIM models for progress reporting, and based on three-dimensional models and progress plans, 4D progress management has been formed. According to the characteristics of the rapid development of engineering project construction, there is no effective progress control platform that can finely manage the weekly project progress, and cannot intuitively and clearly assist the construction of engineering projects to control and correct deviations, which may affect the project schedule, leading to a vicious cycle, and ultimately delaying the schedule and causing various losses. Summary of the invention

[0004] In view of this, the present invention provides a BIM-based intelligent weekly progress visualization display system and method to solve the problem of being unable to finely manage the progress of engineering projects.

[0005] In a first aspect, the present invention provides a BIM-based intelligent weekly progress visualization display system, the system comprising: a weekly report management module, a model management module, a model association module, a coloring module, and a display window module, wherein: Weekly report management module, used to upload and store weekly progress data of target projects; Model management module, used to upload and store the building information model of the target project; Model association module, used to associate weekly progress data with the building information model; A coloring module is used to set the colors of different components in the building information model according to the construction progress in the weekly progress data to obtain a three-dimensional model of the construction progress; Display window module, used to display building information model and construction progress three-dimensional model.

[0006] The BIM-based intelligent weekly progress visualization display system provided by the present invention automatically associates weekly progress data with the building information model, reduces manual operations of model information matching, improves work efficiency, and dynamically updates in real time. It visualizes the weekly progress of the target project based on the BIM model, assists in the refined management of the construction progress of the engineering project, improves the project management level, and foreseeable control and correction to ensure that the project schedule is fulfilled as scheduled.

[0007] In an optional embodiment, the system further includes: Login module, used to preset users to log in to the BIM-based intelligent weekly progress visualization display system; The information editing module is used to edit and enter the basic information of the target project.

[0008] The BIM-based intelligent weekly progress visualization display system provided by the present invention allows various operations to be performed only after logging into the system, thereby improving the security of user personal data. The basic information of the target project is input by using the information editing module, which facilitates the improvement of the status of each project, avoids confusion, and improves the readability of the project.

[0009] In an optional implementation, the construction progress includes: completed construction, unfinished construction, and planned construction next week. The coloring module includes: a first coloring unit, a second coloring unit, and a third coloring unit, wherein: A first coloring unit, configured to set the completed components in the building information model to a first color according to the construction progress in the weekly progress data; A second coloring unit is used to set the components that are planned to be unfinished in the building information model to a second color according to the construction progress in the weekly progress data; The third coloring unit is used to set the components planned for construction next week in the building information model to a third color according to the construction progress in the weekly progress data.

[0010] The BIM-based intelligent weekly progress visualization display system provided by the present invention colors components with different construction progress with different colors, intuitively reflects the actual progress through three-dimensional visualization, improves the recognition of components with different progress in the three-dimensional model, and facilitates the overall grasp of the progress of the target project.

[0011] In an optional implementation, the display window module is also used to display an edit menu, which includes: a screening unit, a transparency setting unit, a copy unit, a storage unit, and a sharing unit, wherein: A screening unit, for checking the floors and / or specialties of a target project, so that the display window module displays the checked components in the three-dimensional model of the construction progress; A transparency setting unit, used to set the transparency of the building information model and the construction progress three-dimensional model; A copy unit, used for copying the three-dimensional model of the construction progress of the target project to obtain a copy of the three-dimensional model of the construction progress of the target project; A storage unit, used for asynchronously storing a construction progress three-dimensional model of a target project and a copy of the construction progress three-dimensional model; Sharing unit, used to generate and share a link to the 3D model of the construction progress.

[0012] The BIM-based intelligent weekly progress visualization display system provided by the present invention sets an editing menu in the display window to facilitate routine processing of the target project, more flexibly processes the three-dimensional model of the construction progress of the target project, and improves the efficiency of project management.

[0013] In a second aspect, the present invention provides a BIM-based intelligent weekly progress visualization display method, which is applied to the BIM-based intelligent weekly progress management and control system of any one of the first aspects, and the method includes: Obtain weekly progress data and building information models of the target project, and associate the weekly progress data with the building information model; According to the construction progress in the weekly progress data, each component in the building information model is colored to obtain a three-dimensional model of the construction progress and display it.

