Narrow space steel beam auxiliary mounting structure
Through the combination of electric forklifts and electric hoists, efficient vertical lifting and rotary installation of steel beams in narrow spaces is achieved, which solves the problem of difficult steel beam lifting in narrow spaces, improves construction efficiency and reduces the impact on personnel health .
Patent Information
- Application Number
- CN202420567999.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-03-22
AI Technical Summary
In a narrow space, the construction of steel beam reinforcement is limited by the obstacles of walls, pipelines and bridges, resulting in difficulty in lifting, which in turn affects construction efficiency and safety.
The lifting mechanism combined with electric forklift and electric hoist is adopted to achieve vertical lifting and installation of steel beams through compartment hoisting and rotation adjustment, avoiding the influence of the original structure, and simplifying the installation and disassembly of equipment.
It improves the installation efficiency of steel beams in narrow spaces, reduces manual demand, reduces energy consumption, and avoids dust and noise pollution, protects the health of construction workers.
Smart Images

Figure CN221973050U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to an auxiliary installation structure of a steel beam in a narrow space. Background Art
[0002] At present, it is popular to build food courts in shopping malls. At the same time, in order to improve their operations, traditional shopping malls will be renovated on the basis of the original structure to adapt to the conditions of catering operations. The newly added catering business is mainly concentrated on floors with a height of only 3.9m. Due to the needs of fire smoke exhaust and electromechanical ventilation, a large number of new floor openings are added. Before the floor openings are opened, it is necessary to reinforce the bottom steel beams and T-beam structures. During the steel beam reinforcement construction process, the reused walls, pipelines, and bridges on site hinder the construction. In addition, the site is small, the reinforced steel beams are long, the space turnover is difficult, the construction period progresses slowly, and the conventional installation scheme has a very high manual efficiency reduction. For the above-mentioned floors with low floor heights, there are also a large number of reused walls, electromechanical pipelines, etc. with high space utilization rates indoors, which leads to the need for structural reinforcement operations in limited space. The construction conditions are extremely harsh. In general practice, the steel beams are directly lifted to the specified height using jacking equipment, but the movement trajectory of the jacking is vertically upward. When hindered by existing pipelines, it is not easy to adjust and avoid. Therefore, the utility model is born. Utility Model Content
[0003] The present application provides a narrow space steel beam auxiliary installation structure to solve the problem that the steel beam cannot be lifted to the specified position when there are walls, pipelines, and bridge frames in the narrow space.
[0004] To solve the above technical problems, the present application provides an auxiliary installation structure for steel beams in a narrow space, comprising: a first supporting beam, a lower floor slab arranged at the top of the first supporting beam, an upper floor slab arranged at intervals at the top of the lower floor slab, and a second supporting beam arranged at the bottom of the upper floor slab; an electric forklift is arranged on the top of the lower floor slab, a reinforcing steel beam is arranged on the electric forklift, a lifting hole is opened in the thickness direction of the upper floor slab, a lifting mechanism is arranged on the top of the upper floor slab, the lifting mechanism comprises two channel steel bases fixed to the top of the upper floor slab, a vertical rod fixed to the top of the two channel steel bases, a horizontal rod arranged between the vertical rods, and a diagonal brace arranged between the vertical rods and the horizontal rod, an electric hoist is arranged on the horizontal rod, the chain of the electric hoist extends into the lifting hole, a hook is arranged at the bottom of the chain, a hanging piece is arranged at the center of the top surface of the reinforced steel beam, and the hook is connected to the hanging piece.
[0005] In some embodiments of the present application, a first mounting plate is provided on the opposite side of the second support beam, and second mounting plates are provided at both ends of the reinforced steel beam in the length direction. Mounting holes are provided on both the first mounting plate and the second mounting plate, and the first mounting plate and the second mounting plate are fixed by bolts.
[0006] In some embodiments of the present application, the diameter of the lifting hole is 120 mm.
[0007] In some embodiments of the present application, the hanging part includes a horizontal plate connected to the top of the reinforced steel beam, and a vertical plate arranged on the top of the horizontal plate. The horizontal plate is welded and fixed to the top surface of the reinforced steel beam. A hanging hole is arranged at the upper end of the vertical plate. A hanging ring is arranged in the hanging hole, and the hanging ring is connected to the hook.
[0008] In some embodiments of the present application, a receiving plate is provided on the top of the electric forklift, a rubber pad is provided on the top of the receiving plate, and the top surface of the rubber pad contacts the bottom surface of the reinforced steel beam.
[0009] In some embodiments of the present application, the electric forklift is arranged in plurality along the bottom of the reinforced steel beam.
