Automatic timing power-on grid-connected and off-grid power-off device for centralized photovoltaic power generation inverter
By designing automatic control circuits in the inverter, the inverter can be automatically powered on and off-grid at a specific time, and the inverter is solved, which shortens the equipment life and waste of power grid resources caused by long-term power-up of the inverter, and extends the problem of Equipment life and reduce grid consumption.
Patent Information
- Application Number
- CN202420536872.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-20
- Publication Date
- 2024-11-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The inverters of existing centralized photovoltaic power stations remain live within 24 hours, resulting in a shortened service life of equipment and components and a waste of power grid resources.
A device including a closing automatic control circuit and a closing automatic control circuit is designed. The inverter is automatically powered on and off-grid at a specific time by using a timing switch controller and a time relay to realize that the inverter is automatically powered on and off-grid at a specific time, so as to avoid the inverter being long. Time runs live.
It extends the service life of equipment and components, reduces the waste of power grid resources, and realizes reasonable power use and energy saving of inverters.
Smart Images

Figure CN221978618U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of power protection control, and in particular to an automatic timing power-on and grid-connection, off-grid and power-off device for a centralized photovoltaic power generation inverter. Background Art
[0002] Photovoltaic grid-connected inverter is a device that converts the direct current generated by the photovoltaic array into alternating current and feeds it back into the power grid. It is an important part of the photovoltaic power generation system. The core of the inverter is the inverter switch circuit, referred to as the inverter circuit. This circuit completes the inverter function by turning on and off the power electronic switch. The inverter not only has the direct-to-alternating current conversion function, but also has the function of maximizing the performance of photovoltaic modules and system fault protection.
[0003] At present, the inverters of centralized photovoltaic grid-connected power stations in China are powered 24 hours a day, but photovoltaic power stations do not participate in power generation at night. Instead, they consume grid electricity as power loads. Therefore, the existing centralized photovoltaic grid-connected power stations will have an adverse effect on the service life of equipment and components, and will also lead to the consumption of offline electricity, resulting in a waste of grid resources. Utility Model Content
[0004] The purpose of the utility model is to address the deficiencies in the above-mentioned prior art and provide a centralized photovoltaic power generation inverter with automatic timed power-on and grid-connection and grid-off power-off devices, thereby improving the waste of equipment and components and the electricity consumption of power plants, thereby increasing the service life of equipment and components and reducing the waste of grid resources.
[0005] To achieve the above purpose, the technical solution adopted by the embodiment of the utility model is as follows:
[0006] The embodiment of the utility model provides a centralized photovoltaic power generation inverter automatic timing power-on and grid-connected, off-grid and power-off device, including: a closing automatic control circuit and an opening automatic control circuit; the closing automatic control circuit includes: a first control circuit, a closing circuit, the first control circuit is connected in parallel with the closing circuit; the opening automatic control circuit includes: a second control circuit, an opening circuit, the closing circuit is connected in parallel with the opening circuit, and the opening circuit is connected in parallel with the second control circuit; the closing automatic control circuit is used to supply power to the closing circuit in time, and the opening automatic control circuit is used to cut off power to the opening circuit in time.
[0007] Optionally, the first control circuit includes: a power supply, a fuse, and a 101 wiring connected in series, the 101 wiring is then connected in parallel with the timing switch controller KT and the normally open contact KA, the timing switch controller KT is connected in series with the intermediate relay KA, the normally open contact KA is connected in series with the time relay KT1, and finally flows out to the power supply N; the closing circuit includes: the 101 wiring first passes through the local control terminal No. 3, is connected in series through the conversion switch SA11, and then passes through the 113 wiring on the local control terminal No. 4 to be connected in series with the closing button SB11, a KT1 auxiliary contact and a KA auxiliary contact are connected in parallel to the closing button SB11, and then passes through the 109 wiring, the 109 wiring passes through the A2 terminal on the circuit breaker QF1, and then passes through the closing coil X to reach the A1 terminal, and flows out from the A1 terminal to the power supply N.
