Dry hanging stone slotting operation device on construction site
By designing a dry-hanging stone grooving operating device suitable for different grooving structures, combined with the marble saw's belt dust collection device, the problems of low stone processing accuracy and safety hazards at the construction site are solved, and high-efficiency, low-loss stone grooving is achieved. Groove work.
Patent Information
- Application Number
- CN202323580800.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2033-12-26
AI Technical Summary
During the construction of stone curtain walls at the construction site, the stone processing accuracy was low, threatening worker safety, and it was unable to adapt to different slotting structures, resulting in extended construction periods and high stone loss.
Design a dry-hanging stone grooving operation device that includes a main support frame, a transmission component, a grooving component, a connecting component and a sub-supporting component. It adapts to a variety of grooving devices through comprehensive connection fasteners to adjust the grooving angle and position. Combined with the marble saw's dust suction device, low-dust, efficient grooving operations are achieved.
It improves the accuracy and safety of grooving, reduces stone loss, improves construction efficiency, is suitable for stones of different shapes and thicknesses, and reduces the risk of dust exposure.
Smart Images

Figure CN221912717U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field, and more specifically to a dry-hanging stone slotting operation device at a construction site. Background Art
[0002] At present, in order to reduce the processing cost of stone materials, when dry-hanging stone curtain walls are constructed on construction sites, construction units often do not groove the incoming stones at the construction site, but hang them while grooving. At the same time, the position of the stone curtain wall keel and the accuracy of the hangers directly affect the position of the stone grooves. For construction projects with tight schedules, it is impossible to uniformly process the grooves in the stone factory. When grooving at the construction site, workers basically use handheld power tools to manually groove, which has low processing accuracy, and the stone grooves are easily damaged. The broken saw blades are easy to injure people, and there is a lot of dust, which is harmful to human health. In this way, an operating platform that can groove stones at any time on the construction site is needed to solve the problem of stone grooves. However, with the development of the times, the shape of stone grooves is also changing, and it is not limited to one groove structure.
[0003] Based on this, those skilled in the art urgently need to design a dry-hanging stone slotting operation device that can be applied to different slotting structures. Utility Model Content
[0004] In view of this, the utility model provides a construction site dry hanging stone grooving operation device, which performs deformation grooving by changing the grooving angle; and by using comprehensive connecting fasteners, it can be compatible with a variety of grooving devices to achieve precise grooving.
[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0006] A construction site dry hanging stone slotting operation device, comprising: a main support frame, a conveying component, a slotting component, a connecting component and a sub-support component;
[0007] The sub-support component is connected to one side of the main support frame;
[0008] The sub-supporting component is movably connected to the slotted component via the connecting component;
[0009] The conveying component is fixed to the top surface of the main supporting frame, and the connection state of the fixed support rod and the adjusting cross bar in the sub-support component is adjusted to make the slotted component cooperate with the conveying component, so that the stone slab placed on the conveying component contacts the working end of the slotted component.
[0010] Preferably, the conveying component comprises: a monomer conveying component and a calibration component;
[0011] Both ends of the plurality of said monomer conveying components are fixedly connected to the inner wall of the top surface of the main supporting frame at a preset interval;
[0012] The calibration component is arranged on the top surface of the main support frame and is slidably connected to the top surface of the main support frame.
[0013] Preferably, the single-body conveying component is a conveying rod comprising a plurality of universal balls.
[0014] Preferably, it also includes a moving part and a water supply part;
[0015] The moving part is connected to the bottom surface of the supporting leg of the main supporting frame;
[0016] The water supply component is movably connected to the supporting legs of the main supporting frame.
[0017] Preferably, the sub-support components include: the fixed support rod, the adjustment cross rod, and the vertical support rod;
[0018] One end of the two fixed support rods is respectively fixedly connected to the two corners of the same side of the main support frame, and the other end is respectively movably connected to the two ends of the adjustment cross bar;
[0019] One end of n vertical support rods is slidably connected to the adjusting cross bar, and the other end is movably connected to the main support frame; n≥2.
[0020] Preferably, the slotted component comprises:
[0021] A support that is clamped with an adjacent pair of vertical support rods;
[0022] A slotting device movably connected to the support.
