Rope head structure with horizontally-arranged upper beam
By designing the horizontal placement structure of the rope head assembly and the guide assembly in the upper beam assembly, the problem of the space occupied by the direction-changing bracket is solved, and the space-minimized installation of the rope head assembly is achieved. It is suitable for home ladders and old building elevators with low top spaces. Transformation.
Patent Information
- Application Number
- CN202420295787.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-18
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-02-18
AI Technical Summary
When the existing home elevator rope head assembly is placed horizontally and horizontally, the direction-changing bracket occupies part of the top space, resulting in a large space occupied, making it difficult to meet the design requirements of the low-ceiling space.
Design a rope head structure with the upper beam placed horizontally. By setting the rope head assembly, guide assembly and buffer spring in the upper beam assembly, the steel wire rope is turned upward through the guide wheel to connect to the elevator traction machine. The rope head assembly is completely placed in the upper beam assembly. Take up extra space and transform with simple hole installation.
It realizes the horizontal placement of the rope head assembly, minimizes the occupied space, and is simple to install. It is suitable for the renovation of household ladders and old building elevators in low top spaces.
Smart Images

Figure CN221796677U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of elevator rope ends, in particular to a rope end structure with an upper beam placed horizontally. Background Art
[0002] The elevator rope assembly is mainly composed of elevator rope, rope box, rope head and rope clamp. The elevator rope assembly is an important part of the elevator operation, and plays a very important role in elevator safety, running stability, noise and life. The current general rope head device length is about 450mm, plus the length of the steel cable clamp, the total length is about 550. The home elevator should use the existing space to design the elevator. When the top floor space is relatively low, the space occupied by vertical placement is crucial.
[0003] The patent specification with announcement number CN214652850U discloses a household elevator rope head assembly, including a rope head bracket, a pull rod, a wedge sleeve and a changing bracket; the rope head bracket includes a bottom plate, a rope head plate and a first connecting plate are respectively provided at both ends of the bottom plate, the pull rod and the wedge sleeve are both horizontally arranged, the pull rod is passed through the rope head plate, one end of the pull rod is connected to the wedge sleeve, and the wedge sleeve is connected to a wire rope; the changing bracket includes a base, a second connecting plate fixed to the first connecting plate is provided on the side of the base, and two mutually parallel guard plates are provided on the top of the base, a changing shaft is connected between the two guard plates, the changing shaft is horizontally arranged, and the axis of the changing shaft is perpendicular to the axis of the pull rod, and a wire rope channel corresponding to the changing shaft is provided on the base. When installing the rope head assembly of the utility model, the first connecting plate and the second connecting plate are first fastened together by fastening bolts and fastening nuts to fix the rope head bracket and the changing bracket in connection, and then the changing bracket is fixed to the hoistway wall or the elevator guide rail, thereby completing the installation of the rope head assembly. The utility model has a reasonable structure and can reduce the requirement for the top floor height of the elevator hoistway.
[0004] However, in the implementation of relevant technologies, it was found that the above-designed household elevator rope end assembly had the following problems: the elevator rope end assembly was connected to a changing bracket, and the changing bracket was used to realize the horizontal placement of the elevator rope end. Although it reduced the space occupancy compared to the original vertical one, the changing bracket still needed to occupy a part of the top space. In view of this, a rope end structure with a horizontally placed upper beam was provided to overcome the above-mentioned defects. Utility Model Content
[0005] The utility model aims to solve the shortcomings in the prior art and proposes a rope head structure with an upper beam placed horizontally.
[0006] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a rope head structure with an upper beam placed horizontally, comprising an upper beam assembly, a rope head assembly is arranged inside the upper beam assembly, a guide assembly is arranged on one side of the rope head assembly, and a steel wire rope is sleeved on the outside of the guide assembly, one end of the steel wire rope is connected to the rope head assembly through the guide assembly, the rope head assembly comprises a mounting bracket, a pull rod inserted into the mounting bracket, and a rope head wedge sleeve arranged on one side of the pull rod, a buffer spring is arranged on the side of the mounting bracket away from the rope head wedge sleeve, and the rope head assembly is installed in the upper beam assembly through the mounting bracket;
[0007] The guide assembly includes a guide wheel installed inside the upper beam assembly, and a mounting rod is provided inside the guide wheel. Both front and rear ends of the mounting rod are sleeved with fixing rings, and the guide assembly is installed in the upper beam assembly through the mounting rod.
