Temporary construction platform for underwater pile foundation construction
By designing fixed components on the underwater pile foundation construction platform, and using the cooperation of threaded rods and adjustment blocks, the Bailey beam can be quickly connected and disassembled, which solves the problem of inconvenient installation and disassembly of the existing platform and improves construction efficiency.
Patent Information
- Application Number
- CN202420444693.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-07
AI Technical Summary
The existing temporary construction platform for underwater pile foundation construction is inconvenient during installation and disassembly, which affects construction efficiency.
A temporary construction platform is designed, which uses a Bailey beam with a connecting frame on the left side and a connecting block on the right side. A fixed through hole is opened on the front of the connecting block, and fixed components are installed on the inside, including a fixed frame, a chute, an adjusting frame, The fixed plate, limit groove and threaded rod drive the threaded rod to rotate through the adjusting button, driving the adjusting block and fixed plate to move, thereby realizing the limit function of connection and disassembly.
The installation and disassembly efficiency of Bailey beams is improved, the device structure is simplified, the operation is more convenient, and the construction efficiency is improved.
Smart Images

Figure CN221919016U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of underwater pile foundation construction devices, in particular to a temporary construction platform for underwater pile foundation construction. Background Art
[0002] The underwater pile foundation construction of the cross-river bridge requires the construction of an above-water working platform to carry the pile foundation drilling construction equipment and construction personnel. The general above-water working platform is based on steel pipe piles, which are built in a grid shape with steel sections on the steel pipe piles and covered with panels on the top. The existing temporary construction platform for underwater pile foundation construction uses Bailey beams when it is built, but the existing Bailey beams are inconvenient to install and disassemble, which affects the construction efficiency.
[0003] Therefore, a temporary construction platform for underwater pile foundation construction is needed to improve the above problems. Utility Model Content
[0004] The purpose of the utility model is to provide a temporary construction platform for underwater pile foundation construction to solve the problems raised in the above background technology.
[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0006] A temporary construction platform for underwater pile foundation construction, comprising a Bailey beam, wherein the upper and lower sides of the left side of the Bailey beam are symmetrically provided with connection frames, the upper and lower sides of the right side of the Bailey beam are symmetrically provided with connection blocks, the front side of the connection blocks is provided with a fixing through hole, and the inner side of the connection frame is provided with a fixing component;
[0007] The fixing assembly includes a fixing frame, the outer end of the fixing frame is symmetrically provided with a sliding groove, a first adjusting frame is slidably arranged on the front side of the fixing frame, and a second adjusting frame is slidably arranged on the rear side of the fixing frame, a first fixing plate is arranged on the outer side surface of the first adjusting frame, and a second fixing plate is arranged on the outer side surface of the second adjusting frame, fixing rods are arranged on the inner sides of the first fixing plate and the second fixing plate, limiting grooves are arranged on the front side and the back side of the first adjusting frame, an adjusting block is slidably arranged between the first adjusting frame and the second adjusting frame, limiting rods are symmetrically arranged on the front and rear sides of the adjusting block, a threaded rod is rotatably arranged on the base surface of the adjusting block, and an adjusting button is arranged on the inner end of the threaded rod through the fixing frame.
[0008] As a preferred solution of the utility model, the connection frame is arranged in a "U"-shaped structure, and the connection block is adapted to correspond to the connection frame.
[0009] As a preferred solution of the utility model, the outer side surface of the fixing frame is fixedly connected to the connecting frame.
[0010] As a preferred solution of the present invention, sliding blocks are provided on the left and right sides of the first adjustment frame and the second adjustment frame corresponding to the slide grooves.
[0011] As a preferred solution of the utility model, the first adjustment frame and the second adjustment frame are both arranged in a "right-angled trapezoid" structure, and the adjustment block is arranged in an "isosceles trapezoid" structure.
