Cutting and dismantling structure for reinforced concrete crash barrier of overpass bridge

By combining the use of crash barrier cutting and stabilizing supports and guide frames, the problems of low construction efficiency and high safety risks in the removal of reinforced concrete crash barriers for overpasses were solved, achieving a fast and safe removal effect.

CN221972128UActive Publication Date: 2024-11-08HUBEI ROAD & BRIDGE GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323664493.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-08
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

Traditional methods for removing reinforced concrete crash barriers from overpasses suffer from low construction efficiency, significant traffic disruption, and high safety risks, failing to meet diverse needs.

Method used

The system employs a crash barrier cutting and stabilizing support frame and a cutting guide frame, including components such as a fall protection net, a cutting and dismantling support frame, a stabilizing support frame, and a guide frame. By using a winch for traction and a telescopic rod for adjustment, the system achieves stable cutting and rapid positioning of the reinforced concrete crash barrier.

Benefits of technology

The removal of reinforced concrete crash barriers on overpasses achieved a short construction period, minimal impact on traffic, and high safety, thus improving construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972128U_ABST
    Figure CN221972128U_ABST
Patent Text Reader

Abstract

The utility model relates to an overpass bridge reinforced concrete crash barrier cutting and dismantling structure which comprises a crash barrier cutting and dismantling support arranged below a bridge deck, a crash barrier cutting and stabilizing support is arranged on the top of the crash barrier cutting and dismantling support, and the crash barrier cutting and stabilizing support is arranged on a cutting and dismantling support bottom plate on the side face of a reinforced concrete crash barrier. The cutting device is used for guaranteeing the stability of the reinforced concrete crash barrier cutting process. The crash barrier cutting guide frame is arranged in the center of the top of the bridge deck slab. According to the cutting and dismantling structure for the reinforced concrete crash barrier of the overpass bridge, the crash barrier cutting stable support and the crash barrier cutting guide frame are adopted, the cutting and dismantling structure has the advantages of being short in construction period, small in influence on traffic, high in safety and the like, rapid cutting and dismantling of the reinforced concrete crash barrier can be achieved, meanwhile, construction safety can be guaranteed, and construction efficiency is improved. Good economic benefits and wide application prospects are realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a cutting and dismantling structure for a reinforced concrete anti-collision barrier of a cross-line bridge, which is applicable to the field of civil engineering and is applicable to the cutting and dismantling construction of a reinforced concrete anti-collision barrier of a cross-line bridge. Background Art

[0002] The impact of overpass removal on surrounding traffic and the environment cannot be ignored, so comprehensive traffic management planning must be carried out before removal. This involves developing temporary traffic routes, notifying the public in advance, setting up signs and roadblocks, and other measures to minimize the disruption of the demolition project to traffic. Among them, the cutting and removal of the reinforced concrete crash barriers of overpasses is a highly difficult project that requires comprehensive background technology planning and execution.

[0003] There are mainly the following traditional methods for removing reinforced concrete crash barriers on overpasses: 1) Blasting method: using blasting technology to blow up the crash barrier. This method has high construction efficiency, but has a great impact on the surrounding environment and high safety risks; 2) Cutting method: using a cutting machine to cut the crash barrier into small pieces and then hoist it down. This method has a long construction period and a great impact on traffic. These traditional methods have their own advantages and disadvantages and cannot meet the diverse needs of overpass reinforced concrete crash barrier removal construction. Therefore, it is necessary to develop new overpass reinforced concrete crash barrier removal technologies to improve construction efficiency and reduce the impact on the environment and traffic.

[0004] The continuous development of the technology for removing reinforced concrete crash barriers on overpasses has provided new technical support for the removal of overpasses. The new technology for removing reinforced concrete crash barriers on overpasses has the advantages of short construction period, little impact on traffic and high safety, and will be more widely used in the future. Utility Model Content

[0005] The purpose of the utility model is to provide a cutting and dismantling structure for reinforced concrete crash barriers of a cross-line bridge, which adopts a stable bracket for cutting crash barriers and a guide frame for cutting crash barriers, has the advantages of short construction period, small impact on traffic, high safety, etc., can realize the rapid cutting and dismantling of reinforced concrete crash barriers, and can ensure construction safety at the same time.

