Steel carrying pole for high-altitude hoisting and mounting
By designing a steel shoulder pole for high-altitude lifting installation and using I-steel and channel steel auxiliary pole reinforcement, the problems of easy bending and large installation deviation of the spreader in the existing technology are solved, and efficient and safe multi-span continuous beam hoisting is achieved, reducing construction costs and improving construction efficiency.
Patent Information
- Application Number
- CN202411559262.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-04
- Publication Date
- 2025-03-04
AI Technical Summary
When lifting multi-span continuous beams at high altitudes, the spreader is easy to bend, has large installation deviations, and has a large safety hazard. It is impossible to effectively lift the multi-span continuous beams.
A steel shoulder pole for high-altitude lifting installation is designed, using a long I-shaped steel main strut pole and a long channel auxiliary strut pole. It is alternately welded and connected by multiple angle steel oblique braces to form a reinforced support system, and is equipped with a lifting ring, a steel ring, a lifting belt and a cable wind rope, which improves the stability and bearing capacity of the spreader.
This steel shoulder pole reduces operational complexity and safety risks in high altitude construction, improves the stability and efficiency of lifting, and can directly lift the combined multi-span continuous beams, reduces construction costs, and improves construction progress and quality.
Smart Images

Figure CN119551539A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of hoisting in the construction industry, and in particular to a steel shoulder pole for high-altitude hoisting and installation. Background Art
[0002] According to the process design requirements, most of the industrial plants in the building industry adopt the portal frame structure of multi-span continuous beams. The conventional installation method is: use at least two cranes to use a single I-beam (with large cross-sectional inertia moment) as a lifting steel pole, and each hoist a single-span beam. After aligning it in place at high altitude, the beams and beams and columns are bolted together with high-strength bolts. At present, at least two cranes are used to use a single I-beam as a lifting device to hoist a single-span beam. After aligning it in place at high altitude, the beams and beams and columns are bolted together. This method requires the cooperation of multiple cranes, and it is difficult to align it in place at high altitude. The installation deviation is large and needs to be adjusted repeatedly. Due to the insufficient load capacity of the single I-beam lifting device of the adapted specifications, it is easy to bend and become unstable, and it is impossible to realize the lifting of multi-span continuous beams (increasing the cross-sectional specifications is not economical). The quality of the superimposed combination welding is difficult to guarantee and is not economical. The personnel need to operate a wide range of procedures at high altitude, which takes a long time and has high safety risks, affecting the smooth progress of the installation and construction progress, quality and safety goals.
[0003] In order to solve the problem of single I-beam hangers being easy to bend, Chinese patent CN203359759U proposes a double-row shoulder pole beam hanger, which includes two H-shaped steels and two lifting lug plates. The two H-shaped steels are used to stabilize the overall hanger, and the two H-shaped steels are fixedly connected by the two lifting lug plates. Chinese patent CN118723779A also proposes a structural combined crane beam, which is composed of two crane beams and a space truss between them to form an overall spatial structure, so that the two crane beams are jointly stressed and jointly resist external loads. However, in the double-row setting, the parts that are not fixed by the lifting lug plates are still weakly stressed, and the overall stability is not the same, and there is still a certain safety risk. Summary of the invention
[0004] In order to solve the problems of the prior art, the present invention proposes a steel shoulder pole for high-altitude lifting and installation that reduces high-altitude operations and is safe and stable. The specific technical solution is as follows:
[0005] A steel shoulder pole for high-altitude lifting and installation, comprising: a full-length I-beam main support rod, two identical full-length channel steel auxiliary support rods, a plurality of angle steel diagonal support rods, a lifting ring, a steel bar ring, a lifting belt and a guy rope, the two full-length channel steel auxiliary support rods are symmetrically located on both sides of the full-length I-beam main support rod, and their centers are located in the same horizontal plane as the center of the full-length I-beam main support rod; the intersections of the upper flange and the lower flange of the full-length I-beam main support rod with the web plate are respectively connected to the lower flange and the intersections of the upper flange and the web plate of the full-length channel steel auxiliary support rod through multiple angle steel diagonal support rods, that is, the intersection of the upper flange of the full-length I-beam main support rod with the web plate and the intersection of the lower flange of the full-length channel steel auxiliary support rod with the web plate are welded together through multiple first angle steel diagonal support rods, and the intersection of the lower flange of the full-length I-beam main support rod with the web plate is connected to the intersection of the lower flange of the full-length channel steel auxiliary support rod with the web plate through multiple first angle steel diagonal support rods The intersection of the upper flange and the web of the support rod is welded and connected by multiple second angle steel diagonal braces, and the first angle steel diagonal braces and the second angle steel diagonal braces are alternately distributed. The welding points at both ends of the angle steel diagonal braces are not on the same vertical plane, and the welding points of two adjacent angle steel diagonal braces on the same full-length channel steel auxiliary support rod are respectively the left end of one angle steel diagonal brace and the right end of the other angle steel diagonal brace; a lifting ring is vertically welded to the center of the upper flange surface of the full-length I-beam main support rod, and a lifting hole is opened at the center of the lifting ring; two steel bar rings are symmetrically installed at both ends of the lower flange of the full-length I-beam main support rod, and a lifting belt is passed through the steel bar ring; a guy rope is passed through the oblique angle formed by the angle steel diagonal brace and the lower flange of the full-length I-beam main support rod, and the guy rope is symmetrically located on both sides of the full-length I-beam main support rod and both sides of the full-length channel steel auxiliary support rod.
