Prefabricated shear wall
Through the design of axial and radial docking components, the problem of unstable connection between upper and lower walls in the prior art is solved, and the stable docking and reinforcement of prefabricated shear walls is realized, and the overall stability and wind resistance of the shear walls are improved. Seismic resistance.
Patent Information
- Application Number
- CN202420355977.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-27
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-02-27
AI Technical Summary
When the existing prefabricated shear wall is lifted, the positioning rods are difficult to accurately align the positioning holes, resulting in unstable connections and poor use.
The axial and radial butt assembly is adopted, and the positioning rod is automatically maintained at the horizontal line through the design of grooves and bumps, and is reinforced by moving wheels and screws to ensure accurate butt and stable connection of the upper and lower walls.
The stable butt and reinforcement of the upper and lower walls is achieved, the stability and firmness of the connection of the shear wall is improved, shaking and tilting are avoided, and wind and earthquake resistance is enhanced.
Smart Images

Figure CN221972735U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a prefabricated shear wall. Background Art
[0002] Shear wall, also known as wind-resistant wall, earthquake-resistant wall or structural wall, is a wall in a house or structure that mainly bears horizontal and vertical loads caused by wind loads or earthquakes to prevent structural shear damage. It is generally made of reinforced concrete. During on-site construction, shear walls are often prefabricated and assembled, and the connection method of prefabricated shear walls is usually steel sleeve grouting connection. This connection method requires the exposed vertical steel bars on the lower shear wall to enter the sleeve on the upper shear wall.
[0003] The existing Chinese patent with announcement number CN209670120U discloses a prefabricated shear wall, including a lower wall and an upper wall. A plurality of vertical steel bars are arranged at intervals on the top surface of the lower wall along the length direction of the lower wall. A plurality of sleeves are arranged at intervals on the bottom surface of the upper wall along the length direction of the upper wall. The sleeves are located in the upper wall. A plurality of first grouting holes are opened on the upper wall, respectively penetrating into each sleeve. Positioning holes are opened at four corners of the top surface of the lower wall. The positioning holes extend into the lower wall along the vertical direction. Positioning rods are arranged at four corners of the bottom surface of the upper wall. The positioning rods extend in the vertical direction away from the upper wall. The length of the positioning rods is equal to the length of the positioning holes. A second grouting hole penetrating into the positioning holes is opened on the side wall of the lower wall at the position where the positioning holes are located. The utility model has the effect of making it easier to align the vertical steel bars and the sleeves.
[0004] With respect to the above-mentioned and existing related technologies, the inventors believe that the following defects often exist: the device manually assists in aligning the positioning rod and the positioning hole by observing the first indicator line and the second indicator line, and since the upper wall is suspended in the air, it is easy to shake when the upper wall is moved, so that the positioning rod cannot be accurately aligned with the positioning hole, and the use effect is not good, which needs to be improved; therefore, a prefabricated shear wall is proposed to address the above problems. Utility Model Content
[0005] In order to make up for the deficiencies of the prior art and solve the above-mentioned technical problems, the utility model proposes a prefabricated shear wall.
[0006] The technical solution adopted by the utility model to solve its technical problems is: a prefabricated shear wall described in the utility model comprises an upper wall and a lower wall, the top of the lower wall is provided with a groove, the bottom of the upper wall is provided with a convex block, the convex block is fitted with the groove, an axial docking assembly is installed below the upper wall, the axial docking assembly comprises a plurality of positioning rods and a plurality of positioning grooves, the positioning rods are embedded and installed inside the upper wall, and the positioning rods extend out of the upper wall, the positioning grooves are provided on the surface of the grooves, and the positions of the positioning rods and the positioning grooves correspond, and the surface of the lower wall is provided with a plurality of positioning rods and a plurality of positioning grooves. A radial docking assembly is installed, which includes a plurality of connecting holes 1. The connecting holes 1 are opened on the upper surface of the lower wall, and the connecting holes 1 are connected to the grooves. The upper wall is lifted and docked with the lower wall for installation. The inclined grooves on both sides make the positioning rod automatically maintain the same horizontal line with the positioning groove when it descends, and the upper wall is supported by the lower wall to prevent shaking. The upper wall can be pushed to move stably by the moving wheels, so that the positioning rod is accurately inserted into the interior of the positioning groove, and the upper wall and the lower wall are accurately docked. Compared with the existing technology, the upper wall and the lower wall can be stably docked.
