Soft soil foundation pile foundation cantilever retaining wall structure

By using conical reinforcement piles and ejection components in the cantilever retaining wall structure, the problem of difficult concrete pouring for spiral pipe piles is solved, effective concrete injection is achieved and the stability of the conical reinforcement piles is improved, and the tilt and inclination of the structure are reduced. Displacement risk.

CN221855591UActive Publication Date: 2024-10-18ZHEJIANG JIUCHEN CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420402824.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2024-10-18
Estimated Expiration
2034-03-04

AI Technical Summary

Technical Problem

In the cantilever retaining wall structure, during the concrete pouring process of the spiral pipe piles, because the soil blocks the slurry outlet hole, the concrete cannot be effectively injected into the soil layer, which affects the reinforcement effect of the spiral pipe piles on the soft soil foundation.

Method used

Conical reinforcement piles and ejection components are used to push out the soil outside the grouting holes to create space and pour concrete to ensure that concrete can be fully injected into the soil layer, increase the stability of the conical reinforcement piles, and reduce the probability of structural tilt and displacement.

Benefits of technology

It effectively solves the problem of concrete injection, improves the stability of the tapered reinforcement piles in the soil layer, and reduces the risk of tilt and displacement of the cantilever retaining wall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855591U_ABST
    Figure CN221855591U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of cantilever retaining wall structures, and discloses a soft soil foundation pile foundation cantilever retaining wall structure which comprises a wall body, a toe board and a heel board, a plurality of conical reinforcing piles are arranged on the toe board and the heel board in a penetrating mode, and each conical reinforcing pile is provided with a grouting channel. A plurality of grouting holes are formed in the outer wall of each conical reinforcing pile, the grouting holes communicate with the grouting channels, and ejection assemblies used for ejecting out soil outside the grouting holes are arranged in the conical reinforcing piles. In the application, a worker knocks the conical reinforcing pile into a soil layer by using an external tool, the soil outside the grouting hole is ejected out by using the ejection assembly for ejecting out the soil outside the grouting hole, then the grouting channel is grouted by using concrete, and the concrete flows out along with the grouting hole; and when a gap between the outside of the slurry hole and the soil layer is fully filled with concrete, the conical reinforcing pile is more stable in the soil layer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cantilever retaining wall structures, in particular to a soft soil foundation pile foundation cantilever retaining wall structure. Background Art

[0002] A cantilever retaining wall is a structure that uses gravity and friction to resist soil pressure. It is often used to protect roads, bridges, dams, buildings and other projects. It is mainly composed of three reinforced concrete components: the vertical wall, the toe plate and the heel plate. It can effectively resist soil and water pressure and maintain the stability of the soil. The retaining wall bears the soil pressure inward, while the support system provides reaction force outward.

[0003] A soft soil foundation pile foundation cantilever retaining wall structure is disclosed in a Chinese utility model patent with publication number CN210288469U, comprising a base and a wall connected to the base, wherein a toe plate is arranged on one side of the wall and a heel plate is arranged on the other side, the base is located between the toe plate and the heel plate, a plurality of pile holes are reserved in the longitudinal direction on the toe plate and the heel plate, screw piles are arranged through the pile holes, the upper ends of the screw piles are flush with the upper surfaces of the toe plate and the heel plate, the screw piles are formed by threading a plurality of sections of screw pipes, a sleeve threadedly connected to the screw piles is arranged on the upper end of the screw piles, the screw pipes are arranged to be hollow inside, and a plurality of slurry outlet holes are evenly distributed on the sleeve and the side wall of each screw pipe near the lower end.

[0004] With respect to the above-mentioned related technologies, the inventors believe that the following defects exist: after the workers drive the screw tube piles into the soil layer and during the grouting process, the soil blocks the grouting holes, so there is not enough space for concrete to enter. The concrete inside the screw tube is subjected to the pressure of the concrete being poured, causing the concrete inside the screw tube to be squeezed out from the grouting holes of the screw tube, and the concrete cannot be effectively injected into the soil layer from the grouting holes, which is not conducive to improving the effect of the screw tube piles in reinforcing the soft soil foundation. Utility Model Content

[0005] In order to solve the above problems, the utility model provides a soft soil foundation pile foundation cantilever retaining wall structure.