[0023] Preferably, one end of the two fixed support rods is respectively fixedly connected to the two corners of the same side of the main support frame, and the other end is respectively movably connected to the two ends of the adjustment cross bar, specifically:
[0024] Among them, the other ends of the two fixed support rods are respectively connected to the two ends of the adjusting cross bar in a limiting manner to limit the contact angle between the stone slab and the working end of the slotted component.
[0025] Preferably, the support is provided with a variety of holes to match a variety of slotters.
[0026] Preferably, the connecting component comprises: a plurality of slide rails and a plurality of sliders;
[0027] The slotted component is engaged with the slide block through the slide rail fixed on the vertical support rod;
[0028] The slotted component is engaged with the slide block and matched with the slide rail fixed on the adjusting cross bar;
[0029] The vertical support rod is fixedly connected to the sliding block and cooperates with the sliding rail fixed on the main support frame.
[0030] Preferably, it also includes a locking device (7);
[0031] A plurality of locking devices (7) are circumferentially arranged on the top outer wall of the main support frame and are movably connected to the top outer wall of the main support frame, and cooperate with the marking component and the fixed support rod to lock the position of the stone slab.
[0032] It can be seen from the above technical solutions that, compared with the prior art, the utility model discloses a construction site dry-hanging stone slotting operation device; (1) Based on the comprehensive connection fastener, it can adapt to a variety of different types of slotters, such as electric drills and marble saws; by changing the angle of the device where the slotter is set, slots of different shapes can be cut to meet the needs of the development of the times for slotting structures. (2) Centralized slotting operations can be carried out according to the position of the dry-hanging stone hangers on the construction site, and centralized processing can be carried out in the stone stacking area, reducing the danger of manual slotting operations with handheld marble saws in the hanging basket. At the same time, the utility model has no specific requirements for the thickness of stones commonly used in stone curtain walls. Stones of 25-50mm can be used for operations with the utility model, and can be adjusted according to the slotting position. Single slots or multiple slots can be formed at one time. At the same time, by utilizing the adjustable angle of the marble saw, the utility model can unlock the horizontal sliding assembly of the marble saw adapter plate to perform chamfering cutting of materials such as stone and tiles, and has a wide range of applications. (3) The utility model is characterized by having no power cutting device, and the cost is relatively low. The construction site can use the leftover steel pipes used for curtain wall construction to make the frame, and the cost of the frame is low. All sliding components are conventional finished parts on the market, and no customization is required. They are easy to purchase and replace after damage. In addition, the marble saw uses a dust suction device to achieve low-dust grooving, reducing the amount of dust inhaled by the grooving personnel. (4) The use of the utility model for stone grooving construction can improve the construction efficiency by 20% compared with the traditional grooving while hanging stones, reduce the stone loss rate by 5%, and achieve a 100% grooving accuracy. For ground grooving operations, the safety factor is increased by 100%. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0034] Figure 1 The accompanying drawing is a schematic diagram of the overall structure of the utility model.
[0035] Figure 2 The accompanying drawing is a schematic diagram of the structure of the connecting component in the utility model.
[0036] In the figure: 11 square frame, 12 supporting legs, 13 first supporting beam, 14 second supporting beam, 3 conveying component, 31 single conveying component, 32 calibration component, 31 conveying rod, 41 support, 51 slide rail, 52 slider, 21 fixed support rod, 22 adjusting cross bar, 23 vertical support rod, 6 moving component, 7 locking device. DETAILED DESCRIPTION
[0037] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0038] Example 1
[0039] The utility model embodiment discloses a construction site dry hanging stone slotting operation device, comprising: a main support frame, a conveying component 3, a slotting component, a connecting component and a sub-support component;
[0040] The sub-support component is connected to one side of the main support frame;
[0041] The sub-supporting parts are movably connected to the slotted parts through the connecting parts;
[0042] The conveying component 3 is fixed to the top surface of the main support frame, and the connection state of the fixed support rod 21 and the adjusting cross bar 22 in the sub-support component is adjusted to make the slotting component cooperate with the conveying component 3, so that the stone slab placed on the conveying component 3 contacts the working end of the slotting component.