[0006] In order to achieve the above application purpose, this application adopts the following technical solution: The cutting and removal structure of the reinforced concrete crash barrier of the overpass includes:

[0007] The anti-collision barrier cutting and removal bracket is arranged under the bridge deck, and a anti-collision barrier cutting and stabilizing bracket is arranged on the top, including an anti-falling net, a cutting and removal bracket bottom plate, and a second supporting column; anti-falling nets are arranged on both sides of the top of the anti-falling net, and multiple rows of second supporting columns are evenly arranged at the bottom of the cutting and removal bracket bottom plate;

[0008] The cutting and stabilizing bracket of the crash barrier is arranged on the cutting and dismantling bracket bottom plate on the side of the reinforced concrete crash barrier, and is used to ensure the stability of the cutting process of the reinforced concrete crash barrier, including connecting ribs, vertical struts, inverted L-shaped stabilizing plates, connecting rods, upper connecting rods, oblique struts, stabilizing bracket base, bottom connecting rods and column struts; the side of the inverted L-shaped stabilizing plate is fixed to the stabilizing bracket base through the upper connecting rod and the bottom connecting rod, and multiple rows of vertical struts are arranged in the center of the top of the stabilizing bracket base, and the vertical struts are connected into a unit through connecting ribs;

[0009] The guardrail cutting guide frame is arranged at the top center of the bridge deck, and includes vertical struts, a sliding base, a plug-in rod, a fan-shaped card plate, a transverse connecting rod, a hanging plate, a telescopic rod, a cutting guide frame base, a slide rail groove, a winch, and a second positioning plate; a slide rail groove is provided in the top center of the cutting guide frame base, and the sliding base is placed in the slide rail groove, and the slide rail groove and the sliding base are in the shape of a "center"; multiple rows of vertical struts are provided on the top of the sliding base, and a hanging plate is provided on the top of the vertical struts, and reserved holes for the plug-in rods are evenly provided on the top of the hanging plate.

[0010] Furthermore, an inverted L-shaped stabilizing plate is fixed on the top of the reinforced concrete crash barrier, and the bottom of the side of the inverted L-shaped stabilizing plate is connected to the center of the side of the stabilizing bracket base through a bottom connecting rod. The stabilizing bracket base is located on the top of the cutting and removal bracket bottom plate, and the cutting and removal bracket bottom plate is supported on the bottom of the bridge deck.

[0011] Furthermore, the bottom of the vertical support rod side is connected to the top of the inverted L-shaped stabilizing plate side through the oblique support rod, the top of the vertical support rod side is connected to the upper center of the inverted L-shaped stabilizing plate side through the upper connecting rod, and the upper connecting rods are connected into a whole through connecting rods.

[0012] Furthermore, fan-shaped clamping plates are evenly arranged on the outer side of the center of the plug-in rod, the bottom of the plug-in rod passes through the reserved hole of the plug-in rod, and the fan-shaped clamping plates are placed on the hanging plate.

[0013] Furthermore, a telescopic rod is provided on the side of the plug-in rod, a steel wire rope is connected to the end of the telescopic rod, a second positioning plate is connected to the bottom of the steel wire rope, and the second positioning plate is located outside the reinforced concrete crash barrier. The second positioning plate can be quickly positioned by adjusting the telescopic rod.

[0014] Furthermore, a winch is provided on the top of the cutting guide frame base, and the winch is connected to the upper end of the sliding base through a traction wire rope, and the sliding of the cutting guide frame base is achieved through the traction of the winch.

[0015] Compared with the prior art, the utility model has the following characteristics and beneficial effects:

[0016] 1. The utility model relates to a cutting and dismantling support structure for the reinforced concrete crash barrier of a cross-line bridge, which has the advantages of short construction period, small impact on traffic, high safety, etc., and has good economic benefits and broad application prospects.

[0017] 2. The utility model uses a stable bracket for cutting the crash barrier, and by adjusting the telescopic rod, it can ensure that the removal of the reinforced concrete crash barrier is stable and not skewed, thereby ensuring the safety of the removal construction.

[0018] 3. The guardrail cutting guide frame involved in the utility model can quickly realize the cutting and positioning of the guardrails at different positions through the traction of a winch, realizes the rapid cutting and removal of reinforced concrete guardrails, and greatly improves the removal construction efficiency.

