Test type plunger tool for gas well
By designing hollow turbulent flow plunger tool and temperature pressure tester, the problem of not being able to obtain downhole pressure and liquid level in the plunger gas lifting process is solved, low-cost and convenient data acquisition is achieved, and process efficiency is improved. reliability.
Patent Information
- Application Number
- CN202323531887.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-25
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-25
AI Technical Summary
Existing plunger tools cannot effectively obtain downhole pressure and liquid level height parameters in the plunger gas lifting process, resulting in high cost and low efficiency in process optimization.
A hollow turbulent flow plunger tool is designed, integrating a temperature and pressure tester and buffer spring, and multi-stage turbulence seal is achieved through upper and lower overflow holes and spinning cone structures, which can test downhole pressure and liquid level height downhole. And record data through a stored temperature and pressure tester.
It achieves low investment and convenient access to key data on plunger gas lifting wells, reduces on-site operation costs, improves the on-site use effect of the process, and can be widely promoted and reused.
Smart Images

Figure CN221973501U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of gas well testing, in particular to a testing plunger tool for a gas well. Background Art
[0002] The main characteristics of tight sandstone gas fields are low permeability, low pressure, and low abundance. With the expansion of gas field development and the extension of production time, the pressure and production of gas wells have gradually decreased, and the number of intermittent wells and liquid accumulation wells has gradually increased. The plunger gas lift process is a process that relies on natural gas lifting energy. Through the gas well production string, matching plunger tools are placed, and the gas well switch state is adjusted through the ground control system, so that natural gas can push the plunger tool to move and perform multiple lifting of liquid accumulation, ultimately reducing the wellbore liquid level, meeting the needs of drainage gas production technology, and tapping the gas well production. The important basis for the implementation of the plunger gas lift process in new wells and the maintenance of old wells is the downhole pressure and liquid level. During the on-site implementation, it is necessary to use the well test vehicle and crane to cooperate with the wire pressure gauge test operation many times, and other operating costs are incurred. The existing plunger tool types mainly include brush type, turbulence type, and bullet type. Among them, the brush type is mainly suitable for oil pipe scaling and slightly sanded gas wells; the turbulence type plunger is the earliest used and is mainly suitable for low liquid volume and relatively clean wellbore gas wells; the main feature of the bullet type plunger is its strong sealing and relatively good liquid carrying effect, but the above plunger tools cannot obtain downhole pressure and liquid level height parameters.
[0003] The above information disclosed in the background technology section is only used to enhance the understanding of the background of the present invention and therefore may contain information that does not constitute the prior art known to ordinary technicians in this field. Utility Model Content
[0004] The purpose of the utility model is to provide a test plunger tool for gas wells, which can obtain downhole pressure and liquid level height only by throwing and fishing operations, and obtain key data of plunger gas lift wells with low investment and convenience, so as to continuously optimize the on-site use effect of the technology.
[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0006] The utility model discloses a test plunger tool for a gas well, comprising:
[0007] A hollow turbulent flow plunger comprising:
[0008] The plunger body is a hollow structure having a plunger inner cavity,
[0009] An upper flow hole is provided at the upper end of the plunger body, and the upper flow hole communicates the plunger inner cavity with the oil pipe to introduce the fluid from the oil pipe.
[0010] A fishing diameter is provided on the outer side of the upper part of the plunger body,
[0011] A sealing flow channel is distributed outside the plunger body and is located below the salvage diameter,
[0012] A lower flow hole, which is disposed at the lower end of the plunger body and communicates with the plunger inner cavity to guide the fluid from the plunger inner cavity;
[0013] The temperature and pressure tester is elastically arranged in the inner cavity of the plunger via a buffer spring and immersed in the fluid.
[0014] In the test plunger tool for a gas well, the fishing diameter includes a pair of protrusions symmetrical with respect to the plunger body, and the protrusions have arc surfaces.
[0015] In the test plunger tool for gas wells, a spindle cone structure is provided on the outside of the plunger body, and the spindle cone structure includes an upper conical portion, a cylindrical portion extending from the upper conical portion, and a lower conical portion connecting the cylindrical portion. The cylindrical portion is provided with a plurality of sealing flow channels for forming a multi-stage turbulent seal between the plunger body and the wellbore.
[0016] In the test plunger tool for a gas well, the spindle cone structure is a symmetrical structure.
[0017] In the test plunger tool for a gas well, the upper flow hole is located on the central axis of the plunger body.