[0008] Optionally, the second control circuit includes: 101 wiring is connected in parallel with the timing switch controller KT2 and the normally open contact KA1, the timing switch controller KT2 is connected in series with the intermediate relay KA1, the normally open contact KA1 is connected in series with the time relay KT3, and finally flows out to the power supply N; the opening circuit includes: the 101 wiring first passes through the local control terminal No. 7, is connected in series through the conversion switch SA11, and then passes through the 111 wiring on the local control terminal No. 8 to be connected in series with the opening button SB12, a KT3 auxiliary contact and a KA1 auxiliary contact are connected in parallel to the opening button SB12, and then passes through the 103 wiring, the 103 wiring passes through the C2 terminal on the circuit breaker QF1, and then passes through the opening coil F to reach the C1 terminal, and flows out from the C1 terminal to the power supply N.
[0009] The beneficial effects of the utility model are:
[0010] The centralized photovoltaic power generation inverter automatic timed power-on and grid-connected, off-grid and power-off device comprises: a closing automatic control circuit and an opening automatic control circuit, which are connected in parallel; the closing automatic control circuit further comprises a first control circuit and a closing circuit, which are connected in parallel; the opening automatic control circuit further comprises a second control circuit and an opening circuit, which are connected in parallel; the closing automatic control circuit can supply power to the closing circuit in time when in a closed state, and the opening automatic control circuit can power off the opening circuit in time when in an open state; through the improvement of the circuit structure, the service life of the equipment and components is not only improved, but also the waste of grid resources is reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0012] Figure 1 A circuit diagram of a centralized photovoltaic power generation inverter automatic timing power-on and grid-connection and grid-off power-off device provided in one embodiment of the utility model. DETAILED DESCRIPTION
[0013] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0014] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0015] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0016] In the description of the present invention, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.
[0017] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "setting" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0018] Figure 1A circuit diagram of a centralized photovoltaic power generation inverter automatic timing power-on and grid-connection and grid-off power-off device provided in one embodiment of the utility model.
[0019] refer to Figure 1 The embodiment of the utility model provides a centralized photovoltaic power generation inverter automatic timing power-on and grid-connected, off-grid and power-off device, including: a closing automatic control circuit and an opening automatic control circuit; the closing automatic control circuit includes: a first control circuit, a closing circuit, the first control circuit is connected in parallel with the closing circuit; the opening automatic control circuit includes: a second control circuit, an opening circuit, the closing circuit is connected in parallel with the opening circuit, and the opening circuit is connected in parallel with the second control circuit; the closing automatic control circuit is used to supply power to the closing circuit in time, and the opening automatic control circuit is used to cut off power to the opening circuit in time.
[0020] In the present application, the closing automatic control circuit and the opening automatic control circuit are connected in parallel; the closing automatic control circuit includes a first control circuit and a closing circuit, which are connected in parallel; the opening automatic control circuit includes a second control circuit and an opening circuit, which are connected in parallel; the closing automatic control circuit can supply power to the closing circuit in time when it is in the closed state, and the opening automatic control circuit can cut off power to the opening circuit in time when it is in the open state; through the improvement of the circuit structure, the service life of the equipment and components is not only improved, but also the waste of power grid resources is reduced.
[0021] Furthermore, the first control circuit includes: a power supply, a fuse, and a 101 wiring connected in series, the 101 wiring is then connected in parallel with the timing switch controller KT and the normally open contact KA, the timing switch controller KT is connected in series with the intermediate relay KA, the normally open contact KA is connected in series with the time relay KT1, and finally flows out to the power supply N; the closing circuit includes: the 101 wiring first passes through the No. 3 terminal of the local control, is connected in series through the conversion switch SA11, and then passes through the 113 wiring terminal on the No. 4 terminal of the local control to be connected in series with the closing button SB11, a KT1 auxiliary contact and a KA auxiliary contact are connected in parallel to the closing button SB11, and then passes through the 109 wiring, the 109 wiring passes through the A2 terminal on the circuit breaker QF1, and then passes through the closing coil X to reach the A1 terminal, and flows out from the A1 terminal to the power supply N.