[0008] As a further description of the above technical solution: threads are provided on the surfaces of the front and rear ends of the mounting rod, and the mounting rod is threadedly connected to the fixing ring. The mounting rod passes through the interior of the upper beam assembly, and the fixing ring can be directly installed on the outside of the mounting rod to fix the mounting rod.
[0009] As a further description of the above technical solution: a fastening bolt is installed on the side of the buffer spring away from the mounting bracket, and the fastening bolt is elastically connected to the mounting bracket through the buffer spring, and the buffer spring can play a certain buffering and shock-absorbing role.
[0010] As a further description of the above technical solution: the buffer spring is sleeved on the outside of the pull rod, and the pull rod is threadedly connected to the fastening bolt, and the fastening bolt can limit the buffer spring.
[0011] As a further description of the above technical solution: the end of the wire rope is fixedly connected to the rope end wedge sleeve, and the other end of the wire rope is fixedly connected to the elevator traction machine. The two ends of the wire rope are respectively connected to the rope end wedge sleeve and the elevator traction machine for pulling the elevator car.
[0012] As a further description of the above technical solution: the cross-section of the mounting bracket is a T-shaped structure, and the mounting bracket is embedded in the interior of the upper beam assembly. Connection holes are opened at the four corners of the top of the mounting bracket. The mounting bracket is located inside the upper beam assembly, and bolts can be installed through the connection holes to fix the mounting bracket to the upper beam assembly.
[0013] As a further description of the above technical solution: through holes are provided at the connection between the upper beam assembly, the rope head assembly and the guide assembly. One group of through holes is located at the top of the upper beam assembly and is used to connect the installation bracket, and the position size is compatible with the connection hole on the installation bracket. The other group of through holes is located on the front and rear sides of the upper beam assembly and is used to pass the installation rod.
[0014] The utility model has the following beneficial effects:
[0015] The utility model designs a rope head structure with an upper beam placed horizontally. The rope head component structure is placed horizontally inside the upper beam assembly. The overall processing and manufacturing are simple, and the installation is simple. The wire rope is fixed on the rope head wedge sleeve. Through the guide wheel, the wire rope is turned upward from the horizontal direction to connect with the elevator traction machine. The rope head component is completely placed inside the upper beam assembly and does not take up any space. It is also relatively simple to transform. It can be installed by only drilling a hole inside the original upper beam assembly. This provides a feasible solution for household elevators and old buildings to install elevators. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;
[0017] Figure 2 This is a structural schematic diagram of the rope head assembly of the utility model;
[0018] Figure 3 This is a schematic diagram of the structure of the guide assembly of the utility model;
[0019] Figure 4 It is a schematic diagram of the structure of the utility model when installed.
[0020] Legend:
[0021] 1. Assemble the upper beam; 2. Install the bracket; 3. Rope head wedge; 4. Install the plug rod; 5. Pull rod; 6. Buffer spring; 7. Guide wheel; 8. Fixing ring; 9. Wire rope. DETAILED DESCRIPTION
[0022] Reference Figure 1-4 The utility model provides a rope head structure with an upper beam placed horizontally: it includes an upper beam assembly 1, a rope head component is arranged inside the upper beam assembly 1, a guide component is arranged on one side of the rope head component, and a steel wire rope 9 is sleeved on the outside of the guide component, one end of the steel wire rope 9 is connected to the rope head component through the guide component, the rope head component includes a mounting bracket 2, a pull rod 5 inserted into the mounting bracket 2, and a rope head wedge sleeve 3 arranged on one side of the pull rod 5, a buffer spring 6 is arranged on the side of the mounting bracket 2 away from the rope head wedge sleeve 3, and the rope head component is installed in the upper beam assembly 1 through the mounting bracket 2;
[0023] The guide assembly includes a guide wheel 7 installed inside the upper beam assembly 1, and a mounting rod 4 is provided inside the guide wheel 7. The front and rear ends of the mounting rod 4 are both provided with fixing rings 8. The guide assembly is installed in the upper beam assembly 1 through the mounting rod 4.
[0024] As a further implementation scheme of the above technical scheme: threads are provided on the surfaces of the front and rear ends of the mounting rod 4, and the mounting rod 4 is threadedly connected to the fixing ring 8, the mounting rod 4 passes through the interior of the upper beam assembly 1, and the fixing ring 8 can be directly installed on the outside of the mounting rod 4 to fix the mounting rod 4.
[0025] As a further implementation scheme of the above technical scheme: a fastening bolt is installed on the side of the buffer spring 6 away from the mounting bracket 2, and the fastening bolt is elastically connected to the mounting bracket 2 through the buffer spring 6. The buffer spring 6 can play a certain buffering and shock-absorbing role.
