Earth excavation backfilling device for half-cover excavation deep foundation pit

By designing simultaneous backfilling and tamping devices in deep foundation pit construction, using screw conveyor rods and motor drive components to process wet soil, and combining tamping rollers and scrapers to improve tamping efficiency, the long construction period of backfilling earthwork in deep foundation pit construction has been solved. problems, improving construction efficiency and reducing costs.

CN221837599UActive Publication Date: 2024-10-15HUBEI DABAN PROJECT MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323668982.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-10-15
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In the construction of deep foundation pits, the backfilling earthwork period is long, and compaction can only be carried out after the backfilling is completed, resulting in low construction efficiency.

Method used

Design a half-cover deep foundation pit earth excavation backfilling device. By setting up a backfilling mechanism and a tamping mechanism on the vehicle body, the backfilling and tamping can be performed simultaneously. The screw conveyor rod and motor drive assembly are used to solve the problem of wet soil adhesion and compaction. Rollers and moldboards improve compaction efficiency and quality.

Benefits of technology

Improved construction efficiency, shortened the construction period, reduced construction costs, and extended the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221837599U_ABST
    Figure CN221837599U_ABST
Patent Text Reader

Abstract

The utility model relates to a half-cover deep excavation foundation pit earthwork excavation backfilling device, and belongs to the field of foundation pit construction, the half-cover deep excavation foundation pit earthwork excavation backfilling device comprises a vehicle body and a backfilling mechanism arranged on the vehicle body and used for backfilling earthwork into a foundation pit, and the vehicle body is provided with a tamping mechanism used for tamping the earthwork in the foundation pit. And under the combined action of the backfilling mechanism and the tamping mechanism, backfilling and tamping are conducted synchronously, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of foundation pit construction, and in particular to a device for excavating and backfilling earthwork in a semi-covered deep foundation pit. Background Art

[0002] Semi-covered excavation is a construction method for deep foundation pit excavation. It refers to temporarily setting up a screen wall on the ground to protect the excavated soil inside the wall from the influence of upper loads and external water and soil pressure, forming a semi-excavated and semi-covered state, reinforcing the excavated slope and reducing the lateral soil pressure, thereby ensuring the stability of the excavated soil.

[0003] After the construction in the deep foundation pit is completed, backfilling of earth is required. Due to the depth of the deep foundation pit, the workload of backfilling is also large. Generally, an excavator or a forklift is used to backfill the earth into the deep foundation pit. After the backfilling is completed, a roller is used to compact the earth in the deep foundation pit.

[0004] Regarding the above-mentioned related technologies, there are the following defects: due to the depth of the deep foundation pit, the backfilling period is long, and the tamping construction can only be carried out after the backfilling construction is completed, which delays the construction period and affects the construction efficiency. Utility Model Content

[0005] In order to improve the problem that backfilling and compaction need to be carried out in steps, the present application provides a semi-covered deep foundation pit earth excavation and backfilling device.

[0006] The present application provides a semi-covered deep foundation pit earth excavation and backfilling device that adopts the following technical solution:

[0007] A device for excavating and backfilling earthwork in a semi-covered deep foundation pit comprises a vehicle body and a backfilling mechanism arranged on the vehicle body for backfilling earthwork into the foundation pit, wherein the vehicle body is provided with a compacting mechanism for compacting the earthwork in the foundation pit.

[0008] By adopting the above technical solution, under the joint action of the backfilling mechanism and the compacting mechanism, backfilling and compacting are carried out simultaneously, thereby improving construction efficiency.

[0009] Optionally: the backfilling mechanism includes a soil storage box arranged at the head of the vehicle body, and a soil outlet is provided on the side of the soil storage box away from the vehicle body.

[0010] By adopting the above technical solution, the earth is temporarily stored in the soil storage box. As the vehicle body moves, the earth passes through the discharge port and falls into the foundation pit. The structure is simple, energy-saving and environmentally friendly.

