New energy automobile circuit board waterproof performance test equipment

By designing waterproof performance testing equipment for new energy vehicle circuit boards, we achieved comprehensive water spraying, dynamic testing, and extreme environment simulation, solving the problems of inaccurate and low efficiency in circuit board testing and improving the accuracy and efficiency of testing.

CN120702690APending Publication Date: 2025-09-26龙南鼎泰电子科技有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511092201.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-08-05
Publication Date
2025-09-26

AI Technical Summary

Technical Problem

In existing circuit board waterproof performance testing, it is difficult to spray water comprehensively and evenly to all parts, resulting in inaccurate test results. In addition, traditional testing methods are inefficient and cannot test multiple circuit boards at the same time, making it difficult to meet the needs of large-scale production.

Method used

A waterproof performance test equipment for new energy vehicle circuit boards was designed. Through duct spraying, shaft rotation, vibration simulation and partition detection system, it can achieve comprehensive water spraying, dynamic testing and extreme environment simulation, and combine with visual detectors to evaluate the waterproof performance of circuit boards.

Benefits of technology

The accuracy and efficiency of detection are improved, and control group detection can be performed on two circuit boards at the same time to simulate the actual use environment, thereby improving the comprehensiveness and reliability of detection, and timely drying treatment is carried out to reduce the risk of failure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120702690A_ABST
    Figure CN120702690A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of circuit board testing, in particular to new energy automobile circuit board waterproof performance testing equipment which comprises a box body, a box door and the like. And a box door is arranged on the box body. According to the invention, water is sprayed to the lower surface of the circuit board at the upper part through the bidirectional spray pipe arranged in the middle of the guide pipe and is sprayed to the upper surface of the circuit board at the lower part, so that the upper surfaces and the lower surfaces of the two circuit boards are subjected to high-pressure impact spraying through the water; whether the circuit board can operate normally under the power-on condition or not is observed through an external visual detector, so that whether the waterproof performance of the circuit board is qualified or not is judged, the waterproof performance of the circuit board is tested, water can be sprayed to all parts of the circuit board more comprehensively by adjusting the angle of the circuit board, and the waterproof performance of the circuit board is improved. And the waterproof performance of the two circuit boards is tested at the same time, so that the two circuit boards form a control group, and the detection efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of circuit board testing, and in particular to a waterproof performance testing device for a new energy vehicle circuit board. Background Art

[0002] Circuit boards are a very common component widely used in various electronic devices. They are very commonly used, and circuit boards usually need to be tested for waterproofing when they are used. Based on existing technology, it has been found that in the existing inspection process, during the spray inspection of circuit boards, due to the unreasonable setting of the circuit board angle, water is difficult to spray all parts comprehensively and evenly. Insufficient water coverage in some areas makes it difficult to effectively detect potential defects, affecting the accuracy of the inspection results. This may cause defective circuit boards to flow into subsequent production, increasing the product defect rate. In terms of waterproof testing, the current detection method is inefficient. It usually tests a single circuit board and cannot test multiple circuit boards at the same time. This greatly limits production efficiency and makes it difficult to meet the needs of large-scale production for efficient and accurate testing. Summary of the Invention

[0003] In order to overcome the disadvantage that water is difficult to spray comprehensively and evenly to all parts of the circuit board during the spraying operation inspection, which affects the accuracy of the inspection results, the present invention provides a new energy vehicle circuit board waterproof performance testing device.

[0004] Technical solution: A waterproof performance testing device for new energy vehicle circuit boards, comprising a box body and a box door; the box door is installed on the box body; it also comprises a drive assembly, a fixed plate, a coupling, an electric clamp, a conduit, a spray pipe, a spur gear I, a motor I and a spur gear II; at least two drive assemblies are installed on the box body; each drive assembly is installed with at least two fixed plates, and the drive assembly is used to drive the fixed plates to move; each fixed plate is connected to a coupling; an electric clamp is installed on the end of each coupling away from the fixed plate; a conduit is installed on the box body, and a two-way nozzle is provided in the middle of the conduit, and unidirectional nozzles are provided at both ends of the conduit; each coupling is fixedly connected to a spur gear I; motor I is installed on the box body; spur gear II is fixedly connected to the output shaft of motor I.

[0005] Furthermore, a wavy rubber block is provided on the clamping portion of the electric clamp.

