Skid-mounted inter-well interconnection series gas lift system

The skid-mounted interconnected series gas lift system between wells solves the problems of low gas well pressure and low gas supply efficiency in multiple wells in oil and gas field development, realizes efficient interconnected gas lift between gas wells, improves production efficiency, and simplifies equipment installation. and transportation.

CN221920924UActive Publication Date: 2024-10-29WUHAN QIDAKANG ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420252534.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-02
Publication Date
2024-10-29
Estimated Expiration
2034-02-02

AI Technical Summary

Technical Problem

During the development and production of oil and gas fields, the later formation pressure decreases, resulting in too low natural gas pressure in gas wells. Some gas wells cannot produce due to liquid accumulation at the bottom of the well. The existing compressor gas lift method may increase the gas well lift time when supplying gas to multiple wells. , affecting production efficiency.

Method used

Design a skid-mounted interconnected series gas lift system between wells. The natural gas in the external pipeline network is compressed through a compressor and injected into the wells. High-pressure separators and sewage manifolds and other equipment are used to connect multiple gas wells to realize gas well inter-well interconnection. Interconnected series gas lift uses the natural gas after lift to improve production efficiency.

Benefits of technology

This system is suitable for situations where there are many gas wells and are widely distributed. It provides a variety of connection methods, improves the production efficiency of gas wells, simplifies the equipment skidding and installation process, reduces the amount of ground engineering and investment costs, and is simple and convenient for later hoisting and transportation. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221920924U_ABST
    Figure CN221920924U_ABST
Patent Text Reader

Abstract

The utility model discloses a skid-mounted interwell interconnection series gas lift system which comprises a compressor skid, a first high-pressure separator, a second high-pressure separator, a third high-pressure separator and a fourth high-pressure separator, an inlet of the compressor skid is communicated with an output pipe network, and an outlet of the compressor skid is communicated with a first natural gas well, a second natural gas well, a third natural gas well and a fourth natural gas well. A compressor skid liquid discharging manifold is connected with an external conveying pipe network, the compressor skid is provided with a fuel gas outlet, the fuel gas outlet is communicated with a generator and connected with a gas inlet of the generator, an outlet of the first natural gas well is connected with an inlet of a first high-pressure separator, and an outlet of the second natural gas well is connected with an outlet of a second high-pressure separator. An outlet of the second natural gas well is connected with an inlet of the second high-pressure separator, an outlet of the third natural gas well is connected with an inlet of the third high-pressure separator, and an outlet of the fourth natural gas well is connected with an inlet of the fourth high-pressure separator.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of natural gas extraction equipment, in particular to a skid-mounted well-to-well interconnected series gas lift system. Background Art

[0002] At present, during the later stages of oil and gas field development and production in my country, the natural gas pressure in the gas wells is too low due to the decrease in formation pressure. Some gas wells cannot produce due to excessive liquid accumulation at the bottom of the wells. The compressor compresses the natural gas and injects high-pressure gas into the gas wells to lift the gas wells. This is a common method to restore the production capacity of gas wells. Compressor gas lift uses the natural gas in the external pipeline network as raw gas to supply the compressor. After compression, the compressor injects it into the well, which increases the pressure in the well and the ability of the gas in the well to carry liquid. The liquid in the gas well is discharged and the gas well resumes production.

[0003] During the compressor gas lift process, if the compressor supplies gas to several wells at the same time, the gas volume may be insufficient, resulting in an increase in the time required to lift the gas wells. Utility Model Content

[0004] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the abstract of the specification and the name of the utility model of this application to avoid blurring the purpose of this section, the abstract of the specification and the name of the utility model, and such simplifications or omissions cannot be used to limit the scope of the utility model.

[0005] In view of the above-mentioned and / or existing problems in the use of skid-mounted well-to-well interconnected series gas lift systems, the present utility model is proposed.

[0006] Therefore, the purpose of the utility model is to provide a skid-mounted well-interconnected series gas lift system, which is suitable for occasions with many gas wells and wide distribution, and has multiple gas well connection methods and strong operability. The natural gas produced after the gas wells are lifted can be used to lift other gas wells, thereby improving production efficiency.

