Pre-embedded anchor bolt component for transformer substation architecture foundation

By designing embedded foundation pits and positioning mechanisms in the substation architecture, and using the cooperation of bolts and screw holes, the problem of inability to locate the anchor bolt installation position is solved, the accurate positioning and fixing of anchor bolts is achieved, and the substation is improved The installation accuracy of components and the stability of the overall structure.

CN221956718UActive Publication Date: 2024-11-05HUBEI HANTANG DIGITAL TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420582381.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-25
Publication Date
2024-11-05
Estimated Expiration
2034-03-25

AI Technical Summary

Technical Problem

The installation position of the base anchor bolts in the existing substation architecture cannot be positioned, resulting in the easy deviation of the installation angle and position, affecting the accurate installation of subsequent components and the stability of the overall structure.

Method used

A pre-embedded anchor bolt member for substation architecture is designed, using embedded foundation pits, column steel bars, bundled steel bars, positioning mechanisms and embedded mechanisms, and through the first and second fixing bolts, thread grooves, screw holes and tightening The fit of the fixing nut ensures accurate positioning and fixing of the anchor bolts and avoids deviation.

Benefits of technology

It effectively prevents the position of the anchor bolt from being displaced, ensures the accurate installation of substation components and the stability of the overall structure, and improves the practicality of construction and the stability of embedded components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956718U_ABST
    Figure CN221956718U_ABST
Patent Text Reader

Abstract

The utility model relates to a transformer substation framework foundation pre-embedded anchor bolt component which comprises a ground, a pre-embedded foundation pit is formed in the upper surface of the ground, stand column steel bars are fixed to the inner bottom wall of the pre-embedded foundation pit, binding steel bars are fixed to the outer sides of the stand column steel bars, a connecting steel plate is arranged above the pre-embedded foundation pit, and the binding steel bars are connected with the connecting steel plate. The embedded foundation pit is provided with a positioning mechanism used for positioning the embedded position of the anchor bolt, and the connecting steel plate is provided with an embedded mechanism facilitating embedding of the anchor bolt. According to the transformer substation framework foundation pre-embedded anchor bolt component, through cooperation of the first fixing bolts and the threaded grooves, the guide mounting plate and the supporting plate can be conveniently fixed, meanwhile, the angle between the guide mounting plate and the supporting plate is kept, and therefore the guide mounting plate is prevented from deviating; and the guide mounting plate and the connecting steel plate can be connected and fixed together, so that the anchor bolt component can be embedded conveniently.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pre-buried substation structure, in particular to a pre-buried ground anchor bolt component for a substation structure foundation. Background Art

[0002] A substation is a place in the power system that transforms voltage and current, receives electric energy and distributes electric energy. The substation in a power plant is a step-up substation, and its function is to step up the voltage of the electric energy generated by the generator and feed it into the high-voltage power grid.

[0003] During the installation of the substation, the components need to be embedded so that the structure of the substation can be more stable. For example, China Utility Model Patent Publication No. (CN219732324U) discloses a pre-embedded anchor bolt structure for the foundation of an outdoor substation structure. The pre-embedded anchor bolt structure for the foundation of an outdoor substation structure embeds multiple anchor bolts in the outdoor structure foundation. The multiple anchor bolts are evenly arranged in a circle. Each anchor bolt is provided with external threads at the top and the middle. The top external thread is used for bolt connection between the pre-embedded anchor bolt and the bottom plate of the structure column. The middle external thread is used for connecting the leveling bolt. The middle steel plate is fastened to the foundation steel bar. The middle steel plate is ring-shaped. Each anchor bolt passes through the middle steel plate respectively. The leveling bolt is adjacent to the bottom surface of the middle steel plate. The upper surface of the middle steel plate is welded to the connecting angle steel. The connecting angle steel is connected to the outdoor frame The longitudinal reinforcement of the outdoor structure foundation is welded and fixed, and annular stirrups are arranged around the longitudinal reinforcement of the outdoor structure foundation. The bottom end of each anchor bolt is fixed to the end anchor plate respectively. This practical solution solves the problem that if the end anchor plate structure is adopted, when the number of anchor bolts is large and the spacing is small, the anchor plates will collide, and the accuracy of the installation height and spacing of the anchor bolts cannot be guaranteed. When the steel bar is welded and fixed in the middle of the anchor bolt, the hot-dip galvanized layer of the anchor bolt is destroyed, weakening the anti-corrosion performance of the structure. Moreover, only the steel bar connection treatment cannot ensure the integrity of the anchor bolt group. In the actual construction process, the problems of deviation and uneven anchor bolts often occur. However, the installation position of the anchor bolt in this patent cannot be located, which makes the installation angle and position easy to offset, making it impossible to accurately install the subsequent substation components, affecting practicality. Utility Model Content

