Sealing connection device for desorption tower

By designing a loop flange and an elastic compensation mechanism between the analytical tower sections, the leakage problem caused by insufficient preload force is solved, the sealing effect and the stability of the equipment are improved, and the frequency of maintenance is reduced.

CN221847123UActive Publication Date: 2024-10-18TANGSHAN SANYOU SILICON IND
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420269634.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-10-18
Estimated Expiration
2034-02-04

AI Technical Summary

Technical Problem

The sealing connections between the tower sections of the existing graphite analytical towers are prone to leakage due to insufficient pre-tightening force, and the graphite material is highly brittle and prone to leaks, affecting the stability and safety of the equipment.

Method used

A sealing connection device for a parsing tower including a looper flange and an elastic compensation mechanism is designed. The looper flange is provided with fastening bolt holes and positioning tie rod holes, and an elastic compensation mechanism is installed between tower sections to avoid iron flange and The graphite is in direct contact and distributes the preload evenly.

Benefits of technology

The tightness of the flange seal is enhanced, the risk of leakage is reduced, the stability and safety of the equipment are improved, the frequency of maintenance is reduced, and the efficiency of tower maintenance is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221847123U_ABST
    Figure CN221847123U_ABST
Patent Text Reader

Abstract

The utility model discloses a sealing connection device for a desorption tower, which comprises a lap joint flange sleeved on the outer side of a tower section, a fastening bolt hole is arranged on the lap joint flange, a positioning pull rod hole is arranged on the outer side of the fastening bolt hole, and an elastic compensation mechanism is arranged between the lap joint flange and the tower section. Compared with the prior art, the lap joint flange is provided with the fastening bolt holes and the positioning pull rod holes, the fastening bolt holes in the inner ring are used for installing fastening bolts and enhancing the sealing fastening performance of the flange, the positioning pull rod holes in the outer ring are used for fixing the tower section body, and the problem of leakage caused by insufficient pretightening force of the tower section flange is solved; and an elastic compensation mechanism is arranged between the lap joint flange and the tower section, so that gouges caused by direct contact between an iron flange and graphite are avoided, pretightening force can be uniformly distributed, and the fastening effect of a fastening bolt is enhanced. The utility model has the advantages of simple structure, strong overhaul flexibility, enhanced flange fastening effect, strong operability and high safety, and reduces the damage probability of the contact part of the flange and the tower section.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of sealing of analytical tower sections, in particular to a sealing connection device for an analytical tower. Background Art

[0002] At present, graphite analytical towers are widely used in the field of chemical production due to their unique heat and corrosion resistance. Since the graphite material itself has low strength and poor hardness, the connection between the tower sections requires an external slip-on flange to connect the two tower sections. Generally, the diameter of the tower equipment is large, and leakage will occur if the sealing performance of the external slip-on flange is slightly insufficient. In addition, the overall height of the equipment is relatively high, and a positioning mechanism is required to achieve the verticality requirement of the tower body, which is generally completed using positioning bolts.

[0003] In order to position the tower body in the prior art, for every two adjacent bolt holes, one is installed with a fastening bolt and the other is installed with a positioning bolt. Therefore, the spacing between the bolts of the tower section that play a fastening role is large, resulting in insufficient pre-tightening force and an increased chance of leakage. The stress-bearing area of ​​the fitting part between the slip-on flange and the graphite tower section is small, and the brittleness of graphite itself also causes insufficient pre-tightening force, which is prone to leakage and brings hidden dangers to stable and safe production. Utility Model Content

[0004] In order to solve the above technical problems, the utility model provides a sealing connection device for an analytical tower, which solves the problem of leakage caused by insufficient pre-tightening force of a tower section flange.

[0005] To achieve this technical purpose, the utility model adopts the following scheme:

[0006] A sealing connection device for an analytical tower comprises a slip-on flange sleeved on the outside of a tower section, a fastening bolt hole is arranged on the slip-on flange, a positioning rod hole is arranged on the outside of the fastening bolt hole, and an elastic compensation mechanism is arranged between the slip-on flange and the tower section.

[0007] Compared with the prior art, the beneficial effects of the utility model are:

[0008] The utility model has fastening bolt holes and positioning rod holes on the slip-on flange. The inner ring fastening bolt holes are used to install fastening bolts to enhance the sealing tightness of the flange. The outer ring positioning rod holes are used to fix the tower section body to solve the leakage problem caused by insufficient pre-tightening force of the tower section flange. An elastic compensation mechanism is set between the slip-on flange and the tower section to avoid scratches caused by direct contact between the iron flange and graphite. At the same time, the pre-tightening force can be evenly distributed to enhance the fastening effect of the fastening bolts. The utility model has a simple structure, strong disassembly and inspection flexibility, enhanced flange fastening effect, reduced damage probability of the contact part between the flange and the tower section, strong operability and high safety.