[0006] Specifically, the two channel steel auxiliary support rods are respectively the first full-length channel steel auxiliary support rod and the second full-length channel steel auxiliary support rod. The angle steel diagonal brace welded between the intersection of the upper flange and the web of the full-length I-beam main support rod and the intersection of the lower flange and the web of the first full-length channel steel auxiliary support rod is the first angle steel diagonal brace, and the angle steel diagonal brace welded between the intersection of the lower flange and the web of the second full-length channel steel auxiliary support rod is the third angle steel diagonal brace. The angle steel diagonal brace welded between the intersection of the lower flange and the web of the full-length I-beam main support rod and the intersection of the upper flange and the web of the first full-length channel steel auxiliary support rod is the second angle steel diagonal brace, and the angle steel diagonal brace welded between the intersection of the upper flange and the web of the second full-length channel steel auxiliary support rod is the fourth angle steel The diagonal braces, the welding points of the first angle steel diagonal brace and the third angle steel diagonal brace with the full-length I-beam main brace are all on the left side of the welding points with the full-length channel steel auxiliary brace, and the welding points of the second angle steel diagonal brace and the fourth angle steel diagonal brace with the full-length I-beam main brace are all on the right side of the welding points with the full-length channel steel auxiliary brace, that is, the directions of the two adjacent angle steel diagonal braces: the first angle steel diagonal brace and the second angle steel diagonal brace, or the third angle steel diagonal brace and the fourth angle steel diagonal brace are opposite, and from the top view, the specific welding points on the first full-length channel steel auxiliary brace are the left end of the second angle steel diagonal brace and the right end of the first angle steel diagonal brace, or the specific welding points on the second full-length channel steel auxiliary brace are the left end of the fourth angle steel diagonal brace and the right end of the third angle steel diagonal brace.
[0007] Furthermore, the height of the two full-length channel steel auxiliary support rods is smaller than the height of the full-length I-beam main support rod.
[0008] Furthermore, the maximum spacing between the two full-length channel steel auxiliary support rods and the full-length I-beam main support rod is 300-600 mm.
[0009] Furthermore, all the angle steel diagonal braces are symmetrically distributed on both sides of the full-length I-beam main support rod, and the projections of two adjacent angle steel diagonal braces connected to the same full-length channel steel auxiliary support rod on the horizontal plane are symmetrical about the vertical direction of the full-length channel steel auxiliary support rod, and the horizontal distance between their welding points is 300-600mm.
[0010] Furthermore, there are four guy ropes in total.