[0014] The intelligent weekly progress visualization display method based on BIM provided by the present invention automatically associates weekly progress data with the building information model, reduces manual operations of model information matching, improves work efficiency, and dynamically updates in real time. It visualizes the weekly progress of the target project based on the BIM model, assists in the refined management of the construction progress of the engineering project, improves the project management level, and foreseeable control and correction to ensure that the project schedule is fulfilled as scheduled.

[0015] In an optional embodiment, the method further includes: Generate and share a link to a 3D model of your construction progress.

[0016] The BIM-based intelligent weekly progress visualization display method provided by the present invention can generate a link and share the three-dimensional model of the construction progress of the target project, which is convenient for multiple people to work together. At the same time, the overall weekly progress implementation of the target project can be intuitively viewed, assisting in the formulation of new plans and management and correction.

[0017] In an optional implementation, associating the weekly progress data with the building information model includes: Correspond and associate the construction content in the weekly progress data with the components in the building information model.

[0018] The intelligent weekly progress visualization display method based on BIM provided by the present invention visualizes the weekly progress by correspondingly associating the construction content in the weekly progress data with the components in the building information model. At the same time, the construction content in the weekly progress is marked with a three-dimensional model, which can be rotated and viewed from all angles to intuitively understand the weekly progress implementation of the target project, thereby improving the refined management of the engineering project.

[0019] In an optional implementation, the construction progress includes: completed construction, planned unfinished construction, and planned construction next week. According to the construction progress in the weekly progress data, each component in the building information model is colored to obtain a three-dimensional model of the construction progress, including: According to the first construction content that has been completed in the weekly progress data, the components corresponding to the first construction content in the building information model are set to the first color; According to the unfinished second construction content in the weekly progress data, the components corresponding to the second construction content in the building information model are set to the second color; According to the third construction content planned to be constructed next week in the weekly progress data, the components corresponding to the third construction content in the building information model are set to the third color.

[0020] The BIM-based intelligent weekly progress visualization display method provided by the present invention colors the construction contents of different progress with different colors to form a three-dimensional model of the construction progress with sharp contrast, intuitively reflects the actual weekly progress, improves the recognition of components with different progress in the three-dimensional model, and facilitates the overall grasp of the progress of the target project.

[0021] In a third aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the method of the first aspect or any corresponding embodiment thereof by executing the computer instructions.

[0022] In a fourth aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to cause a computer to execute the method of the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 is a structural schematic diagram of a BIM-based intelligent weekly progress visualization display system according to an embodiment of the present invention; Figure 2 is a colored schematic diagram of a three-dimensional model of a construction progress in a specific embodiment of a BIM-based intelligent weekly progress visualization display system according to an embodiment of the present invention; Figure 3is a structural schematic diagram of another BIM-based intelligent weekly progress visualization display system according to an embodiment of the present invention; Figure 4 is a schematic diagram of a display window of a BIM-based intelligent weekly progress visualization display system according to an embodiment of the present invention; Figure 5 is a schematic diagram of a screening unit in a BIM-based intelligent weekly progress visualization display system according to an embodiment of the present invention; Figure 6 is a flow chart of a BIM-based intelligent weekly progress visualization display method according to an embodiment of the present invention; Figure 7 is a flowchart of another BIM-based intelligent weekly progress visualization display method according to an embodiment of the present invention; Figure 8 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0026] The embodiment of the present invention provides a BIM-based intelligent weekly progress visualization display system and method, which visualizes the weekly progress by associating weekly progress data with a building information model, so as to achieve the effect of refined management of project progress.

[0027] According to an embodiment of the present invention, a BIM-based intelligent weekly progress visualization display system is provided. Figure 1 As shown, the system includes: a weekly report management module 1, a model management module 2, a model association module 3, a coloring module 4, and a display window module 5.

[0028] Weekly report management module 1 is used to upload and store weekly progress data of the target project.

