Pretreatment device for stabilizing overflow water flow of polymerization pelletizing water system
By setting up a flow stabilizing plate and a pretreatment manifold in the polymerization pelletizing water system, the slicing powder is trapped and the backup manifold is used for cleaning, which solves the problem of overflow water flow fluctuation and improves the stability of the pelletizing system and the product qualification rate.
Patent Information
- Application Number
- CN202420448431.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-08
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-08
AI Technical Summary
In the pelletizing system of the polymerization plant, the overflow water flow rate fluctuation or interruption caused by the sliced powder affects the cutting process of the polymer, resulting in unnecessary discharge of the polymer and a decrease in the product qualification rate.
A pretreatment device for the polymeric granulation water system is designed. By setting up a flow stabilizing plate and a pretreatment manifold in the granulation water storage tank, pressure reducing valves and filters are used to intercept the sliced powder to ensure stable water supply and a backup pipe is activated. Clean the clogged parts during sinking to ensure continuous operation of the system.
It effectively reduces the adhesion of sliced powder in the pipe wall, avoids fluctuations in overflow water flow, ensures the continuous operation of the pelletizer system, and improves product qualification rate and production efficiency.
Smart Images

Figure CN221923108U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water supply devices for polymerization pelletizing water systems, in particular to a pretreatment device for stabilizing overflow water flow in a polymerization pelletizing water system. Background Art
[0002] In a general polymerization plant, the polymer is pressed into strips by a casting head, and the strips are transported to a pelletizer through water to be cut into slices. The operation process of the entire system is called a pelletizer system. A general pelletizing system includes the following equipment: a casting head (A), a pelletizing water storage tank (B), a pelletizer cutter system (C), and a pelletizing water circulation system that provides water for the pelletizer cutter system (C). Among them, the pelletizing water circulation system is relatively important in the production process. Because the pelletizing circulation water system involves a relatively long pipeline, the slice powder produced by pelletizing by the pelletizer during a long circulation process will gradually shorten the pipe diameter. At the same time, flakes will fall off the pipe wall and flow into the overflow water cavity used to provide overflow water for the pelletizer cutter system, causing fluctuations or interruptions in the overflow water flow. The interlocking of the pelletizer system equipment will cause the interruption of polymer pelletizing, resulting in unnecessary discharge of polymer and affecting the product qualification rate. Summary of the invention
[0003] The utility model provides a pretreatment device for stabilizing the overflow water flow of a polymerization pelletizing water system, which overcomes the deficiencies of the above-mentioned prior art and can effectively solve the problem of pelletizing interruption caused by fluctuation or interruption of the existing overflow water flow.
[0004] The technical solution of the utility model is achieved through the following measures: a pretreatment device for stabilizing the overflow water flow of a polymerization pelletizing water system, comprising a pelletizing water storage tank and a pelletizer cutter system, a flow stabilizing plate for dividing the interior of the pelletizing water storage tank into a left chamber and a right chamber is arranged in the pelletizing water storage tank, the water outlet end of the pelletizing water storage tank corresponding to the left chamber is connected with the water inlet end of the pelletizer cutter system, the water inlet end of the pelletizing water storage tank corresponding to the right chamber is fixedly connected with a water inlet pipeline, the water outlet end of the pelletizer cutter system is fixedly connected with a water delivery pipeline, and two groups of pretreatment manifolds connected in parallel are fixedly connected between the water inlet pipeline and the water delivery pipeline.
[0005] The following are further optimizations and / or improvements to the above utility model technical solution:
[0006] Each group of the pretreatment manifolds includes a pretreatment pipeline, the left side of the pretreatment pipeline is fixedly connected with a pressure reducing manifold, and the pretreatment pipeline on the right side of the pressure reducing manifold is fixedly connected with a reserved joint.
[0007] The pressure reducing manifold comprises at least two pressure reducing branches, which are connected in parallel with each other, pressure reducing valves are connected in series on the pressure reducing branches, and valves are connected in series at the pressure reducing branches on both sides of the pressure reducing valve.
