Automatic spraying equipment for tunnel maintenance

By designing automatic spraying equipment, the automatic wetting of the second liner of the tunnel is achieved by using mobile trolleys and arc-shaped spray pipes, the problems of slow strength increase and dry shrinkage cracks caused by dehydration of the tunnel are solved, and the durability of the concrete is ensured. Integrity.

CN221955986UActive Publication Date: 2024-11-05CHINA RAILWAY NO 3 GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420508027.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-11-05
Estimated Expiration
2034-03-15

AI Technical Summary

Technical Problem

After the concrete of the second liner of the tunnel was dehydrated due to the hydration heat, the concrete surface fell off due to the lack of continuous wetting. The existing maintenance methods were artificially affected and could not achieve automation and large-area coverage, resulting in slow increase in concrete strength and dry shrinkage cracks, which affected Durability and integrity.

Method used

A tunnel maintenance automatic spraying equipment is designed, including a mobile trolley and an arc-shaped spray pipe, which is connected to the water storage tank through a water supply assembly, and the arc-shaped spray pipe is moved along the track by using a driving mechanism and a chain transmission assembly. The tunnel second lining is sprayed in large areas to ensure the moist state of the concrete.

Benefits of technology

Automatic tunnel second lining maintenance is realized to ensure that the concrete is in a wet state, eliminate block drops and dry cracks, improve the strength and durability of the concrete, and reduce manual interference and space occupation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221955986U_ABST
    Figure CN221955986U_ABST
Patent Text Reader

Abstract

The utility model discloses automatic spraying equipment for tunnel maintenance, which belongs to the technical field of tunnel maintenance equipment and comprises a trolley and a maintenance frame, a moving mechanism is arranged at the bottom of the trolley, and the maintenance frame moves along a track at the top of the trolley. An arc-shaped spraying pipe matched with the inner wall of the tunnel is arranged at the front part of the maintenance frame, and a plurality of nozzles are arranged at the top of the arc-shaped spraying pipe at intervals; the arc-shaped spraying pipe is connected with the water storage tank through a water supply assembly. After the tunnel secondary lining concrete is demoulded, the trolley is driven by the moving mechanism to move in the tunnel, the water supply assembly conveys water in the water storage tank into the arc-shaped spraying pipe, and the tunnel secondary lining is sprayed through the multiple spraying heads; the maintenance frame moving along the track drives the arc-shaped spraying pipe to carry out large-area maintenance on the tunnel secondary lining on the premise that the trolley does not move, and maintenance operation of the tunnel secondary lining is achieved by moving the trolley step by step. By adopting the device, concrete can be ensured to be in a wet state, the strength and durability of secondary lining concrete are effectively ensured, and the problems of chipping and shrinkage cracks can be effectively avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of tunnel maintenance equipment, in particular to an automatic spraying device for tunnel maintenance. Background Art

[0002] After the second lining of the tunnel is demolded, the concrete will dehydrate due to the heat of concrete hydration, which will prevent the cement particles that have formed a gel from being fully hydrated and thus from being transformed into stable crystals. The lack of sufficient bonding strength will cause flaking or powdery shedding on the concrete surface, affecting driving safety. Therefore, it is necessary to ensure that the surface of the lining concrete remains moist and not dry during the curing period. However, due to the angle of the concrete surface, the tunnel cannot adopt conventional film or geotextile covering and watering curing solutions. At present, the second lining of some projects is maintained by fog cannons, but fog cannons require manual control, occupying limited space in the tunnel, and cannot achieve automatic maintenance. They are also restricted by workers and construction sites.

[0003] Since the traditional maintenance method of the tunnel secondary lining is greatly affected by human factors, there are phenomena such as untimely maintenance and missed maintenance. In addition, due to inadequate maintenance, it is difficult to keep the concrete moist for a long time, which makes the concrete strength increase slowly. The premature evaporation of water will cause large shrinkage deformation and shrinkage cracks, which will affect the durability and integrity of the concrete and cause quality defects. Utility Model Content

[0004] In order to solve the above problems, the utility model provides an automatic spraying device for tunnel maintenance.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:

[0006] An automatic spraying device for tunnel maintenance comprises a trolley and a maintenance frame on top thereof, wherein a moving mechanism is provided at the bottom of the trolley and the maintenance frame can move along a track on the top of the trolley; an arc-shaped spray pipe matching the inner wall of the tunnel is provided at the front of the maintenance frame, and a plurality of spray heads are provided at intervals on the top side surface of the arc-shaped spray pipe; the arc-shaped spray pipe is connected to a water storage tank through a water supply assembly.

