Concrete high pile cap of large tower crane equipment
By designing a high-concrete pile cap for large-scale tower crane equipment, including a concrete base plate, a tower crane foundation cap and multiple concrete cast-in-place piles, and connecting them through horizontal bracing and planting bars, the problem of limited loads for large tower crane equipment and foundation pit sites has been solved. problem, achieving a more stable structure and a simplified construction process.
Patent Information
- Application Number
- CN202420245423.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-31
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-01-31
AI Technical Summary
The existing technology cannot meet the load requirements of large-scale tower crane equipment, and the surrounding and bottom sites of the foundation pit are limited so that the tower crane foundation cannot be installed, making it impossible to install large-scale tower crane equipment.
A high-concrete pile cap for large-scale tower crane equipment is designed, including a concrete base plate, a tower crane foundation cap and multiple concrete cast-in-place piles, which are connected through horizontal bracing and planting bars to enhance structural stability and load-bearing capacity.
It provides a more stable structure that can withstand greater loads, meets the installation requirements of large tower crane equipment, solves the problem of limited space around the foundation pit and at the bottom, simplifies the construction of the basement structure, and reduces the construction cost and construction period.
Smart Images

Figure CN221798499U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to a concrete high pile cap for large tower crane equipment. Background Art
[0002] During the construction of deep foundation pit projects, it is often encountered that due to the limited space around the foundation pit and the limitation of the foundation pit's own support structure, it is impossible to set up a tower crane foundation around the foundation pit and at the bottom of the foundation pit for installing the tower crane. In order to achieve the installation of the tower crane, a high pile cap in the form of a steel lattice is generally used. However, the high pile cap in the form of a steel lattice can generally only meet the installation and use of small tower cranes in terms of load bearing and structural stability, and cannot meet the installation and use of large tower crane equipment with larger loads. Summary of the invention
[0003] The embodiment of the present application provides a large tower crane equipment concrete high pile cap to solve the problems existing in the related technology. The technical solution is as follows:
[0004] An embodiment of the present application provides a concrete high pile pedestal for a large tower crane equipment, comprising a concrete base plate, a tower crane foundation pedestal and a plurality of concrete bored piles, wherein the bottoms of the plurality of concrete bored piles are fixed on the concrete base plate, the tower crane foundation pedestal is fixed on the tops of the plurality of concrete bored piles, the plurality of concrete bored piles are respectively located in the middle and four corners of the concrete base plate, the plurality of concrete bored piles are fixedly connected by horizontal surrounding supports, and the horizontal surrounding supports and the concrete bored piles are connected by embedded reinforcement bars.
[0005] In one embodiment, the number of the horizontal supports is four, and the four horizontal supports are arranged at intervals along the height direction of the concrete pile.
[0006] In one embodiment, the horizontal bracing includes at least a maintenance structure, which is mounted on the concrete piles at the four corners. The maintenance structure has spiral stirrups, and straight anchor steel bars are fixed on the concrete piles. The straight anchor steel bars are fixedly connected to the spiral stirrups.
[0007] In one embodiment, the horizontal bracing further includes a plurality of bracing beams, the two ends of the bracing beams are respectively connected to two adjacent maintenance structures, and / or the two ends of the bracing beams are respectively connected to the maintenance structure and the concrete cast-in-place piles in the middle.
[0008] In one embodiment, the maintenance structure is further provided with connecting longitudinal reinforcements, and the ends of the surrounding bracing beams are connected to the connecting longitudinal reinforcements.
[0009] In one embodiment, the connecting longitudinal reinforcement is located at the upper part and the lower part of the spiral stirrup, and the connecting longitudinal reinforcement is welded to the spiral stirrup.
[0010] In one embodiment, the longitudinal reinforcement is connected to the spiral stirrup by single-sided welding, and the welding length is not less than 10d.
[0011] In one embodiment, the spiral stirrups are located in the middle of the maintenance structure, and the straight anchor steel bars are welded to the spiral stirrups.
[0012] In one embodiment, the number of horizontal supports is four, and the distance between adjacent horizontal supports is 3 meters.
[0013] In one embodiment, the upper surface of the tower crane foundation cap has a tower crane fixed support leg.
[0014] The advantages or beneficial effects of the above technical solution include at least:
[0015] The large tower crane equipment concrete high pile cap of the present application includes a concrete bottom plate, a tower crane foundation cap and a plurality of concrete cast-in-place piles. Compared with the high pile cap in the form of a steel lattice structure in the prior art, the concrete high pile cap of the present application has a more stable structure, can withstand a larger load, and can meet the installation requirements of large tower crane equipment. The present application provides a possibility for installing large tower crane equipment, and solves the problem that the tower crane foundation cannot be set around the foundation pit and at the bottom of the foundation pit for installing a large tower crane due to the limited space around the foundation pit and the limitation of the foundation pit's own support structure.
