Natural gas pipeline sealing structure
By sliding to expand the hose compression seal and automatically locking and sliding the natural gas pipeline sealing structure, the problem of inconvenient operation in a small space is solved, and the convenience of simplified installation and disassembly is achieved.
Patent Information
- Application Number
- CN202420681350.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-04-03
AI Technical Summary
When installing and dismantling natural gas pipeline connections in a small space, the existing technology is inconvenient to operate. In particular, the screwdriver tightening process of clamping the clamp under the cabinet is cumbersome and difficult to simplify.
A natural gas pipeline sealing structure is designed, which uses a first connecting component that slides to expand the hose to compress and seal, and a second connecting component that elastically locks and slides. Combined with the locking component, automatic locking and unlocking are achieved, simplifying operation. .
By sliding to expand the hose compression seal and automatically locking the slide, the installation and disassembly process is simplified, the operation convenience is improved, and the complexity of operation in a small space is reduced.
Smart Images

Figure CN221880593U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of natural gas pipeline sealing, in particular to a natural gas pipeline sealing structure. Background Art
[0002] A natural gas pipeline refers to a pipeline that transports natural gas (including associated gas produced in oil fields) from a mining site or a processing plant to a city gas distribution center or an industrial enterprise user, also known as a gas transmission pipeline. Using a natural gas pipeline to transport natural gas is a way to transport a large amount of natural gas on land. Natural gas pipelines account for about half of the world's total pipeline length. When connecting the natural gas pipeline entering a household to a gas stove, the most commonly used device is a hose, which can be bent and is more convenient when laying the pipeline. When connecting the hose to a gas stove or a natural gas pipeline entering a household, it is necessary to fix a connector at the end of the hose, and the connector is sealed with a thread of the gas stove or the natural gas pipeline entering the household, and then the hose is connected to the connector. After the hose and the connector are connected, they need to be clamped and sealed with a clamp. However, the gas stove and the natural gas pipeline entering the household are generally installed in a cabinet. When installing the clamp, it is necessary to tighten the fixing bolts with a screwdriver. It is very troublesome to install the clamp in the narrow space under the cabinet, and the operation is not simple enough.
[0003] In comparison, a Chinese patent with authorization announcement number CN219300167U discloses a natural gas pipeline sealing device, including a connector and a hose, and also including a fixing assembly for fixing the hose, the fixing assembly including a clamping ring for clamping the hose and an action ring for rotating the clamping ring, the clamping ring being movably arranged in the connector, the action ring being threadedly connected to the outer wall of the connector, a through groove connecting to its inner cavity is provided on the outer surface of the connector, a connecting rod is fixedly arranged on the inner wall of the action ring, the connecting rod passes through the through groove and is fixedly connected to the clamping ring, and the lower end of the clamping ring is provided with an inclined surface for squeezing the hose.
[0004] The above patent adopts the setting of rotating to open the hose and clamp the seal, and the hose can be sealed and connected only by rotating. Although the operation is reduced, it still needs to be rotated, which is still inconvenient in a small space. Therefore, a new device needs to be designed. Utility Model Content
[0005] The purpose of the utility model is to provide a natural gas pipeline sealing structure to solve the problems raised in the above background technology.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] A natural gas pipeline sealing structure, comprising a first connection component for spiral compression and sealing connection of a hard pipe, and a second connection component arranged below the first connection component for sliding downward to open a hose and compress and seal, wherein a locking component for elastically locking and sliding and for downward insertion to release the lock is installed on the second connection component;
[0008] The second connection assembly includes a second connection tube, a clamping tube is slidably installed in the second connection tube, a sealing shoulder is arranged on the top of the clamping tube, a second sealing pad is arranged below the sealing shoulder, a sliding sleeve is slidably installed on the outside of the second connection tube, a plurality of connection blocks are evenly arranged between the sliding sleeve and the clamping tube, a clamping inclined surface is arranged at the bottom of the second connection tube, the clamping inclined surface is located below the clamping tube, and the bottom of the clamping tube is conical;
[0009] The locking assembly includes a pressure ring, and a plurality of insertion rods are evenly arranged below the pressure ring. The bottom of the insertion rod is wedge-shaped, and a lock tongue is arranged below the insertion rod. A slot is opened on the upper surface of the lock tongue, and the shape of the slot is a wedge corresponding to the bottom of the insertion rod. A lock groove is arranged below the lock tongue, and a spring is arranged on the side of the lock tongue away from the lock groove.