[0006] The above-mentioned technical purpose of the utility model is achieved through the following technical scheme: a soft soil foundation pile foundation cantilever retaining wall structure, including a wall body, a toe plate integrally formed on one side of the wall body and a heel plate integrally formed on the other side of the wall, the toe plate and the heel plate are penetrated by a plurality of conical reinforcement piles that are gap-matched with the toe plate and the heel plate, each of the conical reinforcement piles is provided with a grouting channel connected to the top of the conical reinforcement pile, each of the conical reinforcement piles is provided with a plurality of grouting holes evenly distributed about the axis of the conical reinforcement pile on the outer wall, and the grouting holes are connected to the grouting channel, and a ejection component for ejecting soil outside the grouting hole is provided in the conical reinforcement pile.

[0007] By adopting the above technical solution, when the staff uses the structure to reinforce the conical reinforcement piles in the soil layer, first, a plurality of conical reinforcement piles are passed through the toe plate and the heel plate, and the staff uses an external tool to knock the conical reinforcement piles into the soil layer until the top of the conical reinforcement pile is flush with the toe plate and the heel plate, and then uses an ejection assembly for ejecting the soil outside the grouting hole to eject the soil outside the grouting hole, so that a certain gap is left in the soil outside the grouting hole, and then uses concrete to grout the grouting channel, and the concrete will flow out of the grouting hole. When the gap between the outside of the grouting hole and the soil layer is fully filled with concrete, the concrete can be fully injected into the soil layer, thereby making the conical reinforcement piles more stable in the soil layer, reducing the probability of the cantilever retaining wall structure tilting or displacing due to loose soil layer.

[0008] Furthermore, the ejection assembly is provided with multiple groups and is evenly distributed about the axis of the tapered reinforcement pile. The ejection assembly includes a mounting tube arranged in the tapered reinforcement pile and matching the gap with the grouting channel, an ejection cone arranged on the mounting tube, and a moving block fixed on the side wall of the ejection cone close to the axis of the mounting tube. An extrusion pile matching the gap with the mounting tube is arranged in the mounting tube, and through holes equal in number to the grouting holes and corresponding in position are arranged on the mounting tube. The ejection cone is slidably matched with the through holes and the grouting holes, and the bottom of the extrusion pile abuts against the tops of multiple moving blocks.

[0009] By adopting the above technical solution, after the staff knocks the conical reinforcement pile into the soil layer, the installation tube is placed in the conical reinforcement pile, and then the extrusion pile is placed in the installation tube. After the extrusion pile contacts the moving block, the extrusion pile squeezes the moving block, so that the ejector cone fixed on one side of the moving block moves outward, thereby pushing open the soil layer outside the grouting hole, increasing the gap between the conical reinforcement pile and the soil layer, and facilitating the subsequent concrete grouting operation.

[0010] Furthermore, a limiting block is fixed at a position of the bottom of the moving block away from the ejection cone, a spring is fixed on the side wall of the limiting block close to the ejection cone, and one end of the spring away from the limiting block is fixed to the inner wall of the mounting tube.

[0011] By adopting the above technical solution, when the squeezing pile squeezes the moving block, the spring contracts. When the staff pulls out the squeezing pile, the spring resets and drives the moving block to move inward, so that the ejection cone is retracted into the perforation, thereby facilitating the staff to install and disassemble the installation cylinder.

[0012] Furthermore, an inclined surface is provided at the intersection between the top of the moving block and the side wall of the moving block away from the ejection cone.

[0013] By adopting the above technical solution, the inclined surface allows the moving block to move more smoothly when the squeezing pile squeezes the moving block, thereby reducing the probability of the moving block getting stuck when the squeezing pile squeezes the moving block.

[0014] Furthermore, the height of the installation tube is greater than the height of the conical reinforcement pile, and two notches symmetrically distributed about the installation tube are provided on the outer wall of the installation tube near the top thereof.

[0015] By adopting the above technical solution, after the workers push out the soil outside the grouting hole, they can install and disassemble the installation tube through the set gap, thereby reducing the probability of the installation tube slipping when the workers pull out the installation tube.

[0016] Furthermore, a slide groove is provided on the inner wall of the conical reinforcement pile, and a positioning block that slides in cooperation with the slide groove is fixed on the outer wall of the installation tube.