[0007] Furthermore, the maintenance frame includes a rectangular mobile frame and an arc-shaped spray pipe. The top of the trolley is provided with a driving mechanism for driving the mobile frame to reciprocate along the track. The driving mechanism includes a mobile motor and a chain transmission assembly. The chain transmission assembly includes a chain, a driven sprocket and a driving sprocket. The chain connects the driving sprocket and the driven sprocket. The driven sprocket and the driving sprocket are respectively arranged at the front and rear ends of the track. The output end of the mobile motor is connected to the driving sprocket; guide grooves that slide with the mobile frame are provided on both sides of the track. The mobile frame is provided with a rack along its length direction. A gear that meshes with the rack is provided at the front of the track. The gear is coaxially fixed with the driven sprocket.

[0008] Furthermore, the front end of the movable frame is connected to a traction rope, the end of the traction rope is wound on a reel, and the reel is driven by a retractable motor to rotate forward and reverse; the retractable motor is linked to the movable motor.

[0009] Furthermore, the water supply assembly includes a water pump and a water pipe, the water pump is connected to the arc-shaped spray pipe and the water tank through the water pipe respectively, and the upper part of the trolley is provided with a bracket for supporting the water tank and the water pump; the track is arranged in the middle position of the operating table on the top of the trolley, and the track is consistent with the length direction of the tunnel.

[0010] Furthermore, the trolley is a portal frame structure, the two sides of the trolley are rectangular frames, and the bracket, the operating table and the connecting frames on both sides form a trapezoidal frame that is larger at the top and smaller at the bottom.

[0011] Furthermore, climbing frames are provided on both sides of the trolley, and the climbing frames include a first ladder, a first platform, a second ladder, a second platform and a third ladder, the first platform is arranged on the outer side of the middle part of the trolley, the second platform is arranged on the upper part of the trolley, the upper end of the first ladder is connected to the first platform, the second ladder is arranged between the first platform and the second platform, and the third ladder is arranged between the second platform and the operating table.

[0012] Furthermore, the lower parts of the first ladders on both sides are connected to the lower ends of the two sides of the trolley through hydraulic rods respectively, the upper end of the first ladder is rotatably connected to the first platform, and the upper and lower ends of the hydraulic rod are rotatably connected to the first ladder and the trolley respectively.

[0013] Furthermore, the mobile mechanism includes four running wheels, which are respectively arranged at the front and rear ends of both sides of the trolley. The two running wheels at the rear end of the trolley are driving wheels, and the two running wheels at the front end of the trolley are universal wheels. A direction adjustment mechanism is provided between the universal wheels and the bottom of the trolley.

[0014] Furthermore, the direction adjustment mechanism is a hydraulic cylinder arranged at the bottom of the trolley, the piston rod of the hydraulic cylinder is rotatably connected to the wheel seat of the universal wheel, and the cylinder body of the hydraulic cylinder is rotatably connected to the bottom of the trolley; the hydraulic cylinder is used to drive the universal wheel to turn.

[0015] Compared with the prior art, the technical progress achieved by the utility model is:

[0016] The utility model drives the trolley to move in the tunnel through a moving mechanism, and delivers water from the water tank to the arc-shaped spray pipe through a water supply component, and sprays the tunnel secondary lining with the help of multiple nozzles on the arc-shaped spray pipe. The curing frame moving along the track drives the arc-shaped spray pipe to perform large-area curing of the tunnel secondary lining without moving the trolley, and the curing operation of the tunnel secondary lining is realized by moving the trolley. The utility model can be used to maintain the tunnel secondary lining, ensure that the concrete is in a moist state, effectively ensure the strength and durability of the secondary lining concrete, and effectively prevent the problems of falling blocks and shrinkage cracks. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. They are used together with the embodiments of the present invention to explain the present invention and do not constitute a limitation to the present invention.

