Mercury removal system for gold ore leaching pregnant solution containing mercury and silver
Through the combined use of the sulfide precipitation method and the exhaust gas absorption tower, the problem of mercury pollution in the gold mine leaching liquid has been solved, the harmless removal of mercury and the recovery of silver have been achieved, and the safety and environmental protection of the system have been improved.
Patent Information
- Application Number
- CN202420547308.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-20
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2034-03-20
AI Technical Summary
During the cyanide leaching process of gold mines, mercury minerals react with cyanide to generate mercury cyanide ions, causing mercury to enter the cyanide leaching solution in the form of ions, causing environmental pollution and health hazards to workers. Existing measures cannot completely solve mercury leaching. and subsequent contamination issues.
The mercury is precipitated using the sulfide precipitation method and separated by pressure filtration. The silver sulfide is dissolved and recovered in the nitric acid reaction to avoid silver loss, and hydrogen sulfide and hydrogen cyanide are absorbed in the waste gas absorption tower to achieve waste gas recovery.
It effectively reduces the mercury concentration in the cyanide leaching liquid, solves the problem of mercury pollution, avoids the loss of silver metal, and improves the safety and environmental protection of the system.
Smart Images

Figure CN221895077U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a processing system for precious liquid leached from a gold mine, in particular to a mercury removal system for precious liquid leached from a gold mine containing mercury and silver. Background Art
[0002] Gold mines often use cyanide leaching hydrometallurgical processes to recover gold and silver precious metals. During the cyanide leaching process, the associated minerals such as copper, lead, zinc, iron, and mercury in the gold mine react with the leaching agent to a greater or lesser extent, causing these base metal elements to enter the cyanide leaching precious solution in the form of ions, which has an adverse effect on the subsequent leaching precious solution replacement (or activated carbon adsorption) and gold mud replacement (or activated carbon analysis) smelting.
[0003] During the cyanide leaching process, the mercury minerals in the mercury-containing gold ore react with cyanide to form mercury cyanide complex ions [Hg(CN) 4 2- ], so that mercury enters the cyanide leaching solution in the form of ions. During the leaching solution replacement (or activated carbon adsorption) and gold mud replacement (or activated carbon analysis) smelting process, mercury metal element will be generated and volatilized into the atmosphere, causing environmental pollution and seriously damaging the health of workers.
[0004] At present, for mercury-containing cyanide leaching precious liquid, the leaching rate of mercury is reduced by controlling the cyanide leaching conditions, or by strengthening ventilation and adding waste gas treatment devices during the leaching precious liquid replacement and gold mud replacement smelting process to reduce mercury pollution. However, these measures cannot completely solve the problem of mercury leaching and subsequent pollution. Utility Model Content
[0005] The technical problem to be solved by the utility model is to provide a mercury removal system for gold mine leaching precious liquid containing mercury and silver, which is used for treating the gold mine leaching precious liquid containing mercury and silver, realizing the harmless removal of mercury in the mercury-containing cyanide leaching precious liquid, and avoiding the loss of silver metal, so as to achieve the purpose of completely solving the mercury leaching and subsequent pollution.
[0006] The technical solution of the utility model is as follows:
[0007] A mercury removal system for precious liquid leached from a gold mine containing mercury and silver, comprising a first stirring tank and a second stirring tank connected to each other through a pipeline, and further comprising a third stirring tank, a fourth stirring tank, a first filter press and a second filter press, wherein the second stirring tank is connected to a feed end of the first filter press through a pipeline; a belt conveyor is arranged below the first filter press, and a discharge end of the belt conveyor is located above a feed inlet of the third stirring tank; the third stirring tank is connected to a feed end of the second filter press through a pipeline; a filtrate discharge outlet of the second filter press is connected to a main pipeline, and the main pipeline is respectively connected to the third stirring tank and the fourth stirring tank through two branch pipelines with valves.
[0008] Preferably, the system further comprises a waste gas absorption tower; the waste gas absorption tower is respectively connected to the first stirring tank and the second stirring tank through an air intake pipeline; a fan is installed on the air intake pipeline.
[0009] Preferably, the feed end of the connecting pipeline between the first stirring tank and the second stirring tank is higher than the discharge end; the filtrate outlet of the second filter press is higher than the top of the third stirring tank and higher than the top of the fourth stirring tank.
[0010] Preferably, a pH meter is installed in the first stirring tank.
[0011] Preferably, the system further comprises a first dosing tank and a second dosing tank respectively connected to the first stirring tank through dosing pipes.
[0012] Preferably, a first filter press feed pump is installed on the pipeline connecting the second stirring tank and the feed end of the first filter press; and a second filter press feed pump is installed on the pipeline connecting the third stirring tank and the feed end of the second filter press.