[0029] Specifically, the weekly progress data includes the work content of this week, the completion time corresponding to the work content, the completion status and the construction plan for next week. The professional engineers at the construction site of the project need to fill in and summarize the weekly progress data of each profession according to the actual completion status of the construction site and the planning and deployment for next week, and then upload it to the weekly management module 1 of the BIM-based intelligent weekly progress visualization display system by a dedicated person and store it in a folder. The format of the weekly progress data can be word, pdf, excel and other formats. Each weekly report is stored separately, and the weekly report name and upload time are recorded.

[0030] The model management module 2 is used to upload and store the building information model of the target project.

[0031] Specifically, the building information model created according to the engineering construction drawings is uploaded to the corresponding folder. The format of the building information model can be rvt, nwd, or ifc. After the uploaded building information model is uploaded, click the model file name to jump to the display window of the 3D model.

[0032] Create a building information model with an accuracy of L0D350 for each entity and discipline (architecture, structure, electromechanical, etc.) of the construction project, and upload it to the model management module 2. By selecting all the building information model components, adjust the transparency of the initial state of the model to a semi-transparent state, so that there will be no situation where components block each other, making it easier to fully view the 3D model of the entire project.

[0033] The model association module 3 is used to associate the weekly progress data with the building information model.

[0034] Specifically, the model association module 3 can associate and bind a single component (beam, plate, column, door, window, etc.) in the building information model with any work content in the weekly report, so as to update the display of each component in the building information model according to the progress of the work content in the weekly report.

[0035] The coloring module 4 is used to set the colors of different components in the building information model according to the construction progress in the weekly progress data to obtain a three-dimensional model of the construction progress.

[0036] Specifically, the coloring module 4 sets different construction progress in the weekly progress data to different colors in the building information model for display. The color setting can be increased or decreased or adjusted according to the needs, for example: Figure 2As shown in the figure, in the three-dimensional model of the construction progress of a target project, green indicates that the construction has been completed, red indicates that the plan is not completed, and blue indicates that the construction is planned for next week. This is only an example, but not limited to this. The color of each component in the building information model can be colored separately. After the components in the building information model are associated and bound with the weekly progress data, the completion status of the components corresponding to the work content in the weekly report is automatically identified and the corresponding color is automatically assigned. According to the construction progress corresponding to the work content in the weekly progress data, the corresponding components are colored to show the completion status of different components this week.

[0037] The display window module 5 is used to display the building information model and the construction progress three-dimensional model.

[0038] Specifically, the display window module 5 displays the original building information model of the project in the initial state of the project. After the building information model is associated with the weekly progress data, each component is colored to display the three-dimensional model of the construction progress. The building information model and the three-dimensional model of the construction progress are the same except that the colors of each component are different.

[0039] The BIM-based intelligent weekly progress visualization display system provided in this embodiment automatically associates weekly progress data with the building information model, reduces manual operations in model information matching, improves work efficiency, and dynamically updates in real time. It visualizes the weekly progress of the target project based on the BIM model, assists in the refined management of the construction progress of the project, improves the project management level, and ensures that the project schedule is fulfilled as scheduled by predictably controlling and correcting deviations.

[0040] In some optional embodiments, such as Figure 3 As shown, the system also includes: The login module 6 is used to preset a user to log in to the BIM-based intelligent weekly progress visualization display system.

[0041] Specifically, the preset user can be an administrator with viewing and editing permissions. Each user has an account and password to log in. This technology is a mature existing technology and will not be described here. The preset user can log in on different electronic devices (computers) or mobile electronic devices (mobile phones, tablets, etc.).

[0042] The information editing module 7 is used to edit and input the basic information of the target project.

[0043] Specifically, the information editing module 7 can edit and enter basic information such as the project overview according to the actual situation of the target project, such as the start time and planned completion time of the target project, so as to remind users to pay attention to the construction progress in real time and avoid delays. This is only an example, but not limited to this.

[0044] The BIM-based intelligent weekly progress visualization display system provided in this embodiment allows various operations to be performed only after logging into the system, thereby improving the security of user personal data. The basic information of the target project is entered using the information editing module 7, which facilitates the improvement of the status of each project, avoids confusion, and improves the readability of the project.