[0008] The pretreatment pipeline between the above-mentioned pressure reducing manifold and the reserved joint is connected with a spare branch pipe, a filter is fixedly installed on the pretreatment pipeline between the two ends of the spare branch pipe, a first valve is connected in series on the pretreatment pipeline between the two ends of the filter and the two ends of the spare branch pipe, a second valve is connected in series on the pretreatment pipeline between the pressure reducing manifold and the left end of the spare branch pipe, a third valve is connected in series on the pretreatment pipeline on the right side of the reserved joint, a fourth valve is connected in series on the spare branch pipe, and a fifth valve is connected in series on the reserved joint.
[0009] A delivery pump is fixedly installed on the above-mentioned water inlet pipeline, and at least one power branch is fixedly connected to the water inlet pipeline on both sides of the inlet and outlet of the delivery pump. A spare delivery pump is fixedly installed on each power branch, and valves are connected in series on the power branch on both sides of the inlet and outlet of the spare delivery pump. The power branch and the water inlet pipeline on the outlet side of the delivery pump are connected in series with valves, and the power branch and the water inlet pipeline on the inlet side of the delivery pump are connected in series with valves.
[0010] A pressure gauge is fixedly installed on the water delivery pipeline.
[0011] The utility model has a reasonable and compact structure and is easy to use. Through the pretreatment manifold, it can significantly reduce the adhesion of slicing powder to each pipe wall with water circulation. When the pretreatment manifold is partially blocked, another set of pretreatment manifolds can be enabled to ensure the water supply demand of the pelletizer system, thereby avoiding unnecessary discharge of polymers caused by interruption of polymer pelletizing, improving the production efficiency of the pelletizing system, and increasing the product qualification rate. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Attached Figure 1 The figure is a schematic diagram of the process flow of an embodiment of the utility model.
[0013] The codes in the accompanying drawings are: 1 for the left chamber, 2 for the right chamber, 3 for the flow stabilizer, 4 for the water inlet pipeline, 5 for the water delivery pipeline, 6 for the pretreatment pipeline, 7 for the reserved joint, 8 for the pressure reducing branch, 9 for the pressure reducing valve, 10 for the valve, 11 for the spare branch, 12 for the filter, 13 for the first valve, 14 for the second valve, 15 for the third valve, 16 for the fourth valve, 17 for the fifth valve, 18 for the delivery pump, 19 for the power branch, 20 for the spare delivery pump, and 21 for the pressure gauge.
[0014] A is the casting head, B is the pelletizing water storage tank, and C is the pelletizer cutting system. DETAILED DESCRIPTION
[0015] The present invention is not limited by the following embodiments, and specific implementation methods can be determined according to the technical solution of the present invention and actual conditions.
[0016] In the present invention, for the convenience of description, the relative position relationship of each component is described according to the attached manual. Figure 1The layout is described in detail, such as the positional relationship of front, back, top, bottom, left, right, etc., which is based on the attached manual. Figure 1 In the present utility model, unless otherwise specified, the systems described are all well-known and commonly used systems in the art, such as a pelletizer cutter system is a cutter system used for pelletizing polyester products.
[0017] The present invention is further described below in conjunction with the embodiments and drawings:
[0018] Embodiment 1, as attached Figure 1 As shown, the pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system includes a pelletizing water storage tank B and a pelletizer cutter system C. The pelletizing water storage tank B is provided with a flow stabilizing plate 3 which divides the interior of the pelletizing water storage tank B into a left chamber 1 and a right chamber 2. The water outlet of the pelletizing water storage tank B corresponding to the left chamber 1 is connected to the water inlet of the pelletizer cutter system C, the water inlet of the pelletizing water storage tank B corresponding to the right chamber 2 is fixedly connected to a water inlet pipeline 4, the water outlet of the pelletizer cutter system C is fixedly connected to a water delivery pipeline 5, and two sets of pretreatment manifolds connected in parallel are fixedly connected between the water inlet pipeline 4 and the water delivery pipeline 5.
[0019] The utility model sets two sets of pretreatment manifolds between the water inlet pipeline 4 and the water delivery pipeline 5. Generally, one set of pretreatment manifolds is put into use and the other set is in standby. After the slicing powder generated by the pelletizer cutter system C enters the water circulation system with the water flow, the slicing powder is intercepted at the pretreatment manifold. When the interception amount reaches a certain value, it affects the water inlet amount of the pelletizing water storage tank B, that is, the water supply amount of the pelletizer cutter system C, thereby affecting the overflow water flow, thereby causing the fluctuation of the overflow water flow. At this time, the standby pretreatment manifold is activated, and at the same time, the slicing powder intercepted at the pretreatment manifold is removed, and the pretreatment manifold that removes the slicing powder is used as a standby for the next time.