[0011] A method for using the above-mentioned steel shoulder pole for high-altitude lifting and installation, firstly, complete the bolting of the first composite multi-span continuous beam on the ground, wherein the ends of each single-span beam are bolted via a node plate, and the single-span beam has at least four beams; the hook of a single crane passes through the oblong lifting hole of the lifting ring to lift the steel shoulder pole, and move the steel shoulder pole to the top of the middle of the composite multi-span continuous beam; the lower ends of two lifting belts are respectively tied to the outer sides of the node plates where the middle span beam and the two side span beams in the composite multi-span continuous beam are bolted; the crane lifts the steel shoulder pole so that the composite multi-span continuous beam hung under the steel shoulder pole is at the top of the middle span beam and the node plates where the middle span beam and the two side span beams ... The column head elevation position is required; the ground operators hold and pull the lower end of the guy rope hanging from the steel shoulder pole to carry out balanced movement of the combined multi-span continuous beam forward, backward, left and right until the node plate at the end of the combined multi-span continuous beam is aligned with the column head node plate to be connected, and use high-strength bolts to bolt and install the node plate at the end of the combined multi-span continuous beam and the column head node plate to be connected; loosen the lifting belt, lift the steel shoulder pole to the ground, and carry out lifting and installation of the second combined multi-span continuous beam, and so on, until the lifting and installation of all the combined multi-span continuous beams of the project are completed.
[0012] The beneficial effects of the present invention are as follows: the steel shoulder pole is easy to manufacture and can be conveniently and quickly transported during high-altitude construction. A reinforced support system is formed at the weak links on both sides of the I-shaped steel to make it safe and stable, and it has a stronger bearing capacity. It can be directly hoisted on the combined multi-span continuous beam bolted on the ground, reducing the bolting operation procedures of beams and beam columns at high altitudes and avoiding the occurrence of potential safety hazards. At the same time, the production cost is low and it can be reused, which reduces the construction cost and improves the installation and construction efficiency. The present invention is suitable for the hoisting and installation of multi-span continuous beams of various specifications, and solves the construction problems of the current portal frame structure, such as the difficulty in aligning the multi-span continuous beams at high altitude, the large installation deviation and the potential safety hazards, thereby ensuring the smooth implementation of the construction progress and quality and achieving the social and economic benefits of safe construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] The embodiments of the present invention are further described below with reference to the accompanying drawings, in which:
[0014] Figure 1 A top view of the structure of a steel shoulder pole for high-altitude lifting and installation is shown;
[0015] Figure 2 Shown is the attached Figure 1 Side view of the middle AA section;
[0016] Figure 3 The front view of the structure of the steel shoulder pole used for high-altitude lifting installation is shown;
[0017] Figure 4 The diagram shows the usage status of the steel shoulder pole used for high-altitude lifting and installation.
[0018] Among them, 1. Full-length I-beam main support rod; 2. First-length channel steel auxiliary support rod; 3. Second-length channel steel auxiliary support rod; 4. First-length angle steel diagonal support; 5. Second-length angle steel diagonal support; 6. Third-length angle steel diagonal support; 7. Fourth-length angle steel diagonal support; 8. Lifting ring; 9. Lifting hole; 10. Steel bar ring; 11. Combined multi-span continuous beam; 12. Lifting belt; 13. Cable guy rope; 14. Node plate. DETAILED DESCRIPTION
[0019] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below through specific embodiments in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0020] In one embodiment:
[0021] 1) First, according to the length of the middle span beam (two beams) of the portal frame and the weight of the combined multi-span continuous beam in the project engineering design, select a full-length I-beam with a width and height slightly larger than the length of the middle span beam and a rigidity that can bear the weight of the combined beam without bending and instability, and place its lower flange naturally on the ground as the main support rod 1 of the full-length I-beam.
[0022] 2) Select two channel steels with a height less than the full-length I-beam main support 1 and greater rigidity, cut them into the same length as the full-length I-beam main support 1, and place them at a position where the vertical distance between their open ends and the full-length I-beam main support 1 is about 300-600mm. The two channel steels are symmetrically placed in parallel on both sides of the full-length I-beam main support 1 for standby use (as shown in the attached figure). Figure 2 As shown, the horizontal centers of the three sections are on the same center line), and the two channel steels serve as the first full-length channel steel auxiliary support rod 2 and the second full-length channel steel auxiliary support rod 3 respectively.
