Tunnel secondary lining trolley vault pouring monitoring window

By designing the monitoring window and hydraulic lifting mechanism on the tunnel second lining trolley, the problem of not being able to monitor the concrete pouring status during the tunnel second lining pouring and top punching process is solved, ensuring that the concrete quality is qualified and preventing the formwork damage, and realizing the concrete pouring process Effective monitoring and quality control.

CN221957583UActive Publication Date: 2024-11-05CHINA STATE RAILWAY GRP CO LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420049621.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-09
Publication Date
2024-11-05
Estimated Expiration
2034-01-09

AI Technical Summary

Technical Problem

During the casting and top punching process of the second lining of the tunnel, it is impossible to detect whether the pouring status and casting quality of the concrete are qualified, resulting in the problem that the concrete may be unfull or the quality is unqualified.

Method used

Design a tunnel two-lined trolley vault casting monitoring window, including punching holes and monitoring holes set up along the longitudinal interval. The monitoring holes are equipped with monitoring window sealing plates and rotary lock blocks, which are fixed by hinge bases and handrails to ensure that the sealing plates are in It does not open under the weight, provides a window to observe the poured concrete state, and installs a hydraulic hoisting mechanism and pressure sensor in the hoist pipe to induce the concrete pressure to prevent damage to the formwork.

Benefits of technology

Observe the concrete pouring status through the monitoring window to ensure the quality is qualified, and prevent the formwork from being damaged through the hydraulic hoisting mechanism and pressure sensor, effectively monitoring and quality control of the concrete pouring process is achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221957583U_ABST
    Figure CN221957583U_ABST
Patent Text Reader

Abstract

The utility model provides a tunnel secondary lining trolley vault pouring monitoring window which comprises a plurality of top punching holes formed in the top of a tunnel secondary lining formwork trolley at intervals in the longitudinal direction, a plurality of monitoring holes are formed in one side of each top punching hole at intervals in the longitudinal direction, and each monitoring hole is provided with a monitoring window sealing plate. The monitoring window sealing plate is installed on the second lining formwork trolley in a hinged mode through a hinge base at one end, a rotating locking block is arranged on the monitoring hole, and when the monitoring window sealing plate is closed, the rotating locking block rotates to the position below the monitoring window sealing plate to block the monitoring window sealing plate so as to prevent the monitoring window sealing plate from being opened under the dead weight; when concrete pouring is carried out on the second lining section of the tunnel, a worker observes the pouring state of the concrete and whether the arch concrete is poured fully or not through the monitoring window, it is ensured that the pouring quality of the arch concrete is qualified, meanwhile, the window can be used for pre-buried channel installation, comprehensive grounding connection and installation quality inspection, and the monitoring window is connected through the hinge base. And the monitoring window is fixed by the fixing piece, so that the operation is simpler, and the use is more convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field related to tunnel secondary lining casting, in particular to a tunnel secondary lining trolley arch top casting monitoring window. Background Art

[0002] During the pouring and topping process of the tunnel secondary lining, when the tunnel secondary lining trolley is vibrating, it is impossible to detect the pouring status of the concrete, observe whether the concrete is full, and whether the pouring quality of the concrete is qualified. Utility Model Content

[0003] The utility model aims to provide a tunnel secondary lining trolley arch crown pouring monitoring window, which can solve the problem that in the traditional tunnel secondary lining pouring and crowning process, the pouring state of concrete and whether the pouring quality is qualified cannot be monitored.

[0004] To this end, the technical solution adopted by the utility model is: a tunnel secondary lining trolley arch crown casting monitoring window, including a plurality of punching holes arranged at longitudinal intervals on the top of the tunnel secondary lining formwork trolley, a plurality of monitoring holes are longitudinally spaced apart on one side of the punching holes, the monitoring holes are equipped with monitoring window sealing plates, the monitoring window sealing plates are hingedly mounted on the secondary lining formwork trolley through a hinge seat at one end, and a rotating locking block is arranged on the monitoring hole. When the monitoring window sealing plate is closed, the rotating locking block rotates to the bottom of the monitoring window sealing plate to block it to prevent the monitoring window sealing plate from opening under its own weight.

[0005] More preferably, the rotating lock block includes a straight-shaped stopper and a fixing bolt, and the rotating lock block is mounted on the second lining template trolley through the fixing bolt, and the rotating lock block can rotate around the fixing bolt. When the monitoring window sealing plate is closed, the monitoring window sealing plate is fixed by rotating the straight-shaped stopper to prevent the monitoring window sealing plate from opening due to its own weight, which is simple and convenient to operate, saving time and effort.