[0018] In the attached picture:

[0019] Figure 1 A schematic diagram of the structure of an automatic spraying device for tunnel maintenance provided by an embodiment of the utility model;

[0020] Figure 2 for Figure 1 A top view of the central operating console;

[0021] Figure 3 This is a schematic diagram of the connection between the hydraulic cylinder and the universal wheel in the embodiment of the utility model;

[0022] In the figure:

[0023] 1-trolley; 2-maintenance frame; 3-track; 4-sprinkler; 5-water storage tank; 6-mobile motor; 7-transmission assembly, 70-chain, 71-driven sprocket, 72-driving wheel; 8-water pipe; 9-bracket; 10-operating table; 11-first ladder; 12-first platform; 13-second ladder; 14-second platform; 15-third ladder; 16-hydraulic rod; 17-travel wheel; 18-hydraulic cylinder. 20-arc spray pipe; 21-mobile frame DETAILED DESCRIPTION

[0024] The following specific embodiments may be combined with each other, and the same or similar concepts or processes may not be described in detail in some embodiments. The following will describe the embodiments of the present utility model in conjunction with the accompanying drawings.

[0025] like Figure 1 , Figure 2 and Figure 3 As shown, an automatic spraying equipment for tunnel maintenance includes a trolley 1 and a maintenance frame 2 on top thereof. A moving mechanism is provided at the bottom of the trolley 1, and the maintenance frame 2 can move along the track 3 on the top of the trolley; an arc-shaped spray pipe 20 matching the inner wall of the tunnel is provided at the front of the maintenance frame 2, and a plurality of nozzles 4 are provided at intervals on the top side of the arc-shaped spray pipe 20; the arc-shaped spray pipe 20 is connected to a water storage tank 5 through a water supply assembly. The arc-shaped spray pipe is 0.3 to 0.5 m away from the contour of the tunnel secondary lining, and the distance between adjacent nozzles is 50 cm. After the second lining concrete of the tunnel is demolded, the arc-shaped spray pipe is carried out by the trolley to carry out maintenance operations, ensuring that the continuous spraying time at the same fixed point in the tunnel is 5 seconds, and the control trolley moves forward along the center of the tunnel.

[0026] In a specific embodiment of the present invention, Figure 2 As shown, the maintenance frame 2 includes a rectangular mobile frame 21 and an arc-shaped spray pipe 20. The top of the trolley 1 is provided with a driving mechanism for driving the mobile frame 21 to reciprocate along the track. The driving mechanism includes a mobile motor 6 and a transmission assembly 7. The driven wheel 71 and the driving wheel 72 of the transmission assembly 7 are respectively arranged at the front and rear ends of the track 3, and the output end of the mobile motor 6 is connected to the driving wheel. The two sides of the track 3 are provided with guide grooves that slide with the mobile frame 21. The mobile frame 21 is provided with a rack (not shown in the figure) along its length direction. The front part of the track 3 is provided with a gear (not shown in the figure) that meshes with the rack, and the gear is coaxially fixed with the driven wheel. Among them, the transmission assembly 7 is two sets of chain transmission assemblies, the driven wheel and the driving wheel are respectively a driven sprocket and a driving sprocket, and the two sets of chain transmission assemblies are respectively arranged on the outer sides of the two sides of the track 3. A plurality of support rods for supporting the chain 70 are arranged at intervals on the outer walls of the two sides of the track 3. The side of the moving frame is connected to the chain through a connecting piece, and the gear is driven to rotate through the chain transmission, thereby driving the moving frame to move along the track. At the same time, the chain drives the moving frame to move synchronously through the connecting piece.