[0007] In order to solve the above technical problems, according to one aspect of the present invention, the present invention provides the following technical solutions:

[0008] A skid-mounted well-to-well interconnected series gas lift system comprising:

[0009] A compressor skid, wherein the inlet of the compressor skid is connected to an external transmission pipeline network, the outlet of the compressor skid is connected to natural gas well 1, well 2, well 3, well 4, the compressor skid is provided with a manifold from the compressor skid outlet to well 1, well 2, well 3, well 4 and a compressor skid air inlet manifold, the compressor skid is provided with a compressor skid liquid discharge manifold, the compressor skid liquid discharge manifold is connected to the external transmission pipeline network, the compressor skid is provided with a gas outlet, the gas outlet is connected to a generator, the gas outlet is connected to the air inlet of the generator, the outlet of natural gas well 1 is connected to the inlet of a first high-pressure separator, the outlet of natural gas well 2 is connected to the inlet of a second high-pressure separator, the outlet of natural gas well 3 is connected to the inlet of a third high-pressure separator, and the outlet of natural gas well 4 is connected to the inlet of a fourth high-pressure separator;

[0010] The first high-pressure separator is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand. The inlet of the second high-pressure separator is provided with a manual flat gate valve. The second high-pressure separator is provided with a first high-pressure separator safety discharge port connected to the vent manifold. The first high-pressure separator is provided with a first high-pressure separator sewage discharge port, and the first high-pressure separator sewage discharge port is connected to the sewage discharge manifold. The outlet of the first high-pressure separator is connected to the inlets of the second well, the third well, the fourth well, and the external transmission pipeline network;

[0011] The second high-pressure separator is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand. The inlet of the second high-pressure separator is provided with a manual flat gate valve. The second high-pressure separator is provided with a second high-pressure separator safety discharge port connected to the vent manifold. The second high-pressure separator is provided with a second high-pressure separator sewage discharge port connected to the sewage manifold. The outlet of the second high-pressure separator is connected to the inlet of the three wells, the four wells, and the external transmission pipeline network;

[0012] A third high-pressure separator, the third high-pressure separator is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand, the inlet of the third high-pressure separator is provided with a manual flat gate valve, the third high-pressure separator is provided with a third high-pressure separator safety discharge port connected to the vent manifold, the third high-pressure separator safety discharge port is provided with a third high-pressure separator sewage discharge port connected to the sewage discharge manifold, and the outlet of the third high-pressure separator is connected to the four-well inlet and the external transmission pipeline network;

[0013] The fourth high-pressure separator is provided with a vent manifold, the fourth high-pressure separator is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand, the inlet of the fourth high-pressure separator is provided with a manual flat gate valve, the fourth high-pressure separator is provided with a fourth high-pressure separator safety discharge port connected to the vent manifold, the fourth high-pressure separator is provided with a fourth high-pressure separator sewage outlet connected to the sewage manifold, and the outlet of the fourth high-pressure separator is connected to the external transmission pipeline network.

[0014] As a preferred solution of a skid-mounted well-to-well interconnected series gas lift system described in the utility model, the first high-pressure separator outlet is provided with a first high-pressure separator outlet manifold, and the first high-pressure separator outlet manifold is provided with a first high-pressure separator outlet flowmeter, the second high-pressure separator outlet is provided with a second high-pressure separator outlet manifold, and the second high-pressure separator outlet manifold is provided with a second high-pressure separator outlet flowmeter, the third high-pressure separator outlet is provided with a third high-pressure separator outlet manifold, and the third high-pressure separator outlet manifold is provided with a third high-pressure separator outlet flowmeter, the fourth high-pressure separator outlet is provided with a fourth high-pressure separator outlet manifold, and the fourth high-pressure separator outlet manifold is provided with a fourth high-pressure separator outlet flowmeter, the fourth high-pressure separator is connected to an outlet manifold, the outlet manifold is provided with a manual needle throttle valve and an outlet flowmeter, and the sewage manifold is provided with a pressure stabilizing tank.

