Steel member reinforcing device

Through the steel component reinforcement device, prefabricated segments and support components are used to surround the columns and support beams, which solves the problem of column overloading, achieves rapid increase in load-bearing capacity and space saving, and meets the temporary reinforcement needs of building construction and renovation.

CN221920408UActive Publication Date: 2024-10-29MIGUEL (WUHAN) CONSTR TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420371451.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-28
Publication Date
2024-10-29
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

During building construction and renovation, columns may be damaged due to overloading. Existing temporary reinforcement measures such as adding cables or support rods will damage the appearance of the structure or occupy too much space, and cannot effectively improve the load-bearing capacity of the columns.

Method used

Steel component reinforcement devices are used to set prefabricated segments and support components around the columns, adjust the height to support the cross beams, and use tie rods and telescopic screws to connect to achieve rapid installation and disassembly, enhance the load-bearing capacity of the columns, and reduce space occupation.

Benefits of technology

It can quickly and effectively improve the load-bearing capacity of columns to meet construction needs, avoid damage to the original structure, and can be reused to reduce construction delays and cost increases.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221920408U_ABST
    Figure CN221920408U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel member reinforcing device which comprises a device body arranged around a stand column, the device body is located between a cross beam and the ground, the device body comprises prefabricated sections and a supporting assembly, the prefabricated sections are arranged in the axial direction of the stand column, and the overlapped parts of the adjacent prefabricated sections are connected through pull rods. One end of the supporting assembly is connected with the topmost prefabricated section of the device body, and the other end abuts against the cross beam; the prefabricated section comprises a first section and a second section, the first section comprises a first base and a first panel, the first base is rotatably connected with the first panel, the second section comprises a second base and a second panel, and the second base is rotatably connected with the second panel; the device can be arranged around a stand column needing to be reinforced, the height of the device can be adjusted according to the height of the stand column, the device and the stand column jointly support a cross beam, the bearing capacity of the stand column can be rapidly improved, occupation of the internal space of a building is reduced, meanwhile, an original structure cannot be damaged, and the device can be detached and repeatedly used after construction is finished.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building reinforcement, in particular to a steel component reinforcement device. Background Art

[0002] During the construction and renovation of buildings, some columns are often affected by various factors, resulting in overload. For example, the movement of heavy equipment, the accumulation of large amounts of materials, and unforeseen construction loads may cause the columns to be subjected to pressures that exceed their designed bearing capacity. In this case, if there are no timely temporary reinforcement measures, the columns may be damaged due to insufficient bearing capacity, which will not only threaten the overall safety of the building structure, but may also lead to construction delays and increased costs.

[0003] Existing temporary reinforcement measures include adding temporary cables or support rods, which can share the pressure of the columns. However, these measures also have some limitations. Adding additional temporary cables in the building requires setting up multiple anchor points, which will damage the appearance of the original structure. Adding additional temporary support rods will occupy too much space inside the building, affecting the normal progress of construction.

[0004] Therefore, a temporary reinforcement structure is needed to solve the above problems. Summary of the invention

[0005] The purpose of the utility model is to provide a steel member reinforcement device in view of the problems existing in the prior art.

[0006] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0007] A steel member reinforcement device comprises a device body arranged around a column, the device body being located between a beam and the ground, the device body comprising prefabricated segments and a support assembly, the prefabricated segments being arranged along the axial direction of the column, the overlapping parts of adjacent prefabricated segments being interconnected by a tie rod, one end of the support assembly being connected to the topmost prefabricated segment of the device body, and the other end being supported against the beam; the prefabricated segments comprising a first section and a second section, the first section comprising a first base and a first panel, the first base and the first panel being rotatably connected, the second section comprising a second base and a second panel, the second base and the second panel being rotatably connected.

[0008] The utility model is composed of a plurality of prefabricated segments and the supporting components, can be arranged around the columns that need to be reinforced, adjust its own height according to the height of the columns, and support the crossbeams together with the columns, so as to quickly and effectively improve the bearing capacity of the columns, reduce the occupation of the internal space of the building and will not cause damage to the original structure. When installing the prefabricated segments, simple and fast installation can be achieved by opening and closing the first panel and the second panel. After the construction is completed, the panels can be dismantled and reused to meet the actual needs in the process of building construction and renovation.

[0009] Preferably, the first section is arranged above the second section, the projections of the first section and the second section on the horizontal plane are both rectangular, and the projection of the second section on the horizontal plane is located within the projection of the first section on the horizontal plane, and the second section is used to be inserted into the first section of the adjacent prefabricated segment.

[0010] When the upper and lower adjacent prefabricated segments are installed, the second segment of the upper prefabricated segment is inserted into the first segment of the lower prefabricated segment, so that the second segment of the upper prefabricated segment overlaps with the first segment of the lower prefabricated segment.