[0026] As a further implementation scheme of the above technical scheme: the buffer spring 6 is sleeved on the outside of the pull rod 5, and the pull rod 5 is threadedly connected with the fastening bolt, and the fastening bolt can limit the buffer spring 6.
[0027] As a further implementation scheme of the above technical scheme: the end of the wire rope 9 is fixedly connected to the rope end wedge sleeve 3, and the other end of the wire rope 9 is fixedly connected to the elevator traction machine, and the two ends of the wire rope 9 are respectively connected to the rope end wedge sleeve 3 and the elevator traction machine for pulling the elevator car.
[0028] As a further implementation scheme of the above technical scheme: the cross-section of the mounting bracket 2 is a T-shaped structure, and the mounting bracket 2 is embedded in the interior of the upper beam assembly 1, and connecting holes are opened at the four corners of the top of the mounting bracket 2. The mounting bracket 2 is located inside the upper beam assembly 1, and bolts can be installed through the connecting holes to fix the mounting bracket 2 on the upper beam assembly 1.
[0029] As a further implementation scheme of the above technical scheme: through holes are opened at the connection between the upper beam assembly 1 and the rope head assembly and the guide assembly, one group of through holes is located at the top of the upper beam assembly 1 and is used to connect the installation bracket 2, and the position size is compatible with the connection hole on the installation bracket 2, and the other group of through holes is located on the front and rear sides of the upper beam assembly 1, and is used to pass the installation rod 4.
[0030] When the elevator is installed, the lifting device 1 is installed on the upper beam assembly 1, and the lifting device 1 is installed on the upper beam assembly 1. When the lifting device 1 is installed, the lifting device 1 is installed on the upper beam assembly 1, and the lifting device 1 is installed on the upper beam assembly 1. When the lifting device 1 is installed, the lifting device 1 is installed on the upper beam assembly 1, and the lifting device 1 is installed on the upper beam assembly 1. When the lifting device 1 is installed, the lifting device 1 is installed on the upper beam assembly 1, and the lifting device 1 is installed on the upper beam assembly 1. When the lifting device 1 is installed, the lifting device 1 is installed on the upper beam assembly 1, and the lifting device 1 is installed on the upper beam assembly 1. When the lifting device 1 is installed, the lifting device 1 is installed
[0031] Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A rope head structure with an upper beam placed horizontally, comprising an upper beam assembly (1), a rope head assembly being arranged inside the upper beam assembly (1), a guide assembly being arranged on one side of the rope head assembly, and a steel wire rope (9) being sleeved on the outside of the guide assembly, characterized in that: The rope head assembly comprises a mounting bracket (2), a pull rod (5) inserted into the mounting bracket (2), and a rope head wedge sleeve (3) arranged on one side of the pull rod (5); a buffer spring (6) is arranged on the side of the mounting bracket (2) away from the rope head wedge sleeve (3); The guide assembly comprises a guide wheel (7) installed inside the upper beam assembly (1), and a mounting rod (4) is arranged inside the guide wheel (7), and the front and rear ends of the mounting rod (4) are both sleeved with fixing rings (8).
2. The rope head structure with the upper beam placed horizontally according to claim 1, characterized in that: The surfaces of the front and rear ends of the installation rod (4) are both provided with threads, and the installation rod (4) is threadedly connected to the fixing ring (8), and the installation rod (4) passes through the interior of the upper beam assembly (1).
3. The rope head structure with the upper beam placed horizontally according to claim 1, characterized in that: A fastening bolt is installed on the side of the buffer spring (6) away from the mounting bracket (2), and the fastening bolt is elastically connected to the mounting bracket (2) through the buffer spring (6).
4. The rope head structure with the upper beam placed horizontally according to claim 3, characterized in that: The buffer spring (6) is sleeved on the outside of the pull rod (5), and the pull rod (5) is threadedly connected to the fastening bolt.
5. The rope head structure with the upper beam placed horizontally according to claim 1, characterized in that: The end of the steel wire rope (9) is fixedly connected to the rope end wedge sleeve (3), and the other end of the steel wire rope (9) is fixedly connected to the elevator traction machine.
6. The rope head structure with the upper beam placed horizontally according to claim 1, characterized in that: The cross section of the mounting bracket (2) is a T-shaped structure, and the mounting bracket (2) is embedded in the interior of the upper beam assembly (1), and connection holes are provided at the four corners of the top of the mounting bracket (2).
7. The rope head structure with the upper beam placed horizontally according to claim 1, characterized in that: Through holes are provided at the connection points between the upper beam assembly (1), the rope head assembly and the guide assembly.