Tunnel following mold maintenance device
By designing adjustable sprinkler heads and hydraulically driven shear rod components, the problem of insufficient maintenance during tunnel lining construction is solved, efficient tunnel top spray maintenance is achieved, and costs and construction risks are reduced.
Patent Information
- Application Number
- CN202420236965.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-31
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-31
AI Technical Summary
During the existing tunnel lining construction, it is difficult for the maintenance trolley to be in place during construction operations in the tunnel, resulting in insufficient maintenance. When using sprinklers or water pipes, it is easy to block traffic and the cost is high. Insufficient water pressure causes insufficient maintenance of the vault.
A tunnel and mold maintenance device is designed, including an adjustable nozzle, annular baffle, a turntable, a guide block and a shear rod assembly driven by a hydraulic cylinder. By adjusting the size of the water hole of the nozzle and the extension of the shear rod assembly, the Efficient spray maintenance on the top of the tunnel.
It improves the maintenance effect, reduces the cost and labor intensity, prevents damage to the sprinkler device during the construction of the lining trolley, and improves the maintenance efficiency.
Smart Images

Figure CN221907859U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of tunnel lining construction, and in particular relates to a tunnel follower mold maintenance device. Background Art
[0002] In tunnel lining construction, in order to ensure the strength of concrete, it is generally necessary to perform natural curing or artificial spray curing on the tunnel secondary lining. In the prior art, the curing method is mostly to use a curing trolley for curing.
[0003] After searching and analyzing, the authorization announcement number CN211819421 U discloses a steam curing trolley for the secondary lining of a tunnel, which adopts the above-mentioned curing method. The trolley body includes a support portal and an arched support frame, wherein the arched support frame is arranged inside the tunnel and is consistent with the arched direction of the tunnel, there is a curing gap between the arched support frame and the inner wall of the tunnel, the support portal is arranged inside the arched support frame, and a curing walking device is arranged at the bottom of the support portal.
[0004] The above device also has the following problems: due to the influence of construction work in the tunnel, the maintenance trolley near the second lining formwork cannot be fully maintained, and can only be maintained by a sprinkler truck or manually using a water pipe. However, during the maintenance process using a sprinkler truck, the traffic in the tunnel will be blocked, and the maintenance cost is high. When using a water pipe for maintenance, the arch may not be fully maintained due to the high distance from the arch and the low water pressure in the water pipe.
[0005] Based on the above problems, a tunnel follower mold maintenance device is proposed. Utility Model Content
[0006] In order to solve the problems existing in the above-mentioned prior art, a tunnel follower mold maintenance device is provided, comprising a nozzle, the nozzle is provided with a water hole, and further comprising:
[0007] A plurality of annular baffles can move inward or outward at the same time to adjust the water flow rate of the water hole of the sprinkler head;
[0008] A rotating disk, the rotating disk is rotatably connected to the nozzle, the rotating disk is provided with an annular groove, the groove is arranged corresponding to the baffle, and the baffle can slide along the groove;
[0009] A guide block arranged in an inclined direction, the guide block is fixedly connected to the nozzle, and the guide block is provided with a slide groove for guiding the baffle;
[0010] The shifting block is fixedly connected to the rotating disk, and when the shifting block is shifted, the rotating disk can be driven to rotate in the nozzle.
[0011] Preferably, the shift block is connected to a clamping block via a spring, the nozzle is provided with at least one clamping slot, and the clamping block can be matched with one of the clamping slots respectively.
[0012] Preferably, a slider is fixedly connected to the bottom of the baffle, and the slider is slidably disposed in the groove.
[0013] Preferably, a sliding column is fixedly connected to the top of the baffle, and the sliding column is slidably arranged in the sliding groove.
[0014] Preferably, it further comprises a lining trolley, wherein the lining trolley is detachably connected to a water tank, a water pump is connected to the water tank, and the water pump is connected to the nozzle through a water supply pipe.
[0015] Preferably, several groups of shear rod assemblies are included, and the shear rod assemblies include two articulated rods hinged to each other end to end, the middle positions of the two articulated rods are hinged through a central axis, and adjacent shear fork groups are connected through a hinge axis, and spray pipes are fixedly connected to the two articulated rods, and the spray pipes are connected to the water supply pipes, and the spray pipes are connected to the nozzles.
[0016] Preferably, the ends of the two articulated rods are hinged with end point shafts, the lining trolley is fixedly connected to a steel pipe frame, the steel pipe frame is fixedly connected to a hydraulic cylinder, the hydraulic cylinder includes a piston rod, and the end point shaft located at the far left end is hinged to the piston rod.