[0020] From the above, it can be seen that the present invention can significantly reduce the adhesion of slicing powder to each tube wall with water circulation through the pretreatment manifold. When the pretreatment manifold is partially blocked, another set of pretreatment manifolds can be put into use to ensure the water supply demand of the pelletizer system, thereby avoiding unnecessary discharge of the polymer due to interruption of pelletizing of the polymer, improving the production efficiency of the pelletizing system, and increasing the product qualification rate.
[0021] According to actual needs, the pretreatment device for stabilizing the overflow water flow of the above-mentioned polymerization pelletizing water system can be further optimized and / or improved:
[0022] Embodiment 2, as attached Figure 1 As shown, each group of pretreatment manifolds includes a pretreatment pipeline 6, the left side of the pretreatment pipeline 6 is fixedly connected to a pressure reducing manifold, and the pretreatment pipeline 6 on the right side of the pressure reducing manifold is fixedly connected to a reserved joint 7.
[0023] Water and gas can be connected externally through the reserved joint 7.
[0024] Embodiment 3, as attached Figure 1 As shown, the pressure reducing manifold includes at least two pressure reducing branches 8, which are connected in parallel to each other. Pressure reducing valves 9 are connected in series to the pressure reducing branches 8, and valves 10 are connected in series to the pressure reducing branches 8 on both sides of the pressure reducing valves 9.
[0025] Embodiment 4, as attached Figure 1 As shown, the pretreatment pipeline 6 between the pressure reducing manifold and the reserved joint 7 is connected with a spare branch pipe 11, a filter 12 is fixedly installed on the pretreatment pipeline 6 between the two ends of the spare branch pipe 11, a first valve 13 is connected in series on the pretreatment pipeline 6 between the two ends of the filter 12 and the two ends of the spare branch pipe 11, a second valve 14 is connected in series on the pretreatment pipeline 6 between the pressure reducing manifold and the left end of the spare branch pipe 11, a third valve 15 is connected in series on the pretreatment pipeline 6 on the right side of the reserved joint 7, a fourth valve 16 is connected in series on the spare branch pipe 11, and a fifth valve 17 is connected in series on the reserved joint 7.
[0026] The filter 12 can intercept the slice powder in the water. When the interception amount reaches a certain amount, the filtering effect is reduced, and it can be cleaned before use.
[0027] Embodiment 5, as attached Figure 1 As shown, a delivery pump 18 is fixedly installed on the water inlet pipeline 4, and at least one power branch pipe 19 is fixedly connected to the water inlet pipeline 4 on both sides of the inlet and outlet of the delivery pump 18, and a spare delivery pump 20 is fixedly installed on each power branch pipe 19, and valves 10 are serially connected to the power branch pipes 19 on both sides of the inlet and outlet of the spare delivery pump 20, and the power branch pipe 19 and the water inlet pipeline 4 on the outlet side of the delivery pump 18 are serially connected with the valve 10, and the power branch pipe 19 and the water inlet pipeline 4 on the inlet side of the delivery pump 18 are serially connected with the valve 10.
[0028] When more than two power branches 19 are provided, the power branches 19 are connected in parallel. The delivery pump 18 may be a centrifugal pump.
[0029] Embodiment 6: As required, a pressure gauge 21 is fixedly installed on the water delivery pipeline 5.
[0030] The above technical features constitute a preferred embodiment of the present utility model, which has strong adaptability and implementation effect. Non-essential technical features can be added or reduced according to actual needs to meet the requirements of different situations.