[0010] Furthermore: the first connecting assembly includes a connecting nut, a first connecting pipe is rotatably mounted on the bottom of the connecting nut, and a first sealing gasket is arranged on the first connecting pipe.
[0011] Furthermore: the clamping tube is made of stainless steel, and the sealing shoulder and the clamping tube are integrally formed.
[0012] Furthermore: four connecting blocks are provided, and the connecting blocks are connected to the clamping tube by welding.
[0013] Furthermore: six insertion rods are provided, and the pressure ring is installed on the outside of the second connecting pipe, and the two are interference fit.
[0014] Furthermore: the first sealing gasket is made of silicone material.
[0015] Compared with the prior art, the beneficial effects are:
[0016] 1. The setting of sliding and stretching the hose to compress and seal simplifies the operation and facilitates installation;
[0017] 2. Through the setting of elastic locking slide, automatic locking slide is realized, which further simplifies the operation;
[0018] 3. The setting of unlocking by inserting downwards makes disassembly convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of a natural gas pipeline sealing structure described in the utility model;
[0020] Figure 2It is an axonometric diagram of a natural gas pipeline sealing structure described in the utility model;
[0021] Figure 3 It is a front cross-sectional view of a first connecting component of a natural gas pipeline sealing structure described in the utility model;
[0022] Figure 4 It is a front cross-sectional view of a second connection assembly of a natural gas pipeline sealing structure described in the utility model;
[0023] Figure 5 It is a front cross-sectional view of a locking assembly of a natural gas pipeline sealing structure described in the utility model;
[0024] Figure 6 It is a partial enlarged view of the locking component A of the natural gas pipeline sealing structure described in the utility model.
[0025] In the accompanying drawings: 101, connecting nut; 102, first connecting tube; 103, first sealing gasket; 201, second connecting tube; 202, clamping tube; 203, sealing shoulder; 204, second sealing gasket; 205, connecting block; 206, sliding sleeve; 207, clamping slope; 301, pressing ring; 302, insert rod; 303, locking tongue; 304, spring; 305, slot; 306, locking groove. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0027] See also Figure 1-Figure 6 A natural gas pipeline sealing structure includes a first connecting component for spiral compression and sealing connection of a hard pipe, and also includes a second connecting component arranged below the first connecting component for sliding downward to open the hose and compress and seal, and a locking component for elastically locking and sliding and inserting downward to release the lock is installed on the second connecting component.
[0028] In this embodiment: the first connecting assembly includes a connecting nut 101, a first connecting pipe 102 is rotatably mounted at the bottom of the connecting nut 101, a first sealing gasket 103 is arranged on the first connecting pipe 102, the first sealing gasket 103 is made of silicone material, and the first connecting pipe 102 is sealed and connected to the gas hard pipe through the connecting nut 101 and the first sealing gasket 103;
[0029] In this embodiment, the second connecting assembly includes a second connecting tube 201, a clamping tube 202 is slidably installed in the second connecting tube 201, a sealing shoulder 203 is provided on the top of the clamping tube 202, a second sealing pad 204 is provided below the sealing shoulder 203, a sliding sleeve 206 is slidably installed on the outside of the second connecting tube 201, four connecting blocks 205 are evenly provided between the sliding sleeve 206 and the clamping tube 202, a clamping slope 207 is provided at the bottom of the second connecting tube 201, the clamping slope 207 is located below the clamping tube 202, and the bottom of the clamping tube 202 is conical, the clamping tube 202 is made of stainless steel, the sealing shoulder 203 is provided on the top of the clamping tube 202, and the second sealing pad 204 is provided below the sealing shoulder 203. 203 is integrally formed with the clamping tube 202, and the connecting block 205 is welded to the clamping tube 202. The hose is inserted from the bottom of the second connecting tube 201 to the bottom of the clamping tube 202, and the sliding sleeve 206 drives the clamping tube 202 to slide downward along the second connecting tube 201 through the connecting block 205. The cone at the bottom of the clamping tube 202 will be inserted into the inside of the hose, and the clamping slope 207 will clamp and fix the hose. When the bottom of the clamping tube 202 moves to the bottom of the clamping slope 207, the sealing shoulder 203 at the top of the clamping tube 202 will press the second sealing pad 204 to seal the inside of the second connecting tube 201.
