Overpass bridge integral cutting, hoisting and dismantling structure
Through the bridge lifting pre-pressure bracket and half-frame road sealing steel support structure, the inclined leg rigid structure bridge is converted into continuous beams, and combined with the use of fixed protective fences, the green and environmental protection problem of highway span bridge removal in complex traffic environments is solved. , achieving construction safety and traffic impact reduction, ensuring smooth traffic under the bridge.
Patent Information
- Application Number
- CN202323664488.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-29
AI Technical Summary
The demolition of highway span bridges is difficult to achieve green environmental protection in complex traffic environments. The existing directional blasting method and mechanical crushing method lead to large vibrations, strong noise pollution, and long construction periods and great impact on traffic. It is impossible to prevent traffic from being interrupted. conduct.
The bridge lifting pre-pressure bracket structure and half-frame road sealing steel support structure are adopted to convert the inclined leg rigid structure bridge into a continuous beam, and the fixed protective fence is removed in combination with the lower structure to realize traffic control and flow diversion, ensuring smooth traffic under the bridge and Improve construction safety.
The safety of cross-bridge demolition construction and the traffic impact of traffic are reduced, the construction period is shortened, and the smooth traffic under the bridge and construction safety are ensured.
Smart Images

Figure CN221972127U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to an integral cutting, hoisting and dismantling structure for a flying bridge, which is applicable to the field of civil engineering and is suitable for the integral cutting, hoisting and dismantling construction of a flying bridge. Background Art
[0002] The reconstruction and expansion of highways often involves the demolition of a series of ancillary buildings such as overpasses and separation bridges. The methods that are widely used in various engineering practices include integral jacking method, full-frame bracket segmentation method, bridge-erecting machine cantilever segment demolition method, directional blasting method, mechanical crushing method, etc. Among them, directional blasting method and mechanical crushing method have large vibration amplitude and strong noise pollution during construction, long on-site garbage cleaning operation time, and traffic must be closed during operation, so they are not suitable for highway construction. The demolition of highway overpasses often must be carried out without interrupting traffic, so carrying out green and environmentally friendly demolition operations in complex traffic environments is a problem that must be solved in today's highway overpass demolition construction.
[0003] With the continuous development of flyover dismantling technology, new technical support has been provided for the construction and maintenance of flyovers. The new flyover dismantling technology has the advantages of short construction period, small impact on traffic, and high safety, and will be more widely used in the future. The new flyover dismantling technology has been applied in many domestic engineering projects. For example, in the Beijing-Shanghai High-Speed Railway Capacity Expansion and Reconstruction Project, the mobile bracket dismantling method was used to dismantle the flyover across the existing Beijing-Shanghai Railway. The construction period is only 1 / 3 of the traditional method, and the impact on traffic is greatly reduced. The new flyover dismantling technology is an innovative technology in the field of flyover construction and has broad application prospects. With the continuous development of technology, the new flyover dismantling technology will further improve construction efficiency, ensure construction safety, and reduce the impact on traffic. Utility Model Content
[0004] The purpose of the utility model is to provide a structure for the integral cutting, lifting and dismantling of a cross-line bridge, which adopts a bridge jacking pre-stressing support structure and a half-width road-closing steel support structure to convert the inclined-leg rigid frame bridge structure into a continuous beam, thereby avoiding direct block cutting that may easily cause problems such as overall instability and tilt of the bridge, and ensuring the construction safety after the removal of the corbel; adopting the lower structure to dismantle the standardized protective enclosure, and utilizing the bridge dismantling sequence to control and divert traffic on the highway, thereby ensuring smooth traffic under the bridge.
[0005] In order to achieve the above application purpose, this application adopts the following technical solutions: The overall cutting, hoisting and dismantling structure of the overpass includes:
[0006] The half-width road closure steel support structure is set at the central dividing strip and on the road surface on both sides thereof, and includes a crossbeam, an oblique rod, a steel pipe column fixed base, a cross brace, and a steel pipe column; multiple rows of steel pipe columns are arranged on the top of the steel pipe column fixed base, and a crossbeam is arranged on the top of the steel pipe column. The steel pipe columns are connected by oblique rods and cross braces, and the oblique rods are arranged between the cross braces;
[0007] The bridge jacking prestressing support structure is set at the bottom of the solid web, including anchor bolts, longitudinal beams, adjustment jacks, bolts and nuts; the anchor bolts are evenly pre-buried under the solid web, and the longitudinal beams are anchored to the beam body under the bridge deck through anchor bolts and consolidated through anchor bolts; the longitudinal beams are located above the ends of the cross beams, and multiple rows of adjustment jacks are set on the top of the cross beams;
[0008] The lower structure is dismantled and the standardized protective enclosure is installed on half of the road surface of the central dividing strip, including enclosure steel plates, rotatable clamps, nuts, steel plate reserved holes, and tie rods; multiple steel plate reserved holes are provided on the side of the enclosure steel plate, and rotatable clamps are provided on the inner side of the enclosure steel plate. The enclosure steel plates are connected by multiple rows of tie rods, and are temporarily consolidated by rotatable clamps and tightened by nuts.