[0045] In an optional implementation, the construction progress includes: completed, unfinished, and planned for next week. Figure 3 As shown, the coloring module 4 includes: a first coloring unit 41 , a second coloring unit 42 , and a third coloring unit 43 .

[0046] The first coloring unit 41 is used to set the completed components in the building information model to a first color according to the construction progress in the weekly progress data.

[0047] The second coloring unit 42 is used to set the planned unfinished components in the building information model to a second color according to the construction progress in the weekly progress data.

[0048] The third coloring unit 43 is used to set the components planned to be constructed next week in the building information model to a third color according to the construction progress in the weekly progress data.

[0049] Specifically, the weekly progress data includes each work content and the corresponding construction progress. The components corresponding to the work content with completed construction progress are colored with a first color, which may be green; the components corresponding to the work content with unfinished construction progress are colored with a second color, which may be red; the components corresponding to the work content planned for construction next week are colored with a third color, which may be blue.

[0050] The BIM-based intelligent weekly progress visualization display system provided in this embodiment colors components with different construction progress with different colors, intuitively reflects the actual progress through three-dimensional visualization, improves the recognition of components with different progress in the three-dimensional model, and facilitates the overall grasp of the progress of the target project.

[0051] In some optional embodiments, such as Figure 4 As shown, the display window module 5 is also used to display an editing menu, which includes: a filtering unit, a transparency setting unit, a copying unit, a storage unit, and a sharing unit.

[0052] The screening unit is used to select according to the floors and / or specialties of the target project, so that the display window module 5 displays the selected components in the three-dimensional model of the construction progress.

[0053] like Figure 5As shown, the filter unit on the left selects the door on the RF floor and the air duct on the 1F floor of the plant, and the door on the RF floor of the first building and the air duct on the 1F floor of the plant are displayed in the display window. The filter unit can filter by floor (F8, F9, F10, etc.) by checking the box in front of the floor or profession. For each, it can be filtered again by profession (mechanical and electrical, HVAC, water supply and drainage, building structure, electrical). You can also select a single type of component, such as windows, for example, but not limited to this. The components selected by the filter unit are displayed in the display window, and those not selected are not displayed, which is convenient for refined management.

[0054] The transparency setting unit is used to set the transparency of the building information model and the construction progress three-dimensional model.

[0055] Specifically, after being screened by the screening unit, the display window displays the selected model components, and the transparency setting unit can set the transparency of the selected model components by dragging, etc., and the transparency range is 0-100. For a new target project, after being imported into the model management module 2, the transparency of its building information model is 50, that is, semi-transparent, ensuring that the model structure can be viewed without blocking each other between components.

[0056] The copy unit is used to copy the three-dimensional model of the construction progress of the target project to obtain a copy of the three-dimensional model of the construction progress of the target project.

[0057] Specifically, by clicking the Copy button in the Edit menu to call the Copy unit, the 3D model view in the current display window can be copied 1:1. This makes it easier to color the relevant components of the 3D construction progress model based on the construction progress of the previous week and this week's weekly progress data, making data processing faster and simpler.

[0058] The storage unit is used to asynchronously store the construction progress three-dimensional model of the target project and the copy of the construction progress three-dimensional model.

[0059] Specifically, the storage unit can save the 1:1 copied construction progress 3D model display window as an asynchronous construction progress 3D model display window, and perform independent data-model association. For example, when performing this week's weekly progress visualization, the 3D model of the construction progress of the previous week can be copied to obtain a copy of the construction progress 3D model, and the weekly progress data of this week can be associated with the copy of the construction progress 3D model to form this week's construction progress 3D model. Since the data-model association is performed on the copy of the construction progress 3D model, the 3D model of the construction progress of the previous week is not affected. A weekly progress visualization model view can be saved every week to facilitate subsequent review and summary.

[0060] Sharing unit, used to generate and share a link to the 3D model of the construction progress.

