Water diversion tunnel refuge tunnel for water conservancy project
By designing a shelter hole higher than the branch opening in the water diversion tunnel of the water conservancy project and adopting a reverse slope and composite lining structure, the problem of flood backflow and mountain torrent mudslides during the flood season is solved, ensuring personnel safety, and after the project is completed, it is completed Can be used to monitor equipment for housing use.
Patent Information
- Application Number
- CN202420548059.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-03-21
AI Technical Summary
The traditional hydraulic water diversion tunnel does not consider the design of the shelter hole at the entrance, which leads to flooding and mountain torrent mudslide disasters in the construction area during the flood season, endangering the lives and safety of people.
Design a water diversion tunnel refuge hole for water conservancy engineering, with a location higher than the support hole, the bottom is arranged in reverse slope, with a ditch, a steel ladder at the opening, and a circular arch straight wall section and a composite lining structure, including anchor net spray support Reinforcement, mortar anchors, steel mesh and advance small conduits are reinforced to provide temporary shelter.
Effectively prevent floods, landslides, landslides and mudslide disasters, provide construction and maintenance personnel with safe shelter, and can be used for monitoring equipment and house use after the project is completed.
Smart Images

Figure CN221972290U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of water conservancy projects, and in particular relates to a water diversion tunnel refuge cave of a water conservancy project. Background Art
[0002] In the field of water conservancy and hydropower engineering, water transfer mainly relies on diversion tunnels. Diversion tunnels are water transfer structures that divert power generation water from the upstream reservoir area to the vicinity of the power plant. According to the flood control standards for water supply projects, the main tunnel is a Class 1 building, with a design flood standard of once in 50 years and a verification flood standard of once in 200 years. The construction branch tunnel is a Class 4 building, with a design flood standard of once in 20 years. Due to the low location of the branch tunnel and the exit tunnel, rain and flood backflow are prone to occur during the flood season; if an extremely large mountain torrent and mudslide disaster occurs in the construction area, it may cause floods to cross the embankment, thereby endangering the lives of people. At present, traditional hydraulic diversion tunnels only meet the building grade and engineering flood control defense standards, and the design of the entrance refuge tunnel is not considered. Utility Model Content
[0003] In order to make up for the deficiencies of the prior art, the utility model provides a water diversion tunnel refuge tunnel for a water conservancy project, which can provide a temporary refuge place for tunnel construction personnel and later maintenance personnel during the flood season to ensure the safety of personnel lives.
[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0005] A water diversion tunnel refuge tunnel for a water conservancy project, characterized in that: it comprises a refuge tunnel, the refuge tunnel is arranged at a position higher than the branch tunnel opening;
[0006] A waiting area is set up in the refuge cave, and the longitudinal slope at the bottom of the refuge cave adopts a reverse slope arrangement;
[0007] A ditch is set up on the top of the refuge cave.
[0008] Furthermore, the reverse slope of the longitudinal slope is not less than 0.2%.
[0009] Furthermore, a steel ladder is provided at the entrance of the refuge cave.
[0010] Furthermore, the refuge cave adopts a circular arch straight wall section.
[0011] Furthermore, the clearance dimensions of the refuge cave are 4.0m×4.5m in width×height and 5.0m in length.
[0012] Furthermore, the entrance slope and back slope of the refuge cave are supported by anchor mesh spraying.
[0013] Furthermore, the refuge tunnel arch wall is provided with mortar anchor rods and steel mesh, an advanced small guide tube is provided at the 120° position of the arch, and a steel frame is provided at the arch wall position.
[0014] Beneficial effects of the utility model:
[0015] 1) The utility model is safe and reliable, and can prevent natural disasters such as floods, landslides, mudslides, and debris flows during the flood season, and provide a temporary shelter for tunnel construction personnel and later maintenance personnel to ensure the safety of personnel;
[0016] 2) The utility model adopts a composite lining form, and the bottom plate is arranged in a reverse slope, which has the functions of preventing rainwater from flowing back and preventing moisture;
[0017] 3) After the project is completed, the utility model can be used as a tunnel monitoring equipment house. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the structure of the utility model;
[0019] Figure 2 This is the longitudinal section of the opening of the utility model;
[0020] Figure 3 This is the main tunnel support diagram of the utility model;
[0021] In the figure, 1-refuge tunnel, 2-tunnel entrance slope, 3-longitudinal slope, 4-ditch, 5-back slope, 6-secondary lining, 7-steel frame, 8-mortar anchor rod, 9-steel mesh, 10-advance small guide tube. DETAILED DESCRIPTION
[0022] The present invention is described in detail below in conjunction with specific implementation methods.
[0023] The purpose of setting up refuge tunnels is to prevent natural disasters such as floods and provide a refuge for people in the tunnel to escape. Floods are mainly caused by heavy rains. Heavy rains not only directly lead to flooding, but also cause secondary disasters such as landslides, mudslides, and debris flows. The characteristics of heavy rains determine the characteristics of floods. Drowning is the main factor causing deaths in floods, so the setting up of refuge tunnels is very important.
