Positioning auxiliary structure in descending process of reinforcement cage
By installing roller components and buffering and monitoring components on the steel cage, the problem of center position deviation during the steel cage is solved, the positioning accuracy and pile foundation bearing capacity performance are improved, and the precise control of the steel cage is achieved.
Patent Information
- Application Number
- CN202420582826.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-25
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-03-25
AI Technical Summary
In pile foundation construction, due to manual operation errors during the lowering of the steel cage, the center position of the steel cage is easily deviated, affecting the bearing capacity performance of subsequent poured concrete and pile foundation.
Multiple groups of roller components distributed along the circumference of the steel cage are adopted, combining buffer and monitoring components. The auxiliary structure includes rollers, mounting frames, rotating shafts, matte anti-slip layer, buffer components and monitoring components to ensure the center point of the steel cage and steel protection. Align the center point of the cylinder to improve positioning accuracy.
It effectively improves the accuracy of the center position after the steel cage is lowered, ensures the uniformity of concrete pouring and pile foundation bearing capacity, reduces manual operation errors, and improves construction efficiency and safety.
Smart Images

Figure CN221989332U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pile foundation construction, in particular to a positioning auxiliary structure in the process of lowering a reinforcement cage. Background Art
[0002] Pile foundation is a basic component vertically set in the soil. Its function is to transfer the dynamic and static loads borne by the pile top to the harder, denser or less compressible foundation bearing layer to meet the requirements of bearing capacity and settlement. The construction of pile foundation usually includes the following construction steps: burying steel casing, drilling, cleaning holes, lowering steel cage, installing conduit, pouring concrete, etc. In pile foundation construction, lowering steel cage is an important link.
[0003] At present, a crane is usually used to lower the steel cage into the steel casing, and the position of the steel cage is adjusted based on the construction workers' own operating experience to complete the lowering of the steel cage. However, manual operation requires high crane operation and personnel experience, and manual operation may have large errors, which may cause the center position of the steel cage to deviate after being lowered, thereby affecting the subsequent pouring of concrete and the bearing capacity of the pile foundation. Utility Model Content
[0004] The utility model provides a positioning auxiliary structure in the process of lowering a steel cage, so as to improve the accuracy of the center position of the steel cage after it is lowered, and solve the technical problem that the subsequent pouring of concrete and the bearing capacity performance of the pile foundation are affected by the deviation of the steel cage.
[0005] In order to achieve the above purpose, the technical solution of the utility model is:
[0006] A positioning auxiliary structure for lowering a steel cage comprises a plurality of roller assemblies evenly distributed along the circumferential direction of the steel cage, wherein the roller assemblies comprise: a mounting frame, a rotating shaft and rollers; the mounting frame is mounted on the steel cage, the rotating shaft is fixed on the mounting frame, the rotating shaft is arranged along the tangent direction of the steel cage, the rollers are sleeved on the rotating shaft, and the rollers are rotatably connected to the rotating shaft.
[0007] Furthermore, the roller assemblies are evenly arranged in multiple layers along the axis direction of the steel cage.
[0008] Furthermore, each roller assembly is provided with two rollers, and the mounting frame includes a bracket base plate and two sub-brackets, the bracket base plate is installed on the steel cage, the two sub-brackets are fixed on the side of the bracket base plate away from the steel cage, the two sub-brackets are arranged opposite to each other, the two ends of the rotating shaft are respectively fixed on the two sub-brackets, and the two rollers are located between the two sub-brackets.
[0009] Furthermore, the sub-bracket includes: a first support rod, a second support rod and a third support rod; the first support rod is vertically fixed to the bottom plate of the bracket, and the rotating shaft is fixed on the first support rod; one end of the second support rod and the third support rod are fixed to the bottom plate of the bracket, and the other end is fixed to the first support rod, and the second support rod, the third support rod and the bottom plate of the bracket form a triangular structure.
[0010] Furthermore, the outer periphery of the roller is coated with a frosted anti-skid layer.
[0011] Furthermore, it also includes multiple groups of buffer components corresponding to each group of roller components. The buffer components include mounting steel bars and elastic members. The mounting steel bars are fixed on the steel cage. The mounting frame is rotatably connected to the mounting steel bars. The elastic member is located between the mounting frame and the mounting steel bars.
[0012] Furthermore, a limit block is provided on the installation steel bar, and the limit block is located between the installation frame and the installation steel bar.
[0013] Furthermore, a buffer pad is provided at one end of the limiting block facing the mounting frame.