[0043] Specifically:
[0044] The transmission component 3 includes: a single transmission component 31 and a calibration component 32;
[0045] Both ends of the plurality of monomer conveying components 31 are fixedly connected to the inner wall of the top surface of the main support frame at a preset interval;
[0046] The calibration component 32 is disposed on the top surface of the main support frame and is slidably connected to the top surface of the main support frame. In this embodiment, the calibration component 32 is a calibration caliper, and a scale is provided on the surface of the top surface of the main support frame;
[0047] The single transmission component 31 is a transmission rod 31 including a plurality of universal balls. Both ends of the plurality of transmission rods 31 are welded to the inner wall of the top surface of the main support frame in a uniform direction;
[0048] It also includes a moving part 6 and a water supply part;
[0049] The moving part 6 is connected to the bottom surface of the supporting leg 12 of the main supporting frame;
[0050] The water supply component is movably connected to the support legs 12 of the main support frame. Specifically: In this embodiment, the main support frame includes: a square frame 11, support legs 12, a first support beam 13, and a second support beam 14; the four support legs 12 are respectively welded to the four top corners of the bottom surface of the square frame 11, and the two support legs 12 arranged on the same side are fixedly connected through a first support beam 13; the two ends of a second support beam 14 are respectively fixedly connected to two oppositely arranged first support beams 13. The movable component 6 is a universal wheel with a locking function, and the load-bearing requirement is not less than 300kg.
[0051] The sub-support components include: a fixed support rod 21, an adjustable cross rod 22, and a vertical support rod 23;
[0052] One end of the two fixed support rods 21 is fixedly connected to the two corners of the same side of the main support frame, and the other end is movably connected to the two ends of the adjustment cross bar 22;
[0053] One end of the n vertical support rods 23 is slidably connected to the adjustment cross bar 22, and the other end is movably connected to the main support frame; n≥2.
[0054] Slotted parts include:
[0055] A support 41 engaged with an adjacent pair of vertical support rods 23;
[0056] A slotting device movably connected to the support 41.
[0057] One end of the two fixed support rods 21 is fixedly connected to the two corners of the same side of the main support frame, and the other end is movably connected to the two ends of the adjustment cross bar 22. Specifically:
[0058] The other ends of the two fixed support rods 21 are respectively connected to the two ends of the adjusting cross bar 22 to limit the contact angle between the stone slab and the working end of the slotted component.
[0059] The support 41 is provided with a variety of holes to match a variety of slotters. The connecting components include: a plurality of slide rails 51, a plurality of sliders 52;
[0060] The slotted part and the slider 52 are engaged with the slide rail 51 fixed on the vertical support rod 23;
[0061] The slotted part is engaged with the slide block 52 and matched with the slide rail 51 fixed on the adjustment crossbar 22;
[0062] The vertical support rod 23 is fixedly connected to the slide block 52 and matched with the slide rail 51 fixed on the main support frame.
[0063] Also includes a locking device 7;
[0064] A plurality of locking devices 7 are circumferentially arranged on the top outer wall of the main support frame, and are movably connected to the top outer wall of the main support frame, and cooperate with the calibration component 32 and the fixed support rod 21 to lock the position of the stone slab. Specifically, in this embodiment, the locking device 7 cooperates with the scale locking device on the calibration component 32 and the fixed support rod 21 to lock the position of the stone slab.
[0065] In actual application, workers place the stone slab on the conveying component 3, and fix the position of the stone slab on the conveying component 3 based on the locking device 7, the calibration component 32 and the fixed support rod 21; use the calibration component 32 to mark the groove position; move the adjusting cross bar 22 to change the angle between the adjusting cross bar 22 and the fixed support rod 21, and change the height of the groove component based on the connecting component so that different shapes can be grooved when the working end of the groove component works on the stone slab.
[0066] In actual use, the slotting tool produces a lot of dust when slotting the stone slab, so a water supply component is added, and the water supply pipe provided by the water supply component is used to supply water to the slotting component at the working position of the stone slab. In addition, in actual application, the slotting tool is selected according to the actual work needs.