[0030] In this embodiment, the locking assembly includes a pressure ring 301, six insertion rods 302 are evenly arranged below the pressure ring 301, the bottom of the insertion rod 302 is wedge-shaped, a locking tongue 303 is arranged below the insertion rod 302, a slot 305 is opened on the upper surface of the locking tongue 303, the slot 305 is in the shape of a wedge corresponding to the bottom of the insertion rod 302, a locking groove 306 is arranged below the locking tongue 303, and a spring 304 is arranged on the side of the locking tongue 303 away from the locking groove 306, the pressure ring 301 is installed outside the second connecting pipe 201, and both Interference fit, when the bottom of the clamping tube 202 moves to the bottom of the clamping slope 207, the sliding sleeve 206 drives the locking tongue 303 to move downward to the position of the locking groove 306, and the locking tongue 303 enters the locking groove 306 under the push of the spring 304, locking the position of the sliding sleeve 206 to achieve automatic locking. When disassembling, the wedge at the bottom of the insert rod 302 is driven downward by the pressure ring 301 to insert the locking tongue 303 into the locking groove 306 to achieve unlocking, and then the sliding sleeve 206 is slid upward to release the fixation of the hose.
[0031] Working principle: First, the first connecting pipe 102 is sealed and connected to the gas hard pipe through the connecting nut 101 and the first sealing gasket 103, and then the hose is inserted from the bottom of the second connecting pipe 201 to the bottom of the clamping pipe 202, and the sliding sleeve 206 drives the clamping pipe 202 to slide downward along the second connecting pipe 201 through the connecting block 205. The cone at the bottom of the clamping pipe 202 will be inserted into the inside of the hose, and the clamping slope 207 will clamp and fix the hose. When the bottom of the clamping pipe 202 moves to the bottom of the clamping slope 207, the clamping pipe 202 The sealing shoulder 203 at the top will press the second sealing gasket 204 to seal the inside of the second connecting tube 201. At the same time, the sliding sleeve 206 drives the locking tongue 303 to move downward to the position of the locking groove 306. The locking tongue 303 enters the locking groove 306 under the push of the spring 304, locks the position of the sliding sleeve 206, and realizes automatic locking. When disassembling, the wedge at the bottom of the insert rod 302 is driven downward by the pressure ring 301 to insert it into the slot 305, push the locking tongue 303 out of the locking groove 306, and then slide the sliding sleeve 206 upward to release the fixation of the hose.
[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A natural gas pipeline sealing structure, comprising a first connecting assembly for spirally pressing and sealing a hard pipe, characterized in that: It also includes a second connecting component disposed below the first connecting component and used for sliding downward to open the hose and compress and seal, and a locking component for elastically locking and sliding and for unlocking by inserting downward is installed on the second connecting component; The second connection assembly comprises a second connection tube, a clamping tube is slidably mounted in the second connection tube, a sealing shoulder is arranged on the top of the clamping tube, a second sealing pad is arranged below the sealing shoulder, a sliding sleeve is slidably mounted on the outside of the second connection tube, a plurality of connection blocks are evenly arranged between the sliding sleeve and the clamping tube, a clamping slope is arranged at the bottom of the second connection tube, the clamping slope is located below the clamping tube, and the bottom of the clamping tube is conical; The locking assembly includes a pressure ring, a plurality of insertion rods are evenly arranged below the pressure ring, the bottom of the insertion rod is wedge-shaped, a locking tongue is arranged below the insertion rod, a slot is opened on the upper surface of the locking tongue, the slot is in the shape of a wedge corresponding to the bottom of the insertion rod, a locking groove is arranged below the locking tongue, and a spring is arranged on the side of the locking tongue away from the locking groove.
2. A natural gas pipeline sealing structure according to claim 1, characterized in that: The first connecting assembly comprises a connecting nut, a first connecting pipe is rotatably mounted on the bottom of the connecting nut, and a first sealing gasket is arranged on the first connecting pipe.
3. A natural gas pipeline sealing structure according to claim 1, characterized in that: The clamping tube is made of stainless steel, and the sealing shoulder and the clamping tube are integrally formed.
4. A natural gas pipeline sealing structure according to claim 1, characterized in that: Four connecting blocks are provided, and the connecting blocks are connected to the clamping tube by welding.
5. A natural gas pipeline sealing structure according to claim 1, characterized in that: The number of the inserted rods is six, and the pressure ring is installed on the outside of the second connecting pipe, and the two are interference fit.
6. A natural gas pipeline sealing structure according to claim 2, characterized in that: The first sealing pad is made of silicone.