Waterproof laying structure based on integration of tunnel inverted arch and trestle
By adopting a waterproof laying structure based on the tunnel's inverted arch trestle in the railway tunnel, and using arch laying trolleys and carrying trolleys to realize automatic waterproofing material laying, the problems of low work efficiency and safety risks in the existing technology are solved, and the construction efficiency is improved. Efficiency and waterproof quality.
Patent Information
- Application Number
- CN202420540196.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-19
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-19
AI Technical Summary
The existing railway tunnel waterproofing material laying device has low working efficiency and safety risks, and it occupies most of the tunnel, affecting construction efficiency.
A waterproof paving structure based on the tunnel's inverted arch trestle is designed, including an arched paving trolley and a carrying trolley. The inside of the arched paving trolley is used to accommodate the passage of other construction vehicles, and the outside is slidably connected to the carrying trolley for laying waterproof materials. , automatic laying is realized through the traveling mechanism and the adapted wheel set.
It enables the passage of other construction vehicles in the tunnel, avoids manual work in harsh environments, reduces safety risks and labor costs, and improves construction efficiency and waterproofing quality.
Smart Images

Figure CN221920999U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel waterproofing, in particular to a waterproofing paving structure based on an integrated tunnel inverted arch and trestle. Background Art
[0002] Railway tunnels are passages for trains to travel. When railways pass through mountainous areas, due to limited traction capacity and maximum slope requirements (less than 24%), it is necessary to overcome elevation obstacles. Digging tunnels to cross mountains is a reasonable choice. Its function is to shorten the line, reduce the slope, improve operating conditions, and increase traction capacity. According to their location, they can be divided into three categories: mountain tunnels are those that pass under mountains or hills to shorten the distance and avoid large slopes; underwater tunnels are those that pass under rivers or seabeds to cross rivers or straits; urban tunnels are those that pass underground in cities to meet the needs of railways passing through large cities. Waterproof materials need to be laid in railway tunnels. In order to facilitate the laying of waterproof materials, railway tunnel waterproof material laying devices are required.
[0003] The defects of the existing railway tunnel waterproof material laying device are:
[0004] 1. The existing railway tunnel waterproof material laying device is generally only used to transport the waterproof material to the designated location, and it still needs to be laid manually, which has low work efficiency, poor construction environment and safety risks.
[0005] 2. The existing railway tunnel waterproof material laying device occupies most of the tunnel, and other construction vehicles cannot pass through, affecting the overall construction efficiency. Utility Model Content
[0006] In view of this, the utility model provides a waterproof paving structure based on a tunnel inverted arch trestle to solve the problems raised in the above background technology.
[0007] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0008] A waterproof laying structure based on a tunnel inverted arch trestle comprises a trestle on which an arched laying trolley is slidably arranged, the inner side of the arched laying trolley is used to accommodate the passage of other construction vehicles, and the outer side of the arched laying trolley is slidably connected to a carrying trolley for laying waterproof materials on a lining surface of the tunnel.
[0009] Furthermore, the arched laying trolley comprises an arched track, both ends of which are slidably connected to the trestle via a walking mechanism, and a transport trolley is slidably connected to the arched track.
[0010] Furthermore, the walking mechanism includes a walking beam, which is fixedly arranged at both ends of the arched track, an active walking unit is fixedly arranged at one end of the bottom surface of the walking beam, and a passive walking unit is fixedly arranged at the other end, and walking rails are arranged on both sides of the top surface of the trestle, and the active walking unit and the passive walking unit are both adapted to the walking rails.
[0011] Furthermore, the transport trolley includes a support frame and a wheel set adapted to the arch track, the support frame is slidably connected to the arch track through the wheel set, the support frame is provided with an installation groove on one side away from the arch track, a storage unit is provided on one side of the installation groove, and an installation unit is provided on the other side.
[0012] Furthermore, the storage unit includes a core shaft, which is arranged on one side of the installation groove through two fixing frames, and the core shaft is rotatably connected between the two fixing frames, and the core shaft is coated with a waterproof material.