[0004] In view of the shortcomings of the prior art, the utility model provides a pre-buried ground anchor bolt component for the foundation of a substation structure, which has the advantage of locating the installation position of the ground anchor bolt, and solves the problem that the installation position of the ground anchor bolt in the patent cannot be located, resulting in the installation angle and position being easily offset, making it impossible to accurately install the subsequent substation components, affecting practicality.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a pre-buried ground anchor bolt component for a substation structure foundation, comprising a ground, a pre-buried foundation pit is opened on the upper surface of the ground, column steel bars are fixed to the inner bottom wall of the pre-buried foundation pit, and bundled steel bars are fixed to the outer side of the column steel bars, a connecting steel plate is provided above the pre-buried foundation pit, a positioning mechanism for positioning with the pre-buried position of the ground anchor bolt is provided on the pre-buried foundation pit, and a pre-buried mechanism for facilitating the pre-buried ground anchor bolt is provided on the connecting steel plate;

[0006] The positioning mechanism includes a support plate, the lower surface of the support plate is fixed to the inner bottom wall of the embedded foundation pit, the left side of the support plate is fixed to the left inner wall of the embedded foundation pit, a guide mounting plate is placed on the upper surface of the ground, the upper surface of the guide mounting plate is threadedly connected with a first fixing bolt, a thread groove is provided on the upper surface of the support plate, the bottom end of the first fixing bolt passes through and extends to the inside of the thread groove, and is threadedly connected to the inner side of the thread groove, and an installation assembly is provided on the connecting steel plate.

[0007] Furthermore, the number of the column steel bars is not less than two and is evenly distributed inside the embedded foundation pit, and the number of the bundled steel bars is not less than two and is evenly distributed outside the column steel bars.

[0008] Furthermore, the number of the support plates is four, and they are symmetrically distributed around the central axis of the embedded foundation pit. Each of the support plates is provided with no less than two thread grooves, which are equidistantly distributed on the upper surface of each support plate.

[0009] Furthermore, the mounting assembly includes a second fixing bolt, which is threadedly connected to the upper surface of the connecting steel plate. A threaded hole is provided on the upper surface of the guide mounting plate. The second fixing bolt penetrates and extends into the interior of the threaded hole and is threadedly connected to the inner side of the threaded hole.

[0010] Furthermore, the number of the second fixing bolts is four, and they are evenly distributed at the four corners of the upper surface of the connecting steel plate. The number of the guide mounting plates is two, and each of the guide mounting plates is provided with no less than two threaded holes, which are equidistantly distributed on the upper surface of the guide mounting plates.

[0011] Furthermore, the embedded mechanism includes a connecting hole opened on the upper surface of the connecting steel plate, a ground anchor body is arranged inside the connecting hole, an external thread is opened on the outer side of the top of the ground anchor body, a gasket is placed on the upper surface of the connecting steel plate, and a fastening nut is threadedly connected to the external thread.

[0012] Furthermore, the number of the connecting holes is four and they are symmetrically distributed around the central axis of the connecting steel plate. The number of the anchor bolt bodies is equal to the number of the connecting holes and their positions correspond one to one.