[0061] Specifically, the sharing unit is called by clicking the share button in the edit menu. The sharing unit generates an access link for the three-dimensional model of the construction progress in the current display window and sends it to the corresponding personnel. Other personnel can click the access link on other devices to quickly browse the three-dimensional model of the construction progress associated with the weekly progress data directly on the web page without logging in.

[0062] The BIM-based intelligent weekly progress visualization display system provided in this embodiment sets an editing menu in the display window to facilitate routine processing of the target project, more flexibly process the three-dimensional model of the construction progress of the target project, and improve project management efficiency.

[0063] According to an embodiment of the present invention, an embodiment of a BIM-based intelligent weekly progress visualization display method is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0064] In this embodiment, a BIM-based intelligent weekly progress visualization display method is provided, which can be used in the above-mentioned computer system or the BIM-based intelligent weekly progress visualization display system. Figure 6 is a flow chart of a BIM-based intelligent weekly progress visualization display method according to an embodiment of the present invention. Figure 6 As shown, the process includes the following steps: Step S101, obtaining weekly progress data and a building information model of a target project, and associating the weekly progress data with the building information model.

[0065] Specifically, the weekly progress data of the target project can be obtained through the weekly report management module 1, and the building information model of the target project can be obtained through the model management module 2. The work content in the weekly progress data is associated with the components in the building information model. The association method can be implemented by floor and / or specialty, or component name, which is only taken as an example, but not limited to this.

[0066] Step S102, according to the construction progress in the weekly progress data, each component in the building information model is colored to obtain a three-dimensional model of the construction progress and display it.

[0067] Specifically, according to the construction progress of the work content in the weekly progress data, the components corresponding to the work content in the building information model are colored to obtain and display the three-dimensional model of the construction progress.

[0068] For example, the progress of the construction site this week is that the construction of the basement area A floor has been completed, and the construction of the area B floor is planned to be completed but not actually completed. Next week, the construction of the basement area C floor is planned to be completed, and the unfinished area B floor will be completed together. According to the on-site situation this week, the weekly progress data collected this week is shown in Table 1 and Table 2.

[0069] Table 1

[0070] Table 2

[0071] Upload the above-mentioned tables 1 and 2 of the statistical weekly progress data to the weekly management module 1 of the intelligent weekly progress visualization display system, and set the display color of the three-dimensional model of the construction progress through the coloring module 4, setting a green name for completed construction, a red name for planned unfinished construction, and a blue name for planned construction next week. By associating the weekly progress data with the three-dimensional model of the construction progress, the components corresponding to the three-dimensional model of the construction progress are colored according to the color settings and the weekly progress data.

[0072] Copy last week's 3D model of construction progress to obtain a copy of last week's 3D model of construction progress, and upload the copy to the BIM-based intelligent weekly progress visualization display system. Click the file name of the 3D model of construction progress to jump to the display window to display last week's 3D model of construction progress.

[0073] Select the model component of the basement A area floor, right-click, and select "Model Association" in the pop-up task bar. The folder window of the weekly report management module 1 will pop up. Select this week's weekly report in the folder to open it. There will be a small box in front of the serial number corresponding to each work task in the weekly report for checking. Just check the work content corresponding to the model component (basement A area floor), and associate and bind this week's weekly report progress data with the three-dimensional model. After the three-dimensional model is associated with the weekly progress data, the color of the model component will automatically change to the corresponding green, red, and blue according to the color set by the coloring module 4. It should be noted that the basement B area floor should be represented by the color of the plan that is not completed. During the progress management process, the reasons for the delay of the work content that is identified as unfinished in the plan are analyzed: weather reasons, or insufficient materials, work surfaces, and operators, etc., and corresponding measures are taken next week: purchasing materials, increasing operators, increasing equipment, etc. to continue to complete, so as to achieve the control and correction of progress management. This is only an example, but it is not limited to this. In addition to manual association, automatic association can also be set to associate the work content in the weekly progress data with the components in the three-dimensional model according to the floor, profession, and component name. This is only used as an example, but is not limited to this.