[0067] Embodiment 2:
[0068] Based on Example 1, this example further discloses the following contents:
[0069] In the present embodiment 2, the main support frame, the sub-support frame, the transmission component 3, the support 41, the connecting component, and the calibration component 32 are all made of steel materials, and in the present embodiment, a marble saw adapter plate is used as the support 41;
[0070] In this embodiment, the main support frame is composed of four 800mm high 60*60*3mm galvanized square steel pipes as support legs 12. At a height of 500mm from the ground, 50*50*3mm galvanized square steel pipes are used as the first support beam 13 and the second support beam 14 to weld the support legs 12 into a bracket shape.
[0071] Moreover, in this embodiment, the top surface of the main support frame is assembled with galvanized square steel pipes and heavy universal balls, 60*80*3mm galvanized square steel pipes are used to weld into a square frame 11, 60*80*3mm galvanized square steel pipes are used as purlins and welded with the square frame 11, with a center distance of 130mm, and the universal balls are installed on the purlins with screws to form the transmission rod 31 of this embodiment. When the stone is grooved, the top surface of the main support frame plays the role of holding the stone and moving the stone horizontally and vertically.
[0072] In addition, in the present embodiment 1, the marble saw adapter plate is made of 5mm thick galvanized steel plate by stamping, and is used to fix the marble saw. The hole of the marble saw adapter plate is adapted to the size of the marble saw bottom plate, and is fixedly connected to the marble saw by M6 hexagon socket screws. The sliding module connected to the marble saw adapter plate is fixedly connected by M6 hexagon socket screws.
[0073] Furthermore, in this embodiment, the support frame is welded by a fixed support rod 21, an adjustable cross bar 22, and a vertical support rod 23. The fixed support rod 21 adopts a 60*60*3mm galvanized square steel pipe and is welded to the top surface of the main support frame. The adjustable cross bar 22 adopts a 60*80*3mm galvanized square steel pipe and is welded to the fixed support rod 21.
[0074] It should be noted that in this embodiment, the connecting parts fixedly connected to the vertical support rod 23 and the adjusting cross rod 22 are assembled by two sets of vertical and horizontal sliding components connected by M6 hexagonal screws, and two marble saw adapter plates are provided, so that single-sided double hangers of large slabs of stone can be grooved and formed at one time.
[0075] In this embodiment, the horizontal sliding assembly uses a finished linear slide rail and a dustproof slider, model SBR25, with a load-bearing capacity of 300kg and a circular track diameter of 25mm. The slider uses a dustproof slider with good sealing and a built-in locking device, which consists of two slide rails and 8 sliders. It is connected and fixed to the sliding module steel frame by M6 hexagon socket screws.
[0076] The vertical sliding assembly adopts a finished linear slide rail and a dustproof slider, model SBR25, with a load-bearing capacity of 300kg and a circular track diameter of 25mm. The slider adopts a dustproof slider with good sealing and a built-in locking device. A set of marble saw adapter plate sliding groups is composed of two slide rails 51 and four sliders 52, which are connected and fixed to the slider 52 of the horizontal sliding assembly through M6 hexagon socket screws. In this embodiment, two sets of marble saw adapter plate sliding groups are set.
[0077] The scale component used in this embodiment is composed of a galvanized square steel pipe and a linear slide rail. The scale rod is made of a 40*40*2mm galvanized square steel pipe welded and made. The connecting component arranged on the top surface of the main support frame is composed of 3 SBR12 linear slide rails plus 3 sliders 52, which are connected and fixed to the top surface of the main support mine building through hexagon socket screws; the scale rod and the connecting component are connected and fixed through hexagon socket screws. Its main function is to serve as a device for fixing the stone and calibrating the slotting position when the stone is slotted. And the device has a built-in locking device, which can be locked on the sliding platform.