[0019] 4. The utility model relates to a cutting and dismantling support structure for the reinforced concrete crash barrier of a cross-line bridge, and an anti-falling net is arranged on the outer side to ensure the safety of the construction workers. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a three-dimensional schematic diagram of the support structure for cutting and removing the reinforced concrete crash barrier of the overpass;

[0021] Figure 2 It is a three-dimensional schematic diagram of the installation of the crash barrier cutting stabilizing bracket and the crash barrier cutting guide frame;

[0022] Figure 3 This is a schematic diagram of the elevation of the support structure for cutting and removing the reinforced concrete crash barrier of the overpass;

[0023] Figure 4 It is a three-dimensional schematic diagram of the detailed structure of the cutting and stabilizing bracket of the crash barrier;

[0024] Figure 5 It is a three-dimensional schematic diagram of the detailed structure of the guardrail cutting guide frame.

[0025] In the figure, 4, bridge deck; 103, anti-fall net; 104, cutting and removing bracket bottom plate; 105, connecting ribs; 106, vertical struts; 107, reinforced concrete crash barrier; 108, inverted L-shaped stabilizing plate; 109, sliding base; 110, plug-in rod; 111, fan-shaped card plate; 112, horizontal connecting rod; 113, hanging plate; 114, telescopic rod; 115, wire rope; 116, connecting rod; 117, upper connecting rod; 118, oblique struts; 119, stabilizing bracket base; 120, second supporting column; 121, traction wire rope; 122, cutting guide frame base; 123, slide rail groove; 124, winch; 125, second positioning plate; 126, bottom connecting rod; 127, column struts. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments in the present application belong to the scope of protection of this application.

[0027] Those skilled in the art should understand that, in the disclosure of the present application, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, which are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be understood as limiting the present application.

[0028] The construction technical requirements such as steel pipe welding and cutting, steel cage binding, concrete pouring, etc. in the implementation mode of the utility model are not repeated here, and the implementation mode of the cutting and dismantling structure of the reinforced concrete crash barrier of the overpass bridge of the utility model is explained in detail below in combination with the drawings and examples, and the description is not limited to the following examples.

[0029] like Figure 1 to Figure 5 As shown, a structure for cutting and removing reinforced concrete crash barriers of a cross-line bridge comprises:

[0030] The anti-collision barrier cutting and removal bracket is arranged below the bridge deck 4, and the top is provided with an anti-collision barrier cutting and stabilizing bracket, including an anti-falling net 103, a cutting and removal bracket bottom plate 104, and a second supporting column 120; anti-falling nets 103 are arranged on both sides of the top of the anti-falling net 103, and multiple rows of second supporting columns 120 are evenly arranged at the bottom of the cutting and removal bracket bottom plate 104;

[0031] The cutting and stabilizing bracket of the crash barrier is arranged on the cutting and dismantling bracket bottom plate 104 on the side of the reinforced concrete crash barrier 107, and is used to ensure the stability of the cutting process of the reinforced concrete crash barrier 107, including connecting ribs 105, vertical struts 106, inverted L-shaped stabilizing plates 108, connecting rods 116, upper connecting rods 117, oblique struts 118, stabilizing bracket base 119, and bottom connecting rods 126; the side of the inverted L-shaped stabilizing plate 108 is fixed to the stabilizing bracket base 119 through the upper connecting rods 117 and the bottom connecting rods 126, and a plurality of rows of vertical struts 106 are arranged in the center of the top of the stabilizing bracket base 119, and the vertical struts 106 are connected into a unit through connecting ribs 105;

[0032] In this embodiment, the inverted L-shaped stabilizing plate 108 is sleeved on the top of the reinforced concrete crash barrier 107, and the bottom of the side of the inverted L-shaped stabilizing plate 108 is connected to the center of the side of the stabilizing bracket base 119 through the bottom connecting rod 126. The stabilizing bracket base 119 is located on the top of the cutting and removal bracket bottom plate 104, and the cutting and removal bracket bottom plate 104 is supported at the bottom of the bridge deck 4. The bottom of the side of the vertical brace 106 is connected to the top of the side of the inverted L-shaped stabilizing plate 108 through the oblique brace 118, and the top of the side of the vertical brace 106 is connected to the upper center of the side of the inverted L-shaped stabilizing plate 108 through the upper connecting rod 117, and the upper connecting rods 117 are connected to each other through the connecting rod 116 as a whole.

