Variable-span bridge girder erection machine

By introducing the design of a double-rod hydraulic cylinder and adjustable feet into the bridge erecting machine, the problem of the offset of the landing point of the auxiliary legs when erecting bridges of different spans is solved, the precise adjustment of the position of the legs is achieved, and the cost of the bridge and the The offset between preset positions improves construction efficiency.

CN221919028UActive Publication Date: 2024-10-29HENAN ZHONGYUAN AOQI IND
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422301370.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-10-29
Estimated Expiration
2034-09-20

AI Technical Summary

Technical Problem

When the existing variable-span bridge erecting machine is erecting bridges with different spans, the slight inclination of the main beam causes the landing point of the auxiliary legs to deviate, resulting in an offset between the bridge and the preset position, which increases the construction workload.

Method used

A bridge erecting machine is designed that includes a main beam, an upper beam, a lower beam, a lifting hydraulic cylinder, a double-rod hydraulic cylinder and an adjustable foot. The double-rod hydraulic cylinder drives the pillar sliding and the adjustable foot adjustment to realize the bridge erection. Precise adjustment of outrigger position to compensate for offset of landing point.

Benefits of technology

It effectively reduces the offset between the lifting bridge and the preset position, improving the erection efficiency and the accuracy of construction work.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221919028U_ABST
    Figure CN221919028U_ABST
Patent Text Reader

Abstract

The utility model provides a variable span bridge girder erection machine which comprises a main beam and an upper cross beam, the top of the upper cross beam is provided with a walking mechanism used for driving the upper cross beam to move along the main beam, and a lower cross beam parallel to the upper cross beam is arranged below the upper cross beam. A piston rod of the lifting driving hydraulic cylinder is downwards and vertically arranged at the top of the upper cross beam, a supporting column is fixedly arranged at the bottom end of the lifting driving hydraulic cylinder, and the bottom end of the supporting column is in sliding connection with the lower cross beam; a double-rod hydraulic cylinder is fixedly arranged at the top of the lower cross beam, and the ends of two piston rods of the double-rod hydraulic cylinder are fixedly connected with the side faces of the two supporting columns correspondingly. According to the utility model, after the auxiliary supporting leg is fixedly supported on the bridge pier, when the drop point of the auxiliary supporting leg deviates, the two piston rods of the double-rod hydraulic cylinder can be controlled to synchronously act, and the stand column is driven by the double-rod hydraulic cylinder to slide in the lower cross beam, so that the offset of the drop point is compensated, and the offset between a hoisting bridge and a preset position of the hoisting bridge is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of bridge erection machines, and in particular relates to a bridge erection machine with a variable span. Background Art

[0002] The bridge erection machine is a device that places the prefabricated beams on the prefabricated bridge piers. The bridge erection machine belongs to the category of cranes because its main function is to lift the beams, transport them to the location and then put them down. The variable span bridge erection machine can adapt to the new span requirements through specific operations during the construction process to meet the construction of bridges with different spans.

[0003] In the prior art, a Chinese utility model patent document with authorization announcement number CN218116174U discloses a single-girder four-leg universal bridge-building machine with rapid span change. When building bridges of different spans, it is only necessary to determine the fixed position of the auxiliary legs according to the span of the bridge to be built, and move the auxiliary legs according to the determined fixed position. There is no need to adjust the length of the main beam, and the span change can be completed quickly under the premise of ensuring stability. During the span change process, due to the slight inclination of the main beam, the landing point of the auxiliary legs on the pier will be offset. In this way, when the bridge is built, there will be a certain offset between the bridge and the preset position, which needs to be adjusted again, increasing the construction workload.

[0004] Therefore, it is necessary to design a variable-span bridge erecting machine that can adjust the position of the outriggers and reduce the offset between the hoisted bridge and its preset position to solve the current technical problems. Summary of the invention

[0005] In view of the deficiencies in the prior art, the utility model provides a variable span bridge erecting machine capable of adjusting the positions of the outriggers to reduce the offset between the hoisted bridge and its preset position.

[0006] The technical solution of the utility model is: a variable-span bridge-building machine, comprising a main beam and an upper crossbeam, the top of the upper crossbeam is provided with a walking mechanism for driving it to move along the main beam, and a lower crossbeam parallel to the upper crossbeam is provided below the upper crossbeam; both ends of the upper crossbeam are provided with a lifting drive hydraulic cylinder, the piston rod of the lifting drive hydraulic cylinder is vertically arranged downward on the top of the upper crossbeam, the bottom end of the lifting drive hydraulic cylinder is fixedly provided with a pillar, and the bottom end of the pillar is slidably connected to the lower crossbeam; the top of the lower crossbeam is fixedly provided with a double-rod hydraulic cylinder, and the two piston rod ends of the double-rod hydraulic cylinder are respectively fixedly connected to the side surfaces of the two pillars.

[0007] A support plate is fixedly arranged inside the lower cross beam in the horizontal direction, a slideway is provided inside the lower cross beam above the support plate, a slide plate is arranged at the bottom of the slideway, a slider is slidably arranged on the top of the slider, a connecting column is fixedly arranged at the bottom end of the pillar, and the connecting column is vertically fixedly arranged on the top of the slider.