[0017] By adopting the above technical solution, through the sliding cooperation between the positioning block and the slide groove, a good limiting effect is achieved on the installation tube, which makes it convenient for the staff to align the ejector cone with the grouting hole.

[0018] Furthermore, a sleeve is provided on the outer side of the conical reinforcement pile, a mounting ring is integrally formed on the top of the sleeve, a bolt which is gap-matched with the mounting ring is penetrated through the mounting ring, and the lower end of the bolt is threadedly connected to the top of the conical reinforcement pile.

[0019] By adopting the above technical solution, after the staff knocks the conical reinforcement pile into the base layer, they use a suitable wrench to unscrew the bolt and pull out the sleeve to expose the grouting hole. The set sleeve has a good protective effect on the grouting hole, reducing the possibility of soil from the soil layer entering the grouting hole when the conical reinforcement pile is knocked, thereby causing blockage of the grouting hole.

[0020] Furthermore, a knocking ring is fixed on the inner wall of the mounting ring.

[0021] By adopting the above technical solution, the provided knocking ring increases the contact area between the conical reinforcement pile and the external knocking tool, plays a good protective role in the grouting channel, reduces the probability of the conical reinforcement pile being deformed under the action of the knocking force when the conical reinforcement pile is knocked, and is beneficial to the subsequent pouring of concrete.

[0022] In summary, the utility model has the following beneficial effects:

[0023] 1. In the present application, when the staff uses the structure to reinforce the conical reinforcement piles in the soil layer, first, a plurality of conical reinforcement piles are passed through the toe plate and the heel plate, and the staff uses an external tool to knock the conical reinforcement piles into the soil layer until the top of the conical reinforcement pile is flush with the toe plate and the heel plate, and then uses a push-out assembly for pushing out the soil outside the grouting hole to push out the soil outside the grouting hole, so that a certain gap is left in the soil outside the grouting hole, and then uses concrete to grout the grouting channel, and the concrete will flow out with the grouting hole. When the gap between the outside of the grouting hole and the soil layer is fully filled with concrete, the concrete can be fully injected into the soil layer, so that the conical reinforcement piles are more stable in the soil layer, and the probability of the cantilever retaining wall structure tilting or displacement due to loose soil layer is reduced;

[0024] 2. In the present application, when the squeezing pile squeezes the moving block, the spring contracts. When the worker pulls out the squeezing pile, the spring resets and drives the moving block to move inward, so that the ejection cone is retracted into the perforation, thereby facilitating the worker to install and disassemble the installation cylinder. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0026] Figure 2 It is a schematic diagram of the structure of the utility model for highlighting the sleeve;

[0027] Figure 3 It is a schematic diagram of the cross-sectional structure of the utility model for highlighting the knocking ring;

[0028] Figure 4 yes Figure 2 The enlarged schematic diagram of point A in the middle;

[0029] Figure 5 yes Figure 3 A magnified schematic diagram of point B in the middle.

[0030] In the figure: 1, wall; 2, toe plate; 3, heel plate; 4, tapered reinforcement pile; 41, grouting channel; 42, grouting hole; 43, slide groove; 44, sleeve; 441, mounting ring; 4411, bolt; 4412, knocking ring; 5, ejector assembly; 51, mounting tube; 511, extrusion pile; 512, perforation; 513, notch; 514, positioning block; 52, ejector cone; 53, moving block; 531, inclined surface; 532, limit block; 5321, spring. DETAILED DESCRIPTION

[0031] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application; obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments, and all other embodiments obtained by ordinary technicians in this field based on the embodiments in the present application without making creative work are within the scope of protection of the present application.

[0032] like Figure 1-5 As shown, the embodiment of the present application discloses a cantilever retaining wall structure of a pile foundation on a soft soil foundation, including a wall body 1, a toe plate 2, a heel plate 3, a conical reinforcement pile 4 and an ejection assembly 5. The wall body 1 is a retaining wall used to resist soil pressure in the prior art, the toe plate 2 is integrally formed on one side of the wall body 1, and the heel plate 3 is integrally formed on the other side of the wall body 1. There are multiple conical reinforcement piles 4, and the multiple conical reinforcement piles 4 pass through the toe plate 2 and the heel plate 3 and are gap-matched with the toe plate 2 and the heel plate 3. Each conical reinforcement pile 4 is provided with a grouting channel 41 connected to the top of the conical reinforcement pile 4, and each conical reinforcement pile 4 is provided with a plurality of grouting holes 42 evenly distributed about the axis of the conical reinforcement pile 4 on the outer wall, and the grouting holes 42 are connected to the grouting channel 41, and the inner wall of the conical reinforcement pile 4 is provided with a slide groove 43.