[0014] Furthermore, it also includes multiple groups of monitoring components corresponding to each group of roller assemblies, and the monitoring components include: a pressure gauge, an information processing unit, a red indicator light and a green indicator light; the pressure gauge is arranged between the installation steel bar and the elastic member, the information processing unit is arranged on the installation steel bar, and the red indicator light and the green indicator light are arranged on the mounting frame; the pressure gauge, the red indicator light and the green indicator light are electrically connected to the information processing unit; the information processing unit controls the lighting and extinguishing of the red indicator light and the green indicator light according to the pressure value detected by the pressure gauge.
[0015] Furthermore, the installation steel bars are fixed on the longitudinal bars of the steel cage along the axial direction of the steel cage, and a steel bar axial force meter is installed on the installation steel bars.
[0016] Beneficial effects:
[0017] The present application evenly distributes multiple groups of roller assemblies in the circumferential direction of the steel cage. The rollers of the roller assemblies roll along the inner wall of the steel casing to assist in the alignment of the center point of the steel cage with the center point of the steel casing, thereby improving the positioning accuracy of the steel cage and solving the problem of the subsequent pouring of concrete and the bearing capacity performance of the pile foundation affected by the deviation of the steel cage. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0019] Figure 1 It is a structural schematic diagram of a positioning auxiliary structure in the process of lowering a steel cage disclosed in the utility model;
[0020] Figure 2 It is a front view of an assembly of a roller assembly, a buffer assembly and a monitoring assembly of a positioning auxiliary structure in the process of lowering a steel cage disclosed in the utility model;
[0021] Figure 3 It is a left view of an assembly of a roller assembly, a buffer assembly and a monitoring assembly of a positioning auxiliary structure during the lowering process of a reinforcement cage disclosed in the utility model.
[0022] In the figure: 11, mounting frame; 111, bracket bottom plate; 112, first support rod; 113, second support rod; 114, third support rod; 12, rotating shaft; 13, roller; 14, frosted anti-skid layer; 21, installation steel bar; 22, elastic member; 23, limit block; 231, buffer pad; 31, pressure gauge; 32, information processing unit; 33, red indicator light; 34, green indicator light; 35, steel bar axial force gauge. DETAILED DESCRIPTION
[0023] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] A positioning auxiliary structure for the lowering process of the steel cage, combined with Figure 1 , Figure 2 and Figure 3 As shown, it includes multiple groups of roller assemblies evenly distributed along the circumferential direction of the steel cage, and the roller assembly includes: a mounting frame 11, a rotating shaft 12 and a roller 13; the mounting frame 11 is installed on the steel cage, the rotating shaft 12 is fixed on the mounting frame 11, the rotating shaft 12 is arranged along the tangent direction of the steel cage, and the roller 13 is sleeved on the rotating shaft 12, and the roller 13 is rotatably connected with the rotating shaft 12. By evenly distributing multiple groups of roller assemblies in the circumferential direction of the steel cage, the rollers 13 of the roller assembly roll along the inner wall of the steel casing, which assists in completing the alignment of the center point of the steel cage with the center point of the steel casing, improves the positioning accuracy of the steel cage, and solves the problem of affecting the subsequent pouring of concrete and the bearing capacity of the pile foundation due to the deviation of the steel cage. Especially for large-diameter steel cages with greater difficulty in lifting operations, the positioning auxiliary structure can facilitate the alignment of the center point of the large-diameter steel cage with the center point of the steel casing, and improve its positioning accuracy.
[0025] Preferably, the roller assembly is evenly arranged in multiple layers along the axis of the steel cage. Since the steel cage is relatively long, the roller assembly can ensure the stability of the entire lower process of the steel cage and the accuracy of the upper and lower ends of the steel cage. After the roller assembly assists in the alignment of the center point of the steel cage and the center point of the steel casing, the gap between the steel cage and the inner wall of the steel casing is ensured to be uniform and meet the design requirements, avoiding excessive or too small gaps, resulting in uneven or impossible concrete pouring.
[0026] Specifically, the positioning auxiliary structure can be installed on the steel cage when the steel cage is manufactured, and does not need to be installed on site, which can save a lot of operation time.
[0027] Preferably, each group of roller assemblies is provided with two rollers 13, and the mounting frame 11 includes a bracket base plate 111 and two sub-brackets, the bracket base plate 111 is installed on the steel cage, and the two sub-brackets are fixed on the side of the bracket base plate 111 away from the steel cage. The two sub-brackets are arranged opposite to each other, and the two ends of the rotating shaft 12 are respectively fixed on the two sub-brackets, and the two rollers 13 are located between the two sub-brackets. The two rollers 13 can improve the force condition and avoid uneven force on the roller assembly. The two sub-brackets support the rotating shaft 12 from both ends, and the structural rigidity is good, so that the roller assembly can withstand a large force.