[0012] As a preferred solution of the utility model, the threaded rod is threadedly connected to the fixing frame.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] In the utility model, by arranging a fixing component on a temporary construction platform used for underwater pile foundation construction, when the Bailey beams are connected, the connecting blocks on the adjacent Bailey beams are clamped inside the connecting frame, and the threaded rod can be driven to rotate by the adjusting button, and the threaded rod drives the adjusting block to move when rotating, thereby driving the first fixing plate and the second fixing plate to move under the cooperation of the first adjusting frame and the second adjusting frame, and when the fixing rod moves to the inside of the fixing through hole, the connecting block can be limited, so that the connection is completed, and when the fixing rod moves to the outside of the fixing through hole, the adjacent Bailey beams can be disassembled, so that it is more convenient to install and disassemble, and the construction efficiency is increased. The overall device has a simple structure, is easy to operate, and is more practical. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is the overall front view of the utility model;
[0016] Figure 2 This is a structural diagram of the fixed component of the utility model;
[0017] Figure 3 This is a partial structural diagram of the utility model.
[0018] In the figure: 1. Bailey beam; 2. connecting frame; 3. connecting block; 4. fixing through hole; 5. fixing component; 501. fixing frame; 502. slide groove; 503. first adjustment frame; 504. second adjustment frame; 505. first fixing plate; 506. second fixing plate; 507. fixing rod; 508. limiting groove; 509. adjusting block; 510. limiting rod; 511. threaded rod; 512. adjusting button. DETAILED DESCRIPTION
[0019] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0020] For examples, see Figure 1-3 , the utility model provides a technical solution:
[0021] A temporary construction platform for underwater pile foundation construction, comprising a Bailey beam 1, a connection frame 2 is symmetrically arranged on the upper and lower sides of the left side of the Bailey beam 1, a connection block 3 is symmetrically arranged on the upper and lower sides of the right side of the Bailey beam 1, a fixing through hole 4 is opened on the front side of the connection block 3, and a fixing component 5 is arranged on the inner side of the connection frame 2;
[0022] In this embodiment, the fixing component 5 includes a fixing frame 501, and the outer end of the fixing frame 501 is symmetrically provided with a slide groove 502, a first adjustment frame 503 is slidably provided on the front side of the fixing frame 501, and a second adjustment frame 504 is slidably provided on the rear side of the fixing frame 501, a first fixing plate 505 is provided on the outer side of the first adjusting frame 503, and a second fixing plate 506 is provided on the outer side of the second adjusting frame 504, and fixing rods 507 are provided on the inner sides of the first fixing plate 505 and the second fixing plate 506, and limiting grooves 508 are provided on the front side of the first adjusting frame 503 and the back side of the second adjusting frame 504, an adjusting block 509 is slidably provided between the first adjusting frame 503 and the second adjusting frame 504, and limiting rods 510 are symmetrically provided on the front and rear sides of the adjusting block 509, a threaded rod 511 is rotatably provided on the base surface of the adjusting block 509, and an adjusting button 512 is provided on the inner end of the threaded rod 511 passing through the fixing frame 501.
[0023] Among them, the connecting frame 2 is arranged in a "U"-shaped structure, the connecting block 3 is adapted to correspond to the connecting frame 2, so that the connecting block 3 can enter the interior of the connecting frame 2, the outer side surface of the fixed frame 501 is fixedly connected to the connecting frame 2, and the left and right sides of the first adjusting frame 503 and the second adjusting frame 504 are provided with sliders corresponding to the slide groove 502. The first adjusting frame 503 and the second adjusting frame 504 can be limited by the slide groove 502 and the slider, so that it is more stable when moving. The first adjusting frame 503 and the second adjusting frame 504 are both arranged in a "right-angled trapezoid" structure, and the adjusting block 509 is arranged in an "isosceles trapezoid" structure. When the adjusting block 509 moves, it can drive the first adjusting frame 503 and the second adjusting frame 504 to move. The threaded rod 511 is threadedly connected to the fixed frame 501, and can be raised and lowered when the threaded rod 511 rotates.