[0033] There are multiple groups of ejection assemblies 5 that are evenly distributed about the axis of the conical reinforcement pile 4. The ejection assemblies 5 are arranged in the conical reinforcement pile 4 to eject the soil outside the grouting hole 42. Each group of ejection assemblies 5 includes a mounting tube 51, an ejection cone 52, and a moving block 53. The mounting tube 51 is a cylindrical structure. The mounting tube 51 is arranged in the conical reinforcement pile 4 and has a clearance fit with the grouting channel 41. The mounting tube 51 is provided with a squeezing pile 511 that has a clearance fit with the mounting tube 51. The mounting tube 51 is provided with perforations 512 that are equal in number to the grouting holes 42 and have a one-to-one corresponding position. The height of the mounting tube 51 is greater than the height of the conical reinforcement pile 4. Two notches 513 symmetrically distributed about the mounting tube 51 are arranged on the outer wall of the mounting tube 51 near its top. A positioning block 514 that slides with the slide groove 43 is fixed to the outer wall of the mounting tube 51. The ejection cone 52 is arranged on the installation tube 51 and is slidably matched with the through hole 512 and the grouting hole 42. The moving block 53 is fixed on the side wall of the ejection cone 52 close to the axis of the installation tube 51. An inclined surface 531 is arranged at the intersection between the top of the moving block 53 and the side wall of the moving block 53 away from the ejection cone 52. A limit block 532 is fixed at the bottom of the moving block 53 away from the ejection cone 52. A spring 5321 is fixed on the side wall of the limit block 532 close to the ejection cone 52, and one end of the spring 5321 away from the limit block 532 is fixed to the inner wall of the installation tube 51. The bottom of the extrusion pile 511 is in contact with the tops of multiple moving blocks 53.

[0034] In this embodiment, a sleeve 44 is provided on the outside of the conical reinforcement pile 4, and a mounting ring 441 is integrally formed on the top of the sleeve 44. A bolt 4411 is provided through the mounting ring 441, which is in clearance with the mounting ring 441. The lower end of the bolt 4411 is threadedly connected to the top of the conical reinforcement pile 4, and a knocking ring 4412 is fixed on the inner wall of the mounting ring 441. When the staff knocks the conical reinforcement pile 4 into the base layer, the knocking ring 4412 increases the contact area between the conical reinforcement pile 4 and the external knocking tool, and plays a good protective role on the grouting channel 41. The bolt 4411 is unscrewed with an appropriate wrench, and the sleeve 44 is pulled out to expose the grouting hole 42. The sleeve 44 plays a good protective role on the grouting hole 42, and reduces the situation where the soil of the soil layer enters the grouting hole 42 when the conical reinforcement pile 4 is knocked, thereby blocking the grouting hole 42.

[0035] The use principle of a soft soil foundation pile foundation cantilever retaining wall structure in this embodiment is as follows: when the staff uses the structure to reinforce the conical reinforcement piles 4 in the soil layer, first, a plurality of conical reinforcement piles 4 are passed through the toe plate 2 and the heel plate 3, and the staff uses an external tool to knock the conical reinforcement piles 4 into the soil layer until the top of the conical reinforcement pile 4 is flush with the toe plate 2 and the heel plate 3, and then use an appropriate wrench to unscrew the bolt 4411, and pull out the sleeve 44 to expose the grouting hole 42, and place the installation tube 51 in the conical reinforcement pile 4, and then place the squeezing pile 511 in the installation tube 51, and after the squeezing pile 511 contacts the moving block 53, the squeezing pile 511 squeezes the moving block 53, and the spring 5321 contracts. The ejector cone 52 fixed on one side of the movable block 53 moves outward, thereby pushing open the soil layer outside the grouting hole 42. When the staff pulls out the squeezing pile 511, the spring 5321 resets and drives the movable block 53 to move inward, so that the ejector cone 52 is retracted into the perforation 512, increasing the gap between the conical reinforcement pile 4 and the soil layer. Subsequently, the grouting channel 41 is grouted with concrete, and the concrete will flow out through the grouting hole 42. When the gap between the outside of the grouting hole and the soil layer is fully filled with concrete, the concrete can be fully injected into the soil layer, thereby making the conical reinforcement pile 4 more stable in the soil layer, reducing the probability of the cantilever retaining wall structure tilting or displacing due to loose soil layer.