[0013] Compared with the prior art, the technical solution of this application has the following beneficial effects:

[0014] 1. The pre-buried ground anchor bolt component of the substation structure foundation can facilitate the fixing of the guide mounting plate and the support plate through the cooperation of the first fixing bolt and the threaded groove, while keeping the guide mounting plate at a vertical angle to the support plate, thereby preventing the guide mounting plate from shifting. Through the cooperation of the second fixing bolt, the guide mounting plate can be connected and fixed to the connecting steel plate, thereby facilitating the pre-buried ground anchor bolt component.

[0015] 2. The pre-buried anchor bolt component of the substation structure foundation can extend a part of the anchor bolt to the upper side of the connecting steel plate through the cooperation of the connecting hole, so as to facilitate the subsequent installation of the substation structure. The anchor bolt can be fixed to the connecting steel plate through the cooperation of the fastening nut, so as to avoid the position of the anchor bolt from being offset, so as not to affect the subsequent installation work. The fastening nut can be easily removed through the cooperation of the gasket. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the utility model;

[0017] Figure 2 This is a schematic diagram of the positioning mechanism of the utility model;

[0018] Figure 3 It is a schematic diagram of the embedded mechanism of the utility model.

[0019] In the figure: 1 ground, 2 embedded foundation pit, 3 column steel bars, 4 bundled steel bars, 5 connecting steel plate, 6 positioning mechanism, 601 support plate, 602 guide mounting plate, 603 first fixing bolt, 604 threaded groove, 605 second fixing bolt, 606 threaded hole, 7 embedded mechanism, 701 connecting hole, 702 anchor bolt body, 703 external thread, 704 gasket, 705 fastening nut. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] See also Figure 1In the present embodiment, a pre-buried foundation anchor bolt component of a substation structure foundation comprises a ground 1, a pre-buried foundation pit 2 is opened on the upper surface of the ground 1, a column steel bar 3 is fixed to the inner bottom wall of the pre-buried foundation pit 2, and a bundled steel bar 4 is fixed to the outer side of the column steel bar 3, a plurality of column steel bars 3 are installed on the inner bottom wall of the pre-buried foundation pit 2, and after the column steel bars 3 are installed, the bundled steel bars 4 are welded to the outer side of the column steel bars 3 to surround the column steel bars 3, a connecting steel plate 5 is provided above the pre-buried foundation pit 2, and a positioning mechanism 6 for positioning with the pre-buried position of the anchor bolt is provided on the pre-buried foundation pit 2 to avoid position deviation during the process of pre-buried anchor bolts, and a pre-buried mechanism 7 for facilitating the pre-buried anchor bolts is provided on the connecting steel plate 5 to facilitate the pre-buried anchor bolt components.

[0022] Among them, the number of column steel bars 3 is not less than two, and they are evenly distributed inside the embedded foundation pit 2. The number of bundling steel bars 4 is not less than two, and they are equidistantly distributed on the outside of the column steel bars 3, so that after concrete is subsequently injected into the embedded foundation pit 2, the stability of the embedded components can be improved after the concrete is dried.

[0023] See also Figure 2 In order to avoid the position deviation during the process of pre-embedded anchor bolts, the positioning mechanism 6 in this embodiment includes a supporting plate 601, the lower surface of the supporting plate 601 is fixed to the inner bottom wall of the pre-embedded foundation pit 2, the left side of the supporting plate 601 is fixed to the left inner wall of the pre-embedded foundation pit 2, a guide mounting plate 602 is placed on the upper surface of the ground 1, the upper surface of the guide mounting plate 602 is threadedly connected with a first fixing bolt 603, the upper surface of the supporting plate 601 is provided with a threaded groove 604, the bottom end of the first fixing bolt 603 penetrates It passes through and extends into the interior of the thread groove 604 and is connected with the inner thread of the thread groove 604. The first fixing bolt 603 on the guide mounting plate 602 is aligned with the thread groove 604 on the support plate 601 according to the required installation position, and the first fixing bolt 603 is installed into the thread groove 604, thereby fixing the guide mounting plate 602 and keeping the guide mounting plate 602 at a perpendicular angle to the support plate 601 to avoid the guide mounting plate 602 from being offset. An installation component is provided on the connecting steel plate 5.