[0078] Specifically:
[0079] When in use, the marble saw is installed on the marble saw adapter plate, with the saw body facing the rear side of the platform and the saw blade facing the sliding platform. The stone to be grooved is placed flat on the top surface of the main support frame. According to the position to be grooved, the sliding ruler is adjusted, and the ruler is locked on the top surface of the main support frame. Then, the horizontal position of the sliding block 52 connected to the marble saw adapter plate is adjusted, the horizontal sliding assembly is locked, and then the vertical sliding assembly is adjusted according to the vertical position of the stone groove, the vertical sliding assembly is locked, the marble saw is turned on, the stone is pressed against the ruler rod 32, and pushed toward the marble saw for groove cutting. The marble saw blade can be selected according to the groove thickness. The marble saw blade thickness of the present embodiment is 1.5mm-6mm, the saw blade diameter is 110mm, and the groove depth can be 0-40mm deep.
[0080] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0081] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A construction site dry hanging stone slotting operation device, characterized in that: include: A main support frame, a conveying component (3), a slotting component, a connecting component (5) and a sub-support component; The sub-support component is connected to one side of the main support frame; The sub-support component is movably connected to the slotted component via the connecting component (5); The conveying component (3) is fixed to the top surface of the main support frame, and the connection state of the fixed support rod (21) and the adjustment cross rod (22) in the sub-support component is adjusted so that the slotted component and the conveying component (3) cooperate, so that the stone slab placed on the conveying component (3) contacts the working end of the slotted component; wherein the conveying component (3) comprises: a single conveying component (3) and a calibration component (32); Both ends of the plurality of monomer conveying components (3) are fixedly connected to the inner wall of the top surface of the main support frame at a preset interval; The calibration component (32) is arranged on the top surface of the main support frame and is slidably connected to the top surface of the main support frame.
2. The construction site dry hanging stone slotting operation device according to claim 1 is characterized in that: The single-body transmission component (3) is a transmission rod (31) comprising a plurality of universal balls.
3. The construction site dry hanging stone slotting operation device according to claim 1 is characterized in that: It also includes a moving part (6) and a water supply part; The moving component (6) is connected to the bottom surface of the supporting leg of the main supporting frame; The water supply component is movably connected to the supporting legs of the main supporting frame.
4. The construction site dry hanging stone slotting operation device according to claim 1 is characterized in that: The sub-support components include: the fixed support rod (21), the adjustment cross rod (22), and a vertical support rod (23); One end of the two fixed support rods (21) is respectively fixedly connected to two corners on the same side of the main support frame, and the other end is respectively movably connected to two ends of the adjustment cross bar (22); One end of the n vertical support rods (23) is slidably connected to the adjustment cross rod (22), and the other end is movably connected to the main support frame; n≥2.
5. The construction site dry hanging stone slotting operation device according to claim 4 is characterized in that: The slotted component comprises: A support (41) that is clamped to a pair of adjacent vertical support rods (23); A slotting device movably connected to the support (41).
6. The construction site dry hanging stone slotting operation device according to claim 4 is characterized in that: One end of the two fixed support rods (21) is respectively fixedly connected to the two corners of the same side of the main support frame, and the other end is respectively movably connected to the two ends of the adjustment cross bar (22), specifically: The other ends of the two fixed support rods (21) are respectively connected to the two ends of the adjusting cross bar (22) in a limiting manner, thereby limiting the contact angle between the stone slab and the working end of the slotted component.
7. The construction site dry hanging stone slotting operation device according to claim 5, characterized in that: The support (41) is provided with a variety of holes, which are compatible with a variety of slotters.
8. The construction site dry hanging stone slotting operation device according to claim 4, characterized in that: The connecting component (5) comprises: a plurality of slide rails (51) and a plurality of slide blocks (52); The slotted component and the slide block (52) are engaged with the slide rail (51) fixed on the vertical support rod (23); The slotted component and the slide block (52) are engaged with the slide rail (51) fixed on the adjustment cross bar (22); The vertical support rod (23) is fixedly connected to the sliding block (52) and cooperates with the sliding rail (51) fixed on the main support frame.
9. A construction site dry hanging stone slotting operation device according to any one of claims 2 to 6, characterized in that: Also includes a locking device; A plurality of locking devices are circumferentially arranged on the top outer wall of the main support frame and are movably connected to the top outer wall of the main support frame, and cooperate with the marking component (32) and the fixed support rod (21) to lock the position of the stone slab.