[0017] Preferably, the central axis of the endpoint axis close to the leftmost end is fixedly connected to the steel pipe frame, and the hydraulic cylinder drives the two articulated rods to rotate around the central axis.
[0018] Preferably, the water supply pipe is a rubber hose.
[0019] Compared with the prior art, the utility model has the following advantages:
[0020] 1. In the utility model, the turntable can be driven to rotate by the dial block, the baffle will slide in the groove, and will guide the moving direction of the baffle under the action of the guide block, so as to complete the adjustment of the size of the water hole, thereby completing the adjustment of the water pressure, and the spray water is sprayed onto the tunnel through the nozzle and sprayed onto the cast lining, completing the spraying and maintenance of the tunnel top, and the maintenance effect is better.
[0021] 2. The device is provided with several groups of shear bar assemblies. When the lining trolley is normally used, the shear bar assemblies can be retracted under the control of the hydraulic cylinder. When the tunnel needs to be sprayed, the hydraulic rod can be directly operated to control the extension of the shear bar assembly, thereby completing the spraying maintenance of the poured lining, which improves the maintenance efficiency to a certain extent and also prevents possible damage to the spraying device during the moving construction of the lining trolley. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0023] Figure 1 It is a structural stereogram (first state) of the utility model.
[0024] Figure 2 It is a structural stereogram (second state) of the utility model.
[0025] Figure 3 It is a structural diagram of the nozzle in the utility model.
[0026] Figure 4 It is a structural diagram of the guide block in the utility model.
[0027] Figure 5 It is a structural diagram of the baffle in the utility model.
[0028] Figure 6 It is a structural diagram of the turntable in the utility model.
[0029] Figure 7 It is an enlarged view of structure A of the utility model.
[0030] Figure 8 It is an exploded view of the nozzle structure of the utility model.
[0031] Fig. 9 It is a structural schematic diagram of the shear rod group of the utility model (first state).
[0032] Fig.10 It is a structural schematic diagram of the shear rod group of the utility model (second state).
[0033] Fig.11 It is a sectional view of a water tank of the utility model.
[0034] Description of reference numerals:
[0035] 1. Nozzle; 2. Baffle; 3. Turntable; 4. Guide block; 5. Dial block; 6. Slider; 7. Slide column; 8. Slide groove; 9. Groove; 10. Spring; 11. Lining trolley; 12. Water tank; 13. Water pump; 14. Water supply pipe; 15. Steel pipe rack; 16. Spray pipe; 17. Hydraulic cylinder; 171. Piston rod; 18. Articulated rod; 19. Block. DETAILED DESCRIPTION
[0036] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0037] like Figure 1-11 As shown, a tunnel follow-up mold maintenance device includes a nozzle 1, which is provided with a water hole, and also includes: a plurality of annular baffles 2, which can move inward or outward at the same time to complete the adjustment of the water output of the water hole of the nozzle 1; a turntable 3, which is rotatably connected to the nozzle 1, and the turntable 3 is provided with an annular groove 9, the groove 9 is correspondingly arranged with the baffle 2, and the baffle 2 can slide along the groove 9; a guide block 4 arranged in an inclined direction, the guide block 4 is fixedly connected to the nozzle 1, and the guide block 4 is provided with a slide groove 8 that can guide the baffle 2; a dial block 5, the dial block 5 is fixedly connected to the turntable 3, and when the dial block 5 is dialed, the turntable 3 can be driven to rotate in the nozzle 1.
[0038] When spraying and maintaining the tunnel, the water pressure in the water pipe may not reach the expected position due to the high distance of the arch, so it is necessary to adjust the water pressure in the water pipe. According to Pascal's principle, the water pressure can be adjusted according to the thickness of the water pipe. When spraying and maintaining the tunnel, the water outlet height needs to be adjusted. During the preparation process, the operator will turn the dial block 5 according to the height of the tunnel. At this time, the dial block 5 drives the turntable 3 to rotate. When the turntable 3 rotates, the baffle 2 will slide in the groove 9, and will guide the moving direction of the baffle 2 under the action of the guide block 4, thereby completing the adjustment of the size of the water hole, and the spray water is sprayed through the nozzle 1 onto the cast lining to complete the spraying and maintenance of the tunnel top, and the maintenance effect is better.
[0039] The nozzle 1 is provided with at least one card slot 10, and the dial block 5 is connected to the card block 19 through a spring. The card block 19 can be matched with one of the card slots 10 respectively. When it is necessary to dial the dial block 5, the staff needs to press the card block 19, and the card block 19 is disengaged from the card slot 10. At this time, the dial block 5 is dialed, and after the size of the water hole is adjusted, the card block 19 is released. The card block 19 will be pushed into the card slot 10 under the action of the spring, thereby completing the fixation of the dial block 5.