[0015] As a preferred solution of the skid-mounted well-to-well interconnected series gas lift system described in the utility model, the first high-pressure separator, the second high-pressure separator, the third high-pressure separator and the fourth high-pressure separator are all horizontal separators.

[0016] As a preferred solution of a skid-mounted well-interconnected series gas lift system described in the utility model, a first high-pressure separator outlet to the second well is provided with an inlet manifold from the first high-pressure separator outlet to the second well and an inlet manifold from the first high-pressure separator outlet to the third well and the fourth well, and the first high-pressure separator outlet manifold is connected to the inlet manifold from the first high-pressure separator outlet to the second well and the inlet manifold from the first high-pressure separator outlet to the third well and the fourth well.

[0017] As a preferred solution of a skid-mounted well-interconnected series gas lift system described in the utility model, a first high-pressure separator outlet to three wells inlet manifold is provided, and the first high-pressure separator outlet to three wells and four wells inlet manifolds are connected to the first high-pressure separator outlet to three wells inlet manifold.

[0018] As a preferred solution of a skid-mounted well-interconnected series gas lift system described in the utility model, a second high-pressure separator outlet to four wells is provided with a second high-pressure separator outlet to four wells inlet manifold, and a second high-pressure separator outlet to three wells inlet manifold is provided from the second high-pressure separator outlet to three wells, and the second high-pressure separator outlet manifold is connected to the second high-pressure separator outlet to four wells inlet manifold, the second high-pressure separator outlet to three wells inlet manifold and the outlet manifold.

[0019] As a preferred solution of the skid-mounted well-interconnected series gas lift system described in the utility model, a third high-pressure separator outlet to four wells inlet manifold is provided, and the third high-pressure separator safety relief port is connected to the third high-pressure separator outlet to four wells inlet manifold and outlet manifold.

[0020] As a preferred solution of the skid-mounted well-to-well interconnected series gas lift system described in the utility model, the fourth high-pressure separator outlet manifold is connected to the outlet manifold.

[0021] Compared with the prior art, the utility model has the following beneficial effects: the skid-mounted well-interconnected series gas lift system is suitable for situations where there are many gas wells and they are widely distributed, and has multiple gas well connection modes and strong operability; the natural gas produced after the gas wells are lifted can be used to lift other gas wells, thereby improving production efficiency;

[0022] The integrated setting can be quickly installed and assembled at the production site. The equipment is skid-mounted to reduce ground engineering workload and investment costs, shorten the on-site installation cycle, and make subsequent lifting and transportation simple and convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solution of the implementation of the utility model, the utility model will be described in detail below in combination with the drawings and detailed implementation. Obviously, the drawings described below are only some implementations of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:

[0024] Figure 1 The utility model is a schematic diagram of the structure of a skid-mounted well-to-well interconnected series gas lift system.

[0025] 1. External transmission pipeline network; 2. Well 1; 3. First high-pressure separator; 4. Safety discharge port of first high-pressure separator; 5. Outlet manifold of first high-pressure separator; 6. Outlet flowmeter of first high-pressure separator; 7. Outlet of first high-pressure separator to inlet manifold of Well 2; 8. Outlet of first high-pressure separator to inlet manifold of Well 3 and Well 4; 9. Well 2; 10. Second high-pressure separator; 11. Safety discharge port of second high-pressure separator; 12. Outlet manifold of second high-pressure separator; 13. Outlet flowmeter of second high-pressure separator; 14. Outlet of second high-pressure separator to inlet manifold of Well 4; 15. Outlet of first high-pressure separator to inlet manifold of Well 3; 16. Outlet of second high-pressure separator to inlet manifold of Well 3; 17. Well 3; 18. Third high-pressure separator; 19. Safety discharge port of third high-pressure separator; 20. Outlet manifold of third high-pressure separator ; 21. Flowmeter at the outlet of the third high-pressure separator; 22. The outlet of the third high-pressure separator to the inlet manifold of the fourth well; 23. The fourth well; 24. The fourth high-pressure separator; 25. The safety discharge port of the fourth high-pressure separator; 26. The outlet manifold of the fourth high-pressure separator; 27. The outlet flowmeter of the fourth high-pressure separator; 28. The generator; 29. ​​The gas outlet; 30. The compressor pry; 31. The compressor pry outlet to the manifolds of the first well, the second well, the third well and the fourth well; 32. The compressor pry inlet manifold; 33. The compressor pry liquid discharge manifold; 34. The sewage outlet of the first high-pressure separator; 35; The sewage manifold; 36. The outlet manifold; 37. The sewage outlet of the second high-pressure separator; 38. The sewage outlet of the third high-pressure separator; 39. The sewage outlet of the fourth high-pressure separator; 40. The pressure regulating tank; 41. The manual needle throttle valve; 42. The outlet flowmeter; 43. The vent manifold. DETAILED DESCRIPTION