[0033] The guardrail cutting guide frame is arranged at the top center of the bridge deck 4, including a vertical support rod 106, a sliding base 109, a plug-in rod 110, a fan-shaped card plate 111, a transverse connecting rod 112, a hanging plate 113, a telescopic rod 114, a cutting guide frame base 122, a slide rail groove 123, a winch 124, a second positioning plate 125 and a column support rod 127; a slide rail groove 123 is provided in the top center of the cutting guide frame base 122, and the sliding base 109 is placed in the slide rail groove 123, and the slide rail groove 123 and the sliding base 109 are in the shape of a "middle"; a plurality of rows of vertical support rods 106 are provided on the top of the sliding base 109, a hanging plate 113 is provided on the top of the vertical support rods 106, and reserved holes for the plug-in rod 110 are evenly provided on the top of the hanging plate 113.

[0034] In this embodiment, a fan-shaped card plate 111 is evenly arranged on the central outer side of the plug-in rod 110, the bottom of the plug-in rod 110 passes through the reserved hole of the plug-in rod 110, and the fan-shaped card plate 111 is placed on the hanging plate 113. A telescopic rod 114 is arranged on the side of the plug-in rod 110, and a steel wire rope 115 is connected to the end of the telescopic rod 114. The bottom of the steel wire rope 115 is connected to a second positioning plate 125, and the second positioning plate 125 is located on the outer side of the reinforced concrete crash barrier 107. The second positioning plate 125 can be quickly positioned by adjusting the telescopic rod 114.

[0035] In this embodiment, a winch 124 is provided on the top of the cutting guide frame base 122 , and the winch 124 is connected to the upper end of the sliding base 109 through a traction wire rope 121 , and the sliding of the cutting guide frame base 122 is achieved through the traction of the winch 124 .

[0036] Among them, the bridge deck 4 is a part of the overpass that needs to be demolished, and the present application, as a part of the overpass demolition structure, plays a role of rapid cutting in the entire construction process. Specifically, in the actual construction steps, it is necessary to install a crash barrier cutting and removal bracket and a crash barrier cutting and stabilizing bracket, such as:

[0037] After the bridge structure conversion is completed, the second support column 120 is hoisted with the help of the bridge jacking pre-stressing support structure, and the anti-collision barrier cutting and removal support is installed under the bridge deck 4, and the anti-collision barrier cutting and stabilizing support is installed on the cutting and removal support bottom plate 104;

[0038] Then install the guardrail cutting guide frame, such as:

[0039] A guardrail cutting guide frame is installed at the top center of the bridge deck 4, and a winch 124 is arranged. The plug-in rod 110 is installed on the hanging plate 113, and then a second positioning plate 125 is hung.

[0040] Subsequent steps also require the removal of the reinforced concrete crash barrier 107, such as:

[0041] First, the inverted L-shaped stabilizing plate 108 is hung on the top of the reinforced concrete crash barrier 107, and then the telescopic rod 114 is adjusted to the specified position so that the second positioning plate 125 is located at the cutting line position, and then the reinforced concrete crash barrier 107 is cut with a static cutting machine at the position determined by the second positioning plate 125. The sliding of the cutting guide frame base 122 is achieved by traction of the winch 124, so as to realize the removal of the reinforced concrete crash barrier 107 at different positions.

[0042] The parts not described in detail in this application are prior art, so this application does not describe them in detail.

[0043] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0044] Although this article uses more professional terms, it does not exclude the possibility of using other terms. These terms are used only to more conveniently describe and explain the essence of this application; interpreting them as any additional restrictions is contrary to the spirit of this application.

[0045] The present application is not limited to the above-mentioned optimal implementation mode. Anyone can derive other forms of products under the inspiration of this application. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to those of the present application fall within the protection scope of the present application.