[0024] In this example, there are four support plates 601, which are symmetrically distributed around the central axis of the embedded foundation pit 2. Each support plate 601 is provided with no less than two thread grooves 604, which are equidistantly distributed on the upper surface of each support plate 601 to adjust the installation position of the guide mounting plate 602 on the support plate 601.

[0025] It should be noted that the installation assembly includes a second fixing bolt 605, which is threadedly connected to the upper surface of the connecting steel plate 5. A threaded hole 606 is provided on the upper surface of the guide mounting plate 602. The second fixing bolt 605 passes through and extends to the inside of the threaded hole 606, and is threadedly connected to the inner side of the threaded hole 606. The connecting steel plate 5 and the guide mounting plate 602 can be fixed together by the second fixing bolt 605 and the threaded hole 606. There are four second fixing bolts 605, which are evenly distributed at the four corners of the upper surface of the connecting steel plate 5. There are two guide mounting plates 602. Each guide mounting plate 602 is provided with no less than two threaded holes 606, which are equidistantly distributed on the upper surface of the guide mounting plate 602, so as to facilitate the adjustment of the installation position of the connecting steel plate 5 on the guide mounting plate 602.

[0026] See also Figure 3 In order to facilitate the pre-embedding of the anchor bolt component, the pre-embedding mechanism 7 in this embodiment includes a connecting hole 701 opened on the upper surface of the connecting steel plate 5, an anchor bolt body 702 is arranged inside the connecting hole 701, an external thread 703 is arranged on the outer side of the top of the anchor bolt body 702, the inner diameter of the connecting hole 701 is matched with the outer diameter of the external thread 703, a gasket 704 is placed on the upper surface of the connecting steel plate 5, and a fastening nut 705 is threadedly connected to the external thread 703 to fix the anchor bolt. The main body 702 is inserted into the connecting hole 701, and the anchor bolt main body 702 is fixed to the connecting steel plate 5 by the fastening nut 705, so that each anchor bolt main body 702 maintains the same height position, and the gasket 704 can facilitate the removal of the fastening nut 705. After the pre-embedding is completed, the fastening nut 705 needs to be removed, and then the substation structure is installed on the anchor bolt main body 702, and the substation structure and the anchor bolt main body 702 are fixed by the fastening nut 705.

[0027] In this example, there are four connecting holes 701, which are symmetrically distributed around the central axis of the connecting steel plate 5. The number of anchor bolt bodies 702 is equal to the number of connecting holes 701, and their positions correspond one to one, so that stability can be maintained during the subsequent installation process between the substation structure.

[0028] The working principle of the above embodiment is:

[0029] (1) First, a pre-buried foundation pit 2 is dug on the construction ground 1, and then a plurality of column reinforcement bars 3 are installed on the inner bottom wall of the pre-buried foundation pit 2. After the column reinforcement bars 3 are installed, the bundled reinforcement bars 4 are welded to the outer side of the column reinforcement bars 3 to surround the column reinforcement bars 3. Then, the guide mounting plate 602 is installed. According to the required installation position, the first fixing bolt 603 on the guide mounting plate 602 is aligned with the threaded groove 604 on the support plate 601, and the first fixing bolt 603 is installed into the threaded groove 604, thereby fixing the guide mounting plate 602 and keeping the guide mounting plate 602 at a perpendicular angle to the support plate 601 to prevent the guide mounting plate 602 from being offset.

[0030] (2) After the guide mounting plate 602 is fixed, the anchor bolt body 702 is inserted into the connection hole 701, and the anchor bolt body 702 is fixed to the connection steel plate 5 by tightening the nut 705, so that each anchor bolt body 702 maintains the same height position, and then the connection steel plate 5 is placed on the guide mounting plate 602. The connection steel plate 5 and the guide mounting plate 602 can be fixed together by the second fixing bolt 605 and the threaded hole 606. Then, concrete can be injected into the embedded foundation pit 2. After the concrete is dried, the guide mounting plate 602 and the connection steel plate 5 can be removed, thereby completing the embedded work of the component.