[0018] In the test plunger tool for a gas well, one end of the buffer spring is vertically connected to the bottom of the plunger body, and the other end is connected to the temperature and pressure tester.
[0019] In the test plunger tool for a gas well, the central axis of the buffer spring and the central axis of the plunger body are collinear.
[0020] In the test plunger tool for gas wells, the two lower flow holes are symmetrically distributed on both sides of the central axis of the plunger body.
[0021] In the test plunger tool for gas wells, the temperature and pressure tester is a long strip storage-type temperature and pressure tester.
[0022] In the test plunger tool for gas wells, the temperature and pressure tester is a cylindrical structure with a diameter smaller than the inner diameter of the plunger, and its test pressure range is 5-35MPa, the temperature resistance is 150OC, and the sampling frequency is 30s-300s / point.
[0023] In the above technical scheme, the utility model provides a test plunger tool for gas wells, which has the following beneficial effects: the test plunger tool for gas wells solves the problem that the plunger tool cannot realize the testing of downhole pressure, temperature and liquid level conditions during the implementation of the existing plunger gas lift process. It only needs to replace the original wellbore plunger tool and put in the test plunger, avoiding other traditional operations such as wire operation and wellhead disassembly. It is easy to operate, low cost, highly reliable, and can be widely promoted and reused. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present utility model. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.
[0025] Figure 1 It is a structural schematic diagram of a test plunger tool for gas wells of the utility model.
[0026] Figure 2 It is a test curve schematic diagram of the test plunger tool for gas wells of the utility model. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solution and advantages of the implementation of the utility model clearer, the technical solution in the implementation of the utility model will be clearly and completely described below in conjunction with the drawings in the implementation of the utility model. Obviously, the described implementation is a part of the implementation of the utility model, not all of the implementations. Based on the implementation of the utility model, all other implementations obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention.
[0029] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0030] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0031] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0032] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0033] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0034] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below in conjunction with the accompanying drawings.
[0035] like Figure 1-2 As shown, in one embodiment, a test plunger tool for a gas well of the utility model comprises:
[0036] A hollow turbulent flow plunger comprising:
[0037] The plunger body 3 is a hollow structure having a plunger inner cavity 4.
[0038] The upper flow hole 1 is provided at the upper end of the plunger body 3, and the upper flow hole 1 connects the plunger inner cavity 4 with the oil pipe to introduce the fluid from the oil pipe.
[0039] The fishing diameter 2 is arranged on the outer side of the upper part of the plunger body 3,
[0040] The sealing flow channel 5 is distributed outside the plunger body 3 and is located below the salvage path 2.
[0041] a lower flow hole 8, which is disposed at the lower end of the plunger body 3 and communicates with the plunger inner cavity 4 to guide the fluid from the plunger inner cavity 4;
[0042] The temperature and pressure tester 6 is elastically arranged in the plunger inner cavity 4 via a buffer spring 7 and immersed in the fluid.
[0043] In a preferred embodiment of the test plunger tool for a gas well, the fishing diameter 2 includes a pair of protrusions symmetrical with respect to the plunger body 3, and the protrusions have an arc surface.
[0044] In a preferred embodiment of the test plunger tool for gas wells, a spindle-cone structure is provided on the outside of the plunger body 3, and the spindle-cone structure includes an upper conical portion, a cylindrical portion extending from the upper conical portion, and a lower conical portion connecting the cylindrical portion, and the cylindrical portion is provided with a plurality of sealing flow channels 5 for forming a multi-stage turbulent seal between the plunger body 3 and the wellbore.
[0045] In a preferred embodiment of the test plunger tool for a gas well, the spindle cone structure is a symmetrical structure.
[0046] In a preferred embodiment of the test plunger tool for a gas well, the upper flow hole 1 is located on the central axis of the plunger body 3 .
[0047] In a preferred embodiment of the test plunger tool for gas wells, one end of the buffer spring 7 is vertically connected to the bottom of the plunger body 3 , and the other end is connected to the temperature and pressure tester 6 .
[0048] In a preferred embodiment of the test plunger tool for gas wells, the central axis of the buffer spring 7 and the central axis of the plunger body 3 are collinear.
[0049] In a preferred embodiment of the test plunger tool for a gas well, the two lower flow holes 8 are symmetrically distributed on both sides of the central axis of the plunger body 3 .
[0050] In a preferred embodiment of the test plunger tool for a gas well, the temperature and pressure tester 6 is a long storage-type temperature and pressure tester 6 .