[0009] Further, the jack is adjusted to lift the solid web, the longitudinal beam and the cross beam are welded at the same time, and then the inclined arch legs of the arch foot are removed.
[0010] Furthermore, the central dividing strip is provided with traffic diversion openings on both sides of the bridge jacking and prestressing support structure, and standardized protective enclosures for dismantling the lower structure are set at the traffic diversion openings.
[0011] The utility model has the following characteristics and beneficial effects:
[0012] 1 The utility model adopts a bridge jacking pre-stressing support structure, uses the bridge jacking pre-stressing support structure to lift the main beam, converts the inclined leg rigid frame bridge structure into a continuous beam, and ensures the construction safety after the corbel is removed.
[0013] 2 The half-width road-closing steel support structure involved in the utility model enables the force of the main beam to be transferred to the bracket and the abutment after the inclined legs are removed, avoiding direct block cutting that may easily cause problems such as overall instability and tilt of the bridge.
[0014] 3 The utility model involves dismantling the standardized protective enclosure of the lower structure, and utilizing the bridge dismantling sequence to control and divert traffic on the highway to ensure smooth traffic under the bridge.
[0015] 4 The bridge jacking prestressing support structure involved in the utility model is cleverly designed. The thrust of the arch foot is eliminated by adjusting the jacking of the jack. At the same time, the longitudinal beam installed under the main beam is welded to the cross beam above the steel pipe column, so that the force of the main beam is transferred to the half-width road-closing steel support structure, ensuring construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a three-dimensional schematic diagram of the bridge jacking pre-stressing support structure;
[0017] Figure 2 This is a schematic elevation diagram of the steel support structure for half of the road closure;
[0018] Figure 3 This is a schematic diagram of the overall cutting, hoisting and dismantling of the overpass structure;
[0019] Figure 4 It is a schematic diagram of the standardized protective enclosure and traffic diversion for the removal of the lower structure;
[0020] Figure 5 It is the structural diagram of the standardized protective enclosure for the demolition of the lower structure.
[0021] In the figure, 1. arch foot; 2. abutment; 3. diagonal brace; 4. bridge deck; 5. steel plate joint; 6. cast-in-place wet joint; 8. solid web; 10. diagonal arch leg; 11. chord plate; 12. abutment foundation; 13. central dividing strip; 31. road surface; 65. anchor bolts; 66. longitudinal beam; 67. adjustment jack; 68. bolts and nuts; 69. cross beam; 70. diagonal rod; 71. steel pipe column fixed base; 72. cross brace; 73. steel pipe column; 74. enclosure steel plate; 75. diversion port; 76. rotatable clamp; 77. nut; 78. reserved hole in steel plate; 79. pull rod. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments in the present application belong to the scope of protection of this application.
[0023] Those skilled in the art should understand that, in the disclosure of the present application, the orientation or positional relationship indicated by terms such as "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", and "outside" are based on the orientation or positional relationship shown in the accompanying drawings, which are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be understood as limiting the present application.
[0024] like Figure 1 to Figure 5 As shown, the overall cutting, hoisting and dismantling structure of this overpass includes:
[0025] The half-width road closure steel support structure is arranged at the central dividing strip 13 and on the road surface 31 on both sides thereof, and includes a cross beam 69, an oblique rod 70, a steel pipe column fixed base 71, a cross brace 72, and a steel pipe column 73; a plurality of rows of steel pipe columns 73 are arranged on the top of the steel pipe column fixed base 71, a cross beam 69 is arranged on the top of the steel pipe column 73, and the steel pipe columns 73 are connected by oblique rods 70 and cross braces 72, and the oblique rods 70 are arranged between the cross braces 72;
[0026] In this embodiment, the central dividing strip 13 is provided with traffic diversion openings 75 on both sides of the bridge jacking prestressing support structure, and standardized protective enclosures for dismantling the lower structure are provided at the traffic diversion openings 75 .
[0027] The bridge jacking prestressing support structure is arranged at the bottom of the solid web 8, and includes anchor bolts 65, longitudinal beams 66, adjustment jacks 67, and bolts and nuts 68; the anchor bolts 65 are evenly pre-buried under the solid web 8, and the longitudinal beams 66 are anchored to the beam body under the bridge deck 4 through the anchor bolts 65, and are consolidated through the anchor bolts 65; the longitudinal beams 66 are located above the ends of the cross beams 69, and multiple rows of adjustment jacks 67 are arranged on the top of the cross beams 69;
[0028] In this embodiment, the adjustment jack 67 is used to lift the solid web 8 so as to weld the longitudinal beam 66 and the transverse beam 69 to remove the oblique arch leg 10 of the arch foot 1.
[0029] The lower structure is dismantled into a standardized protective enclosure, which is installed on the half-width road surface 31 of the central dividing strip 13, and includes an enclosure steel plate 74, a rotatable clamping piece 76, a nut 77, a steel plate reserved hole 78, and a pull rod 79; a plurality of steel plate reserved holes 78 are provided on the side of the enclosure steel plate 74, and a rotatable clamping piece 76 is provided on the inner side of the enclosure steel plate 74. The enclosure steel plates 74 are connected by multiple rows of pull rods 79, and are temporarily consolidated by the rotatable clamping piece 76 and tightened by the nut 77.