[0006] Furthermore, it also includes a vibration simulation system; the vibration simulation system is connected to the box body; the vibration simulation system includes a long strip, a protrusion, a cross bar, a sliding block, a fixed ring and an elastic member; at least two long strips are fixed to the box body; each long strip is fixed with a number of protrusions; each fixed plate is fixed with at least two cross bars; each cross bar is slidably connected to a sliding block; all sliding blocks in the same fixed plate are commonly fixed to a fixed ring; each fixed ring is rotatably connected to a corresponding connecting shaft; an elastic member is sleeved on the outside of each cross bar, one end of the elastic member is fixed to the sliding block, and the other end of the elastic member is fixed to the fixed plate.

[0007] Furthermore, the sizes of the bumps vary.

[0008] Furthermore, it also includes a partition detection system; the partition detection system is connected to the box body; the partition detection system includes a vertical plate, a horizontal plate, an electric slide rail III, an electric slider III, a cover, a screen curtain, a partition, a screen plate, a seal, an air supply pipe and an air intake pipe; the vertical plate is fixed to the box body; the horizontal plate is fixed to the box body; the electric slide rail III is fixed to the box body; the electric slider III is slidably connected to the electric slide rail III; the cover body is fixed to the electric slider III; the cover body is slidably connected to the box body; the screen curtain is fixed to the cover body, and a spring clip is provided in the screen curtain; the partition is fixed to the cover body; the screen plate is fixed to the cover body; a number of seals are fixed to the cover body; at least two air supply pipes are installed on the box body; each air supply pipe is fixed to and connected to an air intake pipe; all air intake pipes are fixed to the horizontal plate, and all air intake pipes pass through the box body and the horizontal plate.

[0009] Furthermore, a guide rail is provided at the connection between the cover shell and the box body.

[0010] Furthermore, a sealing strip is installed on the vertical plate.

[0011] Furthermore, a sealing strip is provided on the side of the transverse plate away from the box body.

[0012] Furthermore, the shielding curtain is configured to be transparent.

[0013] Furthermore, it also includes an electric actuator and a rack; at least two electric actuators are installed on the box body, and the telescopic parts of all the electric actuators on the same side are fixedly connected to a rack.

[0014] The advantages and positive effects of the present invention are: (1) By supplying water into the conduit, the water flows along the conduit and sprays onto the surface of the circuit board, and the water is sprayed onto the lower surface of the circuit board located above and the upper surface of the circuit board located below through the two-way nozzle set in the middle of the conduit, so that the upper and lower surfaces of the two circuit boards are sprayed with high-pressure water. Then, an external visual detector is used to observe whether the circuit board can operate normally when powered on, so as to determine whether the waterproof performance of the circuit board is qualified, thereby realizing the waterproof performance test of the circuit board.

[0015] (2) The electric fixture is driven to rotate by the shaft, thereby rotating the two circuit boards, and then adjusting the angle of the circuit boards so that water can be sprayed more comprehensively to various parts of the circuit boards, thereby improving the accuracy of the test. By testing the waterproof performance of the two circuit boards at the same time, the two circuit boards form a control group and improve the test efficiency.

[0016] (3) By moving the two circuit boards back and forth, the vibration generated by the circuit boards during actual use is simulated, and then water is sprayed on the surface of the circuit boards again, so that the circuit boards can be vibrated and then tested for waterproof performance again. In this way, the dynamic test and static test of the circuit boards are combined to improve the comprehensiveness and accuracy of the test.

[0017] (4) The cover is moved to rest against the horizontal plate and the box body, so that the cover, the horizontal plate and the box body are combined to form a closed space, and the movement of the cover drives the partition and the shielding plate to move synchronously, and then the interior of the cover is divided into two independent spaces by the partition, the shielding plate and the vertical plate, and then the cold air and hot air are respectively transported to the corresponding air pipes, so that the temperature on one side of the circuit board is low and the temperature on the other side is high, thereby simulating the state of the circuit board in extreme environment, and then the circuit board is subjected to high-pressure impact spraying by water to evaluate the performance of the circuit board in extreme environment, thereby further improving the comprehensiveness of the circuit board detection.