[0006] More preferably, the monitoring window sealing plate is provided with an armrest at one end away from the hinge seat. When the monitoring window sealing plate is closed, the monitoring window sealing plate is fixed by the armrest, which is more convenient when closing the monitoring window sealing plate.

[0007] More preferably, the handrail is stamped into a "U" shape by sheet metal, and is welded to the monitoring window sealing plate through the side of the "U" shape, and the opening of the "U" shape faces one end of the hinge seat. The handrail is in a "U" shape, and the surface that contacts and is welded to the monitoring window sealing plate is larger, and the connection is more secure.

[0008] More preferably, there are two hinge seats, which are spaced apart at one end of the monitoring window sealing plate. The two hinge seats can ensure stability when opening or closing the monitoring window sealing plate.

[0009] More preferably, a vertically arranged jacking pipe and a jacking pipe inclined on the jacking pipe are installed on the jacking hole.

[0010] More preferably, the number of the top punching holes is four, the number of the monitoring holes is five, and the monitoring holes are evenly spaced on one side of the top punching hole. The number of the monitoring holes is five, so that the condition of the concrete pouring of the top punching of the entire secondary lining trolley can be better observed.

[0011] More preferably, a hydraulic jacking mechanism is installed in the jacking pipe, and a pressure sensor is installed on the piston of the hydraulic jacking mechanism. The pressure of the concrete during the jacking is sensed by the pressure sensor to avoid damage to the jacking template.

[0012] It is further preferred that the top pipe on the side close to the tunnel face is inclined in the direction away from the tunnel face, and the other top pipes are inclined in the direction close to the tunnel face, and the inclination angle of all top pipes is 45-60 degrees. The top pipes inclined at 40-60 degrees can avoid the problem of collapse and lining hollowing due to concrete backflow during the process of removing the pipes and sealing after the top is completed.

[0013] The beneficial effects of the utility model are as follows: a monitoring hole is opened on the tunnel secondary lining trolley and is equipped with a monitoring window sealing plate. When pouring concrete on the tunnel secondary lining section, the staff opens the monitoring window sealing plate and reaches into the monitoring hole to observe the pouring status of the concrete and whether the concrete is full, thereby ensuring that the pouring quality of the concrete is qualified. At the same time, the window can be used for pre-buried groove installation and comprehensive grounding connection to check the installation quality. The monitoring window is connected by a hinge seat, and the monitoring window sealing plate is fixed by a rotating locking block, which makes the operation simpler and the use more convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0015] Figure 1 It is a schematic diagram of the closed state of the monitoring hole of the utility model.

[0016] Figure 2 It is a structural diagram of a jacking pipe and a punching pipe of the utility model.

[0017] Figure 3 It is an installation position diagram of the punching top pipe of the utility model. DETAILED DESCRIPTION

[0018] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0019] like Figure 1-3As shown, a tunnel secondary lining trolley arch crown casting monitoring window includes a plurality of punching holes arranged at longitudinal intervals on the top of the tunnel secondary lining formwork trolley, a plurality of monitoring holes are longitudinally spaced on one side of the punching holes, and the monitoring holes are equipped with monitoring window sealing plates 2. The monitoring window sealing plates 2 are hingedly mounted on the secondary lining formwork trolley through a hinge seat 1 at one end, and a rotating locking block 3 is arranged on the monitoring hole. When the monitoring window sealing plate 2 is closed, the rotating locking block 3 rotates to the bottom of the monitoring window sealing plate 2 to block it to prevent the monitoring window sealing plate 2 from opening under its own weight.

[0020] An inspection hole is provided on the tunnel secondary lining trolley and is equipped with an inspection window sealing plate 2. When pouring concrete on the tunnel secondary lining section, the staff opens the inspection window sealing plate and reaches into the inspection hole to observe the pouring status of the concrete and whether the vault concrete is fully poured to ensure that the pouring quality of the vault concrete is qualified. At the same time, the window can be used for pre-buried groove installation and comprehensive grounding connection to check the installation quality. The inspection window is connected by a hinge seat 1, and the inspection window sealing plate 2 is fixed by rotating the locking block 3, which is simpler to operate and more convenient to use.

[0021] The rotating lock block 3 includes a straight-line block 301 and a fixing bolt 302. The rotating lock block 3 is installed on the second lining template trolley through the fixing bolt 302, and the rotating lock block 3 can rotate around the fixing bolt 302. When the monitoring window sealing plate 2 is closed, the monitoring window sealing plate 2 is fixed by rotating the straight-line block to prevent the monitoring window sealing plate 2 from opening due to its own weight. The operation is simple and convenient, saving time and effort.