[0026] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and understandable, the specific implementation methods of the present invention are described in detail below with reference to the accompanying drawings.

[0027] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the implementation of the present invention in detail, for the sake of convenience, the cross-sectional diagram showing the device structure will not be partially enlarged at a general scale, and the schematic diagram is only an example, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0028] In order to make the purpose, technical solution and advantages of the present invention more clear, the implementation mode of the present invention will be further described in detail below with reference to the accompanying drawings.

[0029] The utility model provides a skid-mounted well-interconnected series gas lift system, which is suitable for situations where there are many gas wells and they are widely distributed. It has multiple gas well connection modes and strong operability. The natural gas produced after the gas wells are lifted can be used to lift other gas wells, thereby improving production efficiency.

[0030] Figure 1 The structure diagram of a skid-mounted well-to-well interconnected series gas lift system according to the utility model is shown. Figure 1 The present embodiment is a skid-mounted well-to-well interconnected series gas lift system, the main part of which includes a compressor skid 30, a first high-pressure separator 3, a first high-pressure separator 10, a first high-pressure separator 18 and a first high-pressure separator 24.

[0031] A compressor skid 30, wherein the inlet of the compressor skid 30 is connected to the external transmission pipeline network 1, and the outlet of the compressor skid 30 is connected to the natural gas well 2, the well 9, the well 17, and the well 23. The compressor skid 30 is provided with a manifold 31 from the compressor skid outlet to the well 1, the well 2, the well 3, and the well 4, and a compressor skid air inlet manifold 32. The compressor skid 30 is provided with a compressor skid liquid discharge manifold 33, and the compressor skid liquid discharge manifold 33 is connected to the external transmission pipeline network 1. The compressor skid 30 is provided with a gas outlet 29, and the gas outlet 29 is connected to the generator 28, and the gas outlet 29 is connected to the air inlet of the generator 28. The outlet of the natural gas well 2 is connected to the inlet of the first high-pressure separator 3, the outlet of the natural gas well 9 is connected to the inlet of the second high-pressure separator 10, the outlet of the natural gas well 17 is connected to the inlet of the third high-pressure separator 18, and the outlet of the natural gas well 23 is connected to the inlet of the fourth high-pressure separator 24;

[0032] The first high-pressure separator 3 is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand. The inlet of the second high-pressure separator 10 is provided with a manual flat gate valve. The second high-pressure separator 10 is provided with a first high-pressure separator safety discharge port 4 connected to the vent manifold 43. The first high-pressure separator 3 is provided with a first high-pressure separator sewage outlet 34. The first high-pressure separator sewage outlet 34 is connected to the sewage manifold 35. The outlet of the first high-pressure separator 3 is connected to the inlets of the second well 9, the third well 17, the fourth well 23, and the external transmission pipeline network 1. In implementation, the first high-pressure separator 3 outlet to the second well 9 is provided with the first high-pressure separator outlet to the second well inlet manifold 7 and the first high-pressure separator outlet to the third and fourth well inlet manifolds 8, the first high-pressure separator outlet manifold 5 is connected with the first high-pressure separator outlet to the second well inlet manifold 7 and the first high-pressure separator outlet to the third and fourth well inlet manifolds 8, the first high-pressure separator 3 outlet to the third well 17 is provided with the first high-pressure separator outlet to the third well inlet manifold 15, the first high-pressure separator outlet to the third and fourth well inlet manifolds 8 is connected with the first high-pressure separator outlet to the third well inlet manifold 15;