[0018] (5) The two racks are moved in the direction of the spur gear I on the same side until the racks are engaged with the corresponding spur gear I, and then all the spur gears I are moved and rotated along the corresponding racks, thereby causing the two circuit boards to rotate and tilt, so that the residual moisture on the surfaces of the two circuit boards can automatically flow off, and then the gas is blown to the circuit boards again through the two air inlet pipes to dry the circuit boards, thereby achieving timely drying of the circuit boards after the waterproof performance test of the circuit boards, avoiding moisture from staying on the circuit boards for a long time, and reducing the possibility of failure caused by residual moisture. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1This is a schematic diagram of the three-dimensional structure of the waterproof performance testing equipment for new energy vehicle circuit boards of the present invention; Figure 2 This is a schematic diagram of the three-dimensional structure of the installation position of the electric slide rail I and the electric slider I of the new energy vehicle circuit board waterproof performance testing equipment of the present invention; Figure 3 This is a diagram showing the installation positions of the vertical and horizontal plates of the new energy vehicle circuit board waterproof performance testing equipment of the present invention; Figure 4 This is a schematic diagram of a circuit board in a clamped state of the new energy vehicle circuit board waterproof performance testing device of the present invention; Figure 5 This is a schematic diagram of the installation positions of the long strips and bumps of the new energy vehicle circuit board waterproof performance testing equipment of the present invention; Figure 6 This is a schematic diagram of the installation positions of the crossbar, sliding block, fixing ring and elastic member of the new energy vehicle circuit board waterproof performance testing equipment of the present invention; Figure 7 This is a schematic diagram of the three-dimensional structure of the partition detection system of the new energy vehicle circuit board waterproof performance test equipment of the present invention; Figure 8 This is a schematic diagram of a state in which the cover of the new energy vehicle circuit board waterproof performance testing device of the present invention moves against the horizontal plate; Figure 9 This is a schematic diagram of a state where the circuit board of the new energy vehicle circuit board waterproof performance testing device of the present invention is separated; Figure 10 This is a schematic diagram of the installation positions of the electric actuator and rack of the new energy vehicle circuit board waterproof performance testing equipment of the present invention.

[0020] In the above figures: 1- box body, 11- box door, 2- circuit board, 201- electric slide rail I, 202- electric slider I, 203- electric slide rail II, 204- electric slider II, 205- fixed plate, 206- connecting shaft, 207- electric fixture, 208- guide tube, 209- spray pipe, 210- spur gear I, 211- motor I, 212- spur gear II, 301- long strip plate, 30 2-bump, 303-cross bar, 304-sliding block, 305-fixing ring, 306-elastic member, 12-vertical plate, 13-cross plate, 401-electric slide rail III, 402-electric slider III, 403-cover, 404-shielding curtain, 405-partition, 406-shielding plate, 407-seal, 408-air pipe, 409-intake pipe, 501-electric actuator, 502-rack. DETAILED DESCRIPTION

[0021] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0022] Example 1: A new energy vehicle circuit board waterproof performance test equipment, based on Figure 1-Figure 4 As shown, it includes a box body 1 and a box door 11; the box door 11 is installed on the box body 1; It also includes a drive assembly, a fixed plate 205, a connecting shaft 206, an electric clamp 207, a conduit 208, a spray pipe 209, a spur gear I 210, a motor I 211 and a spur gear II 212; two drive assemblies are installed on the box body 1; each drive assembly is installed with two fixed plates 205; each fixed plate 205 is connected to a connecting shaft 206; each connecting shaft 206 is installed with an electric clamp 207 at one end away from the fixed plate 205; a conduit 208 is installed on the box body 1, and a two-way nozzle is provided in the middle of the conduit 208, and unidirectional nozzles are provided at both ends of the conduit 208; each connecting shaft 206 is fixed with a spur gear I 210; a motor I 211 is installed at the bottom inside the box body 1; a spur gear II 212 is fixed to the output shaft of the motor I 211.

[0023] The clamping portion of the electric clamp 207 is provided with a wavy rubber block to reduce damage to the circuit board 2 when clamping and limiting the circuit board 2.

[0024] The drive assembly includes an electric slide rail I 201, an electric slider I 202, an electric slide rail II 203 and an electric slider II 204; two electric slide rails I 201 are fixedly connected to the upper inner side of the box body 1; each electric slide rail I 201 is slidably connected to an electric slider I 202; each electric slider I 202 is fixedly connected to an electric slide rail II 203; each electric slide rail II 203 is slidably connected to two electric sliders II 204; each electric slider II 204 is fixedly connected to a fixed plate 205.