[0074] The intelligent weekly progress visualization display method based on BIM provided in this embodiment automatically associates weekly progress data with the building information model, reduces manual operations of model information matching, improves work efficiency, and updates in real time. It visualizes the weekly progress of the target project based on the BIM model, assists in the refined management of the construction progress of the project, improves the project management level, and ensures that the project schedule is fulfilled as scheduled by foreseeable control and correction.

[0075] In an optional embodiment, the method further includes: Generate and share a link to a 3D model of your construction progress.

[0076] Specifically, a link to the three-dimensional model of the construction progress can be generated and shared through various communication software. People who receive the link can directly open and view it through the link without logging in.

[0077] The BIM-based intelligent weekly progress visualization display method provided by the present invention can generate a link and share the three-dimensional model of the construction progress of the target project, which is convenient for multiple people to work together. At the same time, the overall weekly progress implementation of the target project can be intuitively viewed, assisting in the formulation of new plans and management and correction.

[0078] In this embodiment, a BIM-based intelligent weekly progress visualization display method is provided, which can be used in the above-mentioned computer system or the BIM-based intelligent weekly progress visualization display system. Figure 7 is a flowchart of a computer system or a BIM-based intelligent weekly progress visualization display system method according to an embodiment of the present invention, such as Figure 7 As shown, the process includes the following steps: Step S201, obtaining weekly progress data and a building information model of a target project, and associating the weekly progress data with the building information model.

[0079] Specifically, the above step S201 includes: Correspond and associate the construction content in the weekly progress data with the components in the building information model.

[0080] Specifically, you can associate the work content in the weekly progress data with the components in the 3D model according to the floor, specialty, and component name. Manually select the model components corresponding to the weekly work content in batches, click the "Associate" button in the edit menu (in Figure 4), select "File Association" in the pop-up task bar, and a file management window will pop up. You can select the corresponding weekly report file in the folder to open it. There will be a small box in front of the serial number corresponding to each work task in the weekly report, and you can check it. Check the work content corresponding to the model component, and you can associate the weekly report with the model component. After the model component is associated with the weekly report, the model component will automatically be assigned the corresponding color based on the color set by the coloring module and the completion of the work content in the weekly report.

[0081] The intelligent weekly progress visualization display method based on BIM provided in this embodiment visualizes the weekly progress by correspondingly associating the construction content in the weekly progress data with the components in the building information model. At the same time, the construction content in the weekly progress is marked with a three-dimensional model, which can be rotated and viewed from all angles to intuitively understand the weekly progress implementation status of the target project, thereby improving the refined management of the project.

[0082] Step S202: coloring each component in the building information model according to the construction progress in the weekly progress data, obtaining a three-dimensional model of the construction progress and displaying it.

[0083] Specifically, the construction progress includes: completed, planned to be completed, and planned to be constructed next week. The above step S202 includes: Step S2021: according to the first construction content that has been completed in the weekly progress data, the components corresponding to the first construction content in the building information model are set to a first color.

[0084] Step S2022: according to the unfinished second construction content in the weekly progress data, the components corresponding to the second construction content in the building information model are set to a second color.

[0085] Step S2023: according to the third construction content planned to be constructed next week in the weekly progress data, the components corresponding to the third construction content in the building information model are set to a third color.

[0086] Specifically, the weekly progress data includes each work content and the corresponding construction progress. The components corresponding to the work content with completed construction progress are colored with a first color, which may be green; the components corresponding to the work content with unfinished construction progress are colored with a second color, which may be red; the components corresponding to the work content planned for construction next week are colored with a third color, which may be blue.

[0087] The BIM-based intelligent weekly progress visualization display method provided in this embodiment colors the construction contents of different progress with different colors to form a three-dimensional model of the construction progress with sharp contrast, intuitively reflects the actual weekly progress, improves the recognition of components with different progress in the three-dimensional model, and facilitates the overall grasp of the progress of the target project.

[0088] The embodiment of the present invention also provides a computer device having the above Figure 1 The BIM-based intelligent weekly progress visualization display system shown.

[0089] See also Figure 8 , Figure 8 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 8 As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 8 A processor 10 is taken as an example.