[0031] The use process of the embodiment of the utility model: When the pressure gauge 21 of the water delivery pipeline 5 shows that the pressure is lower than the standard value, it means that the filter 12 in the pre-treatment manifold may be blocked. The pre-treatment manifold is cleaned and another set of pre-treatment manifolds are activated at the same time. The cleaning operation is as follows:
[0032] (1) Close the third valve 15; (2) Close the second valve 14; (3) Remove the front flange of the second valve 14; (4) Connect water and air to the reserved joint 7 with a three-way pipe, and alternately purge the pipeline and the filter 12 several times. After the water quality is clear, determine whether the internal objects of the pipeline and the filter 12 are clean. Restore the rear flange of the second valve 14 in turn, pay attention to the pressure, open the second valve 14 slightly to inject water into the pipeline, and at the same time open the reserved joint 7 to exhaust slightly and reversely replace the sewage in the pipeline. When the water quality is clear and there is no turbidity, close the reserved joint 7, slowly open the second valve 14 until it is fully opened, and finally pay attention to the pressure change and slowly open the third valve 15 until it is fully opened. The purge is completed, that is, the cleaning is completed.
Claims
1. A pretreatment device for stabilizing the overflow water flow of a polymerization pelletizing water system, characterized in that It includes a pelletizing water storage tank and a pelletizer cutter system. A flow stabilizer is provided in the pelletizing water storage tank for dividing the interior of the pelletizing water storage tank into a left chamber and a right chamber. The water outlet of the pelletizing water storage tank corresponding to the left chamber is connected with the water inlet of the pelletizer cutter system, the water inlet of the pelletizing water storage tank corresponding to the right chamber is fixedly connected with a water inlet pipeline, the water outlet of the pelletizer cutter system is fixedly connected with a water delivery pipeline, and two sets of pre-treatment manifolds connected in parallel are fixedly connected between the water inlet pipeline and the water delivery pipeline.
2. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 1 is characterized in that Each set of pretreatment manifolds includes a pretreatment pipeline. The left side of the pretreatment pipeline is fixedly connected with a pressure reducing manifold, and the pretreatment pipeline on the right side of the pressure reducing manifold is fixedly connected with a reserved joint.
3. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 2 is characterized in that The pressure reducing manifold comprises at least two pressure reducing branches, which are connected in parallel with each other, pressure reducing valves are connected in series on the pressure reducing branches, and valves are connected in series at the pressure reducing branches on both sides of the pressure reducing valve.
4. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 2 or 3, characterized in that The pretreatment pipeline between the pressure reducing manifold and the reserved joint is connected with a spare branch pipe, a filter is fixedly installed on the pretreatment pipeline between the two ends of the spare branch pipe, a first valve is connected in series on the pretreatment pipeline between the two ends of the filter and the two ends of the spare branch pipe, a second valve is connected in series on the pretreatment pipeline between the pressure reducing manifold and the left end of the spare branch pipe, a third valve is connected in series on the pretreatment pipeline on the right side of the reserved joint, a fourth valve is connected in series on the spare branch pipe, and a fifth valve is connected in series on the reserved joint.
5. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 1, 2 or 3, characterized in that A delivery pump is fixedly installed on the water inlet pipeline, and at least one power branch pipe is fixedly connected to the water inlet pipeline on both sides of the inlet and outlet of the delivery pump. A spare delivery pump is fixedly installed on each power branch pipe, and valves are connected in series on the power branch pipes on both sides of the inlet and outlet of the spare delivery pump. The power branch pipe and the water inlet pipeline on the outlet side of the delivery pump are connected in series with valves, and the power branch pipe and the water inlet pipeline on the inlet side of the delivery pump are connected in series with valves.
6. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 4 is characterized in that A delivery pump is fixedly installed on the water inlet pipeline, and at least one power branch pipe is fixedly connected to the water inlet pipeline on both sides of the inlet and outlet of the delivery pump. A spare delivery pump is fixedly installed on each power branch pipe, and valves are connected in series on the power branch pipes on both sides of the inlet and outlet of the spare delivery pump. The power branch pipe and the water inlet pipeline on the outlet side of the delivery pump are connected in series with valves, and the power branch pipe and the water inlet pipeline on the inlet side of the delivery pump are connected in series with valves.
7. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 1, 2, 3 or 6, characterized in that A pressure gauge is fixedly installed on the water pipeline.
8. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 4, characterized in that A pressure gauge is fixedly installed on the water pipeline.
9. The pretreatment device for stabilizing the overflow water flow of the polymerization pelletizing water system according to claim 5, characterized in that A pressure gauge is fixedly installed on the water pipeline.