Highway roadbed structure

By using reinforced concrete columns and steel cable slab components as support structures in the highway subgrade, the subgrade settlement problem was solved, achieving high bearing capacity and stability of the highway subgrade and preventing lateral collapse.

CN221988992UInactive Publication Date: 2024-11-12CCCC RAILWAY (WUHAN) CONSTR TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420587463.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-25
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing mountain or rural roads have limited roadbed bearing capacity, which can easily lead to settlement and pose safety hazards.

Method used

The reinforced concrete column support structure, including central and side columns, combined with steel cables and stone slab tensioning components, forms a stable roadbed structure. The bending of the steel cables and the movement of the stone slabs fill the gaps in the roadbed, maintaining the compactness of the soil and gravel layers.

Benefits of technology

It improves the bearing capacity and stability of the highway subgrade, reduces pavement settlement and deformation, prevents lateral collapse, and enhances the overall structural strength of the subgrade.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221988992U_ABST
    Figure CN221988992U_ABST
Patent Text Reader

Abstract

The utility model discloses a highway subgrade structure, and relates to the technical field of highway subgrades, the highway subgrade structure comprises a bottom layer, a soil layer is laid on the top of the bottom layer, a middle support column is embedded in the soil layer, and tensioning assemblies are fixedly installed on the two sides of the middle support column; cement protective edges are fixedly installed on the two sides of the soil layer, a gravel layer is laid on the top of the soil layer, and two side supporting columns are embedded in the gravel layer. Reinforced concrete columns can be adopted as the middle supporting column and the two lateral supporting columns in the roadbed, so that the roadbed has high bearing capacity and stability, the highway pavement can be effectively supported, and pavement settlement and deformation are reduced; and the cement protective edge can prevent the roadbed from laterally collapsing after long-time use. When settlement occurs, the side supporting columns move downwards to extrude the steel cables, the steel cables are bent, the steel cables pull the stone plates to move towards the middle supporting columns, the stone plates can extrude the soil layer and the gravel layer, and therefore the tightness of the soil layer and the gravel layer in the roadbed is kept.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of highway subgrade, in particular to a highway subgrade structure. Background Art

[0002] Roadbed refers to a strip structure built as the foundation of the road surface according to the route location and certain technical requirements. It is the foundation of railways and highways. The roadbed is a linear structure built with soil or stone.

[0003] Since the main function of the roadbed is to provide the necessary conditions for road paving and driving operations, and to bear the static and dynamic loads of locomotives, vehicles, road surfaces and traffic loads, and to transfer and diffuse the loads deep into the foundation, the highway will bear a high load for a long time. However, the bearing capacity of some existing mountainous or rural roads is limited, which can easily lead to settlement of the roadbed, and gaps can often be seen on mountainous or rural roads. The settlement of the highway roadbed poses a safety hazard to vehicles traveling on the road. Therefore, in order to solve the above problems, we propose a highway roadbed structure. Utility Model Content

[0004] The utility model aims to solve the defects in the prior art and proposes a highway subgrade structure.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] A highway subgrade structure comprises a bottom layer, a soil layer is laid on the top of the bottom layer, a middle pillar is buried inside the soil layer, and tensioning components are fixedly installed on both sides of the middle pillar;

[0007] Cement guardrails are fixedly installed on both sides of the soil layer, a gravel layer is laid on the top of the soil layer, two side pillars are buried inside the gravel layer, the two side pillars are respectively located on the left and right sides of the middle pillar, the top of the middle pillar extends to the inside of the gravel layer, a concrete layer is laid on the top of the gravel layer, and the tops of the two side pillars and the top of the middle pillar are in conflict with the bottom of the concrete layer.

[0008] Furthermore, the tensioning assembly is composed of multiple steel cables and multiple stone slabs, one end of the multiple steel cables is fixedly connected to the left and right sides of the middle pillar, and the other ends of the multiple steel cables are fixedly connected to one side of the multiple stone slabs, and the multiple stone slabs are movably installed on one side of the two cement guardrails.

[0009] Furthermore, the plurality of steel cables are buried inside the soil layer, and the two side supports are located above the plurality of steel cables.

[0010] Furthermore, one side of the two cement guardrails is provided with an installation groove, and the plurality of stone slabs are respectively installed inside the two installation grooves.

[0011] Compared with the prior art, the beneficial effects of the present invention are:

[0012] The internal middle pillar and two lateral pillars of the utility model can adopt reinforced concrete pillars, so that the roadbed has a higher bearing capacity and stability, can effectively support the highway pavement, and reduce pavement settlement and deformation; the cement guardrail can prevent the roadbed from lateral collapse under long-term use.