[0040] A slider 6 is fixedly connected to the bottom of the baffle 2, and the slider 6 is placed in the groove 9 and slidably connected to the turntable 3. When the baffle 2 moves, it will move in the groove 9 under the action of the slider 6. The setting of the groove 9 and the slider 6 can not only limit the baffle 2, but also enable the baffle 2 to move better, thereby completing the adjustment of the size of the water hole.
[0041] A sliding column 7 is fixedly connected to the top of the baffle 2, and the sliding column 7 is placed in the slide groove 8 and slidably connected to the guide block 4. The setting of the sliding column 7 can guide the baffle 2, so that the two adjacent baffles 2 fit together when moving, and there will be no gap between the two baffles 2 for water to flow through, which ensures the water pressure of the spraying water and the maintenance effect. It should be noted that the length of the slide groove 8 must be less than the length from the sliding column 7 to the midpoint of the groove 9, otherwise the baffle 2 will completely block the water hole and the water flow cannot be sprayed out.
[0042] It also includes a lining trolley 11, which is detachably connected to a water tank 12, and a water pump 13 is fixedly connected to the water tank 12. The water pump 13 is connected to the nozzle 1 through a water supply pipe 14. When assembling the lining trolley 11, the water tank 12 needs to be bolted to the lining trolley 11.
[0043] It also includes several groups of shear rod assemblies, which include two hinged rods 18 hinged to each other end to end, the middle positions of the two hinged rods 18 are hinged through a central axis 20, and the adjacent shear fork groups are connected through a hinge axis 21. The two hinged rods 18 are fixedly connected with a spray pipe 16, the spray pipe 16 is connected to the water supply pipe 14, and the spray pipe 16 is connected to the sprinkler 1. One end of the spray pipe 16 is fixedly connected with a flange, and the flange is rotatably connected to the turntable 3. This arrangement can prevent water leakage when the operator turns the dial block 5. For example, when spraying and curing the cast lining, the length can be adjusted by adjusting the shear rod assembly to adjust the spraying area of the spray pipe 16. When the lining trolley 11 is used in normal times, the shear rod assembly can be shortened, which will not cause inconvenience during construction, facilitates the operation of construction personnel, and effectively reduces the labor intensity of the maintenance cost. The extension length of the shear rod assembly can be determined according to the length of the tunnel second lining formwork, thereby ensuring the maintenance efficiency and preventing possible damage to the spray device during the moving construction of the lining trolley.
[0044] The ends of the two articulated rods 18 are both hinged with an end shaft 22, the lining trolley 11 is fixedly connected to the steel pipe frame 15, the steel pipe frame 15 is fixedly connected to the hydraulic cylinder 17, the hydraulic cylinder 17 includes a piston rod 171, the end shaft 22 at the leftmost end is hinged with the piston rod 171, wherein the center axis 20 of the end shaft 22 near the leftmost end is fixedly connected to the steel pipe frame 15, the hydraulic cylinder 17 drives the two articulated rods 18 to rotate around the center axis 20, when the spray area needs to be adjusted, the hydraulic cylinder 17 needs to be started, and the piston rod 171 opens. The two hinged rods 18 start to move, and drive the two hinged rods 18 to rotate around the end point axis 22. The two hinged rods 18 hinged to the central axis 20 fixedly connected to the steel pipe frame 15 will rotate, and under the action of the central axis 20, the shear rod assembly will be deformed, and then the spray pipe 16 will be adjusted, thereby driving the entire shear rod assembly to be stored. When the piston rod 171 contracts, the above steps will be performed in reverse, driving the entire shear rod assembly to extend, thereby completing the adjustment of the position of the spray pipe 16 and ensuring the spraying area.
[0045] The water supply pipe 14 is a rubber hose, which can be freely stored or unfolded without causing breakage, and is light in weight, so that the shear rod assembly can better support the water supply pipe 14 .
[0046] The following is a detailed explanation:
[0047] When the tunnel needs to be lined and maintained, the lining trolley 11 needs to be assembled. When assembling the lining trolley 11, the water tank 12 needs to be bolted to the lining trolley 11, and then the steel pipe frame 15 is welded, and the hydraulic cylinder 17 is welded on the steel pipe frame 15, and two hinged rods 18 are hinged at the piston rod 171 of the hydraulic cylinder 17, and at the same time, an articulated shaft is welded on the steel pipe frame 15, and the articulated shaft is also hinged with two articulated rods 18. The water tank 12 is connected to the water supply pipe 14, and the water supply pipe 14 is connected to the spray pipe 16 through a flange, and the spray pipe 16 is connected to the nozzle 1, and finally the spray pipe 16 is installed on the shear rod assembly, and finally the assembly of the lining trolley 1 is completed.