[0013] Furthermore, the installation unit includes a first rotating base and a second rotating base which are fixedly arranged in sequence on the side of the installation groove away from the core shaft. The driving end of the first rotating base is fixedly connected to a clamping arm for clamping the waterproof material, and the driving end of the second rotating base is fixedly connected to a welding arm for welding the waterproof material.
[0014] Furthermore, the starting end and the terminating end of the arched track are both slidably connected to the transport trolley, or only one transport trolley is slidably connected to the arched track.
[0015] The beneficial effects of the utility model are:
[0016] The utility model provides an arched laying trolley to ensure clearance for passing vehicles and meet the needs of other construction vehicles in the tunnel. By laying waterproof materials with the transport trolley, there is no need for manual work in the harsh environment of the tunnel, there is no safety risk, and the labor cost is reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0018] Figure 1 The utility model is a structural schematic diagram of a waterproof paving structure based on a tunnel inverted arch trestle.
[0019] Figure 2It is a side view of a waterproof paving structure based on a tunnel inverted arch trestle integration according to the utility model.
[0020] Figure 3 It is a side view of the arched paving trolley in the utility model.
[0021] Figure 4 It is a structural schematic diagram of the transport trolley in the utility model.
[0022] Figure 5 It is a left view of the transport trolley in the utility model.
[0023] Figure 6 It is a right side view of the transport trolley in the utility model.
[0024] Figure 7 It is a front view of the installation working platform of the arched paving trolley in the utility model.
[0025] Figure 8 It is a side view of the installation working platform of the arched paving trolley in the utility model.
[0026] Fig. 9 It is a flow chart of the first perspective of a waterproof paving construction method based on the integration of a tunnel, invert and trestle in Example 1.
[0027] Fig.10 This is a flow chart from the second perspective of a waterproof paving construction method based on an integrated tunnel, invert, and trestle in Example 1.
[0028] Fig.11 It is a schematic diagram of a first-person perspective of a waterproof paving construction method based on an integrated tunnel, invert and trestle in Example 2.
[0029] Fig.12 It is a schematic diagram of a second perspective of a waterproof paving construction method based on an integrated tunnel, invert and trestle in Example 2.
[0030] Among them, in the figure:
[0031] 1. Arched laying trolley; 11. Arched track; 12. Walking beam; 13. Active walking unit; 14. Passive walking unit; 2. Carrying trolley; 20. Wheel set; 21. Support frame; 22. Mounting groove; 23. Fixed frame; 24. Mandrel; 25. Waterproof material; 26; First rotating base; 27; Second rotating base; 28. Clamping arm; 29. Welding arm; 3. Second lining of tunnel; 4. First lining of tunnel; 5. Trestle; 51. Walking rail; 6. Working platform. DETAILED DESCRIPTION
[0032] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0034] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.
[0035] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.
[0036] In addition, the terms "installed", "set", "provided with", "connected", "connected", and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0037] Embodiment 1:
[0038] See attached Figure 1-6A waterproof laying structure based on a tunnel inverted arch trestle comprises a trestle 5, on which an arched laying trolley 1 is slidably arranged, the inner side of the arched laying trolley 1 is used to accommodate the passage of other construction vehicles, and the outer side of the arched laying trolley 1 is slidably connected with a carrying trolley 2, which is used to lay waterproof materials on a tunnel lining 4, and the tunnel lining 4 is located outside a tunnel lining 3. The setting of the arched laying trolley 1 in the utility model is used to ensure the clearance for passing vehicles and meet the passage of other construction vehicles in the tunnel. By laying waterproof materials through the carrying trolley 2, there is no need for manual work in the harsh environment of the tunnel, there is no safety risk, and the labor cost is reduced.
[0039] The arched laying trolley 1 comprises an arched track 11, both ends of which are slidably connected to the trestle 5 through a walking mechanism, and a transport trolley 2 is slidably connected to the arched track 11. In this embodiment, the transport trolley 2 is slidably connected to the starting end and the ending end of the arched track 11.
[0040] The walking mechanism includes a walking beam 12, which is fixedly arranged at both ends of the arch track 11. An active walking unit 13 is fixedly arranged at one end of the bottom surface of the walking beam 12, and a passive walking unit 14 is fixedly arranged at the other end. Walking rails 51 are arranged on both sides of the top surface of the trestle 5, and the active walking unit 13 and the passive walking unit 14 are both adapted to the walking rails 51.