[0010] Compared with the prior art, the utility model has the following characteristics and beneficial effects:
[0011] The utility model can realize vertical lifting of steel beams in a narrow space with a small amount of manual assistance through the ingenious cooperation of simple lifting equipment such as electric forklifts and electric hoists. A simple gantry is set on the upper floor, and the electric hoist is used to realize the spatial adjustability of the large steel beams for structural reinforcement. The rotatable installation is improved, and the installation efficiency is improved. The lifting equipment adopted in this scheme is easy to install and disassemble. Compared with the traditional high-power traction lifting mechanism, it has the advantages of efficient construction and saving unit energy consumption. The influence of original structures such as pipelines is avoided through the installation method of combining jacking and hoisting. In addition, no dust and noise pollution will be generated during the construction process, which effectively reduces the impact on the health of workers in indoor limited spaces. Popularization and use can produce better results. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the utility model.
[0013] In the figure, 100, the first supporting beam; 200, the lower floor; 300, the upper floor; 310, the lifting hole; 400, the second supporting beam; 410, the first mounting plate; 500, the electric forklift; 510, the receiving plate; 600, the reinforcing steel beam; 610, the hanging piece; 611, the horizontal plate; 612, the vertical plate; 613, the lifting hole; 620, the second mounting plate; 700, the lifting mechanism; 710, the channel steel base; 720, the vertical rod; 730, the horizontal rod; 740, the diagonal brace; 750, the electric hoist; 760, the chain; 800, the mounting hole. DETAILED DESCRIPTION
[0014] The following is a further detailed description of the specific implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0015] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0016] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0017] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0018] like Figure 1As shown, according to some embodiments of the present application, a narrow space steel beam auxiliary installation structure includes: a first support beam 100, a lower floor 200 arranged on the top of the first support beam 100, an upper floor 300 arranged at intervals on the top of the lower floor 200, and a second support beam 400 arranged at the bottom of the upper floor 300; an electric forklift 500 is arranged on the top of the lower floor 200, and a reinforced steel beam 600 is arranged on the electric forklift 500, a hoisting hole 310 is opened in the thickness direction of the upper floor 300, and a The hoisting mechanism 700 includes two channel steel bases 710 fixed to the top of the upper floor 300, a vertical rod 720 fixed to the top of the two channel steel bases 710, a horizontal rod 730 arranged between the vertical rods 720, and a diagonal brace 740 arranged between the vertical rods 720 and the horizontal rod 730. An electric hoist 750 is arranged on the horizontal rod 730, and a chain 760 of the electric hoist 750 extends into the hoisting hole 310. A hook is arranged at the bottom of the chain 760. A hanger 610 is arranged at the center of the top surface of the reinforced steel beam 600, and the hook is connected to the hanger 610.
[0019] It should be noted here that the lifting mechanism 700 is arranged on the top surface of the upper floor 300, so that the maximum lifting position of the reinforced steel beam 600 can reach close to the bottom surface of the upper floor 300. The reinforced steel beam 600 is first lifted by an electric forklift 500. When encountering an obstacle, the reinforced steel beam 600 is lifted by the lifting mechanism 700, and then slowly rotated manually to avoid obstacles, and then lifted to the installation position for the second time. The operation is simple and the construction efficiency is high.
[0020] According to some embodiments of the present application, a first mounting plate 410 is provided on the opposite side of the second support beam 400, and second mounting plates 620 are provided at both ends of the reinforced steel beam 600 in the length direction. Mounting holes 800 are provided on both the first mounting plate 410 and the second mounting plate 620, and the first mounting plate 410 and the second mounting plate 620 are fixed by bolts.
[0021] According to some embodiments of the present application, the diameter of the hanging hole 310 is 120 mm.
[0022] According to some embodiments of the present application, the hanger 610 includes a horizontal plate 611 connected to the top of the reinforced steel beam 600, and a vertical plate 612 arranged on the top of the horizontal plate 611. The horizontal plate 611 is welded and fixed to the top surface of the reinforced steel beam 600. A hanging hole 613 is provided at the upper end of the vertical plate 612. A hanging ring is provided in the hanging hole 613, and the hanging ring is connected to the hook.
[0023] According to some embodiments of the present application, a receiving plate 510 is disposed on the top of the electric forklift 500 , a rubber pad is disposed on the top of the receiving plate 510 , and the top surface of the rubber pad contacts the bottom surface of the reinforced steel beam 600 .
[0024] According to some embodiments of the present application, the electric forklift 500 is arranged in plurality along the bottom of the reinforced steel beam 600 .
[0025] According to some embodiments of the present application, the specific construction steps are as follows: Step 1, the floor slab is opened. The opening of the upper floor slab 300 should be constructed by a vibration-free machine to avoid affecting the load-bearing of the structural beams and columns. The size of the opening should be φ120mm to ensure that the chain 760 can pass through smoothly. Anti-collision and friction facilities should be set around the opening. The opening position should be basically consistent with the position of the lifting mechanism 700. During the opening process, there should be a dedicated person on the lower floor to guard and ensure safety;
[0026] Step 2: Installation of the hoisting mechanism 700: It is planned to install the channel steel base 710, the vertical rod 720, the horizontal rod 730 and the electric hoist 750, which are mainly used as the main equipment for secondary lifting. The lifting equipment is simple and light, and can be adjusted according to the position of the steel beam to be installed. After the installation is completed, it can be dismantled and stored for turnover use;
[0027] Step 3: Install the hanger 610. The hanger 610 should be at half the length of the steel beam to ensure the center of gravity of the steel beam is balanced during the lifting process.