[0036] The above is only a preferred embodiment of the present invention. The protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A cantilever retaining wall structure of a pile foundation on a soft soil foundation, comprising a wall body (1), a toe plate (2) integrally formed on one side of the wall body (1), and a heel plate (3) integrally formed on the other side of the wall body (1), wherein: The toe plate (2) and the heel plate (3) are both penetrated by a plurality of conical reinforcement piles (4) which are gap-matched with the toe plate (2) and the heel plate (3); each of the conical reinforcement piles (4) is provided with a grouting channel (41) which is connected to the top of the conical reinforcement pile (4); the outer wall of each conical reinforcement pile (4) is provided with a plurality of grouting holes (42) which are evenly distributed about the axis of the conical reinforcement pile (4); the grouting holes (42) are connected to the grouting channel (41); and an ejection assembly (5) for ejecting soil outside the grouting hole (42) is provided inside the conical reinforcement pile (4).

2. The soft soil pile foundation cantilever retaining wall structure according to claim 1 is characterized by: The ejection assembly (5) is provided with a plurality of groups and is evenly distributed about the axis of the conical reinforcement pile (4). The ejection assembly (5) comprises a mounting tube (51) arranged in the conical reinforcement pile (4) and loosely matched with the grouting channel (41), an ejection cone (52) arranged on the mounting tube (51), and a moving block (53) fixed on the side wall of the ejection cone (52) close to the axis of the mounting tube (51). The mounting tube (51) is provided with a squeezing pile (511) loosely matched with the mounting tube (51). The mounting tube (51) is provided with through holes (512) of which the number is equal to the number of grouting holes (42) and the positions correspond one to one. The ejection cone (52) is slidably matched with the through holes (512) and the grouting holes (42). The bottom of the squeezing pile (511) is in contact with the tops of the plurality of moving blocks (53).

3. The soft soil pile foundation cantilever retaining wall structure according to claim 2 is characterized by: A limiting block (532) is fixed at a position of the bottom of the moving block (53) away from the ejection cone (52); a spring (5321) is fixed on a side wall of the limiting block (532) close to the ejection cone (52); and one end of the spring (5321) away from the limiting block (532) is fixed to the inner wall of the mounting tube (51).

4. The soft soil pile foundation cantilever retaining wall structure according to claim 2 is characterized by: An inclined surface (531) is provided at the intersection between the top of the moving block (53) and the side wall of the moving block (53) away from the ejection cone (52).

5. The soft soil pile foundation cantilever retaining wall structure according to claim 2 is characterized by: The height of the installation tube (51) is greater than the height of the conical reinforcement pile (4), and two notches (513) symmetrically distributed about the installation tube (51) are provided on the outer wall of the installation tube (51) near the top thereof.

6. The soft soil pile foundation cantilever retaining wall structure according to claim 2 is characterized by: The inner wall of the conical reinforcement pile (4) is provided with a slide groove (43), and the outer wall of the installation cylinder (51) is fixed with a positioning block (514) that slides with the slide groove (43).

7. The soft soil pile foundation cantilever retaining wall structure according to claim 1 is characterized by: A sleeve (44) is arranged on the outer side of the conical reinforcement pile (4), a mounting ring (441) is integrally formed on the top of the sleeve (44), a bolt (4411) which is loosely matched with the mounting ring (441) is passed through the mounting ring (441), and the lower end of the bolt (4411) is threadedly connected to the top of the conical reinforcement pile (4).

8. The soft soil pile foundation cantilever retaining wall structure according to claim 7, characterized in that: A knocking ring (4412) is fixed to the inner wall of the mounting ring (441).