[0025] The external pump for water delivery is connected to the conduit 208 in advance, and then the box door 11 is opened. With the front side of the box body 1 as the reference, the initial positions of all the electric clamps 207 are located on the inner left side of the box body 1 to facilitate loading and unloading. Then, two circuit boards 2 are placed into the box body 1 in sequence by manual or external robotic arms, and both circuit boards 2 are powered on. Then, all the electric clamps 207 are controlled to operate and clamp the two circuit boards 2 respectively. Figure 4As shown, the two electric sliders Ⅰ 202 are then controlled to move to the right along an electric slide rail Ⅰ 201 respectively. The movement of the two electric sliders Ⅰ 202 drives all connected components to move, and then drives all electric clamps 207 to move, and then drives the two circuit boards 2 to move, and makes the two circuit boards 2 located directly below the spray pipe 209. Then, the external pump for water supply is controlled to start to supply water into the conduit 208. The water flows along the conduit 208 and sprays onto the surface of the circuit board 2. The water is sprayed onto the lower surface of the circuit board 2 located above and the upper surface of the circuit board 2 located below through the two-way nozzle provided in the middle of the conduit 208, so that the upper and lower surfaces of the two circuit boards 2 are sprayed with high-pressure water. At this time, the external visual detector is used to observe whether the circuit board 2 can operate normally when powered on, so as to determine whether the waterproof performance of the circuit board 2 is qualified, thereby realizing the waterproof performance test of the circuit board 2.

[0026] However, in the existing inspection process, the spraying operation on the circuit board 2 is often not properly set at an angle, resulting in water not being able to fully and evenly spray all parts of the circuit board 2. As a result, some areas may not be adequately covered by the water flow, making it difficult to effectively detect potential defects, thereby affecting the accuracy of the inspection results. As a result, some defective circuit boards 2 may flow into subsequent production links, resulting in an increase in product defect rates. To solve the above problem, the two electric sliders II 204 located above are controlled to move downward along the corresponding electric slide rails II 203, and the two electric sliders II 204 located below are controlled to move upward along the corresponding electric slide rails II 203. The movement of the electric sliders II 204 drives the fixed plate 205 to move, and then drives all connected components to move, so that the two circuit boards 2 move toward each other, and at the same time, the corresponding two spur gears I 210 are engaged with the spur gear II 212. Then the motor I 211 is controlled to start, and the output shaft of the motor I 211 rotates to drive the spur gear II 212 to rotate. The rotation of the spur gear II 212 drives the two spur gears I 210 to rotate. The rotation of the two spur gears I 210 each drives a connecting shaft 206 to rotate. The rotation of the connecting shaft 206 drives the electric clamp 207 to rotate, so that the two circuit boards 2 rotate, and then the angle of the circuit board 2 is adjusted so that water can be sprayed more comprehensively to various parts of the circuit board 2, thereby improving the accuracy of the detection. By simultaneously testing the waterproof performance of the two circuit boards 2, the two circuit boards 2 form a control group, and the detection efficiency is improved.

[0027] Example 2: Based on Example 1, Figure 5-Figure 6As shown, it also includes a vibration simulation system; the vibration simulation system is connected to the box body 1; the vibration simulation system includes a long strip 301, a protrusion 302, a cross bar 303, a sliding block 304, a fixed ring 305 and an elastic member 306; two long strips 301 are fixed to the box body 1; each long strip 301 is fixed with a number of protrusions 302; two cross bars 303 are fixed to the inner side of each fixed plate 205; each cross bar 303 is slidably connected to a sliding block 304; all sliding blocks 304 in the same fixed plate 205 are fixed to a fixing ring 305; each fixing ring 305 is rotatably connected to a corresponding connecting shaft 206; an elastic member 306 is sleeved on the outside of each cross bar 303, the elastic member 306 is a spring, one end of the elastic member 306 is fixed to the sliding block 304, and the other end of the elastic member 306 is fixed to the fixed plate 205.

[0028] The sizes of the bumps 302 are different to simulate vibrations of different degrees.