[0051] In the preferred embodiment of the test plunger tool for gas wells, the temperature and pressure tester 6 is a cylindrical structure with a diameter smaller than the diameter of the plunger inner cavity 4, and its test pressure range is 5-35MPa, and its temperature resistance performance is 150 O C, sampling frequency is 30s-300s / point.
[0052] In one embodiment, the test plunger tool for a gas well includes a hollow turbulent flow plunger and a storage-type temperature and pressure tester 6 .
[0053] In one embodiment, the hollow turbulent flow plunger is composed of an upper flow hole 1, a salvage diameter 2, a plunger body 3, a plunger inner cavity 4, a sealed flow channel 5, a storage temperature and pressure tester 6, a buffer spring 7, and a lower flow hole 8. The upper flow hole 1 connects the oil pipe and the plunger cavity, so that the liquid in the oil pipe can enter the plunger tool cavity; the salvage diameter 2 is mainly used for salvaging the plunger tool that falls into the well abnormally; the plunger body 3 and the plunger cavity 4 are the main structures of the test plunger; the sealing flow channel 5 mainly forms a multi-stage turbulent seal when the tool runs from the wellbore to the wellhead, ensuring that the plunger tool can normally ascend to the wellhead; the storage type temperature and pressure tester 6 is built into the plunger cavity 4, follows the movement of the plunger, and tests and records the bottom hole pressure and temperature; the buffer spring 7 slows down the vibration of the storage type temperature and pressure tester 6 in the plunger cavity to avoid collision and damage; the lower flow hole 8 is connected to the upper flow hole 1 through the plunger cavity 4, and is connected to the liquid in the oil pipe to provide a pressure test liquid environment for the storage type temperature and pressure tester 6. The storage type temperature and pressure tester 6 has a test pressure range of 5-35MPa and a temperature resistance of 150 O C, sampling frequency is 30s-300s / point.
[0054] In one embodiment, the physical process of the test plunger tool for gas wells is as follows: construction preparation: including preparation of the test plunger tool, wellhead blowout preventer disassembly tool, storage-type temperature and pressure tester reading software and laptop computer, etc.; taking out the conventional plunger of the original well: according to the plunger well working system, at the well opening stage, after determining that the original well plunger has reached the wellhead, shut down the well, disassemble the blowout preventer, and take out the original well plunger; put in the test plunger tool for gas wells, set the sampling frequency of the storage-type temperature and pressure tester, place it in the plunger cavity, tighten the thread, install the blowout preventer and then open the well, so that the hollow turbulent plunger can fall normally to the downhole limiter position; according to the setting before entering the well In the data acquisition mode set, after the hollow turbulent plunger reaches the downhole limiter, the pressure and temperature recording test is carried out; the well is opened and the test plunger tool for the gas well is taken out, and the analysis data is read: when the oil pressure reaches the minimum value of the original plunger opening oil pressure, the well is opened, and the test plunger tool for the gas well relies on the formation energy to go up to the wellhead, take out the hollow turbulent plunger, and read and play back the pressure and temperature data. According to the downhole pressure recovery rate, the plunger well optimization work system is given; the conventional plunger adjustment system of the original well is re-introduced to resume production: the original well plunger is re-introduced, and the optimization recommendation system is set through the ground controller to resume normal production of the plunger well.
[0055] In one embodiment, the gas well was put into production in December 2019, with an initial oil and casing pressure of 14 / 18 MPa, and an average daily gas production of 9,600 cubic meters; intermittent production began in March 2021, with an average daily well opening time of 11 hours. Before well opening, the oil pressure was 2.86 MPa, the casing pressure was 5.82 MPa, and the average daily gas production was 2,500 cubic meters; the liquid level was measured at 2,855 m in June 2021, and there was a 510 m liquid level above the safety joint at 3,465 m. Implementation of plunger gas lift: The plunger gas lift process was implemented in July 2021, with the downhole stopper at a depth of 3,400 m, and the liquid level height H above the downhole stopper 液面高度初始 The plunger operation system, i.e. the well opening and closing system, is set to open the well for 1 hour and 10 minutes and close the well for 6 hours and 50 minutes, with 3 operation cycles per day. After the measures, the oil and casing pressures are 3.0 / 5.3, and the average daily production is 3,300 cubic meters by December 2021. Implementation of the test plunger tool for gas wells: In January 2022, the original well plunger was salvaged and put into the test plunger tool for gas wells. Stage 1, stage 2, and stage 3 constitute a single test cycle. Figure 2 The test curve shown, the interpretation results are as follows:
[0056] Stage 1: After shutting in the well, the gas well uses a test plunger tool to reach the downhole stopper position until the pressure recovers to a stable pressure before opening the well, which is recorded as P 井下稳定 ;
[0057] Stage 2: After the well is opened, the gas well is moved upward to the wellhead using a test plunger tool, and the initial pressure is measured and recorded as P 井口初始,The stable pressure after stabilization is recorded as P 井口稳定 ;
[0058] Stage 3: After the well is shut in, the gas well is driven downward with a test plunger tool. The pressure mutation trend indicates the time when the test plunger tool enters the wellbore liquid level. The pressure is recorded as P 进入液面 , the initial pressure when reaching the downhole stopper is recorded as P 井下初始 .
