Shield hydraulic tunnel lining convenient for manhole construction
By adopting the design of steel structure segment outer lining and reinforced concrete inner lining in the shield hydraulic tunnel lining, and reserving windows and tongues, the problem of damage to the formed tunnel caused by the construction of the manhole has been solved, and construction quality and safety have been achieved. Improvement avoids quality problems such as honeycombs, pitted surfaces and water leakage, ensuring the durability and structural safety of the project.
Patent Information
- Application Number
- CN202420765261.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-12
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-04-12
AI Technical Summary
The existing shield hydraulic tunnel lining requires destruction and secondary construction of the formed tunnel during the construction of the manhole, resulting in high construction safety risks, long construction period, difficulty in ensuring quality, and prone to problems such as honeycombs, pitted surfaces, and water leakage. , affecting the durability and structural safety of the project.
The design adopts the outer lining of steel structure segments and the inner lining of reinforced concrete. A window and cover are reserved at the top. The window position is equipped with a tongue and groove, allowing the cover to be removed for roughening during the construction of the manhole to avoid damage to the formed tunnel structure. Destruction, support and concrete construction are achieved.
Through this design, the construction quality and safety are guaranteed, the construction period is reduced, quality problems of the concrete structure are avoided, and the durability and structural safety of the project are ensured.
Smart Images

Figure CN221920990U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of shield hydraulic tunnel construction, in particular to a shield hydraulic tunnel lining which is convenient for the construction of a maintenance well. Background Art
[0002] In recent years, with the continuous development and maturity of domestic shield machine technology, and due to the safety, high efficiency and low disturbance of shield construction, more and more hydraulic tunnels are constructed using shield construction. Compared with transportation and municipal tunnels, hydraulic tunnels need to add a second phase of reinforced concrete lining after the lining segments are assembled to prevent water leakage and reduce the water transport resistance of the tunnel wall.
[0003] Long-distance water transmission tunnels need to be equipped with inspection wells at designated locations along the route for pressure regulation and inspection during the later operation period. According to the construction technology of reinforced concrete lined tunnels with shield, it is currently inevitable to destroy the formed tunnel and conduct secondary construction during the construction of inspection wells. The secondary construction technology after the reinforced concrete of the formed tunnel is destroyed has a high construction safety risk, a long construction period, and quality problems such as honeycombs, rough surfaces and water leakage are difficult to avoid. The construction quality is difficult to guarantee, which has an adverse impact on the durability and structural safety of the project. Utility Model Content
[0004] 1. Technical issues to be resolved
[0005] In view of the deficiencies in the prior art, the utility model provides a shield hydraulic tunnel lining that is convenient for the construction of inspection wells, solving the problem of safety and quality risks caused by the removal of reinforced concrete during the secondary construction of the formed tunnel during the construction of inspection wells for shield hydraulic tunnel linings.
[0006] (II) Technical solution
[0007] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:
[0008] A shield hydraulic tunnel lining that is convenient for the construction of a maintenance well, the shield hydraulic tunnel lining comprising: a steel structure segment outer lining and a reinforced concrete inner lining;
[0009] The reinforced concrete lining is arranged on the inner wall of the outer lining of the steel structure segment;
[0010] A window is reserved on the top of the outer lining of the steel structure segment, the window is matched with a cover, and the window is located at the designed construction position of the inspection well;
[0011] The reinforced concrete lining is provided with a tongue and groove at the window.
[0012] Preferably, the outer lining of the steel structure segment is formed by axially assembling a number of unit pipes;
[0013] The unit tube is formed by splicing a number of arc-shaped tube segments end to end.
[0014] Preferably, the unit tube where the window is located is assembled through seams;
[0015] The sealing cover is composed of a plurality of arc-shaped tube segments which are axially spliced.
[0016] Preferably, the joints of the arc-shaped tube segments are filled with water stop plates.
[0017] Preferably, a steel plate is embedded in the tongue and groove, a part of the steel plate is embedded in the reinforced concrete lining, and the other part is used to connect the inspection well.