[0090] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.

[0091] The memory 20 stores instructions executable by at least one processor 10, so that the at least one processor 10 executes the method shown in the above embodiment.

[0092] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the computer device, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0093] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.

[0094] The computer device further comprises a communication interface 30 for the computer device to communicate with other devices or a communication network.

[0095] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.

[0096] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A BIM-based intelligent weekly progress visualization display system, characterized in that: The system includes: a weekly report management module, a model management module, a model association module, a coloring module, and a display window module, wherein: Weekly report management module, used to upload and store weekly progress data of target projects; Model management module, used to upload and store the building information model of the target project; A model association module, used to associate the weekly progress data with a building information model; A coloring module is used to set the colors of different components in the building information model according to the construction progress in the weekly progress data to obtain a three-dimensional model of the construction progress; The display window module is used to display the building information model and the construction progress three-dimensional model.

2. The system according to claim 1, characterized in that The system further comprises: A login module, used for presetting a user to log in to the BIM-based intelligent weekly progress visualization display system; The information editing module is used to edit and enter the basic information of the target project.

3. The system according to claim 1, characterized in that The construction progress includes: completed, unfinished, and planned construction next week. The coloring module includes: a first coloring unit, a second coloring unit, and a third coloring unit, wherein: A first coloring unit, configured to set the completed components in the building information model to a first color according to the construction progress in the weekly progress data; A second coloring unit is used to set the components that are planned to be unfinished in the building information model to a second color according to the construction progress in the weekly progress data; The third coloring unit is used to set the components planned for construction next week in the building information model to a third color according to the construction progress in the weekly progress data.

4. The system according to claim 1, characterized in that The display window module is also used to display an editing menu, which includes: a screening unit, a transparency setting unit, a copy unit, a storage unit, and a sharing unit, wherein: A screening unit, used to select according to the floors and / or specialties of the target project, so that the display window module displays the selected components in the three-dimensional model of the construction progress; A transparency setting unit, used to set the transparency of the building information model and the construction progress three-dimensional model; A copying unit, used to copy the three-dimensional model of the construction progress of the target project to obtain a copy of the three-dimensional model of the construction progress of the target project; A storage unit, used for asynchronously storing the construction progress three-dimensional model of the target project and a copy of the construction progress three-dimensional model; The sharing unit is used to generate and share a link to the three-dimensional model of the construction progress.

5. A BIM-based intelligent weekly progress visualization display method, characterized in that: The method is applied to the BIM-based intelligent weekly progress control system according to any one of claims 1 to 4, and the method comprises: Obtaining weekly progress data and a building information model of a target project, and associating the weekly progress data with the building information model; According to the construction progress in the weekly progress data, each component in the building information model is colored to obtain a three-dimensional model of the construction progress and display it.

6. The method according to claim 5, characterized in that The method further comprises: Generate and share a link to the 3D model of the construction progress.

7. The method according to claim 5, characterized in that Associating the weekly progress data with the building information model, including: The construction contents in the weekly progress data are correspondingly associated with the components in the building information model.

8. The method according to claim 7, characterized in that The construction progress includes: completed construction, unfinished construction, and planned construction next week. According to the construction progress in the weekly progress data, each component in the building information model is colored to obtain a three-dimensional model of the construction progress, including: According to the first construction content that has been completed in the weekly progress data, the components corresponding to the first construction content in the building information model are set to the first color; According to the unfinished second construction content in the weekly progress data, the components corresponding to the second construction content in the building information model are set to the second color; According to the third construction content planned to be constructed next week in the weekly progress data, the components corresponding to the third construction content in the building information model are set to the third color.

9. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the method according to any one of claims 5 to 8 by executing the computer instructions.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the method according to any one of claims 5 to 8.

Citation Information

Patent Citations

  • Visual weekly report management system and method for engineering project

    CN116228469A

  • Engineering BIM progress model comparison method, system, equipment and medium

    CN117910103A

Cited By

  • Method and device for realizing folder skipping

    CN114968929A

  • Construction progress visualization method and system

    CN120912378A