[0016] The above summary is for illustrative purposes only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments and features described above, further aspects, embodiments and features of the present application will be readily apparent by reference to the accompanying drawings and the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In the accompanying drawings, unless otherwise specified, the same reference numerals throughout the multiple drawings represent the same or similar parts or elements. These drawings are not necessarily drawn to scale. It should be understood that these drawings only depict some embodiments disclosed in the present application and should not be regarded as limiting the scope of the present application.
[0018] Figure 1 This is a structural diagram of the concrete high pile cap for large tower crane equipment;
[0019] Figure 2 for Figure 1 Plan view of the middle horizontal brace;
[0020] Figure 3 This is a schematic diagram of the steel bar arrangement at the junction of the horizontal bracing and the concrete cast-in-place piles;
[0021] Figure 4 for Figure 3 Sectional view in the AA direction;
[0022] Figure 5 It is a top view of the steel bar arrangement at the junction of the horizontal bracing and the concrete cast-in-place piles;
[0023] Figure 6 for Figure 3 Construction process diagram of the reverse method of the middle horizontal bracing;
[0024] Description of reference numerals:
[0025] 1. Concrete base plate; 2. Tower crane foundation pedestal; 3. Concrete piles; 4. Horizontal bracing; 41. Maintenance structure; 410. Spiral stirrups; 5. Straight anchor steel bars; 42. Bracing beam; 412. Connecting longitudinal bars. DETAILED DESCRIPTION
[0026] In the following, only some exemplary embodiments are briefly described. As those skilled in the art will appreciate, the described embodiments may be modified in various ways without departing from the spirit or scope of the present application. Therefore, the drawings and descriptions are considered to be exemplary and non-restrictive in nature.
[0027] like Figures 1 to 6 As shown, an embodiment of the present application provides a large tower crane equipment concrete high pile cap, including a concrete base plate 1, a tower crane foundation cap 2 and a plurality of concrete bored piles 3. Preferably, the number of concrete bored piles 3 is five, and the bottoms of the five concrete bored piles 3 are all fixed on the concrete base plate 1. Furthermore, one of the concrete bored piles 3 is fixed to the middle position of the concrete base plate 1, and the other four concrete bored piles 3 are respectively located at the four corners of the concrete base plate 1. The tower crane foundation cap 2 is fixed to the top of the plurality of concrete bored piles 3, and the tower crane foundation cap 2 is supported by the five concrete bored piles 3.
[0028] In order to fix the five concrete piles 3, the large tower crane equipment concrete high pile cap of the present application further includes a horizontal surrounding support 4, and the multiple concrete piles 3 are fixedly connected by the horizontal surrounding support 4. The horizontal surrounding support 4 is connected to the concrete piles 3 by planting steel bars.
[0029] In one embodiment, the number of the horizontal supports 4 is four, and the four horizontal supports 4 are arranged at intervals along the height direction of the concrete pile 3. Preferably, the distance between the upper and lower adjacent horizontal supports 4 is 3 meters.
[0030] In order to realize the connection between the horizontal support 4 and the concrete pile 3, the horizontal support 4 of the present application at least includes a maintenance structure 41, which is sleeved on the concrete piles 3 at the four corners. The middle part of the maintenance structure 41 has a spiral stirrup 410, and the concrete pile 3 is fixed with a straight anchor steel bar 5, which is fixedly connected to the spiral stirrup 410. Preferably, the straight anchor steel bar 5 is welded to the spiral stirrup 410.
[0031] In order to realize the connection and fixation of multiple maintenance structures 41 and the connection and fixation of the maintenance structure 41 with the concrete cast-in-place pile 3 located in the middle, the horizontal surrounding support 4 also includes multiple surrounding support beams 42. The two ends of the surrounding support beam 42 are respectively connected to two adjacent maintenance structures 41, and the maintenance structure 41 and the concrete cast-in-place pile 3 located in the middle are also connected and fixed by the surrounding support beam 42. In one embodiment, the surrounding support beam 42 and the concrete cast-in-place pile 3 located in the middle can be connected by planting reinforcement.