[0028] Step 4: The electric forklift 500 lifts the steel beam to be installed. The electric forklift 500 should meet the maximum load requirement of the steel beam. The electric forklift 500 should slowly lift the reinforced steel beam 600. After the reinforced steel beam 600 is lifted to 100mm below the original structural beam and floor slab or the safe lifting height allowed by the electric forklift 500, the electric forklift 500 stops lifting.
[0029] Step 5: The electric hoist 750 performs secondary lifting and performs rotation adjustment according to the installation situation. When the electric forklift 500 stops lifting, the remaining lifting work will be carried out by the electric hoist 750 for secondary lifting. Before the secondary lifting, the construction workers on both sides of the reinforced steel beam 600 check whether the installation position is accurate. If the error is large, the reinforced steel beam 600 needs to be fine-tuned horizontally. After the fine-tuning is completed, the rotation adjustment is performed. After all adjustments are completed, the electric hoist 750 performs secondary lifting and fixes the steel beam after reaching the specified position.
[0030] Step six, filling holes in the floor slab. After installation is completed, the lifting holes 310 are filled with high-strength micro-expansion grouting material.
[0031] In summary, the utility model relates to the technical field of building steel beams, and discloses an auxiliary installation structure for steel beams in a narrow space, comprising: a first support beam, a lower floor slab arranged on the top of the first support beam, an upper floor slab arranged at intervals on the top of the lower floor slab, and a second support beam arranged at the bottom of the upper floor slab; an electric forklift is arranged on the top of the lower floor slab, a lifting hole is opened in the thickness direction of the upper floor slab, and a lifting mechanism is arranged on the top of the upper floor slab, the lifting mechanism comprises two channel steel bases fixed to the top of the upper floor slab, a vertical rod fixed to the top of the two channel steel bases, a horizontal rod arranged between the vertical rods, and a diagonal brace arranged between the vertical rods and the horizontal rods, an electric hoist is arranged on the horizontal rod, the chain of the electric hoist extends into the lifting hole, a hook is arranged at the bottom of the chain, and a hanging piece is arranged at the center of the top surface of the reinforced steel beam, and the hook is connected to the hanging piece.
[0032] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.
Claims
1. A narrow space steel beam auxiliary installation structure, comprising: A first support beam (100), a lower floor (200) arranged on the top of the first support beam (100), an upper floor (300) arranged at intervals on the top of the lower floor (200), and a second support beam (400) arranged at the bottom of the upper floor (300); characterized in that an electric forklift (500) is arranged on the top of the lower floor (200), a reinforcing steel beam (600) is arranged on the electric forklift (500), a hoisting hole (310) is opened in the thickness direction of the upper floor (300), a hoisting mechanism (700) is arranged on the top of the upper floor (300), and the hoisting mechanism (700) includes a fixed Two channel steel bases (710) are fixed on the top of the upper floor (300), vertical rods (720) are fixed on the tops of the two channel steel bases (710), horizontal rods (730) are arranged between the vertical rods (720), and diagonal braces (740) are arranged between the vertical rods (720) and the horizontal rods (730), an electric hoist (750) is arranged on the horizontal rod (730), a chain (760) of the electric hoist (750) extends into the lifting hole (310), a hook is arranged at the bottom of the chain (760), and a hanging piece (610) is arranged at the center of the top surface of the reinforced steel beam (600), and the hook is connected to the hanging piece (610).
2. The narrow space steel beam auxiliary installation structure according to claim 1 is characterized in that: A first mounting plate (410) is provided on the opposite side of the second support beam (400), and second mounting plates (620) are provided at both ends of the length direction of the reinforced steel beam (600). Both the first mounting plate (410) and the second mounting plate (620) are provided with mounting holes (800), and the first mounting plate (410) and the second mounting plate (620) are fixed by bolts.
3. The narrow space steel beam auxiliary installation structure according to claim 1 is characterized in that: The diameter of the hoisting hole (310) is 120 mm.
4. The narrow space steel beam auxiliary installation structure according to claim 1 is characterized in that: The hanging member (610) includes a horizontal plate (611) connected to the top of the reinforced steel beam (600), and a vertical plate (612) arranged on the top of the horizontal plate (611). The horizontal plate (611) is welded and fixed to the top surface of the reinforced steel beam (600). A hanging hole (613) is arranged at the upper end of the vertical plate (612), and a hanging ring is arranged in the hanging hole (613), and the hanging ring is connected to the hook.
5. The narrow space steel beam auxiliary installation structure according to claim 1 is characterized in that: A receiving plate (510) is arranged on the top of the electric forklift (500), a rubber cushion is arranged on the top of the receiving plate (510), and the top surface of the rubber cushion contacts the bottom surface of the reinforced steel beam (600).
6. The narrow space steel beam auxiliary installation structure according to claim 1 is characterized in that: The electric forklift (500) is arranged in plurality along the bottom of the reinforced steel beam (600).