Claims

1. The cutting and dismantling structure of reinforced concrete crash barriers for overpasses is characterized by: include: A crash barrier cutting and removal bracket is arranged below the bridge deck (4), and a crash barrier cutting and stabilizing bracket is arranged on the top, comprising an anti-falling net (103), a cutting and removal bracket bottom plate (104), and a second supporting column (120); anti-falling nets (103) are arranged on both sides of the top of the anti-falling net (103), and a plurality of rows of second supporting columns (120) are evenly arranged at the bottom of the cutting and removal bracket bottom plate (104); A crash barrier cutting stabilizing bracket is arranged on a cutting and dismantling bracket bottom plate (104) on the side of a reinforced concrete crash barrier (107) and is used to ensure that the cutting process of the reinforced concrete crash barrier (107) is stable, comprising connecting ribs (105), vertical struts (106), an inverted L-shaped stabilizing plate (108), connecting rods (116), upper connecting rods (117), oblique struts (118), a stabilizing bracket base (119), a bottom connecting rod (126) and a column strut (127); the side of the inverted L-shaped stabilizing plate (108) is fixed to the stabilizing bracket base (119) through the upper connecting rod (117) and the bottom connecting rod (126); a plurality of rows of vertical struts (106) are arranged at the top center of the stabilizing bracket base (119); the vertical struts (106) are connected into a unit through connecting ribs (105); The anti-collision barrier cutting guide frame is arranged at the top center of the bridge deck (4), and comprises a vertical support rod (106), a sliding base (109), a plug-in rod (110), a fan-shaped card plate (111), a transverse connecting rod (112), a hanging plate (113), a telescopic rod (114), a cutting guide frame base (122), a slide rail groove (123), a winch (124), and a second positioning plate (125); a slide rail groove (123) is arranged at the top center of the cutting guide frame base (122), and the sliding base (109) is placed in the slide rail groove (123), and the slide rail groove (123) and the sliding base (109) are in the shape of a "Z" character; a plurality of rows of vertical support rods (106) are arranged at the top of the sliding base (109), a hanging plate (113) is arranged at the top of the vertical support rod (106), and reserved holes for the plug-in rod (110) are evenly arranged at the top of the hanging plate (113).

2. The cutting and dismantling structure for reinforced concrete crash barriers of overpass according to claim 1 is characterized in that: The inverted L-shaped stabilizing plate (108) is sleeved on the top of the reinforced concrete crash barrier (107), and the bottom of the side of the inverted L-shaped stabilizing plate (108) is connected to the center of the side of the stabilizing bracket base (119) through a bottom connecting rod (126). The stabilizing bracket base (119) is located on the top of the cutting and removal bracket bottom plate (104), and the cutting and removal bracket bottom plate (104) is supported on the bottom of the bridge deck (4).

3. The cutting and dismantling structure of reinforced concrete crash barriers for overpasses according to claim 2 is characterized in that: The bottom of the side of the vertical support rod (106) is connected to the top of the side of the inverted L-shaped stabilizing plate (108) through the oblique support rod (118), and the top of the side of the vertical support rod (106) is connected to the upper center of the side of the inverted L-shaped stabilizing plate (108) through the upper connecting rod (117), and the upper connecting rods (117) are connected to form a whole through the connecting rod (116).

4. The cutting and dismantling structure for reinforced concrete crash barriers of overpass according to claim 3 is characterized in that: The central outer side of the plugging rod (110) is evenly provided with a fan-shaped clamping plate (111), the bottom of the plugging rod (110) passes through the reserved hole of the plugging rod (110), and the fan-shaped clamping plate (111) is placed on the hanging plate (113).

5. The cutting and dismantling structure for reinforced concrete crash barriers of overpass according to claim 4 is characterized in that: A telescopic rod (114) is provided on the side of the plug-in rod (110), a steel wire rope (115) is connected to the end of the telescopic rod (114), a second positioning plate (125) is connected to the bottom of the steel wire rope (115), and the second positioning plate (125) is located outside the reinforced concrete crash barrier (107). The second positioning plate (125) can be quickly positioned by adjusting the telescopic rod (114).

6. The cutting and dismantling structure for reinforced concrete crash barriers of overpass according to any one of claims 1 to 5, characterized in that: A winch (124) is provided on the top of the cutting guide frame base (122); the winch (124) is connected to the upper end of the sliding base (109) via a traction wire rope (121); and the cutting guide frame base (122) is tractioned by the winch (124) to achieve sliding movement.