[0033] The second high-pressure separator 10 is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand. The inlet of the second high-pressure separator 10 is provided with a manual flat gate valve. The second high-pressure separator 10 is provided with a second high-pressure separator safety discharge port 11 connected to the venting manifold 43. The second high-pressure separator 10 is provided with a second high-pressure separator sewage discharge port 37 connected to the sewage discharge manifold 35. The outlet of the second high-pressure separator 10 is connected to the inlet of the three wells 17 and the four wells 23, and the external transmission pipeline network 1. In this embodiment, the second high-pressure separator 10 outlet to the four wells 23 is provided with a second high-pressure separator outlet to the four wells inlet manifold 14, the second high-pressure separator 10 outlet to the three wells 17 is provided with a second high-pressure separator outlet to the three wells inlet manifold 16, and the second high-pressure separator outlet manifold 12 is connected to the second high-pressure separator outlet to the four wells inlet manifold 14, the second high-pressure separator outlet to the three wells inlet manifold 16 and the outlet manifold 36;

[0034] The third high-pressure separator 18 is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand. The inlet of the third high-pressure separator 18 is provided with a manual flat gate valve. The third high-pressure separator 18 is provided with a third high-pressure separator safety discharge port 19 connected to the venting manifold 43. The third high-pressure separator safety discharge port 19 is provided with a third high-pressure separator sewage discharge port 38 connected to the sewage discharge manifold 35. The outlet of the third high-pressure separator 18 is connected to the inlet of the four wells 23 and the external transmission pipeline network 1. In this embodiment, the outlet of the third high-pressure separator 18 to the four wells 23 is provided with a third high-pressure separator outlet to the four wells inlet manifold 22, and the third high-pressure separator safety discharge port 19 is connected to the third high-pressure separator outlet to the four wells inlet manifold 22 and the outlet manifold 36;

[0035] The fourth high-pressure separator 24 is provided with a vent manifold 43, the fourth high-pressure separator 24 is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand, the inlet of the fourth high-pressure separator 24 is provided with a manual flat gate valve, the fourth high-pressure separator 24 is provided with a fourth high-pressure separator safety discharge port 25 connected to the vent manifold 43, the fourth high-pressure separator 24 is provided with a fourth high-pressure separator sewage outlet 39 connected to the sewage manifold 35, the outlet of the fourth high-pressure separator 24 is connected to the external transmission pipeline network 1, in this embodiment, the outlet of the first high-pressure separator 3 is provided with a first high-pressure separator outlet manifold 5, the first high-pressure separator outlet manifold 5 is provided with a first high-pressure separator outlet flowmeter 6, the outlet of the second high-pressure separator 10 is provided with a second high-pressure separator outlet manifold 12, the second high-pressure separator A second high-pressure separator outlet flowmeter 13 is provided on the outlet manifold 12 of the separator, a third high-pressure separator outlet manifold 20 is provided at the outlet of the third high-pressure separator 18, a third high-pressure separator outlet flowmeter 21 is provided on the third high-pressure separator outlet manifold 20, a fourth high-pressure separator outlet manifold 26 is provided at the outlet of the fourth high-pressure separator 24, a fourth high-pressure separator outlet flowmeter 27 is provided on the fourth high-pressure separator outlet manifold 26, the fourth high-pressure separator 24 is connected to an outlet manifold 36, a manual needle throttle valve 41 and an outlet flowmeter 42 are provided on the outlet manifold 36, a pressure stabilizing tank 40 is provided on the sewage manifold 35, the first high-pressure separator 3, the second high-pressure separator 10, the third high-pressure separator 18 and the fourth high-pressure separator 24 are all horizontal separators, and the fourth high-pressure separator outlet manifold 26 is connected to the outlet manifold 36.