[0041] The transport trolley includes a support frame 21 and a wheel set 20 adapted to the arch track 11. The support frame 21 is slidably connected to the arch track 11 through the wheel set 20. The support frame 21 is provided with a mounting groove 22 on the side away from the arch track 11. A storage unit is provided on one side of the mounting groove 22, and a mounting unit is provided on the other side.
[0042] The storage unit includes a core shaft 24, which is arranged on one side of the installation groove 22 through two fixing frames 23, and the core shaft 24 is rotatably connected between the two fixing frames 23. The core shaft 24 is rolled with a waterproof material 25. In this embodiment, the core shaft 24 is perpendicular to the depth direction of the tunnel.
[0043] The installation unit includes a first rotating base 26 and a second rotating base 27 which are fixedly arranged in sequence on the side of the installation groove 22 away from the core shaft 24. The driving end of the first rotating base 26 is fixedly connected with a clamping arm 28 for clamping the waterproof material 25. The driving end of the second rotating base 27 is fixedly connected with a welding arm 29 for welding the waterproof material 25. In this embodiment, both the clamping arm 28 and the welding arm 29 can rotate 360 degrees. The welding arm 29 welds the waterproof material 25 to the tunnel lining 4 through a hot-melt gasket and inspects the quality of the welding between the waterproof material 25 and the hot-melt gasket.
[0044] See attached Figure 7-8The carrying trolley on the arch laying trolley 1 can be disassembled, and a plurality of detachable working platforms can be evenly installed on the arch laying trolley 1. The operators can stand on the detachable working platforms to complete the steel bar binding operation or tunnel maintenance.
[0045] See attached Figure 9-10 A waterproof paving construction method based on tunnel invert trestle integration includes the following steps:
[0046] S1: Move the trestle 5 to the tunnel construction position, the arched track 11 is located at the starting point of the construction section, and the two transport trolleys 2 are located at the starting end and the ending end of the arched track 11. First, the clamping arm 28 clamps the waterproof material 25 rolled on the core shaft 24, and presses the waterproof material 25 onto the tunnel lining 4. Then the welding arm 29 welds the waterproof material 25 to the tunnel lining 4 of the tunnel. After welding, the active walking unit 13 drives the arched track 11 to move along the walking rail 51 to the end of the construction section, and repeats the above-mentioned waterproof material 25 laying process until the waterproof material 25 of the tunnel lining 4 at the same height of the entire construction section is laid; in this embodiment, the construction section is 12m, the arched track 11 is 4m long in the longitudinal direction of the tunnel, the operating range of the welding arm 29 and the clamping arm 28 is 4m, and the arched track 11 needs to be shifted at least 3 times from the starting point to the end point of the construction section, and can also be gradually shifted during the work process according to needs;
[0047] S2: At this time, the arched track 11 is located at the end of the construction section, and the two transport trolleys 2 move toward the center of the arched track 11 to continue laying the waterproof material 25, and ensure that it is circumferentially overlapped with the waterproof material 25 laid in S1. In this embodiment, the width of the waterproof material 25 is 4m, and the circumferential overlap length is 125mm. After welding is completed, the active walking unit 13 drives the arched track 11 to move along the walking rail 51 to the starting point of the construction section, and repeats the above-mentioned waterproof material 25 laying process to complete the laying of the waterproof material 25 of the tunnel lining 4 at the same height of the entire construction section;
[0048] S3: Repeat S1 and S2. After the laying of the waterproof material 25 of the tunnel lining 4 of the entire construction section is completed, the arched track 11 moves to the next construction section to lay the waterproof material 25 of the tunnel lining 4, and ensures the longitudinal overlap with the waterproof material 25 laid in the previous construction section, until the laying of the waterproof material 25 of the tunnel lining 4 at the construction position where the trestle 5 is located is completed, the trestle 5 moves to the next construction position to lay the waterproof material 25 until the laying of the waterproof material 25 of the entire tunnel lining 4 is completed.