[0009] Furthermore, the elastic compensation mechanism includes a shell and an elastic corrugated plate, and the elastic corrugated plate is arranged inside the shell. The setting of the elastic compensation mechanism avoids the iron flange from directly contacting the graphite tower section and causing scratches, and at the same time, the pre-tightening force can be evenly distributed, thereby enhancing the tightening effect of the fastening bolts. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 This is a half-section schematic diagram of the structure of the analytical tower connection device according to an embodiment of the utility model;

[0011] Figure 2 This is a half-section schematic diagram of the slip-on flange structure of an embodiment of the utility model;

[0012] In the figure: 1. tower section; 2. elastic compensation mechanism; 3. slip-on flange; 4. fastening bolt hole; 5. positioning rod hole; 6. outer shell; 7. elastic corrugated plate. DETAILED DESCRIPTION

[0013] In order to fully understand the purpose, features and effects of the present invention, the present invention is described in detail through the following specific implementation methods, but the present invention is not limited thereto.

[0014] See also Figure 1 to Figure 2 The embodiment of the utility model provides a sealing connection device for an analytical tower, including a tower section 1, which is made of graphite. A slip-on flange 3 is sleeved on the outer side of the tower section 1. An elastic compensation mechanism 2 is arranged between the tower section 1 and the slip-on flange 3. The elastic compensation mechanism 2 is composed of an outer shell 6 and an elastic corrugated plate 7. The outer shell 6 is arranged on both sides of the elastic corrugated plate 7. The outer shell 6 is an elastic material, such as rubber, foam, felt, etc. The elastic corrugated plate 7 is an existing product and can be purchased from the market. The outer shell 6 contacts the inner side of the slip-on flange 3 and the flange of the tower section 1 respectively to avoid scratches caused by direct contact between the iron flange and the graphite tower section 1. The elastic corrugated plate 7 plays a buffering role and can evenly distribute the preload force to enhance the tightening effect of the fastening bolts. A fastening bolt hole 4 is provided on the slip-on flange 3, and the fastening bolt is inserted into the fastening bolt hole 4, and the locking nut is tightened to fix the two tower sections 1. A positioning rod hole 5 is provided on the outer side of the fastening bolt hole 4, and the positioning rod is inserted into the positioning rod hole 5. The positioning rod passes through the upper and lower tower sections 1 to achieve the fixation of the analytical tower.

[0015] The working process of the sealing connection device of the analytical tower of the utility model is as follows: when the analytical tower is installed, the slip-on flange 3 of the tower section 1 is aligned, and each pair of slip-on flanges 3 is fastened by inserting the fastening bolts into the fastening bolt holes 4 and locking the nuts. After the installation and fastening of the tower section 1 is completed, the positioning rod is inserted into the positioning rod hole 5, and the positioning rod passes through the upper and lower tower sections 1 to achieve the fixation of the overall analytical tower. The positioning rod is adjusted by tightening to achieve the upright stability of the entire tower body to prevent shaking. An elastic compensation mechanism 2 is installed between the tower section 1 and the slip-on flange 3, and the shell 6 of the elastic compensation mechanism 2 is in contact with the inner side of the slip-on flange 3 and the flange of the tower section 1 to avoid the problem of knocks caused by direct contact between the iron flange and the graphite. The shell 6 plays the role of a soft gasket between the inner side of the slip-on flange 3 and the tower section 1, and an elastic corrugated plate 7 is arranged inside the shell 6. When locking the fastening bolts, the elastic corrugated plate 7 can make the fastening force evenly distributed, and at the same time play a buffering role to enhance the fastening effect.

[0016] After the implementation of the solution of the utility model, the leakage problem caused by insufficient bolt pre-tightening force between the analysis tower sections can be effectively solved, the frequency of equipment maintenance is reduced, and the efficiency of tower maintenance work is improved.

[0017] Finally, it should be noted that the above-listed examples are only preferred embodiments of the present invention. Of course, those skilled in the art can make changes and modifications to the present invention. If these modifications and modifications fall within the scope of the claims of the present invention and their equivalent technologies, they should be considered to be within the scope of protection of the present invention.

Claims

1. A sealing connection device for a desorption tower, comprising a slip-on flange (3) sleeved on the outside of a tower section (1), characterized in that: A fastening bolt hole (4) is provided on the slip-on flange (3), a positioning rod hole (5) is provided outside the fastening bolt hole (4), and an elastic compensation mechanism (2) is provided between the slip-on flange (3) and the tower section (1).

2. The analytical tower sealing connection device according to claim 1, characterized in that: The elastic compensation mechanism (2) comprises an outer shell (6) and an elastic corrugated plate (7), wherein the elastic corrugated plate (7) is arranged inside the outer shell (6).