[0022] In this embodiment, in the closing circuit, a KT1 auxiliary contact and a KA auxiliary contact are connected in parallel on the closing button SB11, and are energized through the timing switch controller KT to turn on the KA intermediate relay. After the KA intermediate relay is energized, the normally open contact KA is closed, and the circuit breaker QF1 in the closing circuit is turned on and closed, so that the entire inverter device is energized and ready for standby operation, waiting for grid-connected power generation. At the same time, in the first control circuit, the normally open contact KA of the intermediate relay KA is closed, and the time relay KT1 starts timing. After the timing reaches the set value, the KT1 auxiliary contact in the closing circuit is disconnected, and the closing circuit of the circuit breaker QF1 is disconnected at the same time, and the closing coil X loses power, thereby avoiding long-term power-carrying damage to the coil.
[0023] This solution realizes that in the morning, before the photovoltaic power generation equipment is connected to the grid for power generation, the timing switch controller KT will be activated after a set reasonable time, the circuit breaker QF1 closing circuit is connected, the low-voltage side circuit breaker is closed, and the inverter is energized and on standby, waiting for grid-connected power generation. This realizes the timed closing and energizing of the grid-connected power generation, avoiding the inverter device from running with power 24 hours a day, thereby reducing the waste of power grid resources.
[0024] Furthermore, the second control circuit includes: 101 wiring is connected in parallel with the timing switch controller KT2 and the normally open contact KA1, the timing switch controller KT2 is connected in series with the intermediate relay KA1, the normally open contact KA1 is connected in series with the time relay KT3, and finally flows out to the power supply N; the opening circuit includes: the 101 wiring first passes through the local control terminal No. 7, is connected in series through the conversion switch SA11, and then passes through the 111 wiring on the local control terminal No. 8 to be connected in series with the opening button SB12, a KT3 auxiliary contact and a KA1 auxiliary contact are connected in parallel to the opening button SB12, and then passes through the 103 wiring, the 103 wiring passes through the C2 terminal on the circuit breaker QF1, and then passes through the opening coil F to reach the C1 terminal, and flows out from the C1 terminal to the power supply N.
[0025] In this embodiment, in the opening circuit, a KT3 auxiliary contact and a KA1 auxiliary contact are connected in parallel on the opening button SB12, and the timing switch controller KT2 loses power and disconnects the KA1 intermediate relay. After the KA1 intermediate relay loses power, the normally open contact KA1 is disconnected, and the circuit breaker QF1 in the opening circuit is disconnected, causing the entire inverter device to lose power and shut down. At the same time, in the second control circuit, the normally open contact KA1 of the intermediate relay KA1 is closed, and the time relay KT3 starts timing. After the timing reaches the set value, the KT3 auxiliary contact in the opening circuit is disconnected, and the opening circuit of the circuit breaker QF1 is disconnected at the same time, and the opening coil F loses power, thereby preventing the coil from being energized for a long time and being damaged.
[0026] This implementation scheme realizes that after the photovoltaic area power generation equipment is disconnected from the grid at night, the timing switch controller KT2 will be activated after a set reasonable time, connecting the circuit breaker QF1 disconnection circuit, disconnecting the low-voltage side circuit breaker, and causing the inverter to enter a power-off shutdown state, thereby realizing the inverter to be shut down for rest at night without consuming any electrical energy, that is, realizing the timed disconnection and power-off of the grid-connected power generation, avoiding the inverter device from running with power on for 24 hours, thereby reducing the waste of grid resources.
[0027] Among them, the timing switch controller can usually automatically control the switch of electrical equipment according to the time set as needed. It can not only avoid energy waste, but also extend the service life of electrical appliances.
[0028] The time relay can realize delay control. It delays the closing or breaking of the contact through electromagnetic principle or mechanical action principle, so that the timing starts after receiving the start signal. After the timing ends, the working contact closes or opens to promote the subsequent circuit operation. The characteristic of the time relay is that there is a delay from the time the attraction coil receives the signal to the contact action. This delay performance can be adjusted within the designed range, which is convenient for adjusting the delay time.