[0031] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0032] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that many changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention.

Claims

1. A pre-buried ground anchor bolt component for a substation structure foundation, comprising a ground (1), characterized in that: A pre-buried foundation pit (2) is provided on the upper surface of the ground (1), column reinforcement bars (3) are fixed to the inner bottom wall of the pre-buried foundation pit (2), and bundled reinforcement bars (4) are fixed to the outer sides of the column reinforcement bars (3). A connecting steel plate (5) is provided above the pre-buried foundation pit (2), and a positioning mechanism (6) for positioning with the pre-buried position of the anchor bolt is provided on the pre-buried foundation pit (2), and a pre-buried mechanism (7) for facilitating the pre-buried anchor bolt is provided on the connecting steel plate (5); The positioning mechanism (6) comprises a supporting plate (601), the lower surface of the supporting plate (601) is fixed to the inner bottom wall of the embedded foundation pit (2), the left side of the supporting plate (601) is fixed to the left inner wall of the embedded foundation pit (2), a guide mounting plate (602) is placed on the upper surface of the ground (1), the upper surface of the guiding mounting plate (602) is threadedly connected with a first fixing bolt (603), a thread groove (604) is provided on the upper surface of the supporting plate (601), the bottom end of the first fixing bolt (603) penetrates and extends to the inside of the thread groove (604), and is threadedly connected to the inner side of the thread groove (604), and a mounting assembly is provided on the connecting steel plate (5).

2. A pre-buried anchor bolt component for a substation structure foundation according to claim 1, characterized in that: The number of the column steel bars (3) is not less than two and they are evenly distributed inside the pre-buried foundation pit (2); the number of the bundled steel bars (4) is not less than two and they are evenly distributed outside the column steel bars (3).

3. A pre-buried anchor bolt component for a substation structure foundation according to claim 1, characterized in that: The number of the support plates (601) is four and they are symmetrically distributed around the central axis of the pre-buried foundation pit (2). Each of the support plates (601) is provided with no less than two thread grooves (604) which are equidistantly distributed on the upper surface of each support plate (601).

4. A pre-buried anchor bolt component for a substation structure foundation according to claim 1, characterized in that: The mounting assembly includes a second fixing bolt (605), which is threadedly connected to the upper surface of the connecting steel plate (5). A threaded hole (606) is provided on the upper surface of the guide mounting plate (602). The second fixing bolt (605) passes through and extends to the interior of the threaded hole (606), and is threadedly connected to the inner side of the threaded hole (606).

5. A pre-buried ground anchor bolt component for a substation structure foundation according to claim 4, characterized in that: The number of the second fixing bolts (605) is four, and they are evenly distributed at the four corners of the upper surface of the connecting steel plate (5). The number of the guide mounting plates (602) is two, and each of the guide mounting plates (602) is provided with no less than two threaded holes (606), which are evenly distributed on the upper surface of the guide mounting plates (602).

6. A pre-buried anchor bolt component for a substation structure foundation according to claim 1, characterized in that: The embedded mechanism (7) comprises a connection hole (701) formed on the upper surface of the connecting steel plate (5), a ground anchor bolt body (702) is provided inside the connection hole (701), an external thread (703) is provided on the outer side of the top end of the ground anchor bolt body (702), a gasket (704) is placed on the upper surface of the connecting steel plate (5), and a fastening nut (705) is threadedly connected to the external thread (703).

7. A pre-buried ground anchor bolt component for a substation structure foundation according to claim 6, characterized in that: The number of the connection holes (701) is four and they are symmetrically distributed around the central axis of the connecting steel plate (5). The number of the anchor bolt bodies (702) is equal to the number of the connection holes (701) and their positions correspond one to one.