[0011] Optionally, a plurality of spiral conveying rods are rotatably connected at intervals near the bottom of the soil storage box, the spiral conveying rods extend to the soil discharge port, and a driving assembly for driving the spiral conveying rods to rotate is provided on the soil storage box.

[0012] By adopting the above technical solution, if the soil is very humid, it is very easy to stick together in the soil storage box and cannot be discharged; under the action of the driving component, the spiral conveying rod rotates, thereby discharging the soil normally.

[0013] Optional: The driving assembly includes a driven bevel gear arranged on the spiral conveying rod, a motor is provided on the soil storage box, and a plurality of active bevel gears meshing with the driven bevel gear are arranged on the output shaft of the motor at intervals along the length direction of the output shaft, and the active bevel gear corresponds to the driven bevel gear one by one.

[0014] By adopting the above technical solution, under the driving action of the motor and the transmission action of the active bevel gear and the driven bevel gear, multiple spiral conveying rods rotate simultaneously, thereby discharging the earth. One motor realizes the synchronous rotation of multiple spiral conveying rods, which is energy-saving and environmentally friendly, and is in line with the concept of sustainable development.

[0015] Optionally: the compacting mechanism includes a compacting roller rotatably connected to the soil storage box, and the compacting roller is located between the soil outlet and the vehicle body.

[0016] By adopting the above technical solution, the movement of the vehicle body is locked, and the compacting roller abuts against the earth and rotates, thereby compacting the earth, with high compaction efficiency and high earth flatness.

[0017] Optionally: a scraper plate is provided on the soil storage box, and the scraper plate abuts against the compaction roller.

[0018] By adopting the above technical solution, during the process of compacting earth, the compacting roller is easily attached with earth, which not only affects the compaction quality, but also affects the normal driving of the vehicle body; during the rotation of the compacting roller, the scraper plate scrapes off the earth on the compacting roller, thereby improving the compaction quality and ensuring the normal driving of the vehicle body.

[0019] Optional: The scraper board is slidably connected to the soil storage box, a spring is provided between the scraper board and the soil storage box, one end of the spring is connected to the scraper board, and the other end of the spring is connected to the soil storage box, the spring is in a compressed state, and the spring causes the scraper board to have a tendency to slide toward the compaction roller.

[0020] By adopting the above technical solution, some soil has strong adhesion and is not easy to scrape off. When the scraper board contacts it, the scraper board rebounds under the action of the spring. After multiple contacts, it can be scraped off, reducing the possibility of damage or jamming of the scraper board, extending the service life of the scraper board, and ensuring the normal driving of the vehicle body.

[0021] Optionally, the scraper plate is provided with a pointed end on the side close to the tamping roller.

[0022] By adopting the above technical solution, the contact area between the scraper plate and the compacting roller is reduced, the scraping effect is improved, and the compacting roller rotates more smoothly.

[0023] In summary, this application has the following beneficial effects:

[0024] Under the action of the spiral conveyor roller, the soil in the soil storage box is discharged through the outlet, and the compaction roller compacts the soil in the foundation pit. Backfilling and compaction are carried out simultaneously, which improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 is a cross-sectional view of the overall structure of the embodiment of the present application from a first viewing angle;

[0026] Figure 2 It is a top view of the overall structure from a second viewing angle of an embodiment of the present application.

[0027] Description of reference numerals:

[0028] 1. Vehicle body; 2. Backfilling mechanism; 21. Soil storage box; 22. Discharge port; 23. Screw conveyor rod; 24. Driving assembly; 25. Driven bevel gear; 26. Motor; 27. Output shaft; 28. Driving bevel gear; 3. Tamping mechanism; 31. Tamping roller; 32. Scraper board; 33. Spring; 34. Tip; 41. Discharge pipe; 42. Support rod. DETAILED DESCRIPTION

[0029] The present application is further described in detail below in conjunction with the accompanying drawings.