[0029] The main function of the intermediate relay is to transmit signals in the control circuit. It generates magnetic force by energizing the coil, which attracts the moving iron core and the fixed iron core, thereby driving the contact to move. Specifically, when the coil is energized, the moving iron core moves and attracts under the action of electromagnetic force, driving the moving contact to move, so that the normally closed contact opens and the normally open contact closes. When the coil is de-energized, the moving iron core drives the moving contact to reset under the action of the spring, so that the normally closed contact and the normally open contact of the relay return to their original state.
[0030] The working principle of the automatic timing power-on and grid-connection and off-grid power-off device of the centralized photovoltaic power generation inverter is as follows:
[0031] 1. Add a timing switch controller KT in the closing automatic control circuit. Assuming that the inverter device is connected to the grid for power generation at 6:00 in the morning, set the time of the timing switch controller KT to 5:30 (the time can be freely set according to the actual situation of the power station). When the set time is reached, the timing switch controller KT will act, the intermediate relay KA will be energized, the KA auxiliary contact in the closing circuit will be closed, the closing circuit will be connected, the circuit breaker QF1 will be closed, and the inverter device will be energized and enter the standby state, waiting for grid-connected power generation.
[0032] 2. At the same time, in the time relay KT1 circuit, the normally open contact KA is connected, and the time relay KT1 is energized. After setting a reasonable time, the time relay KT1 delays the action, and the auxiliary contact of KT1 in the closing circuit is disconnected, thus disconnecting the closing circuit.
[0033] 3. Similarly, a set of the above-mentioned devices is also set in the automatic opening control circuit. After disconnection from the grid, the circuit breaker QF1 is disconnected at a preset time, and the inverter enters a power-off shutdown state.
[0034] Equipment Name Comparison Table
[0035]
[0036]
[0037] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. Centralized photovoltaic power generation inverter automatic timing power-on and grid-connection, off-grid power-off device, It is characterized in that include: Closing automatic control circuit and opening automatic control circuit; The closing automatic control circuit comprises: a first control circuit and a closing circuit, wherein the first control circuit is connected in parallel with the closing circuit; The opening automatic control circuit comprises: a second control circuit and an opening circuit, wherein the closing circuit is connected in parallel with the opening circuit, and the opening circuit is connected in parallel with the second control circuit; The automatic closing control circuit is used to supply power to the closing circuit in time, and the automatic opening control circuit is used to cut off power to the opening circuit in time.
2. The centralized photovoltaic power generation inverter automatic timing power-on and grid-connection, off-grid and power-off device as claimed in claim 1, It is characterized in that The first control circuit comprises: The power supply V, fuse FU1, and 101 wiring are connected in series, and the 101 wiring is then connected in parallel with the timing switch controller KT and the normally open contact KA. The timing switch controller KT is connected in series with the intermediate relay KA, and the normally open contact KA is connected in series with the time relay KT1, and finally flows out to the power supply N; The closing circuit comprises: The 101 wiring first passes through the No. 3 terminal of the local control, is connected in series through the transfer switch SA11, and then is connected in series with the closing button SB11 through the 113 wiring terminal on the No. 4 terminal of the local control. After a KT1 auxiliary contact and a KA auxiliary contact are connected in parallel to the closing button SB11, it passes through the 109 wiring. The 109 wiring passes through the A2 terminal on the circuit breaker QF1, and then passes through the closing coil X to the A1 terminal, and flows out from the A1 terminal to the power supply N.
3. The automatic timed power-on and grid-connection and off-grid power-off device for centralized photovoltaic power generation inverter according to claim 1, It is characterized in that The second control circuit comprises: 101 wiring is connected in parallel with the timing switch controller KT2 and the normally open contact KA1, the timing switch controller KT2 is connected in series with the intermediate relay KA1, the normally open contact KA1 is connected in series with the time relay KT3, and finally flows out to the power supply N; The opening circuit comprises: The 101 wiring first passes through the local control terminal No. 7, is connected in series through the conversion switch SA11, and then is connected in series with the opening button SB12 through the 111 wiring on the local control terminal No.
8. A KT3 auxiliary contact and a KA1 auxiliary contact are connected in parallel to the opening button SB12, and then passes through the 103 wiring. The 103 wiring passes through the C2 terminal on the circuit breaker QF1, and then passes through the opening coil F to reach the C1 terminal, and flows out from the C1 terminal to the power supply N.