[0023] 3) Cut several equal-length angle steels of suitable specifications as the first angle steel diagonal brace 4, the second angle steel diagonal brace 5, the third angle steel diagonal brace 6, and the fourth angle steel diagonal brace 7. The angle steel diagonal brace welded between the intersection of the upper flange and the web of the full-length I-beam main support rod 1 and the intersection of the lower flange and the web of the first full-length channel steel auxiliary support rod 2 is the first angle steel diagonal brace 4, and the lower flange and web of the second full-length channel steel auxiliary support rod 3. The angle steel diagonal brace welded between the intersection of the lower flange of the full-length I-beam main support rod 1 and the web plate is the third angle steel diagonal brace 6, the first angle steel diagonal brace 4 and the third angle steel diagonal brace 6 are the first angle steel diagonal brace; the angle steel diagonal brace welded between the intersection of the lower flange of the full-length I-beam main support rod 1 and the web plate and the upper flange of the first full-length channel steel auxiliary support rod 2 and the web plate is the second angle steel diagonal brace 5, and the angle steel diagonal brace welded between the intersection of the upper flange of the second full-length channel steel auxiliary support rod 3 and the web plate is the The angle steel diagonal brace is the IV angle steel diagonal brace 7, and the II angle steel diagonal brace 5 and the IV angle steel diagonal brace 7 are the second angle steel diagonal brace; the welding points at both ends of all the angle steel diagonal braces are not on the same vertical plane, the first angle steel diagonal brace and the second angle steel diagonal brace are alternately distributed, that is, the I angle steel diagonal brace 4 and the II angle steel diagonal brace 5 are alternately distributed, and the III angle steel diagonal brace 6 and the IV angle steel diagonal brace 7 are alternately distributed; the welding points of the I angle steel diagonal brace 4 and the III angle steel diagonal brace 6 with the full-length I-beam main support rod 1 are all on the left side of the welding points with the full-length channel steel auxiliary support rod, and the welding points of the II angle steel diagonal brace 5 and the IV angle steel diagonal brace 7 with the full-length I-beam main support rod 1 are all on the right side of the welding points with the full-length channel steel auxiliary support rod, that is, the directions of the two adjacent angle steel diagonal braces, that is, the I angle steel diagonal brace 4 and the II angle steel diagonal brace 5, or the III angle steel diagonal brace 6 and the IV angle steel diagonal brace 7, are opposite. Multiple first angle steel diagonal braces 4 are arranged in parallel and equidistantly, and second angle steel diagonal braces 5, third angle steel diagonal braces 6 and fourth angle steel diagonal braces 7 are also arranged. The horizontal distance between the welding point of first angle steel diagonal brace 4 on the full-length I-beam main support rod 1 and the welding point of second angle steel diagonal brace 5 on the full-length I-beam main support rod 1 is 300-600mm. The angle steel diagonal braces on both sides of the full-length I-beam main support rod 1 are symmetrically distributed, and the projections of two adjacent angle steel diagonal braces connected to the same full-length channel steel auxiliary support rod on the horizontal plane are symmetrical about the vertical direction of the full-length channel steel auxiliary support rod. A symmetrical reinforcement support system is formed for the weak link positions on both sides of the full-length I-beam main support rod 1.
[0024] 4) A lifting ring 8 is vertically welded at the center of the upper flange surface of the full-length I-beam main support rod 1, and an oblong lifting hole 9 is opened in the center of the lifting ring 8; two steel rings 10 are symmetrically installed at both ends of the lower flange of the full-length I-beam main support rod 1, and a lifting belt 12 is inserted into the steel ring 10; a cable wind rope 13 is inserted into the oblique angle formed by the angle steel diagonal support and the lower flange of the full-length I-beam main support rod 1, and the cable wind ropes 13 are symmetrically located on both sides of the full-length I-beam main support rod 1 and on both sides of the full-length channel steel auxiliary support rod. There are four cables 13 in total, and the length of the cables 13 is greater than the distance from the required lifting elevation to the ground, that is, greater than the height of the rigid frame column.