[0030] This embodiment: a semi-covered deep foundation pit earthwork excavation and backfilling device, referring to Figure 1 and Figure 2 , including: a vehicle body 1 and a backfilling mechanism 2 arranged on the vehicle body 1 for backfilling earth into the foundation pit, and a tamping mechanism 3 for tamping the earth in the foundation pit is arranged on the vehicle body 1. The vehicle body 1 moves, the backfilling mechanism 2 backfills earth into the foundation pit, and the tamping mechanism 3 tamps the earth in the foundation pit. Backfilling and tamping are carried out simultaneously without waiting, which improves construction efficiency and reduces construction costs.

[0031] Among them, the backfilling mechanism 2 includes a soil storage box 21 fixedly connected to the head of the vehicle body 1, the top of the soil storage box 21 is open, and a discharging pipe 41 is fixedly connected to the side of the soil storage box 21 away from the vehicle body 1 near the bottom. The discharging pipe 41 is inclined downward at 15°, and a discharging port 22 is opened on the side of the discharging pipe 41 away from the soil storage box 21.

[0032] Five spiral conveying rods 23 are connected to the soil storage box 21 near the bottom and are rotated at intervals along the width direction of the soil storage box 21. The spiral conveying rods 23 extend along the length direction of the soil storage box 21. The heads of the spiral conveying rods 23 extend into the excavation pipe 41, and the tails of the spiral conveying rods 23 pass through the soil storage box 21. The soil storage box 21 is provided with a driving assembly 24 for driving the spiral conveying rods 23 to rotate.

[0033] The soil is poured from the top of the soil storage box 21 into the soil storage box 21, the vehicle body 1 moves, and under the action of the driving assembly 24, the five spiral conveying rods 23 rotate simultaneously. Under the conveying action of the spiral conveying rods 23, the soil in the soil storage box 21 passes through the excavation pipe 41 and falls into the foundation pit.

[0034] Among them, the driving assembly 24 includes a driven bevel gear 25 arranged at the tail of the spiral conveying rod 23, and a motor 26 is installed on the outer side of the tail of the soil storage box 21. The output shaft 27 of the motor 26 extends along the width direction of the soil storage box 21. Five active bevel gears 28 meshing with the driven bevel gear 25 are fixedly connected to the output shaft 27 of the motor 26 at intervals along the length direction of the output shaft 27. The five active bevel gears 28 correspond to the five driven bevel gears 25 one by one.

[0035] The motor 26 drives the five active bevel gears 28 to rotate, the five active bevel gears 28 drive the five driven bevel gears 25 to rotate, and the five driven bevel gears 25 respectively drive the five spiral conveying rods 23 to rotate, which is energy-saving and environmentally friendly and consistent with the concept of sustainable development.

[0036] The compacting mechanism 3 includes a compacting roller 31 rotatably connected to the bottom of the soil storage box 21, the compacting roller 31 extends along the width direction of the soil storage box 21, and the compacting roller 31 is located between the soil outlet 22 and the vehicle body 1. A scraper plate 32 is slidably connected to the bottom of the soil storage box 21 along the length direction of the soil storage box 21, and the scraper plate 32 is located between the compacting roller 31 and the vehicle body 1. A support rod 42 for the scraper plate 32 to slide is fixedly connected to the soil storage box 21.

[0037] A spring 33 is sleeved on the support rod 42, one end of the spring 33 is fixedly connected to the side of the scraper plate 32 away from the tamping roller 31, and the other end of the spring 33 is fixedly connected to the support rod 42. The spring 33 is in a compressed state, and the spring 33 makes the scraper plate 32 tend to slide toward the tamping roller 31. A tip 34 is provided on the side of the scraper plate 32 close to the tamping roller 31, and the side of the scraper plate 32 close to the tamping roller 31 abuts against the tamping roller 31.