[0007] Preferably, the grooves and protrusions are set to be trapezoidal or arc-shaped.
[0008] Preferably, a moving wheel is fixedly connected to the bottom end of the positioning rod.
[0009] Preferably, a plurality of sleeves are embedded and connected inside the upper wall, and the sleeves extend out of the upper wall.
[0010] Preferably, a plurality of vertical steel bars are embedded and connected to the top of the lower wall, and the vertical steel bars extend out of the lower wall. The vertical steel bars are cross-distributed with the connecting holes. After the upper wall and the lower wall are butt-jointed, the vertical steel bars are automatically aligned and inserted into the interior of the sleeve.
[0011] Preferably, a pouring channel is pre-buried inside the upper wall, a flow port is opened at the bottom of the pouring channel corresponding to the sleeve, and a pouring port 1 is opened on the side wall of the pouring channel and the surface of the upper wall respectively, and cement mortar is poured through the pouring port 1. The cement mortar flows through the pouring channel and enters the interior of the sleeve, thereby improving the stability of the shear wall connection.
[0012] Preferably, the casting channel is made of steel.
[0013] Preferably, the axial docking assembly further comprises a plurality of pouring ports 2, wherein the pouring ports 2 are provided on the surface of the lower wall and are connected to the positioning grooves, and cement mortar is poured into the interior of the positioning grooves through the pouring ports.
[0014] Preferably, the radial docking assembly further comprises a plurality of second connection holes, wherein the second connection holes are formed on the surface of the protrusion, and the positions of the second connection holes and the first connection holes correspond to each other.
[0015] Preferably, a screw is inserted into the inside of the connecting hole 2 and the connecting hole 1, and a nut is threadedly connected to the screw. After the upper wall and the lower wall are connected, the screw passes through the connecting hole 2 and the connecting hole 1 and is fixed by the nut, so that the upper wall and the lower wall are radially reinforced, further improving the firmness and stability of the shear wall and effectively preventing the upper wall from tilting or overturning.
[0016] Preferably, both sides of the top of the lower wall are respectively convex upward to form a water retaining layer, and both sides of the bottom of the upper wall are respectively provided with water retaining grooves. The cooperation of the water retaining layer and the water retaining groove can effectively prevent the entry of rainwater.
[0017] The utility model is beneficial in that:
[0018] 1. The utility model hangs the upper wall and docks it with the lower wall. The inclined grooves on both sides allow the positioning rod to automatically maintain the same horizontal line with the positioning groove when it descends, and the upper wall is supported by the lower wall to prevent shaking. The upper wall can be pushed to move stably by the moving wheels, so that the positioning rod is accurately inserted into the interior of the positioning groove, and the upper wall and the lower wall are accurately docked. Compared with the existing technology, the upper wall and the lower wall can be stably docked.
[0019] 2. The utility model has a screw rod passing through the second connection hole and fixed together with the first connection hole by a nut, so that the upper wall and the lower wall are radially reinforced, thereby further improving the firmness and stability of the shear wall and effectively preventing the upper wall from tilting or overturning. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0021] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0022] Figure 2 For this utility model Figure 1 Expand the structural diagram;
[0023] Figure 3 This is a schematic diagram of the structure of the axial docking assembly of the utility model;
[0024] Figure 4 This is a cross-sectional view of the upper wall of the utility model;
[0025] Figure 5It is a schematic diagram of the structure of the radial docking assembly of the utility model.