[0013] The positive effects of the utility model are:
[0014] When removing mercury by sulfidation, silver sulfide will be generated. Both mercuric sulfide and silver sulfide are precipitates. If silver sulfide and mercuric sulfide cannot be separated, silver metal will be lost together with mercuric sulfide. Based on this, the utility model removes mercury in the form of mercuric sulfide, and silver sulfide is dissolved and recovered, thereby avoiding the loss of silver.
[0015] Specifically, the utility model system adopts a sulfide precipitation method to precipitate the mercury and silver in the precious liquid of the gold mine leaching containing mercury and silver, and separates them through the first stage filter pressing. The mercury precipitate in the filter cake produced by the first stage filter pressing is removed in the form of a filter cake through the second stage filter pressing. The silver precipitate is dissolved by reacting with nitric acid in the third stirring tank and then enters the fourth stirring tank. The silver ions are precipitated and recovered in the form of silver chloride. Through the above process, the utility model reduces the mercury concentration in the cyanide leaching precious liquid, solves the mercury pollution problem in the process of cyanide leaching precious liquid replacement and replacement gold mud smelting, and solves the problem of part of the silver metal entering the precipitate slag loss while removing mercury. While achieving the removal of mercury (generating mercuric sulfide precipitation) from the precious liquid of the gold mine leaching containing mercury and silver, the silver precipitated together with the mercury (generating silver sulfide precipitation) is recovered again, avoiding the loss of silver.
[0016] The optimized technical solution of the utility model also realizes the absorption of waste gas (hydrogen sulfide, hydrogen cyanide) by setting up a waste gas absorption tower, thereby avoiding the loss of reagents and making the system safer and more environmentally friendly. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural schematic diagram of an embodiment of the utility model.
[0018] In the figure, 1-1, the first stirring tank, 1-2, the second stirring tank, 1-3, the third stirring tank, 1-4, the fourth stirring tank, 2-1, the first filter press, 2-2, the second filter press, 3, the belt conveyor, 4, the exhaust gas absorption tower, 5-1, the first dosing tank, 5-2, the second dosing tank, 6, the fan, 7-1, the first filter press feed pump, 7-2, the second filter press feed pump, 8, the pH meter. DETAILED DESCRIPTION
[0019] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0020] The basic components of the embodiment of the mercury removal system of the utility model include a first stirring tank 1-1, a second stirring tank 1-2, a third stirring tank 1-3 with a feed port at the upper end, a fourth stirring tank 1-4, a first filter press 2-1, a second filter press 2-2, a first filter press feed pump 7-1 and a second filter press feed pump 7-2. The first stirring tank 1-1, the second stirring tank 1-2, the third stirring tank 1-3 and the fourth stirring tank 1-4 are all equipped with stirring mechanisms.
[0021] like Figure 1 , the first stirring tank 1-1 and the second stirring tank 1-2 are connected to each other through a pipeline, and the bottom end of the second stirring tank 1-2 is connected to the feed end of the first filter press 2-1 through a pipeline equipped with a first filter press feed pump 7-1. The filtrate produced by the first filter press 2-1 is used for subsequent zinc powder replacement and other operations. A belt conveyor 3 is installed below the first filter press 2-1, and the feed end of the belt conveyor 3 is located directly below the filter cake falling part of the first filter press 2-1, and the discharge end of the belt conveyor 3 is directly above the feed port of the third stirring tank 1-3. The bottom end of the third stirring tank 1-3 is connected to the second filter press 2-2 through a pipeline equipped with a second filter press feed pump 7-2. The filtrate produced by the second filter press 2-2 is connected to the third stirring tank 1-3 through a pipeline with a valve, and the filtrate produced by the second filter press 2-2 is also connected to the fourth stirring tank 1-4 through a pipeline with a valve. Specifically, the filtrate outlet of the second filter press 2-2 is connected to a main pipeline, and the main pipeline is respectively connected to the top of the third stirring tank 1-3 and the top of the fourth stirring tank 1-4 through two branch pipelines with valves.
[0022] Furthermore, in order to realize the slurry self-flow, the feed end position of the connecting pipeline between the first stirring tank 1-1 and the second stirring tank 1-2 is higher than the discharge end position. The filtrate outlet position of the second filter press 2-2 is higher than the top position of the third stirring tank 1-3 and higher than the top position of the fourth stirring tank 1-4.
[0023] Furthermore, the present embodiment may further include an exhaust gas absorption tower 4. The exhaust gas absorption tower 4 is connected to the top of the first stirring tank 1-1 and the top of the second stirring tank 1-2 through an air intake pipeline, and a fan 6 is installed on the air intake pipeline.
[0024] Furthermore, a pH meter 8 is installed in the first stirring tank 1 - 1 .
[0025] Furthermore, the present embodiment may further include a first dosing tank 5-1 and a second dosing tank 5-2 respectively connected to the first stirring tank 1-1 through a dosing pipe. The dosing pipe is equipped with a dosing pump. The first dosing tank 5-1 and the second dosing tank 5-2 are respectively used to pump sodium sulfide and sulfuric acid solution into the first stirring tank 1-1.
