Fabricated building wall butt joint landing joint
By using a combined structure of hanging rings, long ribs, short ribs, installation slots, concrete blocks and slots in the wall of the prefabricated building, the problem of offset and tilt of the docking position of the wall of the prefabricated building is solved, and convenient docking and The installation is stable and the sealing layer prevents rainwater intrusion, improving the overall installation quality.
Patent Information
- Application Number
- CN202420431055.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-06
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-06
AI Technical Summary
Existing prefabricated building wall docking technology has problems with positional offset and tilt, making installation inconvenient and unstable, and there is a lack of effective sealing measures to prevent rainwater from entering.
Design a prefabricated building wall docking node, which adopts a combined structure of pre-embedded lifting rings, long bars, short bars, installation grooves, concrete blocks and clamping grooves. The lifting rings are used to facilitate lifting, and the long bars are limited to ensure that the docking holes are inserted The installation groove and the card groove cooperate to prevent tilting, and the sealing layer is filled at the contact point between the structure and the wall.
It realizes the convenient docking and vertical installation of prefabricated building walls, improves the overall stability, and prevents rainwater from entering and damaging the reserved steel bars.
Smart Images

Figure CN221878456U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of joint installation of prefabricated building walls, and in particular to a joint placement node for prefabricated building walls. Background Art
[0002] Prefabricated building walls refer to wall components that are prefabricated in a factory and then transported to the construction site for assembly. Prefabricated building walls can greatly shorten the construction period. By prefabricating in the factory, a considerable number of wall components can be completed in advance.
[0003] The installation of prefabricated building walls usually uses lifting equipment, which is lifted to the construction location where the wall needs to be installed. The wall is then inserted into the reserved steel bars. Workers can use mirrors as auxiliary tools to check the situation of the wall steel bars. In order to facilitate the docking of prefabricated walls, it is necessary to design a prefabricated building wall docking node. The two sides of the docking steel bars are longer, and the two points determine that the wall position will not change. The remaining steel bars are directly docked downward, and combined with the cooperation of the groove, the prefabricated building wall docking is effective and convenient and can remain vertical. Utility Model Content
[0004] In order to solve the existing technical problems, the present application provides a prefabricated building wall docking node.
[0005] The present application provides a prefabricated building wall docking node, which adopts the following technical solution: a prefabricated building wall docking node, which is arranged at the top of a structure, and an prefabricated building wall is arranged at the top of the structure, and three lifting rings are embedded in the top of the prefabricated building wall, and an installation groove is opened at the top of the structure, and a plurality of reserved steel bars are arranged in the inner cavity of the installation groove, and the reserved steel bars include a plurality of short bars reserved at the top of the structure, and long bars arranged in the inner cavity of the installation groove are reserved on both sides of the top of the structure, and the top of the long bar is longer than the top of the short bar, and a docking hole compatible with the reserved steel bars is opened at the bottom of the prefabricated building wall, a concrete block is cast at the bottom of the inner cavity of the installation groove, and a card slot compatible with the concrete block is opened on the rear side of the bottom of the prefabricated building wall.
[0006] By adopting the above technical scheme, the utility model facilitates the lifting of the prefabricated building wall through the setting of the lifting ring, and through the setting of two long reinforcements, it is preferentially connected with the docking holes on both sides of the bottom of the prefabricated building wall, so that the prefabricated building wall will not shift when moving downward, thereby facilitating the docking of multiple short reinforcements with the remaining multiple docking holes. The coordinated use of the installation groove, concrete block and the card groove can prevent the prefabricated building wall from tilting, thereby achieving the purpose of convenient docking of the prefabricated building wall and maintaining verticality.
[0007] Preferably, an additional layer is spread on the top of the structure, and a surface layer is spread on the top of the additional layer.
[0008] Preferably, the prefabricated building wall includes an inner leaf wall placed on the top of the structure, a thermal insulation layer is laid on the rear side of the inner leaf wall, and an outer leaf wall is arranged on the rear side of the thermal insulation layer.
[0009] Preferably, a plurality of connecting ribs 1 are pre-embedded on both sides of the prefabricated building wall, and a plurality of connecting ribs 2 are pre-embedded on the top of the prefabricated building wall.
[0010] By adopting the above technical solution, through the coordinated use of connecting ribs one and two, it is convenient to connect the prefabricated building wall with other cavities, making the prefabricated building wall more firm and stable after installation, thereby improving the stability of the overall prefabricated wall after installation.
[0011] Preferably, a reserved window is provided on the front side of the prefabricated building wall.