[0024] The working process of the utility model is as follows: when using the temporary construction platform for underwater pile foundation construction, when the Bailey beam 1 is being built, the adjacent Bailey beams 1 are being connected. When connecting, the connecting blocks 3 on the adjacent Bailey beams 1 are clamped inside the connecting frame 2, and then the adjusting button 512 is rotated. The threaded rod 511 can be driven to rotate by the adjusting button 512. Since the threaded rod 511 is connected to the fixed frame 501 in a threaded connection, the threaded rod 511 drives the adjusting block 509 to move when rotating, and the adjusting block 509 drives the first adjusting frame 503 and the second adjusting frame 504 to move when moving, thereby driving the first fixing plate 505 and the second fixing plate 506 to move under the cooperation of the first adjusting frame 503 and the second adjusting frame 504. When the fixing rod 507 moves to the inside of the fixing through hole 4, the connecting block 3 can be limited, so that the connection is completed. When the fixing rod 507 moves to the outside of the fixing through hole 4, the adjacent Bailey beams 1 can be disassembled, which is more convenient during installation and disassembly, thereby increasing the construction efficiency.
[0025] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A temporary construction platform for underwater pile foundation construction, comprising a Bailey beam (1), Features: A connection frame (2) is symmetrically arranged on the upper and lower sides of the left side of the Bailey beam (1), a connection block (3) is symmetrically arranged on the upper and lower sides of the right side of the Bailey beam (1), a fixing through hole (4) is provided on the front side of the connection block (3), and a fixing component (5) is arranged on the inner side of the connection frame (2); The fixing assembly (5) comprises a fixing frame (501), the outer end of the fixing frame (501) is provided with a sliding groove (502) symmetrically on the left and right sides, a first adjustment frame (503) is slidably arranged on the front side of the fixing frame (501), a second adjustment frame (504) is slidably arranged on the rear side of the fixing frame (501), a first fixing plate (505) is arranged on the outer side of the first adjustment frame (503), a second fixing plate (506) is arranged on the outer side of the second adjustment frame (504), the first fixing plate (505) and the second fixing plate (506) are arranged on the outer side of the second adjustment frame (504), and the first fixing plate (505) and the second fixing plate (506) are arranged on the outer side of the fixing frame (503). 06) are provided with fixing rods (507), the front side of the first adjusting frame (503) and the back side of the second adjusting frame (504) are provided with limiting grooves (508), an adjusting block (509) is slidably arranged between the first adjusting frame (503) and the second adjusting frame (504), limiting rods (510) are symmetrically arranged on the front and rear sides of the adjusting block (509), a threaded rod (511) is rotatably arranged on the base surface of the adjusting block (509), and an adjusting button (512) is arranged on the inner end of the threaded rod (511) passing through the fixing frame (501).
2. A temporary construction platform for underwater pile foundation construction according to claim 1, Features: The connection frame (2) is arranged in a "U"-shaped structure, and the connection block (3) is arranged to be adapted to correspond to the connection frame (2).
3. A temporary construction platform for underwater pile foundation construction according to claim 1, Features: The outer side surface of the fixing frame (501) is fixedly connected to the connecting frame (2).
4. A temporary construction platform for underwater pile foundation construction according to claim 1, Features: Slide blocks are provided on the left and right sides of the first adjustment frame (503) and the second adjustment frame (504) corresponding to the slide groove (502).
5. A temporary construction platform for underwater pile foundation construction according to claim 1, Features: The first adjustment frame (503) and the second adjustment frame (504) are both arranged in a "right-angled trapezoid" structure, and the adjustment block (509) is arranged in an "isosceles trapezoid" structure.
6. A temporary construction platform for underwater pile foundation construction according to claim 1, Features: The threaded rod (511) is threadably connected to the fixing frame (501).