[0008] A support plate is evenly and fixedly arranged between the bottom of the supporting plate and the inner bottom of the lower cross beam.

[0009] The slide plate is an MGE slide plate fixedly arranged on the top of the support plate.

[0010] An adjustable foot is provided at the bottom of the lower cross beam, and the adjustable foot has an upper foot fixedly provided at the bottom of the lower cross beam, a lower foot is slidably sleeved on the outer side of the lower end of the upper foot, a foot adjustment hydraulic cylinder is fixedly provided inside the lower foot, and the upper end of the foot adjustment hydraulic cylinder is fixedly connected to the inner top of the upper foot.

[0011] A convex edge slidably arranged inside the lower base foot is fixedly arranged on the outer side of the bottom end of the upper base foot, and a stop edge corresponding to the convex edge is arranged on the inner side of the upper end of the lower base foot.

[0012] The tops of both ends of the lower cross beam are provided with travel switches corresponding to the pillars.

[0013] Beneficial effects of the utility model: In the utility model, after the auxiliary support leg is fixedly supported on the bridge pier, when it is found that the landing point is offset, the two piston rods of the double-rod hydraulic cylinder can be controlled to move synchronously, and the double-rod hydraulic cylinder can drive the support to slide in the lower beam to compensate for the offset of the landing point, thereby reducing the offset between the lifting bridge and its preset position. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of the variable-span bridge erecting machine in the utility model.

[0015] Figure 2 It is a schematic diagram of the connection structure between the lower end of the support column and the lower cross beam in the utility model.

[0016] Figure 3 It is a structural schematic diagram of the adjustable foot in the utility model. DETAILED DESCRIPTION

[0017] Various exemplary embodiments of the present invention will now be described in detail with reference to the accompanying drawings. The description of the exemplary embodiments is merely illustrative and is not intended to be any limitation on the present invention and its application or use. The present invention can be implemented in many different forms and is not limited to the embodiments described herein. These embodiments are provided to make the present invention thorough and complete and to fully express the scope of the present invention to those skilled in the art. It should be noted that unless otherwise specifically stated, the relative arrangement of the components and steps, the composition of the materials, the numerical expressions and the numerical values ​​set forth in these embodiments should be interpreted as being merely exemplary and not as limitations.

[0018] The words "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different parts. The words "include" or "comprise" and similar words mean that the elements before the word include the elements listed after the word, and do not exclude the possibility of including other elements. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0019] like Figures 1 to 3 As shown, a variable-span bridge-building machine comprises a main beam 1 and an upper cross beam 4, a walking mechanism 2 for driving the upper cross beam 4 to move along the main beam 1 is arranged on the top of the upper cross beam 4, a lower cross beam 5 parallel to the upper cross beam 4 is arranged below the upper cross beam 4, both ends of the upper cross beam 4 are provided with a lifting drive hydraulic cylinder 3, the piston rod of the lifting drive hydraulic cylinder 3 is vertically arranged downward on the top of the upper cross beam 4, a support 6 is fixedly arranged at the bottom end of the lifting drive hydraulic cylinder 3, and the bottom end of the support 6 is slidably connected to the lower cross beam 5; a double-rod hydraulic cylinder 7 is fixedly arranged on the top of the lower cross beam 5, and the two piston rod ends of the double-rod hydraulic cylinder 7 are respectively fixedly connected to the side surfaces of the two support pillars 6; in this embodiment, after the auxiliary support leg is fixedly supported on the bridge pier, when it is found that its landing point is offset, the two piston rods of the double-rod hydraulic cylinder 7 can be controlled to move synchronously, and the support pillar 6 can be driven by the double-rod hydraulic cylinder 7 to slide in the lower cross beam 5, so as to compensate for the offset of the landing point and reduce the offset between the lifting bridge and its preset position.

[0020] In some embodiments, Figure 2As shown, a support plate 51 is fixedly provided inside the lower cross beam 5 in the horizontal direction, a slideway 53 is provided inside the lower cross beam 5 above the support plate 51, a slide plate 54 is provided at the bottom of the slideway 53, a slider 61 is slidably provided on the top of the slider 54, a connecting column 62 is fixedly provided at the bottom end of the pillar 6, the connecting column 62 is vertically fixedly provided on the top of the slider 61, the bottom end of the pillar 6 is connected to the slider 61 through the connecting column 62, the slider 61 slides inside the slideway 53, realizing the sliding connection between the pillar 6 and the lower cross beam 5, the slide plate 54 has a low friction coefficient, which can reduce the friction force of the slider 61 sliding inside the slideway 53, thereby ensuring smooth adjustment.

[0021] In some embodiments, a support plate 52 is evenly fixed between the bottom of the support plate 51 and the inner bottom of the lower cross beam 5. The upper and lower sides of the support plate 52 are respectively fixedly connected to the bottom of the support plate 51 and the lower cross beam 5 to form an integrated structure. The support plate 52 provides support to the bottom of the support plate 51, thereby ensuring the strength of the support plate 51.