[0030] Among them, the arch foot 1, abutment 2, diagonal brace 3, bridge deck 4, steel plate joint 5, cast-in-place wet joint 6, solid web 8, diagonal arch leg 10, chord plate 11, abutment foundation 12, central dividing strip 13, and road surface 31 are all parts of the overpass that need to be demolished. As part of the overpass demolition structure, this application plays a supporting and protective role in the entire construction process to ensure smooth traffic under the bridge during the demolition process. In the actual construction steps, after determining the cutting positions of the arch foot 1, abutment 2, diagonal brace 3, and bridge deck 4, it is necessary to install a standardized protective enclosure structure and traffic diversion, such as:
[0031] A standardized protective enclosure for dismantling the lower structure is set up on the half-width road surface 31 on one side of the central dividing strip 13, and a traffic diversion opening 75 is excavated at the central dividing strip 13 below the two sides of the bridge deck 4; wherein, the standardized protective enclosure for dismantling the lower structure is set at the traffic diversion opening 75; thereby, the vehicles traveling on the half-width road on the closed side can be diverted to the half-width road on the other side, thereby realizing construction without traffic interruption.
[0032] In the subsequent steps, it is also necessary to install the half-width road closure steel support structure, such as:
[0033] A half-width road-closing steel support structure is set up at the central dividing strip 13 and on the road surface 31 on both sides thereof; a steel pipe column fixed base 71 is cast on the road surface 31, multiple rows of steel pipe columns 73 are installed on the top of the steel pipe column fixed base 71, and a crossbeam 69 is installed on the top of the steel pipe column 73.
[0034] Next, it is necessary to erect the bridge jacking prestressing support structure and complete the beam structure conversion, such as:
[0035] The longitudinal beam 66 is anchored to the beam body under the bridge deck 4 by the anchor bolts 65 embedded under the solid web 8. After adjusting the jack 67 to lift the solid web 8 to the specified position, the longitudinal beam 66 and the cross beam 69 are welded, and then the inclined arch leg 10 of the arch foot 1 is removed to realize the conversion of the inclined leg rigid frame bridge structure into a continuous beam bridge, thereby ensuring construction safety.
[0036] The parts not described in detail in this application are prior art, so this application does not describe them in detail.
[0037] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.
[0038] Although this article uses more professional terms, it does not exclude the possibility of using other terms. These terms are used only to more conveniently describe and explain the essence of this application; interpreting them as any additional restrictions is contrary to the spirit of this application.
[0039] The present application is not limited to the above-mentioned optimal implementation mode. Anyone can derive other forms of products under the inspiration of this application. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to those of the present application fall within the protection scope of the present application.
Claims
1. The overall cutting, hoisting and dismantling structure of the overpass is characterized by: include: The half-width road closure steel support structure is arranged at the central dividing strip (13) and on the road surface (31) on both sides thereof, and comprises a cross beam (69), an oblique rod (70), a steel pipe column fixed base (71), a cross brace (72), and a steel pipe column (73); a plurality of rows of steel pipe columns (73) are arranged on the top of the steel pipe column fixed base (71), a cross beam (69) is arranged on the top of the steel pipe column (73), and the steel pipe columns (73) are connected by oblique rods (70) and cross braces (72), and the oblique rods (70) are arranged between the cross braces (72); The bridge jacking prestressing support structure is arranged at the bottom of the solid web (8), and comprises anchor bolts (65), longitudinal beams (66), adjustment jacks (67), and bolt nuts (68); the anchor bolts (65) are uniformly pre-buried under the solid web (8), the longitudinal beams (66) are anchored to the beam body under the bridge deck (4) through the anchor bolts (65), and are fixed through the anchor bolts (65); the longitudinal beams (66) are located above the ends of the cross beams (69), and a plurality of rows of adjustment jacks (67) are arranged on the top of the cross beams (69); The lower structure is dismantled into a standardized protective enclosure, which is arranged on the half-width road surface (31) of the central dividing strip (13), and includes an enclosure steel plate (74), a rotatable clamping piece (76), a nut (77), a steel plate reserved hole (78), and a pull rod (79); the side of the enclosure steel plate (74) is provided with a plurality of steel plate reserved holes (78), the inner side of the enclosure steel plate (74) is provided with a rotatable clamping piece (76), the enclosure steel plates (74) are connected by a plurality of rows of pull rods (79), and are temporarily fixed by the rotatable clamping piece (76) and tightened by the nut (77).
2. The integral cutting, lifting and dismantling structure for overpass according to claim 1 is characterized in that: The adjusting jack (67) is used to lift the solid web (8) to weld the longitudinal beam (66) and the cross beam (69) to remove the oblique arch leg (10) of the arch foot (1).
3. The integral cutting, lifting and dismantling structure for overpass according to claim 1 is characterized in that: The central dividing strip (13) is provided with traffic diversion openings (75) on both sides of the bridge jacking pre-stressing support structure, and the lower structure removal standardized protective enclosure is arranged at the traffic diversion opening (75).