[0012] Preferably, the left and right hanging rings are symmetrically arranged, and the middle hanging ring is in the middle of the top of the prefabricated building wall.
[0013] Preferably, the contact position between the structure and the prefabricated building wall is filled with a sealing layer.
[0014] By adopting the above technical solution and setting a sealing layer, the connection between the structure and the prefabricated building wall is sealed and reinforced, preventing liquids such as rainwater from entering the inner cavity of the installation groove, thereby causing damage to the reserved steel bars.
[0015] In summary, the present application includes at least one of the following beneficial technical effects:
[0016] 1. The utility model facilitates the lifting of the prefabricated building wall by setting the lifting ring, and the two long bars are set so that they are preferentially plugged into the docking holes on both sides of the bottom of the prefabricated building wall, so that the prefabricated building wall will not deviate when moving downward, thereby facilitating the docking of multiple short bars with the remaining multiple docking holes. The prefabricated building wall is prevented from tilting by the coordinated use of the installation groove, the concrete block and the card groove, so that the prefabricated building wall can be conveniently docked and kept vertical.
[0017] 2. The utility model facilitates the docking of the assembled building wall with other cavities through the coordinated use of the connecting ribs 1 and 2, making the assembled building wall more firm and stable after installation, thereby improving the stability of the assembled wall after overall installation.
[0018] 3. The utility model seals and reinforces the connection between the structure and the prefabricated building wall by setting a sealing layer, thereby preventing liquids such as rainwater from entering the inner cavity of the installation groove and causing damage to the reserved steel bars. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:
[0020] Figure 1 It is a main perspective three-dimensional structural schematic diagram of the utility model.
[0021] Figure 2 It is a main three-dimensional structural schematic diagram of the utility model structure.
[0022] Figure 3 It is a schematic diagram of the three-dimensional structure of the assembled building wall of the utility model when viewed from above.
[0023] Figure 4 This utility model Figure 1 Schematic diagram of the enlarged structure of A.
[0024] Explanation of the reference numerals in the drawings: 1. Structure; 101. Structural layer; 102. Additional layer; 103. Surface layer; 2. Prefabricated building wall; 21. Inner leaf wall; 22. Insulation layer; 23. Outer leaf wall; 3. Connecting bar one; 4. Connecting bar two; 5. Reserved window; 6. Lifting ring; 7. Installation groove; 8. Reserved steel bar; 81. Short bar; 82. Long bar; 9. Docking hole; 10. Concrete block; 11. Slot; 12. Sealing layer. DETAILED DESCRIPTION
[0025] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0026] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0027] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.
[0028] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.
[0029] In addition, the term "plurality" shall mean two or more.
[0030] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0031] Embodiment 1:
[0032] Combination Figure 1 and Figure 4The embodiment of the present application discloses a joint landing node of a prefabricated building wall, which is arranged at the top of a structure 1, an additional layer 102 is spread on the top of the structure 1, a surface layer 103 is spread on the top of the additional layer 102, and a prefabricated building wall 2 is arranged on the top of the structure 1, the prefabricated building wall 2 includes an inner leaf wall 21 placed on the top of the structure 1, an insulation layer 22 is laid on the rear side of the inner leaf wall 21, and an outer leaf wall 23 is arranged on the rear side of the insulation layer 22, a plurality of connecting ribs 1 3 are pre-embedded on both sides of the prefabricated building wall 2, and a plurality of connecting ribs 2 4 are pre-embedded on the top of the prefabricated building wall 2, and the coordinated use of the connecting ribs 1 3 and the connecting ribs 2 4 facilitates the jointing of the prefabricated building wall 2 with other cavities, so that the prefabricated building wall 2 is more firm and stable after installation, and the overall strength of the prefabricated wall is improved. For stability after installation, a reserved window 5 is provided on the front side of the prefabricated building wall 2, three lifting rings 6 are embedded in the top of the prefabricated building wall 2, the left and right lifting rings 6 are symmetrically arranged, and the middle lifting ring 6 is in the middle of the top of the prefabricated building wall 2; a mounting groove 7 is provided on the top of the structure 1, and a plurality of reserved steel bars 8 are provided in the inner cavity of the mounting groove 7. The reserved steel bars 8 include a plurality of short bars 81 reserved at the top of the structure 1, and long bars 82 are reserved on both sides of the top of the structure 1 and arranged in the inner cavity of the mounting groove 7, and the top of the long bar 82 is longer than the top of the short bar 81; a docking hole 9 compatible with the reserved steel bars 8 is provided at the bottom of the prefabricated building wall 2, a concrete block 10 is cast at the bottom of the inner cavity of the mounting groove 7, and a card slot 11 compatible with the concrete block 10 is provided on the rear side of the bottom of the prefabricated building wall 2.