[0038] The vehicle body 1 drives the compacting roller 31 to move, and the compacting roller 31 rolls along the soil, thereby compacting the soil. Under the action of the restoring force of the spring 33, the scraper blade 32 abuts against the compacting roller 31 to scrape off the soil attached to the compacting roller 31. When encountering soil with strong adhesion, the scraper blade 32 rebounds, reducing the possibility of damage to the scraper blade 32 and increasing the service life of the scraper blade 32.

[0039] The implementation principle of the semi-covered deep foundation pit excavation and backfilling device of the embodiment of the present application is: the soil is dumped from the top of the soil storage box 21 into the soil storage box 21, the vehicle body 1 moves, and under the driving action of the motor 26, under the transmission action of the active bevel gear 28 and the driven bevel gear 25, the spiral conveying rod 23 rotates, and under the conveying action of the spiral conveying rod 23, the soil in the soil storage box 21 passes through the excavation pipe 41 and falls into the foundation pit.

[0040] The vehicle body 1 drives the compacting roller 31 to move, and the compacting roller 31 rotates against the soil, thereby compacting the soil. The scraper blade 32 scrapes off the soil attached to the compacting roller 31. When it contacts the soil with strong adhesion, the scraper blade 32 rebounds under the action of the spring 33. After multiple contacts, the soil can be scraped off. Backfilling and compaction are carried out simultaneously, which improves the construction efficiency.

[0041] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A semi-covered deep foundation pit earth excavation and backfilling device, characterized in that: include: A vehicle body (1) and a backfilling mechanism (2) disposed on the vehicle body (1) for backfilling earth into a foundation pit, wherein the vehicle body (1) is provided with a compacting mechanism (3) for compacting the earth in the foundation pit; the backfilling mechanism (2) comprises a soil storage box (21) disposed at the head of the vehicle body (1), and a soil discharge port (22) is provided on a side of the soil storage box (21) away from the vehicle body (1); a plurality of spiral conveying rods (23) are rotatably connected at intervals near the bottom of the soil storage box (21), and the spiral conveying rods (23) extend to the soil discharge port (22); and a driving assembly (24) for driving the spiral conveying rods (23) to rotate is provided on the soil storage box (21).

2. The device for excavating and backfilling a semi-covered deep foundation pit according to claim 1 is characterized in that: The driving assembly (24) comprises a driven bevel gear (25) arranged on the spiral conveying rod (23); a motor (26) is arranged on the soil storage box (21); a plurality of driving bevel gears (28) meshing with the driven bevel gear (25) are arranged at intervals on the output shaft (27) of the motor (26) along the length direction of the output shaft (27); the driving bevel gears (28) correspond to the driven bevel gears (25) one by one.

3. The device for excavating and backfilling a semi-covered deep foundation pit according to claim 1, characterized in that: The compacting mechanism (3) comprises a compacting roller (31) rotatably connected to the soil storage box (21); the compacting roller (31) is located between the soil discharge port (22) and the vehicle body (1).

4. The device for excavating and backfilling earthwork in a semi-covered deep foundation pit according to claim 3 is characterized in that: The soil storage box (21) is provided with a scraper plate (32), and the scraper plate (32) abuts against the tamping roller (31).

5. The device for excavating and backfilling earthwork in a semi-covered deep foundation pit according to claim 4, characterized in that: The scraper plate (32) is slidably connected to the soil storage box (21); a spring (33) is provided between the scraper plate (32) and the soil storage box (21); one end of the spring (33) is connected to the scraper plate (32); the other end of the spring (33) is connected to the soil storage box (21); the spring (33) is in a compressed state; the spring (33) causes the scraper plate (32) to have a tendency to slide toward the tamping roller (31).

6. The device for excavating and backfilling earthwork in a semi-covered deep foundation pit according to claim 4, characterized in that: The scraper plate (32) is provided with a tip (34) on a side close to the tamping roller (31).