[0029] Since the circuit board 2 will vibrate with the vibration of the equipment during actual use, and the vibration and splashing of the car exist at the same time, and the two environmental factors also affect each other, which can easily cause the circuit board 2 to malfunction during use, affecting the normal operation of the equipment. By controlling the two electric sliders I 202 to move to the right along an electric slide rail I 201, all the connected components are driven to move, and the two circuit boards 2 are driven to move, and at the same time, the four connecting shafts 206 touch the corresponding long strips 301, and then all the electric sliders II 204 are controlled to start and move downward along the corresponding electric slide rails II 203. The electric slider II 204 moves to drive the fixed plate 205, and the fixed plate 205 moves to drive the corresponding cross bar 303, the sliding block 304, the fixed ring 305 and the elastic member 306 to move synchronously, and then drive the connecting shaft 206 to move to touch the protrusion 302, and is squeezed by the protrusion 302 to displace, and the connecting shaft 2 06 moves and drives the fixed ring 305 to move, and the movement of the fixed ring 305 drives the corresponding sliding block 304 to move, thereby compressing the corresponding elastic member 306. When the connecting shaft 206 moves away from the protrusion 302, the elastic force generated by the corresponding elastic member 306 drives all connected parts to move, thereby causing the connecting shaft 206 to move and reset, thereby causing the two circuit boards 2 to move back and forth, thereby simulating the vibration generated by the circuit board 2 during actual use, and then controlling the two electric sliders Ⅰ202 to move and reset to the left along an electric slide rail Ⅰ201, thereby causing the two circuit boards 2 to move and reset, and then controlling the external pump for water supply to start and supply water to the conduit 208, thereby spraying water on the surface of the circuit board 2 again, thereby achieving a waterproof performance test on the circuit board 2 after the circuit board 2 is vibrated, thereby improving the comprehensiveness and accuracy of the test by combining dynamic testing and static testing of the circuit board 2.

[0030] It should be noted that before the connecting shaft 206 touches the long strip 301, all the electric sliders II 204 are controlled to start moving toward each other along the corresponding electric slide rails II 203, so that the corresponding two spur gears I 210 are engaged with the spur gear II 212. Then, the motor I 211 is controlled to start, and the angle of the circuit board 2 is adjusted, thereby simulating the posture changes of the circuit board 2 when a car is driving on different road conditions (such as uphill, downhill, and flat roads). Then, the connecting shaft 206 is made to touch the corresponding long strip 301 in the same manner as above, thereby simulating the waterproof performance of the circuit board 2 that vibrates after the posture changes.

[0031] Example 3: Based on Example 2, Figure 2 、 Figure 3 and Figure 7-10 As shown, it also includes a partition detection system; the partition detection system is connected to the box 1; the partition detection system includes a vertical plate 12, a horizontal plate 13, an electric slide rail III 401, an electric slider III 402, a cover 403, a shielding curtain 404, a partition 405, a shielding plate 406, a seal 407, an air pipe 408 and an air inlet pipe 409; the vertical plate 12 is fixed to the middle of the inner side of the box 1; the horizontal plate 13 is fixed to the upper inner side of the box 1; the electric slide rail III 401 is fixed to the upper inner side of the box 1; the electric slider III 402 is slidably connected to the electric slide rail III 401; the electric slider III 402 is fixed to the upper inner side of the box 1 There is a cover shell 403; the cover shell 403 is slidably connected to the box body 1; a shielding curtain 404 is fixed to the cover shell 403, and a spring is provided inside the shielding curtain 404; a partition 405 is fixed to the upper inner side of the cover shell 403; a shielding plate 406 is fixed to the inner side of the cover shell 403; a plurality of seals 407 are fixed to the cover shell 403, and the seals 407 are rubber strips; two air pipes 408 are installed on the top of the box body 1; each air pipe 408 is fixed to and connected to an air intake pipe 409; all air intake pipes 409 are fixed to the horizontal plate 13, and all air intake pipes 409 pass through the box body 1 and the horizontal plate 13.

[0032] A guide rail is provided at the connection between the cover shell 403 and the box body 1 to facilitate the movement of the cover shell 403. The cover shell 403 and the guide rail cooperate to limit the water flowing to the bottom inside the box body 1, so that the water flows to the drain outlet on the box body 1.

[0033] A sealing strip is installed on the vertical plate 12 to cooperate with the partition 405 and the shielding plate 406 to separate the interior of the cover 403 into two independent spaces.

[0034] A sealing strip is provided on the side of the transverse plate 13 away from the box body 1 , so as to combine the box body 1 and the cover shell 403 to form a closed space.

[0035] The shielding curtain 404 is set to be transparent to facilitate manual observation and loading and unloading.