[0011] Preferably, the first section is provided with a plurality of first connecting holes, which are arranged around the first section, the second section is provided with a plurality of second connecting holes, which are arranged around the second section, and the pull rod passes through the overlapping parts of adjacent prefabricated sections through the first connecting holes and the second connecting holes.

[0012] Preferably, the pull rod is distributed on both sides of the column, and limiting nuts are respectively provided at both ends of the pull rod.

[0013] The tie rod passes through the overlapping parts of the prefabricated segments and fixes the upper and lower adjacent prefabricated segments together. Finally, the tie rod is fixed by a limit nut to prevent the tie rod from accidentally falling out.

[0014] Preferably, the support assembly includes a support plate, a telescopic screw and a connecting rod, the support plate is used to support the crossbeam, the telescopic screws are respectively provided on both sides of the support plate, one end of the telescopic screw is hinged to the connecting rod, and the other end is hinged to the support plate.

[0015] The telescopic screw rod facilitates adjustment of the support angle of the support assembly and enables the support assembly to cope with beams located at different heights.

[0016] Preferably, the support assembly is arranged on both sides of the column, and the connecting rod is connected to the prefabricated segment through the first connecting hole or the second connecting hole.

[0017] Compared with the prior art, the beneficial effects of the utility model are:

[0018] The utility model is composed of a plurality of prefabricated segments and supporting components, which can be arranged around the columns that need to be reinforced, adjust their own height according to the height of the columns, and support the crossbeams together with the columns, so as to quickly and effectively improve the bearing capacity of the columns, reduce the occupation of the internal space of the building and will not cause damage to the original structure. When installing the prefabricated segments, simple and fast installation can be achieved by opening and closing the first panel and the second panel. After the construction is completed, the panels can be dismantled and reused to meet the actual needs in the process of construction and renovation. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the structure of an embodiment of the utility model;

[0020] Figure 2 This is a schematic diagram of the state when the prefabricated segments are installed in the embodiment of the utility model;

[0021] Figure 3 This is a schematic diagram of the structure of the prefabricated segment in the embodiment of the utility model;

[0022] Figure 4 This is a schematic diagram of the structure of the first section in the embodiment of the utility model. Figure 1 ;

[0023] Figure 5 This is a schematic diagram of the structure of the first section in the embodiment of the utility model. Figure 2 ;

[0024] Figure 6 This is a schematic diagram of the structure of the support assembly in the embodiment of the utility model;

[0025] Figure 7 This is a schematic diagram of the structure of the support assembly after removing the support plate in the embodiment of the utility model;

[0026] In the figure: 1. column; 2. beam; 3. prefabricated segment; 4. first section; 401. first base; 402. first panel; 403. first connecting hole; 5. second section; 501. second base; 502. second panel; 503. second connecting hole; 6. pull rod; 7. support assembly; 8. support plate; 9. telescopic screw; 10. connecting rod; 11. ear plate. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the utility model to clearly and completely describe the technical solution of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0028] In the description of the present invention, it should be noted that the directions or positional relationships indicated by terms such as "middle", "upper", "lower", "left", "right", "inside" and "outside" are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0029] like Figures 1 to 7 As shown, the specific scheme of the embodiment is as follows: a steel structure reinforcement device is suitable for temporarily reinforcing a column 1, replacing the column 1 to bear the load of the beam 2 above it, and a steel structure reinforcement device includes a device body arranged around the column 1, the device body is located between the beam 2 and the ground, the bottom of the device body is close to the ground, and the top of the device body is close to the beam 2.

[0030] The device body includes a prefabricated segment 3 and a support assembly 7. The prefabricated segment 3 is arranged along the axial direction of the column 1. One end of the support assembly 7 is connected to the top prefabricated segment 3 of the device body, and the other end supports the beam 2 to expand the contact area between the device body and the beam 2.

[0031] The prefabricated segment 3 includes a first segment 4 and a second segment 5. The first segment 4 is arranged above the second segment 5. The projections of the first segment 4 and the second segment 5 on the horizontal plane are both rectangular, and the projection of the second segment 5 on the horizontal plane is located within the projection of the first segment 4 on the horizontal plane.

[0032] When installing the upper and lower adjacent prefabricated segments 3, the second segment 5 of the upper prefabricated segment 3 is inserted into the first segment 4 of the lower prefabricated segment 3, so that the second segment 5 of the upper prefabricated segment 3 and the first segment 4 of the lower prefabricated segment 3 overlap with each other, and the overlapping parts of the adjacent prefabricated segments 3 are connected to each other through the pull rod 6.

[0033] The first section 4 includes a first base 401 and a first panel 402, and the first base 401 and the first panel 402 are rotatably connected via a first rotating shaft, and the first rotating shaft is arranged on the side of the first panel 402; the second section 5 includes a second base 501 and a second panel 502, and the second base 501 and the second panel 502 are rotatably connected via a second rotating shaft, and the second rotating shaft is arranged on the side of the second panel 502; the first base 401 and the second base 501 are a whole, and the first panel 402 and the second panel 502 can rotate independently.