[0036] Combination Figure 1 The present embodiment is a skid-mounted well-to-well interconnected series gas lift system. The specific use process is as follows: the raw gas from the external transmission pipeline 1 enters the compressor skid 30, and the high-pressure gas compressed after being processed in the compressor skid 30 is injected into the gas well. According to the system operation, it can be divided into single gas well gas lift, multi-well series gas lift, series gas lift with well cutting gas lift and parallel gas lift. It only needs to connect the corresponding natural gas well with the high-pressure separator device.

[0037] Single-well gas lift: the outlet of the compressor skid 30 is connected to the inlet of the natural gas well 2, the outlet of the natural gas well 2 is connected to the inlet of the first high-pressure separator 3, and the outlet of the first high-pressure separator 3 is connected to the first high-pressure separator outlet manifold 5, the outlet manifold 36, and the external transmission pipeline network 1.

[0038] The compressor skid 30 outlet is connected to the inlet of the second natural gas well 9 , the second natural gas well 9 outlet is connected to the inlet of the second high-pressure separator 10 , and the second high-pressure separator 10 outlet is connected to the second high-pressure separator outlet manifold 12 , the outlet manifold 36 , and the external transmission pipeline 1 .

[0039] The compressor skid 30 outlet is connected to the inlet of the natural gas three wells 17, the natural gas three wells 17 outlet is connected to the inlet of the third high-pressure separator 18, and the third high-pressure separator 18 outlet is connected to the third high-pressure separator outlet manifold 20, the outlet manifold 36, and the external transmission pipeline network 1.

[0040] The outlet of the compressor skid 30 is connected to the inlet of the fourth natural gas well 23 , the outlet of the fourth natural gas well 23 is connected to the inlet of the fourth high-pressure separator 24 , and the outlet of the fourth high-pressure separator 24 is connected to the fourth high-pressure separator outlet manifold 26 , the outlet manifold 36 , and the external transmission pipeline network 1 .

[0041] Multi-well gas lift: the outlet of compressor skid 30 is connected to the inlet of natural gas well 1 2, the outlet of natural gas well 1 2 is connected to the inlet of the first high-pressure separator 3, the outlet of the first high-pressure separator 3 is connected to the inlet of natural gas well 2 9, the outlet of natural gas well 2 3 is connected to the inlet of the second high-pressure separator 10, the outlet of the second high-pressure separator 9 is connected to the inlet of natural gas well 3 17, the outlet of natural gas well 3 17 is connected to the inlet of the third high-pressure separator 18, the outlet of the third high-pressure separator 18 is connected to the inlet of natural gas well 4 23, the outlet of natural gas well 4 23 is connected to the inlet of the fourth high-pressure separator 24, and the outlet of the fourth high-pressure separator 24 is connected to the external transmission pipeline network 1.

[0042] Well cutting gas lift during series gas lift: During multi-well gas lift, a certain well needs to be cut out, for example, well 2 9 is cut out, the outlet of the first high-pressure separator 3 is connected to the inlet of well 3 17, the outlet of the first high-pressure separator 3 and the inlet of well 2 9 of natural gas are closed, the inlet and outlet of the second high-pressure separator 10 and the bypass 16 are closed, and well 2 9 can be cut out of the process.

[0043] Parallel gas lift: The outlet of the compressor 30 is connected to the inlet of the natural gas well 2, the well 9, the well 17, and the well 23, and only the outlets of the first high-pressure separator 3, the second high-pressure separator 10, the third high-pressure separator 18, and the fourth high-pressure separator 24 are connected to the external transmission pipeline network 1.

[0044] In the outlet manifold 36, a manual needle throttle valve 41 is used to adjust the pressure to a suitable level, and the gas enters the external transmission pipeline network 1 after being measured by a gas flow meter 42.