[0027] To further optimize the above scheme, the front end of the mobile frame 21 is connected to a traction rope (not shown in the figure), the end of the traction rope is wound on a reel, and the reel is driven by a retractable motor to rotate forward and reverse; the retractable motor is linked to the mobile motor. When the mobile frame moves forward, the mobile motor rotates forward to drive the gear to rotate forward, driving the rack to move forward, and the retractable motor reverses to release the traction rope on the reel, so that the traction rope can move forward with the mobile frame; conversely, when the mobile frame moves backward and retracts, the mobile motor reverses to drive the gear to rotate in the opposite direction, driving the rack to move backward, and the retractable motor rotates forward to wind the traction rope on the reel, and the traction rope assists in pulling the mobile frame backward.

[0028] In specific application, the water supply assembly includes a water pump (not shown) and a water pipe 8. The water pump is connected to the arc-shaped spray pipe 20 and the water tank 5 through the water pipe 8. The upper part of the trolley 1 is provided with a bracket 9 for supporting the water tank 5 and the water pump; the track 3 is arranged in the middle position of the operating table 10 on the top of the trolley 1, and the track 3 is consistent with the length direction of the tunnel. Among them, the two water tanks are connected by a corrugated pipe, and an electric control valve, a heater and a temperature sensor are installed at the outlet of the water tank. The water outlet pipe is connected to the filter, the water pump, the folded soft water pipe in turn until the nozzle interface. The nozzle is installed along the arc arch at a spacing of 50cm. During installation, the nozzle direction is at an angle of 45 degrees to the longitudinal direction of the tunnel, and the nozzle groove is rotated 15 degrees with the arc-shaped spray pipe. At the same time, the nozzle uses a metal spray nozzle.

[0029] In order to realize automatic control, the water pump, electric control valve, heater, temperature sensor, mobile motor, and receiving and discharging motor can be connected to the controller, and the controller controls the linkage of each part to realize automatic spraying maintenance. Among them, the moving speed of the maintenance rack is controlled at 6m / min. When watering for maintenance, adjust the outlet control valve of the water pump to control the water spraying pressure and water mist volume. When spraying water, the continuous spraying time at the same fixed point is 5s; the maintenance period is generally 14 days, and the interval between spraying maintenance is 2 hours to ensure that the concrete always remains moist.

[0030] When designing specifically, Figure 1As shown, the trolley 1 is a door-type frame structure, and the two sides of the trolley 1 are rectangular frames. The bracket 9, the operating platform 10 and the connecting frames on both sides form a trapezoidal frame with a large upper part and a small lower part. In order to facilitate operators to get on and off the trolley to operate and maintain equipment, climbing frames are provided on both sides of the trolley 1, and the climbing frames include a first ladder 11, a first platform 12, a second ladder 13, a second platform 14 and a third ladder 15. The first platform 12 is arranged on the outer side of the middle part of the trolley 1, and the second platform 14 is arranged on the upper part of the trolley 1. The upper end of the first ladder 11 is connected to the first platform 12, the second ladder 13 is arranged between the first platform 12 and the second platform 14, and the third ladder 15 is arranged between the second platform 14 and the operating platform 10. At the same time, the lower parts of the first ladders 11 on both sides are respectively connected to the lower ends of the two sides of the trolley 1 through hydraulic rods 16, the upper end of the first ladder 11 is connected to the first platform 12 for rotation, and the upper and lower ends of the hydraulic rod 16 are respectively connected to the first ladder 11 and the trolley 1 for rotation. When the trolley moves, the first ladder is lifted off the ground by the hydraulic rod. After it is moved into place, the first ladder is lowered to the ground to facilitate people to go up and down.

[0031] In a specific embodiment of the present invention, Figure 1 As shown, the mobile mechanism includes four running wheels 17, and the four running wheels 17 are respectively arranged at the front and rear ends of both sides of the trolley 1. The two running wheels 17 at the rear end of the trolley 1 are driving wheels, and the two running wheels 17 at the front end of the trolley 1 are universal wheels. A direction adjustment mechanism is provided between the universal wheels and the bottom of the trolley. Among them, the driving wheel can adopt electric steering tires, without laying tracks, the direction can be adjusted at any time, and the walking and shifting are convenient and efficient. If an ordinary driving wheel without steering function is selected, it is necessary to provide a maintenance guide rail that cooperates with the running wheel in the tunnel to facilitate movement along the length direction of the tunnel. The driving wheel adopts the existing technology, and is equipped with a motor and a reducer inside, which will not be repeated here.