[0022] In some embodiments, the skateboard 54 is an MGE skateboard fixedly arranged on the top of the support plate 51. The characteristics of the MGE skateboard mainly include good elasticity and impact resistance, low friction coefficient, self-lubrication and maintenance-free, high load-bearing capacity and seismic resistance, wear resistance and corrosion resistance, no peeling and strong shear resistance, low water absorption and good dimensional stability.

[0023] In some embodiments, Figure 3 As shown, an adjustable foot 8 is provided at the bottom of the lower cross beam 5, and the adjustable foot 8 has an upper foot 82 fixedly arranged at the bottom of the lower cross beam 5, and a lower foot 81 is slidably sleeved on the outer side of the lower end of the upper foot 82, and a foot adjustment hydraulic cylinder 84 is fixedly provided inside the lower foot 81, and the upper end of the foot adjustment hydraulic cylinder 84 is fixedly connected to the inner top of the upper foot 82. The upper foot 82 can be driven to move in the lower foot 81 through the foot adjustment hydraulic cylinder 84, thereby realizing the height adjustment of the adjustable foot 8 to adapt to the tops of piers with different heights, so that the adjustable foot 8 is in good contact with the tops of the piers, and good support is guaranteed.

[0024] In some embodiments, a flange 83 slidably disposed inside the lower base 81 is fixedly disposed on the outer side of the bottom end of the upper base 82 , and a retaining edge 85 corresponding to the flange 83 is disposed on the inner side of the upper end of the lower base 81 .

[0025] In some embodiments, when the double-rod hydraulic cylinder 7 drives the two pillars 6 to move synchronously to the two ends of the lower beam 5, in order to avoid affecting the stability of the support due to excessive moving distance, travel switches 9 corresponding to the pillars 6 are provided at the top of both ends of the lower beam 5. When the double-rod hydraulic cylinder 7 drives the two pillars 6 to move synchronously to the lower beam 5, the corresponding travel switch 9 is triggered when the maximum position that may affect the stability of the support is reached. After the travel switch 9 is triggered, the double-rod hydraulic cylinder 7 is controlled to stop moving, thereby limiting the continued movement of the pillars 6.

[0026] So far, various embodiments of the present invention have been described in detail. In order to avoid obscuring the concept of the present invention, some details known in the art are not described. Based on the above description, those skilled in the art can fully understand how to implement the technical solution disclosed here.

[0027] The above-mentioned embodiments only express some implementation methods of the utility model, and the description is relatively specific and detailed, but it cannot be understood as limiting the scope of the utility model patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the utility model, which all belong to the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.

Claims

1. A variable span bridge erecting machine, characterized in that: It includes a main beam and an upper cross beam, the top of the upper cross beam is provided with a walking mechanism for driving it to move along the main beam, and a lower cross beam parallel to the upper cross beam is provided below the upper cross beam; both ends of the upper cross beam are provided with lifting drive hydraulic cylinders, the piston rod of the lifting drive hydraulic cylinder is vertically arranged downward on the top of the upper cross beam, and a pillar is fixedly arranged at the bottom end of the lifting drive hydraulic cylinder, and the bottom end of the pillar is slidably connected to the lower cross beam; a double-rod hydraulic cylinder is fixedly arranged on the top of the lower cross beam, and the two piston rod ends of the double-rod hydraulic cylinder are respectively fixedly connected to the side surfaces of the two pillars.

2. The variable span bridge erecting machine according to claim 1, characterized in that: A support plate is fixedly arranged inside the lower cross beam in the horizontal direction, a slideway is provided inside the lower cross beam above the support plate, a slide plate is arranged at the bottom of the slideway, a slider is slidably arranged on the top of the slider, a connecting column is fixedly arranged at the bottom end of the pillar, and the connecting column is vertically fixedly arranged on the top of the slider.

3. The variable span bridge erecting machine according to claim 2, characterized in that: A support plate is evenly and fixedly arranged between the bottom of the supporting plate and the inner bottom of the lower cross beam.

4. The variable span bridge erecting machine according to claim 2, characterized in that: The slide plate is an MGE slide plate fixedly arranged on the top of the support plate.

5. The variable span bridge erecting machine according to claim 1, characterized in that: An adjustable foot is provided at the bottom of the lower cross beam, and the adjustable foot has an upper foot fixedly provided at the bottom of the lower cross beam, a lower foot is slidably sleeved on the outer side of the lower end of the upper foot, a foot adjustment hydraulic cylinder is fixedly provided inside the lower foot, and the upper end of the foot adjustment hydraulic cylinder is fixedly connected to the inner top of the upper foot.

6. The variable span bridge erecting machine according to claim 5, characterized in that: A convex edge slidably arranged inside the lower base foot is fixedly arranged on the outer side of the bottom end of the upper base foot, and a stop edge corresponding to the convex edge is arranged on the inner side of the upper end of the lower base foot.

7. The variable span bridge erecting machine according to claim 1, characterized in that: The tops of both ends of the lower cross beam are provided with travel switches corresponding to the pillars.