[0028] Preferably, the sub-bracket includes: a first support rod 112, a second support rod 113 and a third support rod 114; the first support rod 112 is vertically fixed to the support bottom plate 111, and the rotation shaft 12 is fixed to the first support rod 112; one end of the second support rod 113 and the third support rod 114 are fixed to the support bottom plate 111, and the other end is fixed to the first support rod 112, and the second support rod 113, the third support rod 114 and the support bottom plate 111 are in a triangular structure. The second support rod 113 and the third support rod 114 are in a triangular shape to reinforce the support for the first support rod 112, and the three support rods of the mounting frame 11 are stressed at the same time, so as to ensure sufficient bearing capacity on the basis of reducing the weight of the mounting frame 11.
[0029] Specifically, the bracket bottom plate 111, the first support rod 112, the second support rod 113 and the third support rod 114 are all made of steel and are fixed together by welding to form a sub-bracket. The roller 13 is installed on the rotating shaft 12 through a bearing, and then the two ends of the rotating shaft 12 are welded to the first support rods 112 of the two sub-brackets to achieve smooth rotation of the roller 13.
[0030] Specifically, the mounting frame 11 and the roller 13 are made of steel to avoid damage due to collision during transportation and lowering.
[0031] Preferably, the outer periphery of the roller 13 is coated with a frosted anti-skid layer 14 having a large roughness. The frosted anti-skid layer 14 contacts the inner wall of the steel casing to ensure smooth rotation of the roller 13 and avoid the roller 13 from getting stuck.
[0032] Preferably, the positioning auxiliary structure also includes a plurality of buffer components corresponding to each group of roller components. The buffer components include installation steel bars 21 and elastic members 22. The installation steel bars 21 are fixed on the steel cage. The mounting frame 11 is rotatably connected to the installation steel bars 21. The elastic member 22 is located between the mounting frame 11 and the installation steel bars 21. In this embodiment, the elastic member 22 is a compression spring. When the steel cage is hoisted and lowered, if the steel cage tends to deviate, the bracket bottom plate 111 can rotate around the installation steel bars 21. The elastic member 22 is compressed and deformed to provide elastic force, play a shock-absorbing role, and can give the steel cage a smaller acceleration force to prevent the steel cage from deformation. It can also prevent the inner wall of the steel casing from being damaged by the roller 13.
[0033] Specifically, each group of buffer components has two installation steel bars 21, and the two installation steel bars 21 are arranged in parallel. The bracket bottom plate 111 is located between the two installation steel bars 21, and the bracket bottom plate 111 is connected to the two installation steel bars 21 through a hinge. The middle part of the hinge is welded and fixed to the bracket bottom plate 111, and the two end parts of the hinge are respectively welded and fixed to the ends of the two installation steel bars 21, so as to realize the rotation connection between the bracket bottom plate 111 and the two installation steel bars 21, and the two installation steel bars 21 can improve the reliability of the rotation connection between the bracket bottom plate 111 and the two installation steel bars 21.
[0034] Preferably, a limit block 23 is provided on the installation steel bar 21, and the limit block 23 is located between the installation frame 11 and the installation steel bar 21. After the bracket bottom plate 111 rotates to a certain position, it abuts against the limit block 23, and the limit block 23 limits the position of the bracket bottom plate 111, ensuring that the center position of the steel cage does not exceed the allowable error range under the positioning assistance of the roller assembly.
[0035] Preferably, a buffer pad 231 is provided at one end of the limiting block 23 facing the mounting frame 11 . In the present embodiment, the buffer pad 231 is made of rubber material, and the buffer pad 231 acts as a buffer for the contact between the bracket bottom plate 111 and the limiting block 23 .
[0036] Preferably, the positioning auxiliary structure also includes multiple groups of monitoring components corresponding to each group of roller assemblies, and the monitoring components include: a pressure gauge 31, an information processing unit 32, a red indicator light 33 and a green indicator light 34; the pressure gauge 31 is arranged between the installation steel bar 21 and the elastic member 22, the information processing unit 32 is arranged on the installation steel bar 21, and the red indicator light 33 and the green indicator light 34 are arranged on the mounting frame 11; the pressure gauge 31, the red indicator light 33 and the green indicator light 34 are electrically connected to the information processing unit 32; the information processing unit 32 controls the lighting and extinguishing of the red indicator light 33 and the green indicator light 34 according to the pressure value detected by the pressure gauge 31.