[0026] In the figure: 1. upper wall; 2. lower wall; 3. groove; 4. protrusion; 5. axial docking assembly; 51. positioning rod; 52. positioning groove; 53. moving wheel; 54. pouring port two; 6. radial docking assembly; 61. connecting hole one; 62. connecting hole two; 63. screw; 64. nut; 7. pouring channel; 8. sleeve; 9. vertical steel bar; 10. pouring port one; 11. circulation port; 12. water retaining layer; 13. water retaining groove. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] See also Figure 1-5 As shown, a prefabricated shear wall comprises an upper wall 1 and a lower wall 2, a groove 3 is provided at the top of the lower wall 2, a convex block 4 is provided at the bottom of the upper wall 1, and the convex block 4 is fitted with the groove 3, an axial docking assembly 5 is installed below the upper wall 1, and the axial docking assembly 5 comprises a plurality of positioning rods 51 and a plurality of positioning grooves 52, the positioning rods 51 are embedded and installed inside the upper wall 1, and the positioning rods 51 extend out of the upper wall 1, the positioning grooves 52 are provided on the surface of the groove 3, and the positions of the positioning rods 51 and the positioning grooves 52 correspond, and a radial docking assembly 6 is installed on the surface of the lower wall 2, and the radial docking assembly 6 comprises a plurality of There are a plurality of connecting holes 61, which are arranged on the upper surface of the lower wall 2 and are connected with the groove 3. The upper wall 1 is lifted and connected to the lower wall 2 for docking and installation. The inclined grooves 3 on both sides make the positioning rod 51 automatically maintain the same horizontal line with the positioning groove 52 when it descends, and the upper wall 1 is supported by the lower wall 2 to prevent shaking. The upper wall 1 can be pushed to move stably by the moving wheel 53, so that the positioning rod 51 is accurately inserted into the interior of the positioning groove 52, so that the upper wall 1 and the lower wall 2 are accurately docked. Compared with the prior art, the upper wall 1 and the lower wall 2 can be stably docked.
[0029] The groove 3 and the projection 4 are set to be trapezoidal or arc-shaped.
[0030] A moving wheel 53 is fixedly connected to the bottom end of the positioning rod 51 .
[0031] A plurality of sleeves 8 are embedded and connected inside the upper wall 1 , and the sleeves 8 extend out of the upper wall 1 .
[0032] A plurality of vertical steel bars 9 are embedded and connected to the top of the lower wall 2, and the vertical steel bars 9 extend out of the lower wall 2. The vertical steel bars 9 are cross-distributed with the connecting hole 61. After the upper wall 1 and the lower wall 2 are connected, the vertical steel bars 9 are automatically aligned and inserted into the interior of the sleeve 8.
[0033] A pouring channel 7 is pre-buried inside the upper wall 1, and a flow port 11 is opened at the bottom of the pouring channel 7 corresponding to the sleeve 8. The side wall of the pouring channel 7 and the surface of the upper wall 1 are respectively opened with pouring ports 10. Cement mortar is poured through the pouring ports 10. The cement mortar flows through the pouring channel 7 and enters the interior of the sleeve 8, thereby improving the stability of the shear wall connection.
[0034] The pouring channel 7 is made of steel material.
[0035] The axial docking assembly 5 further includes a plurality of second pouring ports 54 , which are provided on the surface of the lower wall 2 and are connected to the positioning groove 52 , and cement mortar is poured into the positioning groove 52 through the pouring ports.
[0036] The radial docking assembly 6 further includes a plurality of second connection holes 62 . The second connection holes 62 are formed on the surface of the protrusion 4 , and the positions of the second connection holes 62 and the first connection holes 61 correspond to each other.
[0037] A screw 63 is inserted into the inside of the second connecting hole 62 and the first connecting hole 61, and a nut 64 is threadedly connected to the screw 63. After the upper wall 1 and the lower wall 2 are connected, the screw 63 passes through the second connecting hole 62 and the first connecting hole 61 and is fixed by the nut 64, so that the upper wall 1 and the lower wall 2 are radially reinforced, further improving the firmness and stability of the shear wall, and effectively preventing the upper wall 1 from tilting or overturning.
[0038] Both sides of the top of the lower wall 2 are convex upward to form a water retaining layer 12, and both sides of the bottom of the upper wall 1 are provided with a water retaining groove 13. The cooperation between the water retaining layer 12 and the water retaining groove 13 can effectively prevent rainwater from entering.
[0039] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art.