[0032] In one embodiment, in order to achieve the connection between the maintenance structure 41 and the surrounding support beam 42, the maintenance structure 41 is further provided with a connecting longitudinal reinforcement 412, and the end of the surrounding support beam 42 is connected to the connecting longitudinal reinforcement 412. Further, the connecting longitudinal reinforcement 412 is located at the upper and lower parts of the spiral stirrup 410, and the connecting longitudinal reinforcement 412 is welded to the spiral stirrup 410. The connecting longitudinal reinforcement 412 is welded to the spiral stirrup 410 on one side, and the welding length is not less than 10d.
[0033] The tower crane is installed on the upper surface of the tower crane foundation pedestal 2. In order to realize the installation of the tower crane, a tower crane fixing leg is provided on the upper surface of the tower crane foundation pedestal 2. The tower crane is installed on the upper surface of the tower crane foundation pedestal 2 through the tower crane fixing leg.
[0034] When the large tower crane equipment concrete high pile cap of the present application is constructed, the construction method includes the following steps:
[0035] Step 1: Measurement, positioning and laying out
[0036] Combined with the design blueprint, determine the precise location of the tower crane. The location of the tower crane pile foundation should avoid the civil defense wall, equipment room, fire water tank, foundation pit support and other parts. Determine the installation location of the tower crane according to the actual situation of the construction site. Then, through on-site measurement and positioning, the coordinate position needs to be reviewed to ensure the accurate construction position of the pile foundation.
[0037] Step 2: Tower crane pile foundation construction and inspection
[0038] According to the site conditions and the requirements of the tower crane selection, the specific construction position of the tower crane pile is measured and located. Five concrete cast-in-place piles 3 are selected as tower crane piles on site. According to the geological conditions of the site, the concrete cast-in-place piles 3 are embedded from the bottom plate position of the tower crane foundation pedestal 2, and the depth should not be less than the depth required by the specification. The pile foundation of the concrete cast-in-place pile 3 should be tested for pile body integrity using a low-strain method.
[0039] The deviation of the concrete pile 3 must be within the allowable deviation range, and two adjacent concrete piles 3 cannot deviate in the same direction. When testing the integrity of the concrete pile 3, the ultrasonic projection method is used for testing, and three concrete piles 3 are selected to be pre-buried with ultrasonic catheters to determine whether there are cavities in the pile body through ultrasonic testing.
[0040] The existence of the 3 deviation of concrete cast-in-place piles will affect the bearing capacity and stability of the pile foundation, so it must be strictly controlled. Ensure the implementation of bored cast-in-place pile engineering requirements and strictly control the allowable deviation range of the hole depth.
[0041] During the hole cleaning process of the tower crane pile foundation construction, the mud should be replaced continuously until the underwater concrete is poured. The mud ratio of the concrete pile 3 needs to be determined according to the stratum conditions and the stability of the hole wall. In the soil layer that is prone to mud leakage, measures should be taken to maintain the stability of the hole wall.
[0042] 3. When the drilling depth reaches the requirement, the hole should be inspected and the sediment and silt at the bottom of the hole should be removed. The sediment at the bottom of the hole should meet the requirements.
[0043] Step 3: Construction of tower crane foundation pedestal 2
[0044] After the construction and inspection of the tower crane pile foundation are completed, the construction of the tower crane foundation pedestal 2 is carried out, and five concrete cast-in-place piles 3 are used as the construction of the tower crane foundation pedestal 2.
[0045] During the construction of the tower crane foundation pedestal 2, after the cushion layer of the tower crane foundation pedestal 2 is completed, the steel bars are tied to anchor the column head bars of the concrete piles 3 into the tower crane foundation pedestal 2, and then the formwork support and concrete pouring processes are carried out.
[0046] The stirrups of the concrete pile 3 anchored in the tower crane foundation pedestal 2 play a role in connecting the concrete pile 3 and the tower crane foundation pedestal 2 in the structure, which can prevent the concrete pile 3 from moving or tilting due to force. At the same time, it also bears a certain bending moment and shear force, ensuring the stability of the tower crane foundation pedestal 2.
[0047] Step 4: Tower crane installation
[0048] After the construction of the tower crane foundation pedestal 2 is completed and the required strength is reached, the tower crane can be installed to meet the needs of transporting materials in the later stage.
[0049] Step 5: Earth excavation and horizontal support 4 construction
[0050] There are four horizontal braces 4, which are used to strengthen the connection between the concrete piles 3. The horizontal braces 4 are connected with the concrete piles 3 by planting steel bars. First, the concrete piles 3 need to be positioned and drilled, then glue injection and steel bar insertion, finished product protection and pull-out resistance testing are performed, and finally the horizontal braces 4 are constructed, the template is set, and the concrete is poured.