[0018] (III) Beneficial effects
[0019] The utility model provides a shield hydraulic tunnel lining that is convenient for the construction of inspection wells. Compared with the prior art, it has the following beneficial effects:
[0020] In the utility model, the shield hydraulic tunnel lining comprises: a steel structure segment outer lining and a reinforced concrete lining; the reinforced concrete lining is arranged on the inner wall of the steel structure segment outer lining; a window is reserved on the top of the steel structure segment outer lining, the window is matched with a cover, and the window is located at the design and construction position of the inspection well; the reinforced concrete lining is reserved with a tongue and groove at the window; during the excavation of the shield machine, the shield hydraulic tunnel lining is used for support at the design and construction position of the inspection well, and when the inspection well is excavated to the window, the cover is removed, and the tongue and groove of the reinforced concrete lining are roughened before the inspection well concrete construction can be carried out; different from the previous destruction and secondary construction of the formed tunnel reinforced concrete structure, it can fully guarantee the construction quality and construction safety, reduce the construction period, and avoid quality problems such as honeycomb, rough surface and water leakage of the concrete structure, thereby ensuring the durability of the project and the structural safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0022] Figure 1 An exploded view of the shield hydraulic tunnel lining in the embodiment of the utility model;
[0023] Figure 2 It is an axonometric diagram of the shield hydraulic tunnel lining in the embodiment of the utility model;
[0024] Figure 3 This is a front view of the shield hydraulic tunnel lining in the embodiment of the utility model;
[0025] Figure 4 for Figure 3 Cross-section of the middle AA;
[0026] The reference numerals in the figure are set as: steel structure segment outer lining 10, window 11, cover 12, reinforced concrete lining 20, tongue and groove 21, steel plate 22, unit pipe 30, arc segment 31. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solution and advantages of the embodiments of the utility model clearer, the technical solution in the embodiments of the utility model is described clearly and completely. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] The embodiments of the present application provide a shield hydraulic tunnel lining that is convenient for the construction of inspection wells, thereby solving the problem that the construction of inspection wells for shield hydraulic tunnel linings causes safety and quality risks in the secondary construction of the formed tunnel by chiseling out reinforced concrete.
[0029] The technical solution in the embodiment of the present application is to solve the above technical problems, and the overall idea is as follows:
[0030] In the embodiment of the utility model, the shield hydraulic tunnel lining includes: a steel structure segment outer lining and a reinforced concrete lining; the reinforced concrete lining is arranged on the inner wall of the steel structure segment outer lining; a window is reserved at the top of the steel structure segment outer lining, the window is matched with a cover, and the window is located at the designed construction position of the inspection well; the reinforced concrete lining is reserved with a tongue and groove at the window; during the excavation of the shield machine, the shield hydraulic tunnel lining is used for support at the designed construction position of the inspection well, and when the inspection well is excavated to the window, the cover is removed, and the tongue and groove of the reinforced concrete lining are roughened before the inspection well concrete construction can be carried out; different from the previous destruction and secondary construction of the formed tunnel reinforced concrete structure, it can fully guarantee the construction quality and construction safety, reduce the construction period, and avoid quality problems such as honeycomb, rough surface and water leakage of the concrete structure, thereby ensuring the durability of the project and the structural safety.
[0031] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0032] Example:
[0033] like Figure 1 to Figure 4As shown, the utility model provides a shield hydraulic tunnel lining that is convenient for the construction of a maintenance well, and the shield hydraulic tunnel lining includes: a steel structure segment outer lining 10 and a reinforced concrete inner lining 20;
[0034] The reinforced concrete lining 20 is arranged on the inner wall of the steel structure segment outer lining 10;
[0035] A window 11 is reserved on the top of the steel structure segment outer lining 10, and the window 11 is matched with a cover 12. The window 11 is located at the design and construction position of the inspection well;
[0036] The reinforced concrete lining 20 has a reserved groove 21 at the window 11 .
[0037] During the tunneling process of the shield machine, the shield hydraulic tunnel lining is used for support at the designed construction position of the inspection well. When the inspection well is excavated to the window 11, the cover 12 is removed, and the groove 21 of the reinforced concrete lining 20 is roughened before the inspection well concrete construction can be carried out. Different from the previous destruction and secondary construction of the formed tunnel reinforced concrete structure, it can fully guarantee the construction quality and construction safety, shorten the construction period, avoid quality problems such as honeycomb, rough surface and water leakage of the concrete structure, thereby ensuring the durability of the project and the structural safety.