[0040] Working principle: the upper wall 1 is lifted and docked with the lower wall 2 for installation. The inclined grooves 3 on both sides are used to automatically keep the positioning rod 51 at the same horizontal line with the positioning groove 52 when it descends, and the upper wall 1 is supported by the lower wall 2 to prevent shaking. The upper wall 1 can be pushed to move stably by the moving wheels 53, so that the positioning rod 51 is accurately inserted into the interior of the positioning groove 52, and the upper wall 1 and the lower wall 2 are accurately docked. Compared with the prior art, the upper wall 1 and the lower wall 2 can be stably docked. After the upper wall 1 and the lower wall 2 are docked, the vertical steel bars 9 are automatically aligned and inserted into the interior of the sleeve 8;
[0041] The cement mortar is poured through the pouring port 10, the cement mortar flows through the pouring channel 7 and enters the interior of the sleeve 8, and the cement mortar is poured into the interior of the positioning groove 52 through the pouring port. After the cement mortar solidifies, the stability of the shear wall connection can be effectively improved;
[0042] After the upper wall 1 and the lower wall 2 are butt-jointed, the cooperation between the water retaining layer 12 and the water retaining groove 13 can effectively prevent the entry of rainwater. The screw 63 passes through the connecting hole 2 62 and the connecting hole 1 61 and is fixed by the nut 64 to reinforce the upper wall 1 and the lower wall 2 in the radial direction, further improving the firmness and stability of the shear wall and effectively preventing the upper wall 1 from tilting or overturning.
[0043] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0044] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.
Claims
1. A prefabricated shear wall, comprising an upper wall (1) and a lower wall (2), Features: The top of the lower wall (2) is provided with a groove (3), the bottom of the upper wall (1) is provided with a protrusion (4), the protrusion (4) is fitted with the groove (3), an axial docking assembly (5) is installed below the upper wall (1), the axial docking assembly (5) comprises a plurality of positioning rods (51) and a plurality of positioning grooves (52), the positioning rods (51) are embedded and installed inside the upper wall (1), and the positioning rods (51) extend out of the upper wall (1), the positioning grooves (52) are provided on the surface of the groove (3), and the positions of the positioning rods (51) and the positioning grooves (52) correspond to each other, and a radial docking assembly (6) is installed on the surface of the lower wall (2), the radial docking assembly (6) comprises a plurality of connecting holes (61), the connecting holes (61) are provided on the upper surface of the lower wall (2), and the connecting holes (61) are connected with the groove (3).
2. The prefabricated shear wall according to claim 1, Features: The groove (3) and the projection (4) are arranged in a trapezoidal or arc shape.
3. The prefabricated shear wall according to claim 1, Features: The bottom end of the positioning rod (51) is fixedly connected to a moving wheel (53).
4. The prefabricated shear wall according to claim 1, Features: A plurality of sleeves (8) are embedded and connected inside the upper wall (1), and the sleeves (8) extend out of the upper wall (1).
5. The prefabricated shear wall according to claim 1, Features: A plurality of vertical steel bars (9) are embedded and connected to the top of the lower wall (2), and the vertical steel bars (9) extend out of the lower wall (2), and the vertical steel bars (9) are cross-distributed with the connection hole 1 (61).
6. The prefabricated shear wall according to claim 4, Features: A pouring channel (7) is pre-buried inside the upper wall (1), a flow opening (11) is provided at the bottom of the pouring channel (7) corresponding to the sleeve (8), and a pouring opening (10) is provided on the side wall of the pouring channel (7) and the surface of the upper wall (1).
7. The prefabricated shear wall according to claim 6, Features: The casting channel (7) is made of steel material.
8. The prefabricated shear wall according to claim 1, Features: The axial docking assembly (5) further comprises a plurality of second pouring ports (54), wherein the second pouring ports (54) are provided on the surface of the lower wall (2) and are connected to the positioning groove (52).
9. The prefabricated shear wall according to claim 1, Features: The radial docking assembly (6) further comprises a plurality of second connection holes (62), wherein the second connection holes (62) are formed on the surface of the protrusion (4), and the positions of the second connection holes (62) and the first connection holes (61) correspond to each other.
10. The prefabricated shear wall according to claim 9, Features: A screw rod (63) is inserted into the interior of the second connecting hole (62) and the first connecting hole (61), and a nut (64) is threadedly connected to the screw rod (63).