[0045] Therefore, during use, the natural gas coming out of the external transmission pipeline network can be processed and compressed, and the high-pressure gas obtained after compression can be injected into the gas well blocked by liquid, so that the gas well can be lifted and resumed production. The system can lift multiple gas wells at the same time, and can also cut a certain gas well out of the process when lifting multiple wells, thereby improving the use value of the equipment. At the same time, the processing equipment of the utility model is simpler and less difficult.

[0046] Although the present invention has been described above with reference to the embodiments, various modifications may be made thereto and parts thereof may be replaced with equivalents without departing from the scope of the present invention. In particular, as long as there is no structural conflict, the various features in the embodiments disclosed in the present invention may be used in combination with each other in any manner, and the fact that these combinations are not exhaustively described in this specification is only for the sake of omitting space and saving resources. Therefore, the present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.

Claims

1. A skid-mounted well-to-well interconnected series gas lift system, characterized in that: include: A compressor skid (30), wherein the inlet of the compressor skid (30) is connected to an external transmission pipeline network (1), and the outlet of the compressor skid (30) is connected to a natural gas well 1 (2), a well 2 (9), a well 3 (17), and a well 4 (23). The compressor skid (30) is provided with a manifold (31) from the compressor skid outlet to the well 1, well 2, well 3, and well 4, and a compressor skid air intake manifold (32). The compressor skid (30) is provided with a compressor skid liquid discharge manifold (33), and the compressor skid liquid discharge manifold (33) is connected to the external transmission pipeline network (1). The compressor skid (30) is provided with a gas outlet (29), the gas outlet (29) is connected to a generator (28), the gas outlet (29) is connected to the gas inlet of the generator (28), the outlet of the first natural gas well (2) is connected to the inlet of the first high-pressure separator (3), the outlet of the second natural gas well (9) is connected to the inlet of the second high-pressure separator (10), the outlet of the third natural gas well (17) is connected to the inlet of the third high-pressure separator (18), and the outlet of the fourth natural gas well (23) is connected to the inlet of the fourth high-pressure separator (24); A first high-pressure separator (3), wherein the first high-pressure separator (3) is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand; the inlet of the second high-pressure separator (10) is provided with a manual flat gate valve; the second high-pressure separator (10) is provided with a first high-pressure separator safety discharge port (4) connected to a venting manifold (43); the first high-pressure separator (3) is provided with a first high-pressure separator sewage discharge port (34); the first high-pressure separator sewage discharge port (34) is connected to a sewage discharge manifold (35); the outlet of the first high-pressure separator (3) is connected to the inlets of the second well (9), the third well (17), the fourth well (23), and the external transmission pipeline network (1); A second high-pressure separator (10), wherein the second high-pressure separator (10) is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand; the inlet of the second high-pressure separator (10) is provided with a manual flat gate valve; the second high-pressure separator (10) is provided with a second high-pressure separator safety discharge port (11) connected to a vent manifold (43); the second high-pressure separator (10) is provided with a second high-pressure separator sewage discharge port (37) connected to a sewage discharge manifold (35); the outlet of the second high-pressure separator (10) is connected to the inlets of the third well (17), the fourth well (23), and the external transmission pipeline network (1); A third high-pressure separator (18), wherein the third high-pressure separator (18) is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand; the inlet of the third high-pressure separator (18) is provided with a manual flat gate valve; the third high-pressure separator (18) is provided with a third high-pressure separator safety discharge port (19) connected to a venting manifold (43); the third high-pressure separator safety discharge port (19) is provided with a third high-pressure separator sewage discharge port (38) connected to a sewage discharge manifold (35); the outlet of the third high-pressure separator (18) is connected to the inlet of the four wells (23) and the external transmission pipeline network (1); A fourth high-pressure separator (24), wherein the fourth high-pressure separator (24) is provided with a vent manifold (43), the fourth high-pressure separator (24) is provided with a pressure gauge for measuring pressure, a level gauge for measuring liquid level, and a sand discharge port for discharging sand, the inlet of the fourth high-pressure separator (24) is provided with a manual flat gate valve, the fourth high-pressure separator (24) is provided with a fourth high-pressure separator safety discharge port (25) connected to the vent manifold (43), the fourth high-pressure separator (24) is provided with a fourth high-pressure separator sewage discharge port (39) connected to the sewage discharge manifold (35), and the outlet of the fourth high-pressure separator (24) is connected to the external transmission pipeline network (1).