[0049] When there is insufficient working space for laying the waterproof material 25 to the center of the tunnel lining 4, the transport trolley 2 on one side moves away from the center of the arched track 11 to leave enough working space, and the transport trolley 2 on the other side moves closer to the center of the arched track 11 to complete the laying of the waterproof material 25 at the center of the tunnel lining 4.
[0050] In this embodiment, the waterproof material 25 includes a geotextile and a waterproof board. The geotextile is laid first and then the waterproof board is laid.
[0051] Embodiment 2:
[0052] See attached Figure 11-12 A waterproof laying structure based on a tunnel inverted arch trestle comprises a trestle 5, on which an arched laying trolley 1 is slidably arranged, the inner side of the arched laying trolley 1 is used to accommodate the passage of other construction vehicles, and the outer side of the arched laying trolley 1 is slidably connected with a carrying trolley 2, which is used to lay waterproof materials on a tunnel lining 4, and the tunnel lining 4 is located outside a tunnel lining 3. The setting of the arched laying trolley 1 in the utility model is used to ensure the clearance for passing vehicles and meet the passage of other construction vehicles in the tunnel. By laying waterproof materials through the carrying trolley 2, there is no need for manual work in the harsh environment of the tunnel, there is no safety risk, and the labor cost is reduced.
[0053] The arched laying trolley 1 comprises an arched track 11, both ends of which are slidably connected to the trestle 5 via a walking mechanism, and a transport trolley 2 is slidably connected to the arched track 11. In this embodiment, only one transport trolley 2 is slidably connected to the arched track 11.
[0054] The walking mechanism includes a walking beam 12, which is fixedly arranged at both ends of the arch track 11. An active walking unit 13 is fixedly arranged at one end of the bottom surface of the walking beam 12, and a passive walking unit 14 is fixedly arranged at the other end. Walking rails 51 are arranged on both sides of the top surface of the trestle 5, and the active walking unit 13 and the passive walking unit 14 are both adapted to the walking rails 51.
[0055] The transport trolley includes a support frame 21 and a wheel set 20 adapted to the arch track 11. The support frame 21 is slidably connected to the arch track 11 through the wheel set 20. The support frame 21 is provided with a mounting groove 22 on the side away from the arch track 11. A storage unit is provided on one side of the mounting groove 22, and a mounting unit is provided on the other side.
[0056] The storage unit includes a core shaft 24, which is arranged on one side of the installation groove 22 through two fixing frames 23, and the core shaft 24 is rotatably connected between the two fixing frames 23. The core shaft 24 is rolled with a waterproof material 25. In this embodiment, the core shaft 24 is parallel to the depth direction of the tunnel.
[0057] The installation unit includes a first rotating base 26 and a second rotating base 27 which are fixedly arranged in sequence on the side of the installation groove 22 away from the core shaft 24. The driving end of the first rotating base 26 is fixedly connected with a clamping arm 28 for clamping the waterproof material 25. The driving end of the second rotating base 27 is fixedly connected with a welding arm 29 for welding the waterproof material 25. In this embodiment, both the clamping arm 28 and the welding arm 29 can rotate 360 degrees. The welding arm 29 welds the waterproof material 25 to the tunnel lining 4 through a hot-melt gasket and inspects the quality of the welding between the waterproof material 25 and the hot-melt gasket.
[0058] The transport trolley on the arch laying trolley 1 can be disassembled, and a plurality of detachable working platforms can be evenly installed on the arch laying trolley 1. Operators standing on the detachable working platforms can complete the steel bar binding operation or tunnel maintenance.
[0059] A waterproof paving construction method based on tunnel invert trestle integration includes the following steps:
[0060] S1: Move the trestle 5 to the tunnel construction position, the arched track 11 is located at the starting point of the construction position, and a transport trolley 2 is located at the starting end of the arched track 11. First, the clamping arm 28 clamps the waterproof material 25 rolled on the core shaft 24, and presses the waterproof material 25 onto the tunnel lining 4. Then, the welding arm 29 welds the waterproof material 25 to the tunnel lining 4 of the tunnel. After welding, the transport trolley 2 moves to the terminal end of the arched track 11, and repeats the above-mentioned waterproof material 25 laying process until the waterproof material 25 of the tunnel lining 4 of the same depth and circumference of the entire construction position is laid.