[0036] It also includes an electric actuator 501 and a rack 502; two electric actuators 501 are installed on the rear side of the box body 1. The electric actuators 501 are electric push rods, and the telescopic parts of all electric actuators 501 on the same side are fixedly connected to a rack 502.

[0037] The two external fans are connected to an air pipe 408 in advance. When the circuit board 2 is loaded and unloaded, the shielding curtain 404 is squeezed to deform the shielding curtain 404, thereby facilitating manual loading and unloading. Since the production environment and use environment of the circuit board 2 are complex and changeable, a single detection method often cannot fully cover all potential problems, especially in extreme environments such as high temperature, low temperature, and alternating hot and cold. It is difficult for traditional detection methods to effectively evaluate the reliability and stability of the circuit board 2. By controlling the electric slider III 402 to start moving along the electric slide rail III 401 toward the horizontal plate 13, the movement of the electric slider III 402 drives the cover shell 403 to move, and the movement of the cover shell 403 drives all connected components to move, thereby causing the cover shell 403 to move against the horizontal plate 13 and against the box body 1, as shown Figure 8 As shown, the cover 403, the horizontal plate 13 and the box body 1 are combined to form a closed space, and the movement of the cover 403 drives the partition 405 and the shielding plate 406 to move synchronously, so that when the cover 403 moves to abut the horizontal plate 13, the partition 405 and the shielding plate 406 are combined with the vertical plate 12, so that the interior of the cover 403 is divided into two independent spaces by the partition 405, the shielding plate 406 and the vertical plate 12, and the two independent spaces separated inside the cover 403 are made more sealed by the setting of the sealing member 407, and the two sides of the circuit board 2 are respectively isolated in the corresponding independent spaces by the partition 405, the shielding plate 406 and the vertical plate 12, as shown in FIG. Figure 9 As shown, the two external fans are then controlled to operate to deliver cold air and hot air to the corresponding air pipes 408, respectively, so that the gas flows along the air pipe 408 and the air inlet pipe 409 until it enters the cover 403, thereby making the temperature on one side of the circuit board 2 low and the temperature on the other side high, thereby simulating the state of the circuit board 2 being used in an extreme environment. The circuit board 2 is then subjected to high-pressure impact spraying with water to evaluate the performance of the circuit board 2 in the extreme environment, thereby further improving the comprehensiveness of the detection of the circuit board 2.

[0038] And after simulating the state of the circuit board 2 being used in an extreme environment, the circuit board 2 needs to be dried, and the electric slider III 402 is controlled to start and move along the electric slide rail III 401 to reset, so that the cover 403 moves away from the box body 1, and the partition 405 and the shielding plate 406 are synchronously moved away from the circuit board 2, and then all the electric sliders II 204 are controlled to move along the corresponding electric slide rail II 203, so that the two circuit boards 2 move away from each other, and thus both circuit boards 2 are away from the vertical plate 12, and then all the electric actuators 501 are controlled to start and drive the corresponding racks 502 to move, so that the two racks 502 move toward the direction of the spur gear I 210 on the same side until the racks 50 2 is meshed with the corresponding spur gear I 210, and then all the electric sliders II 204 are controlled to move along the corresponding electric slide rails II 203, thereby making all the spur gears I 210 move and rotate along the corresponding racks 502, thereby making the two circuit boards 2 rotate and tilt, so that the moisture remaining on the surfaces of the two circuit boards 2 can automatically flow away, and the two air inlet pipes 409 are still in the jet state, and then the gas is blown toward the circuit board 2 again to dry the circuit board 2, thereby achieving timely drying of the circuit board 2 after the waterproof performance test of the circuit board 2, avoiding moisture from staying on the circuit board 2 for a long time, and reducing the possibility of malfunction caused by residual moisture.

[0039] The above embodiments are intended only to illustrate the technical concepts and features of the present invention. Their purpose is to enable those skilled in the art to understand the contents of the present invention and implement them accordingly. They are not intended to limit the scope of protection of the present invention. Any equivalent changes or modifications made in accordance with the spirit of the present invention are intended to be covered by the scope of protection of the present invention.