[0059] pass Figure 2 You can get P 井下稳定 is 5.17MPa, corresponding to P 井下稳定油压 It can be directly obtained from the ground pressure gauge as 3.16MPa, and then H can be calculated 液面高度 =(P 井下稳定 -P 井下稳定油压 )*100m / MPa=201m, compared with H 液面高度初始 At 445m, the wellbore liquid accumulation has significantly decreased, and the liquid accumulation is less, so the single well opening time can be appropriately extended. Therefore, the opening and closing well system has been optimized from the original opening well 1 hour and 10 minutes, closing well 6 hours and 50 minutes to opening well 1 hour and 30 minutes, closing well 6 hours and 30 minutes, 3 times a day, and gradually observed and extended the opening time. After optimization, it has been operating normally for 3 months, with an average daily output of 44,600 cubic meters, oil pressure of 5.3MPa, casing pressure of 5.5MPa, and oil-casing pressure difference of 0.2MPa, indicating that the liquid accumulation is also gradually decreasing, which has played a significant effect of lifting the liquid accumulation and increasing production.
[0060] Finally, it should be noted that the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without making any creative work are within the scope of protection of the present application.
[0061] The above only describes some exemplary embodiments of the present invention by way of illustration. It is undoubted that those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.
Claims
1. A test plunger tool for a gas well, characterized in that: These include, A hollow turbulent flow plunger comprising: The plunger body is a hollow structure having a plunger inner cavity, An upper flow hole is provided at the upper end of the plunger body, and the upper flow hole communicates the plunger inner cavity with the oil pipe to introduce the fluid from the oil pipe. A fishing diameter is provided on the outer side of the upper part of the plunger body, A sealing flow channel is distributed outside the plunger body and is located below the salvage diameter, A lower flow hole, which is disposed at the lower end of the plunger body and communicates with the plunger inner cavity to guide the fluid from the plunger inner cavity; The temperature and pressure tester is elastically arranged in the inner cavity of the plunger via a buffer spring and immersed in the fluid.
2. A gas well test plunger tool according to claim 1, characterized in that: The fishing diameter includes a pair of protrusions symmetrical with respect to the plunger body, and the protrusions have arc surfaces.
3. A gas well test plunger tool according to claim 1, characterized in that: A spindle cone structure is provided on the outside of the plunger body, and the spindle cone structure includes an upper cone portion, a cylindrical portion extending from the upper cone portion, and a lower cone portion connecting the cylindrical portion. The cylindrical portion is provided with a plurality of sealing flow channels for forming a multi-stage turbulent seal between the plunger body and the wellbore.
4. A gas well test plunger tool according to claim 3, characterized in that: The spindle cone structure is a symmetrical structure.
5. A gas well test plunger tool according to claim 1, characterized in that: The upper flow hole is located on the central axis of the plunger body.
6. A gas well test plunger tool according to claim 1, characterized in that: One end of the buffer spring is vertically connected to the bottom of the plunger body, and the other end is connected to the temperature and pressure tester.
7. A gas well test plunger tool according to claim 1, characterized in that: The central axis of the buffer spring and the central axis of the plunger body are collinear.
8. A gas well test plunger tool according to claim 1, characterized in that: The two lower flow holes are symmetrically distributed on both sides of the central axis of the plunger body.
9. A gas well testing plunger tool according to claim 1, characterized in that: The temperature and pressure tester is a long strip storage type temperature and pressure tester.
10. A gas well testing plunger tool according to claim 1, characterized in that: The temperature and pressure tester is a cylindrical structure with a diameter smaller than the inner diameter of the plunger, a test pressure range of 5-35MPa, a temperature resistance of 150°C, and a sampling frequency of 30s-300s / point.