[0061] S2: At this time, the transport trolley 2 is located at the end of the arched track 11, and the active walking unit 13 drives the arched track 11 to move along the walking rail 51 to the end of the construction position, and continues to lay the waterproof material 25, and ensures that it is longitudinally overlapped with the waterproof material 25 laid in S1. After welding is completed, the transport trolley 2 moves to the starting end of the arched track 11, and repeats the above-mentioned waterproof material 25 laying process until the waterproof material 25 of the tunnel lining 4 of the same longitudinal depth and circumferential direction of the entire construction position is laid;
[0062] S3: Repeat S1 and S2 until the waterproof material 25 of the tunnel lining 4 at the construction location where the trestle 5 is located is laid, and then the trestle 5 moves to the next construction location to lay the waterproof material 25 until the waterproof material 25 of the entire tunnel lining 4 is laid.
[0063] In this embodiment, the waterproof material 25 includes a geotextile and a waterproof board. The geotextile is laid first and then the waterproof board is laid.
[0064] During the laying of waterproof materials by the utility model, the clearance for passing vehicles is guaranteed to meet the passage of other construction vehicles in the tunnel. The construction process is fully automated, and operators can operate by pressing buttons on site or by remote control, thereby improving the waterproof quality of the tunnel. There is no need for manual work in the harsh environment of the tunnel, there is no safety risk, the labor cost is reduced, and the construction progress is greatly accelerated.
[0065] The utility model is suitable for construction in tunnels with large dust, large noise, easy generation of harmful gases and high ventilation difficulty.
[0066] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A waterproof paving structure based on the integration of tunnel inverted arch and trestle, It is characterized in that It comprises a trestle (5), on which an arched laying trolley (1) is slidably arranged, the inner side of the arched laying trolley (1) is used to accommodate the passage of construction vehicles, and the outer side of the arched laying trolley (1) is slidably connected to a transport trolley (2), and the transport trolley (2) is used to lay waterproof materials on a lining surface (4) of a tunnel; The arched laying trolley (1) comprises an arched track (11), both ends of which are slidably connected to the trestle (5) via a walking mechanism, and a transport trolley (2) is slidably connected to the arched track (11); The transport trolley comprises a support frame (21) and a wheel set (20) adapted to the arch track (11); the support frame (21) is slidably connected to the arch track (11) via the wheel set (20); a mounting groove (22) is provided on one side of the support frame (21) away from the arch track (11); a storage unit is provided on one side of the mounting groove (22) and a mounting unit is provided on the other side.
2. A waterproof paving structure based on the integration of tunnel, invert and trestle according to claim 1, It is characterized in that The walking mechanism comprises a walking beam (12), the walking beam (12) being fixedly arranged at both ends of the arched track (11), an active walking unit (13) being fixedly arranged at one end of the bottom surface of the walking beam (12), and a passive walking unit (14) being fixedly arranged at the other end, walking steel rails (51) being arranged at both sides of the top surface of the trestle (5), and the active walking unit (13) and the passive walking unit (14) both being adapted to the walking steel rails (51).
3. A waterproof paving structure based on the integration of tunnel, invert and trestle according to claim 1, It is characterized in that The storage unit comprises a core shaft (24), the core shaft (24) is arranged on one side of the installation groove (22) through two fixing frames (23), the core shaft (24) is rotatably connected between the two fixing frames (23), and the core shaft (24) is rolled with a waterproof material (25).
4. A waterproof paving structure based on the integration of tunnel, invert and trestle according to claim 3, It is characterized in that The installation unit comprises a first rotating base (26) and a second rotating base (27) which are fixedly arranged in sequence on a side of the installation groove (22) away from the core shaft (24); a clamping arm (28) is fixedly connected to a driving end of the first rotating base (26) for clamping the waterproof material (25); and a welding arm (29) is fixedly connected to a driving end of the second rotating base (27) for welding the waterproof material (25).
5. A waterproof paving structure based on the integration of tunnel, invert and trestle according to claim 1, It is characterized in that The starting end and the ending end of the arched track (11) are both slidably connected to the transport trolley (2), or only one transport trolley (2) is slidably connected to the arched track (11).
Citation Information