[0024] like Figure 1 As shown, the utility model includes a refuge cave 1, which is arranged 3.0m higher than the branch cave entrance; the refuge cave 1 is 10.0-20.0m away from the main cave and the branch cave entrance;
[0025] like Figure 2 As shown, the longitudinal slope 3 at the bottom of the refuge cave 1 is arranged in reverse slope to prevent rainwater from flowing back, and the reverse slope gradient of the longitudinal slope 3 is not less than 0.2%; a ditch 4 is arranged on the top of the refuge cave 1.
[0026] like Figure 3As shown, the refuge cave 1 adopts a circular arch straight wall section. The clear dimensions of the refuge cave 1 are 4.0m×4.5m in width×height and 5.0m in length. The cave length can be adjusted appropriately according to the number of construction shifts.
[0027] The refuge cave 1 adopts a composite lining structure. The initial support of the refuge cave 1 adopts sprayed anchor mesh support, and the sprayed concrete adopts wet spraying technology; the secondary lining 6 adopts C25 concrete lining. The location of the refuge cave should be determined according to the surrounding topography, engineering geology and hydrogeology, and the excavation height of the side and back slopes should be strictly controlled to reduce the excavation of the original hillside and the damage to vegetation.
[0028] In order to ensure the stability of the slope, the entrance slope 2 and the back slope 5 of the refuge tunnel 1 are supported by anchor mesh spraying to ensure the safety of the entrance construction.
[0029] The arch wall of the refuge cave 1 is equipped with Φ22 mortar anchor rods 8, with a length of 3.0m, a spacing of 1.2m×1.2m, and a plum blossom shape arrangement; and φ8 steel mesh 9 is laid with a spacing of 20cm×20cm; a Φ42 advanced small guide tube 10 is installed at the 120° position of the arch to reinforce the stratum by grouting, and a 16-type steel frame 7 is installed at the arch wall position; the shotcrete adopts the wet spraying process with a thickness of 10cm.
[0030] There is a waiting area in the refuge cave 1, and the waiting area is 0.5m 2 / Designed by people; ventilation, emergency lighting, emergency communication, monitoring and other facilities are set up in the refuge cave to facilitate communication with the outside world; in order to avoid the influence of jet fans on the passage of personnel, the fans are set at the arch; a steel ladder is set at the entrance of refuge cave 1 to facilitate the normal entry and exit of escapees.
[0031] The side slope support is carried out from top to bottom in layers and steps, with a step height of 2 to 3 meters. After the refuge hole is opened, C20 concrete is sprayed in time to seal the exposed surrounding rock to ensure the stability of the slope. The refuge hole adopts short steps and reserves the core soil method when necessary. The support is constructed in a top-down sequence of arch first and then side wall, and the lining is cast by formwork. The step excavation length shall not be greater than the spacing between two arch frames. After excavation, spray concrete 4cm first, drive in Φ22 full-thread mortar anchor rods, hang φ8 steel mesh on the arch wall, and then erect the steel frame and spray concrete to the designed thickness to ensure the stability of the steel frame. The steel frames need to be welded together with Φ22 longitudinal tie rods, and the circumferential spacing of the tie rods is 1m. Ф32 locking foot anchor pipes are used at the arch waist to better fit the rock surface. A φ42 advanced small pipe is installed at 120° of the arch to reinforce the stratum by grouting. The small pipe is 3.0m long, with a circumferential spacing of 0.3m, an overlap length of not less than 1.0m, an external insertion angle of 5 to 10°, and the secondary lining adopts C25 concrete lining. The thickness of the arch wall lining is 30cm and the thickness of the bottom plate is 35cm.
[0032] In the description of the present invention, unless otherwise clearly specified and limited, the terms "set", "install", "connect", "connect", and "fix" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0033] The content of the utility model is not limited to the examples listed, and any equivalent changes made to the technical solution of the utility model by ordinary technicians in this field after reading the specification of the utility model are covered by the claims of the utility model.
Claims
1. A water diversion tunnel refuge tunnel for a water conservancy project, characterized in that: It comprises a refuge cave (1), wherein the refuge cave (1) is arranged at a position higher than the branch cave entrance; A waiting area is provided in the refuge cave (1), and the longitudinal slope (3) at the bottom of the refuge cave (1) is arranged in a reverse slope; A water ditch (4) is arranged on the top of the refuge cave (1).
2. A water conservancy project diversion tunnel refuge cave according to claim 1, characterized in that: The reverse slope of the longitudinal slope (3) is not less than 0.2%.
3. A water conservancy project diversion tunnel refuge cave according to claim 2, characterized in that: A steel ladder is provided at the entrance of the refuge cave (1).
4. A water conservancy project water diversion tunnel refuge cave according to claim 3, characterized in that: The refuge cave (1) adopts a circular arch straight wall section.
5. A water conservancy project diversion tunnel refuge cave according to claim 4, characterized in that: The clear dimensions of the refuge cave (1) are 4.0 m in width × 4.5 m in height, and 5.0 m in length.
6. A water conservancy project diversion tunnel refuge cave according to claim 5, characterized in that: The entrance side slope (2) and the back slope (5) of the refuge cave (1) are supported by anchor net spraying.
7. A water conservancy project diversion tunnel refuge cave according to claim 6, characterized in that: The refuge cave (1) is provided with mortar anchor rods (8) and steel mesh sheets (9) on its arch wall, with a small advance guide tube (10) provided at the 120° position of the arch, and a steel frame (7) provided at the arch wall position.