[0032] In specific production, the direction adjustment mechanism is a hydraulic cylinder 18 disposed at the bottom of the trolley 1, the piston rod of the hydraulic cylinder 18 is rotatably connected to the wheel seat of the universal wheel, and the cylinder body of the hydraulic cylinder 18 is rotatably connected to the bottom of the trolley 1; the hydraulic cylinder 18 is used to drive the universal wheel to turn. The rotation of the universal wheel is achieved through the action of the hydraulic cylinder, and then the steering operation of the trolley is achieved, which is convenient for steering operations outside the tunnel.

[0033] To further optimize the above scheme, the hydraulic rod and the hydraulic cylinder can be connected to the controller, and the controller can be wirelessly connected to the remote controller, so that the free movement of the trolley, the forward and backward movement of the top curing frame, and the start and stop of the water spraying of the sprinkler pipe can be remotely controlled through the remote controller. At the same time, a heater for controlling the temperature of the water storage tank, a temperature sensor for detecting the temperature of the concrete, and a temperature and humidity sensor for detecting the ambient temperature and humidity are installed on the trolley, and the heater, temperature sensor, and temperature and humidity sensor are connected to the controller to facilitate automatic adjustment of the curing water temperature according to the concrete temperature.

[0034] At the same time, the trolley is equipped with a safety voice alarm system to implement real-time monitoring and fault detection of the entire equipment, and provide voice broadcasts. When the equipment fails, it can switch to manual assistance mode for normal operation.

[0035] The utility model has the following beneficial effects:

[0036] 1. Independent operation and maintenance: According to the environmental conditions after the second lining of the tunnel is demolded, the second lining concrete is automatically sprayed and maintained. The trolley runs along an independent maintenance guide rail. After the trolley moves to the designated maintenance position, automatic maintenance is started. The trolley does not move, and the maintenance frame automatically moves along the independently set track on the trolley for maintenance. The operation is smooth and safe, without dragging of cables, water pipes, air ducts, etc., and no manual supervision is required.

[0037] 2. Automatic maintenance: It can automatically perform concrete maintenance operations according to the time and frequency set by the controller, automatically record the current number of maintenance cycles, maintenance time, real-time maintenance temperature, etc., and automatically generate a construction log, with the function of automatic real-time storage of real-time information.

[0038] 3. Intelligent temperature control: It can detect concrete temperature, ambient temperature and humidity, and automatically adjust the curing water temperature according to the concrete temperature.

[0039] 4. Human-computer interaction: strong controllability, simple operation, real-time monitoring of the equipment's operating status, and ability to adjust maintenance parameters in real time according to construction parameter requirements.

[0040] 5. Full-platform workbench: The climbing frame is humanized in design, the ladder is designed with widened pedals, and a step platform is set on the arch waist. All platforms are fully covered with patterned steel plates. It can be used as an operating platform for secondary lining concrete surface maintenance, radar detection, secondary lining knocking detection, etc.

[0041] In summary, the utility model has a simple overall structure, convenient and quick operation, and can maintain the secondary lining of the tunnel. The maintenance period is generally 14 days, and the interval between spraying water mist maintenance is 2 hours, ensuring that the concrete is in a moist state, effectively ensuring the strength and durability of the secondary lining concrete, and effectively preventing the problems of falling blocks and shrinkage cracks. The utility model can be used to comprehensively maintain the secondary lining of the tunnel, ensure the maintenance effect of the lining concrete, and enhance the strength of the lining concrete. At the same time, automatic spray maintenance can suppress dust in the tunnel, maintain a moist environment in the tunnel, and provide a better construction environment for construction workers. The utility model can realize automatic spray maintenance, which is suitable for highway and railway tunnel projects.

[0042] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein with equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the scope of protection of the claims of the utility model.