[0026] The following examples illustrate the workflow of the present utility model.
[0027] The precious liquid from the gold ore leaching containing mercury and silver is added to the first stirring tank 1-1. Under the stirring action of the stirring mechanism, it is mixed with the sodium sulfide added through the first dosing tank 5-1 and the dilute sulfuric acid added through the second dosing tank 5-2 for reaction. The pH of the reaction system is detected by the pH meter 8, and the addition ratio of sodium sulfide and dilute sulfuric acid is controlled to control the pH of the system within the set range (for example, pH 9.5-10.5). The reaction obtains a suspension containing mercuric sulfide. The suspension after the reaction flows into the second stirring tank 1-2 by gravity, and the reaction time of the suspension is extended in the second stirring tank 1-2. The second stirring tank 1-2 also serves as the feed pump tank of the first filter press 2-1.
[0028] The liquid discharged from the second stirring tank 1-2 is pumped into the first filter press 2-1 through the first filter press feed pump 7-1, and the first solid-liquid separation is achieved through the first filter press 2-1. The filtrate produced by the first filter press 2-1 enters the subsequent zinc powder replacement and other operations, and the filter cake is sent to the third stirring tank 1-3 by the belt conveyor 3, and reacts with the concentrated nitric acid in the third stirring tank 1-3 under the stirring action of the stirring mechanism. The suspension after the reaction is pumped into the second filter press 2-2 by the second filter press feed pump 7-2, and the second solid-liquid separation is achieved through the second filter press 2-2. The filtrate produced by the second filter press 2-2 returns to the third stirring tank 1-3, and the filtrate circulates between the second filter press 2-2 and the third stirring tank 1-3. When the silver nitrate content in the circulating filtrate reaches the set requirement (the specific content is determined according to the actual situation), the filtrate is controlled by the pipeline valve to enter the fourth stirring tank 1-4, and sodium chloride is added to the fourth stirring tank 1-4 to precipitate and recover the silver ions in the filtrate in the form of silver chloride.
[0029] At the same time, under the action of the fan 6, the waste gases such as hydrogen sulfide and hydrogen cyanide generated in the first stirring tank 1-1 and the second stirring tank 1-2 are sent to the bottom of the waste gas absorption tower 4 through the suction pipeline, and react with the sodium hydroxide solution in the waste gas absorption tower 4 to generate soluble salts such as sodium sulfide and sodium cyanide, thereby realizing waste gas recovery.
Claims
1. A mercury removal system for a gold ore leaching precious liquid containing mercury and silver, comprising a first stirring tank (1-1) and a second stirring tank (1-2) connected to each other by a pipeline, a third stirring tank (1-3), a fourth stirring tank (1-4), a first filter press (2-1) and a second filter press (2-2), Features: The second stirring tank (1-2) is connected to the feed end of the first filter press (2-1) through a pipeline; a belt conveyor (3) is arranged below the first filter press (2-1), and the discharge end of the belt conveyor (3) is located above the feed inlet of the third stirring tank (1-3); the third stirring tank (1-3) is connected to the feed end of the second filter press (2-2) through a pipeline; the filtrate discharge outlet of the second filter press (2-2) is connected to a main pipeline, and the main pipeline is respectively connected to the third stirring tank (1-3) and the fourth stirring tank (1-4) through two branch pipelines with valves.
2. The mercury removal system for the precious solution of gold ore leaching containing mercury and silver according to claim 1, Features: The system further comprises a waste gas absorption tower (4); the waste gas absorption tower (4) is respectively connected to the first stirring tank (1-1) and the second stirring tank (1-2) via an air intake pipeline; a fan (6) is installed on the air intake pipeline.
3. The mercury removal system for the precious solution of gold ore leaching containing mercury and silver according to claim 1 or 2, Features: The feed end position of the connecting pipeline between the first stirring tank (1-1) and the second stirring tank (1-2) is higher than the discharge end position; the filtrate outlet position of the second filter press (2-2) is higher than the top position of the third stirring tank (1-3) and higher than the top position of the fourth stirring tank (1-4).
4. The mercury removal system for gold ore leaching precious liquid containing mercury and silver according to claim 1 or 2, Features: A pH meter (8) is installed in the first stirring tank (1-1).
5. The mercury removal system for the precious solution of gold ore leaching containing mercury and silver according to claim 1 or 2, Features: The system further comprises a first dosing tank (5-1) and a second dosing tank (5-2) respectively connected to the first stirring tank (1-1) via dosing pipes.
6. The mercury removal system for the precious solution of gold ore leaching containing mercury and silver according to claim 1 or 2, Features: A first filter press feed pump (7-1) is installed on a pipeline connecting the second stirring tank (1-2) and the feed end of the first filter press (2-1); and a second filter press feed pump (7-2) is installed on a pipeline connecting the third stirring tank (1-3) and the feed end of the second filter press (2-2).