[0022] The monitoring window sealing plate 2 is provided with a handrail 4 at one end away from the hinge seat 1. The handrail 4 is stamped into a "U" shape by sheet metal parts and welded to the monitoring window sealing plate 2 through the side of the "U" shape, and the opening of the "U" shape faces one end of the hinge seat 1. When the monitoring window sealing plate 2 is closed, the monitoring window sealing plate 2 is fixed by the handrail 4, which is more convenient when closing the monitoring window sealing plate 2. The shape of the handrail 4 is "U", and the surface contacting and welding with the monitoring window sealing plate 2 is larger, and the connection is more secure.

[0023] There are two hinge seats 1, which are arranged at intervals at one end of the monitoring window sealing plate 2. The two hinge seats 1 can ensure stability when the monitoring window sealing plate 2 is opened or closed.

[0024] The punching holes are equipped with a vertically arranged jacking pipe 5 and a punching pipe 6 inclined on the jacking pipe 5. There are four punching holes and five monitoring holes, which are evenly spaced on one side of the punching holes. There are five monitoring holes, which can better observe the pouring of concrete on the entire secondary lining trolley.

[0025] A hydraulic jacking mechanism 7 is installed in the jacking pipe 5, and a pressure sensor 8 is installed on the piston of the hydraulic jacking mechanism 7. The pressure of the concrete during the top punching is sensed by the pressure sensor 8 to avoid damage to the template of the top punching.

[0026] The top punching pipe 6 on the side close to the tunnel face is inclined in the direction away from the tunnel face, and the other top punching pipes 6 are inclined in the direction close to the tunnel face, and the inclination angle of all top punching pipes 6 is 45-60 degrees. The top punching pipe 6 set at an inclination of 40-60 degrees can avoid the problem of collapse and lining hollowing due to concrete backflow during the process of removing the pipe and sealing after the top punching is completed.

[0027] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A tunnel secondary lining trolley arch top pouring monitoring window, comprising a plurality of top punching holes arranged at intervals along the longitudinal direction on the top of the tunnel secondary lining formwork trolley, characterized in that: A plurality of monitoring holes are longitudinally spaced apart on one side of the punch hole. The monitoring holes are equipped with monitoring window sealing plates (2). The monitoring window sealing plates (2) are hingedly mounted on the secondary lining template trolley via a hinge seat (1) at one end. A rotating lock block (3) is provided on the monitoring hole. When the monitoring window sealing plate (2) is closed, the rotating lock block (3) rotates to the bottom of the monitoring window sealing plate (2) to block it and prevent the monitoring window sealing plate (2) from opening under its own weight.

2. A tunnel secondary lining trolley arch casting monitoring window according to claim 1, characterized in that: The rotating lock block (3) comprises a straight-line stopper (301) and a fixing bolt (302). The rotating lock block (3) is mounted on the second lining template trolley via the fixing bolt (302), and the rotating lock block (3) can rotate around the fixing bolt (302).

3. The tunnel secondary lining trolley arch casting monitoring window according to claim 1 is characterized in that: A handrail (4) is provided at one end of the monitoring window sealing plate (2) away from the hinge seat (1).

4. A tunnel secondary lining trolley arch casting monitoring window according to claim 3, characterized in that: The handrail (4) is formed into a "U" shape by stamping a sheet metal part, and is welded to the monitoring window sealing plate (2) through the side of the "U" shape, and the opening of the "U" shape faces one end of the hinge seat (1).

5. The tunnel secondary lining trolley arch casting monitoring window according to claim 1 is characterized in that: There are two hinge seats (1) in total, which are arranged at intervals at one end of the monitoring window sealing plate (2).

6. The tunnel secondary lining trolley arch casting monitoring window according to claim 1 is characterized in that: A vertically arranged jacking pipe (5) and a jacking pipe (6) obliquely arranged on the jacking pipe (5) are installed on the jacking hole.

7. A tunnel secondary lining trolley arch casting monitoring window according to claim 6, characterized in that: The number of the top punching holes is four, the number of the monitoring holes is five, and the monitoring holes are evenly spaced and arranged on one side of the top punching holes.

8. The tunnel secondary lining trolley arch casting monitoring window according to claim 6 is characterized in that: A hydraulic lifting mechanism (7) is installed in the lifting pipe (5), and a pressure sensor (8) is installed on the piston of the hydraulic lifting mechanism (7).

9. The tunnel secondary lining trolley arch casting monitoring window according to claim 6 is characterized in that: The punching pipe (6) on the side close to the tunnel face is inclined in a direction away from the tunnel face, and the other punching pipes (6) are inclined in a direction close to the tunnel face. The inclination angles of all the punching pipes (6) are 45-60 degrees.