[0034] When installing the prefabricated segments 3 one by one, the first panel 402 and the second panel 502 are opened so that the prefabricated segments 3 can be arranged around the columns 1 , which also facilitates the installation of the subsequent adjacent prefabricated segments 3 .

[0035] The first section 4 is provided with a plurality of first connection holes 403, the first connection holes 403 are arranged in pairs, and the first connection holes 403 are arranged around the first section 4, at least one pair of first connection holes 403 is provided on the four sides of the first section 4, and on each side of the first section 4, the pairs of first connection holes 403 are arranged at intervals from top to bottom.

[0036] A plurality of second connection holes 503 are provided on the second section 5. The second connection holes 503 are arranged in pairs and are arranged around the second section 5. At least one pair of second connection holes 503 is provided on each of the four surfaces of the second section 5, and on each surface of the second section 5, the pairs of second connection holes 503 are arranged at intervals from top to bottom.

[0037] When the upper and lower adjacent prefabricated segments 3 are connected to each other, in the overlapping part of the adjacent prefabricated segments 3, the partial second connecting hole 503 of the second section 5 of one prefabricated segment 3 will be aligned with the partial first connecting hole 403 of the first section 4 of another prefabricated segment 3, so that the pull rod 6 passes through the first connecting hole 403 and the second connecting hole 503 and penetrates the overlapping part of the adjacent prefabricated segments 3.

[0038] Each pair of tie rods 6 is distributed in parallel on both sides of the column 1, and two pairs of tie rods 6 can be set in each overlapping part. The two pairs of tie rods 6 are located at different heights, and the upper tie rods 6 are perpendicular to the lower tie rods 6 to improve the connection strength of the upper and lower adjacent prefabricated segments 3, thereby improving the bearing capacity of the device body.

[0039] Limit nuts are respectively provided at both ends of the pull rod 6 to prevent the pull rod 6 from accidentally falling out.

[0040] The support assembly 7 is arranged on both sides of the column 1, and the support assembly 7 includes a support plate 8, a telescopic screw 9 and a connecting rod 10. The support plate 8 is used to support the cross beam 2. Telescopic screws 9 are respectively provided on both sides of the support plate 8. One end of the telescopic screw 9 is hinged to the connecting rod 10, and the other end is hinged to the ear plate 11. The support plate 8 is arranged on the two ear plates 11.

[0041] When installing the support assembly 7, first pass the connecting rod 10 through the two opposite first connecting holes 403 or the two opposite second connecting holes 503 of the prefabricated segment 3, then hinge the telescopic screw 9 to the connecting rod 10, and hinge the two ear plates 11 of the support plate 8 to the two telescopic screws 9 respectively, finally adjust the length of the telescopic screw 9, and adjust the angle of the telescopic screw 9 and the support plate 8 so that the support plate 8 can press against the cross beam 2, finally screw nuts on both ends of the connecting rod 10 so that the nuts clamp the connecting rod 10 to prevent the connecting rod 10 from rotating relative to the prefabricated segment 3.

[0042] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A steel member reinforcement device, comprising a device body arranged around a column, the device body being located between a crossbeam and the ground, characterized in that: The device body includes prefabricated segments and support assemblies, the prefabricated segments are arranged along the axial direction of the columns, the overlapping parts of adjacent prefabricated segments are connected to each other by pull rods, one end of the support assembly is connected to the topmost prefabricated segment of the device body, and the other end supports the crossbeam; the prefabricated segments include a first section and a second section, the first section includes a first base and a first panel, the first base and the first panel are rotatably connected, the second section includes a second base and a second panel, the second base and the second panel are rotatably connected.

2. A steel member reinforcement device according to claim 1, characterized in that: The first section is arranged above the second section, the projections of the first section and the second section on the horizontal plane are both rectangular, and the projection of the second section on the horizontal plane is located within the projection of the first section on the horizontal plane, and the second section is used to be inserted into the first section of the adjacent prefabricated segment.

3. A steel member reinforcement device according to claim 1, characterized in that: The first section is provided with a plurality of first connection holes, which are arranged around the first section; the second section is provided with a plurality of second connection holes, which are arranged around the second section; and the pull rod passes through the first connection holes and the second connection holes and penetrates the overlapping parts of adjacent prefabricated sections.

4. A steel member reinforcement device according to claim 3, characterized in that: The pull rods are distributed on both sides of the column, and limiting nuts are respectively provided at both ends of the pull rods.

5. A steel member reinforcement device according to claim 3, characterized in that: The support assembly includes a support plate, a telescopic screw and a connecting rod. The support plate is used to support the crossbeam. The telescopic screws are respectively provided on both sides of the support plate. One end of the telescopic screw is hinged to the connecting rod and the other end is hinged to the support plate.

6. A steel member reinforcement device according to claim 5, characterized in that: The support assembly is arranged on both sides of the column, and the connecting rod is connected to the prefabricated segment through the first connecting hole or the second connecting hole.