[0037] The pressure gauge 31 monitors the pressure of the limit block 23 in real time, and the pressure gauge 31 uploads the measured pressure value to the information processing unit 32, which determines whether the pressure value meets the requirements according to the preset specified range; when the pressure value is within the specified range, the information processing unit 32 controls the green indicator light 34 to light up and the red indicator light 33 to go out; when the pressure value is within the specified range, the information processing unit 32 controls the red indicator light 33 to light up and the green indicator light 34 to go out. Construction personnel can quickly understand whether the steel cage is too deviated during the lowering process by observing the changes in the light at the pile foundation hole, so as to solve the problem that the pile foundation hole is too deep and difficult to observe.
[0038] Preferably, the installation steel bar 21 is fixed on the longitudinal bars of the steel cage along the axial direction of the steel cage, and a steel bar axial force meter 35 is installed on the installation steel bar 21. The steel bar axial force meter 35 can realize stress monitoring after the pile foundation construction is completed, realize intelligent daily use, and no need to install redundant detection equipment.
[0039] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.
Claims
1. A positioning auxiliary structure during the lowering of the steel cage, It is characterized in that The invention comprises a plurality of roller assemblies evenly distributed along the circumferential direction of the steel cage, wherein the roller assemblies comprise: a mounting frame (11), a rotating shaft (12) and a roller (13); the mounting frame (11) is mounted on the steel cage, the rotating shaft (12) is fixed on the mounting frame (11), the rotating shaft (12) is arranged along the tangent direction of the steel cage, the roller (13) is sleeved on the rotating shaft (12), and the roller (13) is rotatably connected to the rotating shaft (12).
2. A positioning auxiliary structure for lowering a steel cage according to claim 1, It is characterized in that The roller components are evenly arranged in multiple layers along the axis direction of the steel cage.
3. The positioning auxiliary structure during the lowering process of the steel cage according to claim 1, It is characterized in that Each group of the roller assemblies is provided with two rollers (13); the mounting frame (11) comprises a bracket base plate (111) and two sub-brackets; the bracket base plate (111) is mounted on the steel cage; the two sub-brackets are fixed on a side of the bracket base plate (111) away from the steel cage; the two sub-brackets are arranged opposite to each other; the two ends of the rotating shaft (12) are respectively fixed on the two sub-brackets; and the two rollers (13) are located between the two sub-brackets.
4. A positioning auxiliary structure for lowering a steel cage according to claim 3, It is characterized in that The sub-support comprises: a first support rod (112), a second support rod (113) and a third support rod (114); the first support rod (112) is vertically fixed to the support bottom plate (111), and the rotation axis (12) is fixed to the first support rod (112); one end of the second support rod (113) and the third support rod (114) are both fixed to the support bottom plate (111), and the other end is both fixed to the first support rod (112); the second support rod (113), the third support rod (114) and the support bottom plate (111) present a triangular structure.
5. The positioning auxiliary structure during the lowering process of the steel cage according to claim 1, It is characterized in that The outer periphery of the roller (13) is coated with a frosted anti-slip layer (14).
6. The positioning auxiliary structure during the lowering of the steel cage according to claim 1, It is characterized in that It also includes a plurality of groups of buffer assemblies corresponding one to one to each group of the roller assemblies, the buffer assemblies including mounting steel bars (21) and elastic members (22), the mounting steel bars (21) being fixedly mounted on the steel cage, the mounting frame (11) being rotatably connected to the mounting steel bars (21), and the elastic member (22) being located between the mounting frame (11) and the mounting steel bars (21).
7. A positioning auxiliary structure for lowering a reinforcement cage according to claim 6, It is characterized in that A limit block (23) is provided on the installation steel bar (21), and the limit block (23) is located between the installation frame (11) and the installation steel bar (21).
8. The positioning auxiliary structure for lowering the steel cage according to claim 7, It is characterized in that A buffer pad (231) is provided at one end of the limit block (23) facing the mounting frame (11).
9. The positioning auxiliary structure for lowering a steel cage according to claim 6, It is characterized in that The invention also comprises a plurality of monitoring components corresponding to each group of the roller components, the monitoring components comprising: a pressure gauge (31), an information processing unit (32), a red indicator light (33) and a green indicator light (34); the pressure gauge (31) is arranged between the installation steel bar (21) and the elastic member (22); the information processing unit (32) is arranged on the installation steel bar (21); the red indicator light (33) and the green indicator light (34) are arranged on the installation frame (11); the pressure gauge (31), the red indicator light (33) and the green indicator light (34) are electrically connected to the information processing unit (32); the information processing unit (32) controls the lighting and extinguishing of the red indicator light (33) and the green indicator light (34) according to the pressure value detected by the pressure gauge (31).
10. The positioning auxiliary structure for lowering a reinforcement cage according to claim 6, It is characterized in that The installation steel bar (21) is fixedly mounted on the longitudinal bars of the steel cage along the axial direction of the steel cage, and a steel bar axial force meter (35) is mounted on the installation steel bar (21).