2. A skid-mounted well-to-well interconnected series gas lift system according to claim 1, characterized in that: The outlet of the first high-pressure separator (3) is provided with a first high-pressure separator outlet manifold (5), and the first high-pressure separator outlet manifold (5) is provided with a first high-pressure separator outlet flowmeter (6); the outlet of the second high-pressure separator (10) is provided with a second high-pressure separator outlet manifold (12), and the second high-pressure separator outlet manifold (12) is provided with a second high-pressure separator outlet flowmeter (13); the outlet of the third high-pressure separator (18) is provided with a third high-pressure separator outlet manifold (20), and the third high-pressure separator (18) is provided with a third high-pressure separator outlet manifold (21). The outlet manifold (20) is provided with a third high-pressure separator outlet flowmeter (21); the outlet of the fourth high-pressure separator (24) is provided with a fourth high-pressure separator outlet manifold (26); the fourth high-pressure separator outlet manifold (26) is provided with a fourth high-pressure separator outlet flowmeter (27); the fourth high-pressure separator (24) is connected to an outlet manifold (36); the outlet manifold (36) is provided with a manual needle throttle valve (41) and an outlet flowmeter (42); and the sewage manifold (35) is provided with a pressure stabilizing tank (40).

3. A skid-mounted well-to-well interconnected series gas lift system according to claim 2, characterized in that: The first high-pressure separator (3), the second high-pressure separator (10), the third high-pressure separator (18) and the fourth high-pressure separator (24) are all horizontal separators.

4. A skid-mounted well-to-well interconnected series gas lift system according to claim 3, characterized in that: The outlet of the first high-pressure separator (3) to the second well (9) is provided with a first high-pressure separator outlet to the second well inlet manifold (7) and a first high-pressure separator outlet to the third and fourth well inlet manifolds (8), and the first high-pressure separator outlet manifold (5) is connected to the first high-pressure separator outlet to the second well inlet manifold (7) and the first high-pressure separator outlet to the third and fourth well inlet manifolds (8).

5. A skid-mounted well-to-well interconnected series gas lift system according to claim 4, characterized in that: The first high-pressure separator (3) outlet to three wells (17) is provided with a first high-pressure separator outlet to three wells inlet manifold (15), and the first high-pressure separator outlet to three wells and four wells inlet manifolds (8) are connected to the first high-pressure separator outlet to three wells inlet manifold (15).

6. A skid-mounted well-to-well interconnected series gas lift system according to claim 5, characterized in that: The outlet of the second high-pressure separator (10) to the four wells (23) is provided with a second high-pressure separator outlet to the four wells inlet manifold (14), the outlet of the second high-pressure separator (10) to the three wells (17) is provided with a second high-pressure separator outlet to the three wells inlet manifold (16), and the second high-pressure separator outlet manifold (12) is connected to the second high-pressure separator outlet to the four wells inlet manifold (14), the second high-pressure separator outlet to the three wells inlet manifold (16) and the outlet manifold (36).

7. The skid-mounted well-to-well interconnected series gas lift system according to claim 6, characterized in that: The outlet of the third high-pressure separator (18) to the four wells (23) is provided with a third high-pressure separator outlet to the four wells inlet manifold (22), and the third high-pressure separator safety relief port (19) is connected to the third high-pressure separator outlet to the four wells inlet manifold (22) and the outlet manifold (36).

8. The skid-mounted well-to-well interconnected series gas lift system according to claim 7, characterized in that: The fourth high-pressure separator outlet manifold (26) is connected to the outlet manifold (36).