[0025] The method for using the above-mentioned steel shoulder pole for high-altitude lifting and installation is as follows: first, complete the bolting of the first composite multi-span continuous beam 11 on the ground, wherein the ends of each single-span beam are bolted via a node plate 14, and there are at least four single-span beams; the hook of a single crane passes through the oblong lifting hole 9 of the lifting ring 8 to lift the steel shoulder pole, and move the steel shoulder pole to the top of the middle of the composite multi-span continuous beam 11; the lower ends of the two lifting belts 12 are respectively tied to the outer sides of the node plates 14 bolted to the middle span beam and the two side span beams in the composite multi-span continuous beam 11; the crane lifts the steel shoulder pole so that the composite multi-span continuous beam 11 hanging under the steel shoulder pole is at the required column head elevation position; the ground Four operators on both sides of the portal frame column respectively hold and pull the lower end of the guy rope 13 hanging from the steel shoulder pole to balance the combined multi-span continuous beam 11 forward, backward, left and right until the node plate 14 at the end of the combined multi-span continuous beam 11 is aligned with the node plates of the portal frame column heads at both ends, and the node plate 14 at the end of the combined multi-span continuous beam 11 is bolted and installed with the node plates of the portal frame column heads at both ends using high-strength bolts; loosen the lifting belt 12, lift the steel shoulder pole to the ground, and lift and install the second combined multi-span continuous beam 11, and so on, until the lifting and installation of all the combined multi-span continuous beams 11 of the project are completed.
[0026] Some exemplary embodiments of the present invention are described above. It can be understood that the above embodiments are only used to explain the present invention and do not constitute a limitation on the protection scope of the present invention. The features in these embodiments can be recombined in a suitable manner, and the scheme obtained thereby is still within the protection scope required by the present invention. Based on the above embodiments, all other embodiments obtained by those skilled in the art without making creative work, that is, all modifications, equivalent substitutions and improvements made within the spirit and principles of this application, fall within the protection scope required by the present invention.
Claims
1. A steel shoulder pole for high-altitude lifting and installation, characterized in that: include: A full-length I-beam main support rod (1), two identical full-length channel steel auxiliary support rods, a plurality of angle steel diagonal support rods, a lifting ring (8), a steel bar ring (10), a lifting belt (12) and a guy rope (13), wherein the two full-length channel steel auxiliary support rods are symmetrically located on both sides of the full-length I-beam main support rod (1), and their centers are located in the same horizontal plane as the center of the full-length I-beam main support rod (1); the intersections of the upper flange and the lower flange of the full-length I-beam main support rod (1) with the web are respectively connected to the intersections of the lower flange and the upper flange of the full-length channel steel auxiliary support rod with the web via a plurality of angle steel diagonal support rods alternately welded, the welding points at both ends of the angle steel diagonal support rods are not on the same vertical plane, and two adjacent angle steel diagonal support rods are on the same The welding points on the full-length channel steel auxiliary support rod are respectively the left end of an angle steel diagonal support and the right end of another angle steel diagonal support; a lifting ring (8) is vertically welded at the center of the upper flange surface of the full-length I-beam main support rod (1), and a lifting hole (9) is opened at the center of the lifting ring (8); two steel rings (10) are symmetrically installed at both ends of the lower flange of the full-length I-beam main support rod (1), and a lifting belt (12) is inserted into the steel ring (10); a cable wind rope (13) is inserted into the oblique angle formed by the angle steel diagonal support and the lower flange of the full-length I-beam main support rod (1), and the cable wind rope (13) is symmetrically located on both sides of the full-length I-beam main support rod (1) and on both sides of the full-length channel steel auxiliary support rod.
2. The steel shoulder pole for high-altitude lifting and installation according to claim 1 is characterized in that: The height of the two full-length channel steel auxiliary support rods is smaller than the height of the full-length I-beam main support rod (1).
3. The steel shoulder pole for high-altitude lifting and installation according to claim 1 is characterized in that: The maximum distance between the two full-length channel steel auxiliary support rods and the full-length I-beam main support rod (1) is 300-600 mm.
4. The steel shoulder pole for high-altitude lifting and installation according to claim 1 is characterized in that: All the angle steel braces are symmetrically distributed on both sides of the full-length I-beam main support rod (1), and the projections of two adjacent angle steel braces connected to the same full-length channel steel auxiliary support rod on the horizontal plane are symmetrical about the vertical direction of the full-length channel steel auxiliary support rod, and the horizontal distance between their welding points is 300-600mm.
5. The steel shoulder pole for high-altitude lifting and installation according to claim 1 is characterized in that: There are four guy ropes (13) in total.
Citation Information
Patent Citations
Lattice type combined crane beam and light steel structure plant
CN118723779A
Double-row shoulder pole beam hoisting tool
CN203359759U