[0048] After assembling the lining trolley 11, the size of the water outlet of the sprinkler head 1 is adjusted according to the tunnel that needs to be maintained. The operator toggles the dial block 5, and the staff presses the card block 19. At this time, the card block 19 is out of the card slot 10. At this time, the dial block 5 is toggled. After the adjustment of the size of the water hole is completed, the card block 19 is released. The card block 19 will be pushed into the card slot 10 under the action of the spring, thereby completing the fixation of the dial block 5. At this time, the dial block 5 drives the turntable 3 to rotate. When the turntable 3 rotates, the baffle 2 will slide in the groove 9, and will play a guiding role in the moving direction of the baffle 2 under the action of the guide block 4, thereby completing the adjustment of the size of the water hole.
[0049] When the tunnel needs to be sprayed for maintenance, the operator starts the hydraulic cylinder 17, and the piston rod 171 will be retracted. At this time, under the action of the central axis 20 welded to the steel pipe rack 15, the shear rod assembly drives the spray pipe 16 to extend. At this time, the water pump 13 is started, and the water pump 13 fills water into the water supply pipe 14, and finally the maintenance water is sprayed out from the nozzle 1 to complete the maintenance of the tunnel. During normal construction, the shear rod assembly is in a stored state and does not need to occupy more space, thereby ensuring the maintenance efficiency and preventing the possible damage to the spray device during the mobile construction of the lining trolley.
[0050] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.
Claims
1. A tunnel mold maintenance device, comprising a nozzle (1), wherein the nozzle (1) is provided with a water hole, It is characterized in that Also includes: A plurality of baffles (2) are arranged in an annular shape, and the plurality of baffles (2) can move inward or outward at the same time to adjust the water flow rate of the water hole of the spray head (1); A rotating disk (3), the rotating disk (3) is rotatably connected to the nozzle (1), the rotating disk (3) is provided with an annular groove (9), the groove (9) is arranged corresponding to the baffle (2), and the baffle (2) can slide along the groove (9); A guide block (4) arranged in an inclined direction, the guide block (4) is fixedly connected to the nozzle (1), and the guide block (4) is provided with a slide groove (8) capable of guiding the baffle (2); A shifting block (5) is fixedly connected to the rotating disk (3). When the shifting block (5) is shifted, the rotating disk (3) can be driven to rotate in the spray head (1).
2. A tunnel follower mold maintenance device according to claim 1, It is characterized in that The shifting block (5) is connected to a clamping block (19) via a spring, the spray head (1) is provided with at least one clamping slot (10), and the clamping block (19) can be matched with one of the clamping slots (10) respectively.
3. A tunnel follower mold maintenance device according to claim 1, It is characterized in that A slider (6) is fixedly connected to the bottom of the baffle (2), and the slider (6) is slidably disposed in the groove (9).
4. A tunnel follower mold maintenance device according to claim 1, It is characterized in that A sliding column (7) is fixedly connected to the top of the blocking piece (2), and the sliding column (7) is slidably arranged in the sliding groove (8).
5. A tunnel follower mold maintenance device according to claim 1, It is characterized in that It also comprises a spray trolley (11), the spray trolley (11) being detachably connected to a water tank (12), a water pump (13) being connected inside the water tank (12), and the water pump (13) being connected to the spray head (1) via a water supply pipe (14).
6. A tunnel follower mold maintenance device according to claim 5, It is characterized in that It also comprises a plurality of shear rod assemblies, wherein the shear rod assemblies comprise two hinged rods (18) hinged to each other end to end, the middle positions of the two hinged rods (18) are hinged via a central axis (20), adjacent shear fork groups are connected via a hinge axis (21), and the two hinged rods (18) are fixedly connected with a spray pipe (16), the spray pipe (16) is connected to the water supply pipe (14), and the spray pipe (16) is connected to the spray head (1).
7. A tunnel follower mold maintenance device according to claim 6, It is characterized in that The ends of the two hinged rods (18) are both hinged with end shafts (22); the lining trolley (11) is fixedly connected with a steel pipe frame (15); the steel pipe frame (15) is fixedly connected with a hydraulic cylinder (17); the hydraulic cylinder (17) includes a piston rod (171); the end shaft (22) at the leftmost end is hinged with the piston rod (171).
8. A tunnel follower mold maintenance device according to claim 7, It is characterized in that The central axis (20) of the end axis (22) close to the leftmost end is fixedly connected to the steel pipe frame (15), and the hydraulic cylinder (17) drives the two hinged rods (18) to rotate around the central axis (20).
9. A tunnel follower mold maintenance device according to claim 8, It is characterized in that The water supply pipe (14) is a rubber hose.