[0013] When settlement occurs, the downward movement of the side pillars will squeeze the steel cables, causing them to bend. The steel cables will pull the stone slabs toward the middle pillars. The stone slabs can squeeze the soil and gravel layers, thereby maintaining the tightness of the soil and gravel layers inside the roadbed. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. They are used together with the embodiments of the present invention to explain the present invention and do not constitute a limitation to the present invention.

[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0016] Figure 2 It is a left view of the utility model;

[0017] Figure 3 It is a three-dimensional diagram of the cement edge guard of the present utility model.

[0018] In the figure: 1, bottom layer; 2, middle pillar; 3, soil layer; 4, cement guardrail; 5, gravel layer; 6, side pillar; 7, steel cable; 8, stone slab; 9, installation groove; 10, concrete layer. DETAILED DESCRIPTION

[0019] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings in the embodiments of the present invention;

[0020] Reference Figure 1-3A highway subgrade structure comprises a bottom layer 1, a soil layer 3 is laid on the top of the bottom layer 1, a middle pillar 2 is buried inside the soil layer 3, and tensioning components are fixedly installed on both sides of the middle pillar 2; cement guardrails 4 are fixedly installed on both sides of the soil layer 3, a crushed stone layer 5 is laid on the top of the soil layer 3, two side pillars 6 are buried inside the crushed stone layer 5, the two side pillars 6 are respectively located on the left and right sides of the middle pillar 2, the top of the middle pillar 2 extends to the inside of the crushed stone layer 5, a concrete layer 10 is laid on the top of the crushed stone layer 5, and the tops of the two side pillars 6 and the top of the middle pillar 2 are in conflict with the bottom of the concrete layer 10.

[0021] Vehicles can travel on the top of the concrete layer 10; the middle pillar 2 and the two lateral pillars 6 inside the roadbed can be made of reinforced concrete columns, so that the roadbed has a higher bearing capacity and stability, can effectively support the highway pavement, and reduce pavement settlement and deformation; the cement guardrail 4 can prevent the roadbed from lateral collapse under long-term use.

[0022] The tensioning assembly is composed of a plurality of steel cables 7 and a plurality of stone slabs 8. One end of the plurality of steel cables 7 is fixedly connected to the left and right sides of the middle pillar 2, and the other end of the plurality of steel cables 7 is fixedly connected to one side of the plurality of stone slabs 8. The plurality of stone slabs 8 are movably installed on one side of the two cement guard edges 4. The plurality of steel cables 7 are buried inside the soil layer 3, and the two side pillars 6 are located above the plurality of steel cables 7. One side of the two cement guard edges 4 is provided with an installation groove 9, and the plurality of stone slabs 8 are installed inside the two installation grooves 9, respectively.

[0023] When settlement occurs, the side pillar 6 moves downward to squeeze the steel cable 7, causing the steel cable 7 to bend. The steel cable 7 will pull the stone slab 8 to move toward the middle pillar 2. The stone slab 8 can squeeze the soil layer 3 and the gravel layer 5 to fill the internal gap of the roadbed, thereby maintaining the tightness of the soil layer 3 and the gravel layer 5 inside the roadbed.

Claims

1. A highway subgrade structure, comprising a bottom layer (1), characterized in that: A soil layer (3) is laid on the top of the bottom layer (1), a middle pillar (2) is buried inside the soil layer (3), and tensioning components are fixedly installed on both sides of the middle pillar (2); Cement guardrails (4) are fixedly installed on both sides of the soil layer (3); a crushed stone layer (5) is laid on the top of the soil layer (3); two side pillars (6) are buried inside the crushed stone layer (5); the two side pillars (6) are respectively located on the left and right sides of the middle pillar (2); the top of the middle pillar (2) extends to the inside of the crushed stone layer (5); a concrete layer (10) is laid on the top of the crushed stone layer (5); the tops of the two side pillars (6) and the top of the middle pillar (2) are in contact with the bottom of the concrete layer (10).

2. A highway subgrade structure according to claim 1, characterized in that: The tensioning assembly is composed of a plurality of steel cables (7) and a plurality of stone slabs (8), one end of the plurality of steel cables (7) is fixedly connected to the left and right sides of the middle pillar (2), and the other end of the plurality of steel cables (7) is fixedly connected to one side of the plurality of stone slabs (8), and the plurality of stone slabs (8) are movably mounted on one side of the two cement guardrails (4).

3. A highway subgrade structure according to claim 2, characterized in that: The plurality of steel cables (7) are buried inside the soil layer (3), and the two side pillars (6) are located above the plurality of steel cables (7).

4. A highway subgrade structure according to claim 3, characterized in that: One side of the two cement guard edges (4) is provided with a mounting groove (9), and the plurality of stone slabs (8) are respectively mounted inside the two mounting grooves (9).