Claims

1. An automatic spraying device for tunnel maintenance, characterized in that: It includes a trolley and a maintenance frame on top of the trolley, a moving mechanism is provided at the bottom of the trolley, and the maintenance frame can move along the track on the top of the trolley; the front part of the maintenance frame is provided with an arc-shaped spray pipe matching the inner wall of the tunnel, and a plurality of nozzles are arranged at intervals on the top side of the arc-shaped spray pipe; the arc-shaped spray pipe is connected to the water tank through a water supply assembly; the maintenance frame includes a rectangular moving frame and an arc-shaped spray pipe, and the top of the trolley is provided with a driving mechanism for driving the moving frame to reciprocate along the track, the driving mechanism includes a moving motor and a transmission assembly, the driven wheel and the driving wheel of the transmission assembly are respectively arranged at the front and rear ends of the track, and the output end of the moving motor is connected to the driving wheel; guide grooves that slide with the moving frame are provided on both sides of the track, and a rack is provided on the moving frame along its length direction, and a gear meshing with the rack is provided at the front part of the track, and the gear is coaxially fixed with the driven wheel.

2. The automatic spraying equipment for tunnel maintenance according to claim 1, characterized in that: The transmission assembly is two sets of chain transmission assemblies, the driven wheel and the driving wheel are respectively a driven sprocket and a driving sprocket, the two sets of chain transmission assemblies are respectively arranged on the outer sides of the track, and a plurality of support rods for supporting the chain are spaced apart on the outer walls on both sides of the track.

3. The automatic spraying equipment for tunnel maintenance according to claim 1, characterized in that: The front end of the mobile frame is connected to a traction rope, the end of the traction rope is wound on a reel, and the reel is driven by a retractable motor to rotate forward and reverse; The transmitting and receiving motor is linked with the moving motor.

4. The automatic spraying equipment for tunnel maintenance according to claim 1, characterized in that: The water supply assembly includes a water pump and a water pipe. The water pump is connected to the arc-shaped spray pipe and the water tank through the water pipe respectively. The upper part of the trolley is provided with a bracket for supporting the water tank and the water pump. The track is arranged in the middle position of the operating table on the top of the trolley, and the track is consistent with the length direction of the tunnel.

5. The automatic spraying equipment for tunnel maintenance according to claim 4 is characterized in that: The trolley is a door-type frame structure, and the two sides of the trolley are rectangular frames. The bracket, the operating table and the connecting frames on both sides form a trapezoidal frame that is larger at the top and smaller at the bottom.

6. The automatic spraying equipment for tunnel maintenance according to claim 5, characterized in that: Climbing frames are provided on both sides of the trolley, and the climbing frames include a first ladder, a first platform, a second ladder, a second platform and a third ladder. The first platform is arranged on the outer side of the middle part of the trolley, the second platform is arranged on the upper part of the trolley, the upper end of the first ladder is connected to the first platform, the second ladder is arranged between the first platform and the second platform, and the third ladder is arranged between the second platform and the operating table.

7. The automatic spraying equipment for tunnel maintenance according to claim 6, characterized in that: The lower parts of the first ladders on both sides are connected to the lower ends of the two sides of the trolley through hydraulic rods respectively, the upper end of the first ladder is rotatably connected to the first platform, and the upper and lower ends of the hydraulic rod are rotatably connected to the first ladder and the trolley respectively.

8. The automatic spraying equipment for tunnel maintenance according to any one of claims 1 to 7, characterized in that: The moving mechanism includes four running wheels, which are respectively arranged at the front and rear ends of both sides of the trolley. The two running wheels at the rear end of the trolley are driving wheels, and the two running wheels at the front end of the trolley are universal wheels. A direction adjustment mechanism is provided between the universal wheels and the bottom of the trolley.

9. The automatic spraying equipment for tunnel maintenance according to claim 8, characterized in that: The direction adjustment mechanism is a hydraulic cylinder arranged at the bottom of the trolley, the piston rod of the hydraulic cylinder is rotatably connected to the wheel seat of the universal wheel, and the cylinder body of the hydraulic cylinder is rotatably connected to the bottom of the trolley; the hydraulic cylinder is used to drive the universal wheel to turn.