[0038] like Figure 1 to Figure 4 As shown, the steel structure segment outer lining 10 is composed of a plurality of unit tubes 30 assembled axially;
[0039] The unit tube 30 is formed by splicing a plurality of arc-shaped tube segments 31 end to end.
[0040] like Figure 1 to Figure 3 As shown, the unit tubes 30 where the windows 11 are located are assembled through seams, that is, the joint seams of the arc-shaped tube segments 31 of adjacent unit tubes 30 are aligned with each other, and the unit tubes 30 at other locations are assembled with staggered seams;
[0041] The cover 12 is composed of a plurality of arc-shaped tube segments 31 that are axially spliced together.
[0042] The joints of the arc-shaped segments 31 are filled with water-stopping plates for water-stopping between the arc-shaped segments 31 .
[0043] like Figure 1 , Figure 4 As shown, a steel plate 22 is embedded in the groove 21 , a part of the steel plate 22 is embedded in the reinforced concrete lining 20 , and the other part is used to connect the inspection well. Specifically, the exposed steel plate 22 is poured into the concrete during the construction of the inspection well, thereby improving the connection stability between the inspection well and the reinforced concrete lining 20 .
[0044] In summary, compared with the prior art, the present invention has the following beneficial effects:
[0045] In the embodiment of the utility model, the shield hydraulic tunnel lining includes: a steel structure segment outer lining and a reinforced concrete lining; the reinforced concrete lining is arranged on the inner wall of the steel structure segment outer lining; a window is reserved at the top of the steel structure segment outer lining, the window is matched with a cover, and the window is located at the designed construction position of the inspection well; the reinforced concrete lining is reserved with a tongue and groove at the window; during the excavation of the shield machine, the shield hydraulic tunnel lining is used for support at the designed construction position of the inspection well, and when the inspection well is excavated to the window, the cover is removed, and the tongue and groove of the reinforced concrete lining are roughened before the inspection well concrete construction can be carried out; different from the previous destruction and secondary construction of the formed tunnel reinforced concrete structure, it can fully guarantee the construction quality and construction safety, reduce the construction period, and avoid quality problems such as honeycomb, rough surface and water leakage of the concrete structure, thereby ensuring the durability of the project and the structural safety.
[0046] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0047] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A shield hydraulic tunnel lining for easy construction of inspection wells, characterized in that: The shield hydraulic tunnel lining comprises: a steel structure segment outer lining (10) and a reinforced concrete inner lining (20); The reinforced concrete lining (20) is arranged on the inner wall of the steel structure segment outer lining (10); A window (11) is reserved at the top of the outer lining (10) of the steel structure segment, the window (11) is matched with a cover (12), and the window (11) is located at the designed construction position of the inspection well; The reinforced concrete lining (20) is provided with a tongue and groove (21) at the window (11).
2. The shield hydraulic tunnel lining for facilitating the construction of a maintenance well as claimed in claim 1 is characterized in that: The steel structure segment outer lining (10) is formed by axially assembling a plurality of unit tubes (30); The unit tube (30) is formed by splicing a plurality of arc-shaped tube segments (31) end to end.
3. The shield hydraulic tunnel lining for facilitating the construction of inspection wells as claimed in claim 2 is characterized in that: The unit tube (30) where the window (11) is located is assembled through seams; The sealing cover (12) is composed of a plurality of axially spliced arc-shaped tube segments (31).
4. The shield hydraulic tunnel lining for facilitating the construction of inspection wells as claimed in claim 2 is characterized in that: The joint seams of the arc-shaped tube segments (31) are filled with water stop plates.
5. The shield hydraulic tunnel lining for facilitating the construction of a maintenance well as claimed in any one of claims 1 to 4, characterized in that: A steel plate (22) is pre-buried at the tongue and groove (21), a portion of the steel plate (22) is pre-buried in the reinforced concrete lining (20), and the other portion is used to connect to the inspection well.