Claims

1. A waterproof performance testing device for a new energy vehicle circuit board, comprising a box body (1) and a box door (11); the box door (11) is installed on the box body (1); characterized in that, The invention also includes a drive assembly, a fixed plate (205), a connecting shaft (206), an electric clamp (207), a conduit (208), a spray pipe (209), a spur gear I (210), a motor I (211) and a spur gear II (212); at least two drive assemblies are installed on the box body (1); at least two fixed plates (205) are installed on each drive assembly, and the drive assembly is used to drive the fixed plates (205) to move; each fixed plate (205) is connected to a connecting shaft (2 06); an electric clamp (207) is installed at one end of each connecting shaft (206) away from the fixed plate (205); a guide tube (208) is installed on the box body (1), and a two-way nozzle is provided in the middle of the guide tube (208), and one-way nozzles are provided at both ends of the guide tube (208); a spur gear I (210) is fixedly connected to each connecting shaft (206); a motor I (211) is installed on the box body (1); a spur gear II (212) is fixedly connected to the output shaft of the motor I (211).

2. A new energy vehicle circuit board waterproof performance testing device according to claim 1, characterized in that: A wavy rubber block is provided on the clamping portion of the electric clamp (207).

3. A new energy vehicle circuit board waterproof performance testing device according to claim 2, characterized in that: The invention also includes a vibration simulation system; the vibration simulation system is connected to the box body (1); the vibration simulation system includes a long strip (301), a protrusion (302), a cross bar (303), a sliding block (304), a fixing ring (305) and an elastic member (306); at least two long strips (301) are fixed to the box body (1); a plurality of protrusions (302) are fixed to each long strip (301); at least two cross bars (303) are fixed to each fixing plate (205); each Each cross bar (303) is slidably connected to a sliding block (304); all sliding blocks (304) in the same fixed plate (205) are fixedly connected to a fixed ring (305); each fixed ring (305) is rotatably connected to a corresponding connecting shaft (206); an elastic member (306) is sleeved on the outside of each cross bar (303), one end of the elastic member (306) is fixedly connected to the sliding block (304), and the other end of the elastic member (306) is fixedly connected to the fixed plate (205).

4. A new energy vehicle circuit board waterproof performance testing device according to claim 3, characterized in that: The sizes of the bumps (302) vary.

5. A new energy vehicle circuit board waterproof performance testing device according to claim 4, characterized in that: The partition detection system is also included; the partition detection system is connected to the box body (1); the partition detection system includes a vertical plate (12), a horizontal plate (13), an electric slide rail III (401), an electric slider III (402), a cover (403), a shielding curtain (404), a partition (405), a shielding plate (406), a sealing member (407), an air pipe (408) and an air inlet pipe (409); the vertical plate (12) is fixed to the box body (1); the horizontal plate (13) is fixed to the box body (1); the electric slide rail III (401) is fixed to the box body (1); the electric slider III (402) is slidably connected to the electric slide rail III (401); the electric slider III (402) is fixed to the electric slider III (402). A cover shell (403) is connected; the cover shell (403) is slidably connected to the box body (1); a shielding curtain (404) is fixedly connected to the cover shell (403), and a spring piece is provided in the shielding curtain (404); a partition (405) is fixedly connected to the cover shell (403); a shielding plate (406) is fixedly connected to the cover shell (403); a plurality of sealing members (407) are fixedly connected to the cover shell (403); at least two air pipes (408) are installed on the box body (1); each air pipe (408) is fixedly connected to and communicated with an air inlet pipe (409); all the air inlet pipes (409) are fixedly connected to the transverse plate (13), and all the air inlet pipes (409) pass through the box body (1) and the transverse plate (13).

6. A new energy vehicle circuit board waterproof performance testing device according to claim 5, characterized in that: A guide rail is provided at the connection between the cover shell (403) and the box body (1).

7. A new energy vehicle circuit board waterproof performance testing device according to claim 5, characterized in that: A sealing strip is installed on the vertical plate (12).

8. A new energy vehicle circuit board waterproof performance testing device according to claim 5, characterized in that: A sealing strip is provided on the side of the transverse plate (13) away from the box body (1).

9. A new energy vehicle circuit board waterproof performance testing device according to claim 5, characterized in that: The shielding curtain (404) is set to be transparent.

10. A new energy vehicle circuit board waterproof performance testing device according to any one of claims 5 to 9, characterized in that: It also includes an electric actuator (501) and a rack (502); at least two electric actuators (501) are installed on the box body (1), and the telescopic parts of all the electric actuators (501) on the same side are fixedly connected to a rack (502).