[0051] The horizontal bracing 4 is connected and fixed to the concrete pile 3 by welding the straight anchor steel bar 5 in the concrete pile 3 and then welding the straight anchor steel bar 5 to the spiral stirrup 410 of the maintenance structure 41. The maintenance structure 41 and the bracing beam 42 are connected by connecting longitudinal bars 412 welded to the bolt stirrups, and then the formwork and concrete are poured.
[0052] Step 6: Concrete Base Plate 1 Reinforcement
[0053] Due to the use of high pile caps in the tower crane foundation construction, in order to ensure the overall stability and safety of the tower crane, the concrete bottom plate 1 within the projection range of the tower crane foundation cap 2 and the outside expansion range of the pile edge needs to be thickened.
[0054] The large tower crane equipment concrete high pile cap of the present application includes a concrete bottom plate 1, a tower crane foundation cap 2 and a plurality of concrete cast-in-place piles 3. Compared with the high pile cap in the form of a steel lattice structure in the prior art, the concrete high pile cap of the present application has a more stable structure, can withstand a larger load, and can meet the installation requirements of large tower crane equipment. The present application provides a possibility for installing large tower crane equipment, and solves the problem that the tower crane foundation cannot be set around the foundation pit and at the bottom of the foundation pit for installing a large tower crane due to the limited space around the foundation pit and the limitation of the foundation pit's own support structure.
[0055] This application realizes the construction of concrete cast-in-place piles 3, tower crane foundation pedestal 2 and horizontal bracing 4 through reverse construction, which makes it possible to install large tower crane equipment in advance. At the same time, it solves the problem that large tower cranes required in the basement structure construction stage cannot be installed, provides convenience for the construction of the basement structure, guarantees the construction period, reduces the input of labor and materials in the basement construction stage, and reduces the construction cost investment.
[0056] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples, unless they are contradictory.
[0057] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0058] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of various changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A large tower crane equipment concrete high pile cap, characterized in that: It includes a concrete base plate, a tower crane foundation pedestal and multiple concrete bored piles. The bottoms of the multiple concrete bored piles are fixed on the concrete base plate, the tower crane foundation pedestal is fixed on the tops of the multiple concrete bored piles, the multiple concrete bored piles are respectively located in the middle and four corners of the concrete base plate, the multiple concrete bored piles are fixedly connected by horizontal bracing, and the horizontal bracing and the concrete bored piles are connected by embedded reinforcement.
2. The large tower crane equipment concrete high pile cap according to claim 1 is characterized in that: The number of the horizontal supports is four, and the four horizontal supports are arranged at intervals along the height direction of the concrete cast-in-place piles.
3. The large tower crane equipment concrete high pile cap according to claim 1 is characterized in that: The horizontal bracing at least includes a maintenance structure, which is sleeved on the concrete piles at the four corners. The maintenance structure is provided with spiral stirrups, and straight anchor steel bars are fixed on the concrete piles. The straight anchor steel bars are fixedly connected to the spiral stirrups.
4. The large tower crane equipment concrete high pile cap according to claim 3 is characterized in that: The horizontal bracing also includes a plurality of bracing beams, the two ends of which are respectively connected to two adjacent maintenance structures, and / or the two ends of which are respectively connected to the maintenance structure and the concrete cast-in-place piles in the middle.
5. The large tower crane equipment concrete high pile cap according to claim 4 is characterized in that: The maintenance structure also has connecting longitudinal reinforcement, and the ends of the bracing beams are connected to the connecting longitudinal reinforcement.
6. The large tower crane equipment concrete high pile cap according to claim 5, characterized in that: The connecting longitudinal reinforcement is located at the upper and lower parts of the spiral stirrups, and the connecting longitudinal reinforcement is welded to the spiral stirrups.
7. The large tower crane equipment concrete high pile cap according to claim 6, characterized in that: The longitudinal reinforcement and spiral stirrups are connected by single-sided welding, and the welding length shall not be less than 10d.
8. The large tower crane equipment concrete high pile cap according to claim 3, characterized in that: The spiral stirrups are located in the middle of the maintenance structure, and the straight anchor steel bars are welded to the spiral stirrups.
9. The large tower crane equipment concrete high pile cap according to any one of claims 1 to 8, characterized in that: The number of horizontal supports is four, and the distance between adjacent horizontal supports is 3 meters.
10. The large tower crane equipment concrete high pile cap according to any one of claims 1 to 8, characterized in that: The upper surface of the tower crane foundation cap is provided with tower crane fixed legs.