[0033] Embodiment 2:
[0034] Combination Figure 1 and Figure 3 A plurality of connecting ribs 1 3 are pre-buried on both sides of the prefabricated building wall 2, and a plurality of connecting ribs 2 4 are pre-buried on the top of the prefabricated building wall 2. The coordinated use of the connecting ribs 1 3 and the connecting ribs 2 4 facilitates the docking of the prefabricated building wall 2 with other cavities, making the prefabricated building wall 2 more firm and stable after installation, thereby improving the stability of the overall prefabricated wall after installation.
[0035] Working principle: When the utility model is used, the user connects the lifting ring 6 through the lifting equipment, and then lifts the lifting ring 6 to the top of the structure 1. Then the user can hold the assembled building wall 2 so that the two long bars 82 are inserted into the inner cavity of the two side docking holes 9 at the bottom of the assembled building wall 2. Then the user does not need to adjust the position of the assembled building wall 2, because the assembled building wall 2 is limited by the two long bars 82. At this time, continue to move downward, and multiple short bars 81 will be inserted into the inner cavity of the remaining multiple docking holes 9 until the assembled building wall 2 falls into the inner cavity of the installation groove 7, and at the same time, the concrete block 10 is engaged with the inner cavity of the card slot 11. At this time, the assembled building wall 2 is restrained by the reserved steel bars 8, the installation groove 7, the concrete block 10 and the card slot 11, and will not tilt, so that the assembled building wall can be easily docked and kept vertical.
[0036] In summary, the jointing node of the prefabricated building wall is convenient for lifting the prefabricated building wall 2 through the setting of the lifting ring 6. The two long bars 82 are set so that they are preferentially plugged into the jointing holes 9 on both sides of the bottom of the prefabricated building wall 2, so that the prefabricated building wall 2 will not shift when moving downward, thereby facilitating the jointing of multiple short bars 81 with the remaining multiple jointing holes 9. The coordinated use of the mounting groove 7, the concrete block 10 and the card groove 11 can prevent the prefabricated building wall 2 from tilting, thereby achieving the purpose of convenient jointing of the prefabricated building wall and maintaining verticality.
[0037] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A joint node for a prefabricated building wall, characterized in that: The node is arranged at the top of a structure (1); an assembled building wall (2) is arranged at the top of the structure (1); three lifting rings (6) are embedded at the top of the assembled building wall (2); an installation groove (7) is provided at the top of the structure (1); a plurality of reserved steel bars (8) are provided in the inner cavity of the installation groove (7); the reserved steel bars (8) include a plurality of short bars (81) reserved at the top of the structure (1); long bars (82) are reserved at both sides of the top of the structure (1) and are arranged in the inner cavity of the installation groove (7); the top of the long bars (82) is longer than the top of the short bars (81); a docking hole (9) matching the reserved steel bars (8) is provided at the bottom of the assembled building wall (2); a concrete block (10) is cast at the bottom of the inner cavity of the installation groove (7); and a clamping groove (11) matching the concrete block (10) is provided at the rear side of the bottom of the assembled building wall (2).
2. The assembly-type building wall docking node according to claim 1, characterized in that: An additional layer (102) is spread on the top of the structure (1), and a surface layer (103) is spread on the top of the additional layer (102).
3. The assembly-type building wall docking node according to claim 2, characterized in that: The assembled building wall (2) comprises an inner leaf wall (21) placed on the top of the structure (1), a thermal insulation layer (22) is provided on the rear side of the inner leaf wall (21), and an outer leaf wall (23) is provided on the rear side of the thermal insulation layer (22).
4. The assembly-type building wall docking node according to claim 3, characterized in that: A plurality of first connecting ribs (3) are pre-buried on both sides of the prefabricated building wall (2), and a plurality of second connecting ribs (4) are pre-buried on the top of the prefabricated building wall (2).
5. The assembly-type building wall docking node according to claim 4, characterized in that: A reserved window (5) is provided on the front side of the assembled building wall (2).
6. The assembly-type building wall docking node according to claim 5, characterized in that: The two left and right lifting rings (6) are symmetrically arranged, and the middle lifting ring (6) is located in the middle of the top of the assembled building wall (2).
7. The assembly-type building wall docking node according to claim 6, characterized in that: The contact position between the structure (1) and the prefabricated building wall (2) is filled with a sealing layer (12).