Basement drainage pressure reduction anti-floating structure
By designing a hydrophobic well structure and a water collecting well structure in the basement, combining sand-free concrete pipe wells and medium-coarse sand backfilter layer, rapid hydrophobic and automatic transport of groundwater is achieved, and the cost and efficiency of existing floating-resistant designs is solved. The problem has reduced the engineering cost and realized the secondary utilization of groundwater.
Patent Information
- Application Number
- CN202420040352.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-01-05
AI Technical Summary
The existing anti-float design method has high cost for ultra-deep basement structures and is difficult to effectively and quickly discharge groundwater. In particular, the blind ditch drainage method has insufficient engineering cost and efficiency.
Design a basement drainage reduction and anti-floating structure including a hydrophobic well structure, a water collection well structure and a drainage system. Through the combination of sand-free concrete pipe well and a medium-coarse sand filter layer, the rapid hydrophobic and automatic transport of groundwater is achieved, combined with a submersible pump. Secondary use of groundwater.
It realizes the rapid and effective discharge of groundwater, reduces engineering costs, improves economic benefits, and reduces manual operations through automated systems, and has green and environmentally friendly secondary utilization functions.
Smart Images

Figure CN221989402U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of groundwater anti-floating structures, in particular to a basement drainage decompression anti-floating structure. Background Art
[0002] There are four main anti-floating design methods for building structures with basements: counterweight method, blind ditch drainage method, pull-out pile method and anti-floating anchor rod. For ultra-deep basement structures, due to the high anti-floating requirements of the basement, the cost of using the counterweight method, pull-out pile and anti-floating anchor rod is relatively high. Comprehensively consider the project characteristics, geological conditions, site conditions and environmental factors. Now it is necessary to propose an anti-floating structure that uses active anti-floating technology to drain and decompress water, and optimize the existing blind ditch drainage method. Utility Model Content
[0003] In view of the technical problems existing in the prior art, the purpose of the utility model is to provide a basement drainage pressure-reducing and anti-floating structure to quickly discharge groundwater.
[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0005] A basement drainage pressure-reducing and anti-floating structure comprises a basement structure, a drain well structure, a water collecting well structure, a water delivery structure and a drainage system; a well pit is arranged under the bottom plate of the waterproof basement structure, and a water-permeable drain well structure is arranged in the well pit; the drain well structure comprises a crushed stone cushion layer, a medium-coarse sand filter layer and a sandless concrete pipe well, the crushed stone cushion layer is laid on the bottom of the well pit, the tubular sandless concrete pipe well is placed on the crushed stone cushion layer, a medium-coarse sand filter layer is laid on the bottom of the sandless concrete pipe well, and the outer wall of the sandless concrete pipe well is wrapped by the medium-coarse sand filter layer; a water collecting well is arranged in the water collecting well structure; the water delivery structure is arranged between the sandless concrete pipe well and the water collecting well to transport the water in the sandless concrete pipe well to the water collecting well; the drainage system is connected to the water collecting well.
[0006] As a preferred embodiment, the upper end of the sandless concrete pipe well is connected to an inspection port, which penetrates upward through the bottom plate of the basement structure; the drain well structure also includes a steel grille cover plate, which is installed to cover the upper end of the inspection port.
[0007] As a preferred embodiment, the bottom plate of the basement structure includes a crushed stone hydrophobic layer, a geomembrane, a plain concrete cushion layer, a reinforced concrete bottom plate, and a decoration layer, which are arranged in sequence from bottom to top.
[0008] As a preference, the gravel drain layer extends to the well pit and wraps around the periphery of the drain well structure.
[0009] As a preferred embodiment, the sandless concrete pipe well is a prefabricated structure, including multiple ring wells, each of which is arranged in sequence up and down; the ring well includes four equally divided fan-shaped rings, or includes two equally divided semicircular rings, or is a circular ring. After adopting this structure, the appropriate ring well splicing structure can be selected according to the actual construction situation to better adapt to different basement structures.
[0010] As a preferred embodiment, when the ring well is a structure composed of four equally divided fan-shaped rings or two semicircular rings, joints are formed between adjacent fan-shaped rings or adjacent semicircular rings, and the joints of upper and lower adjacent ring wells are staggered.
[0011] As a preferred embodiment, the water supply structure includes a drainage pipe, a water outlet is opened on the side wall of the sandless concrete pipe well, a water inlet is arranged on the side wall of the water collection well, the water outlet is higher than the water inlet, the drainage pipe connects the water outlet and the water inlet, and the drainage pipe is arranged obliquely.
[0012] As a preferred embodiment, screens are provided at the drain pipe ports at the water inlet and the water outlet. After adopting this structure, the screens prevent mud and sand from clogging the drain pipe.
[0013] As a preference, the drainage system comprises a submersible pump, which is located at the bottom of the sump.
[0014] As a preferred embodiment, the basement drainage pressure-reducing and anti-floating structure further includes a water reservoir outside the building structure, and the drainage system is arranged between the water collection well and the water reservoir outside the building structure.
[0015] The principle of the utility model is:
[0016] A waterproof basement structure is set up, and a permeable drainage well structure is set up in the basement structure area. The groundwater in the area will be discharged through the drainage well structure, and transported to the water collection well structure for storage through the water delivery structure, and finally discharged through the drainage system. The utility model also optimizes the design of the drainage well structure and the basement structure.
[0017] The utility model utilizes the good drainage performance of sandless concrete. Groundwater seeps into the sandless concrete pipe well. The inclined drainage pipe automatically collects the accumulated water in the sandless concrete pipe well into the collection well, and then discharges it to the water storage tank outside the building structure through a submersible pump. Finally, the water in the water storage tank outside the building structure is used for garden watering or other secondary utilization, and has the function of automatically balancing groundwater utilization.
[0018] The utility model has the following advantages:
[0019] 1. The drainage well structure is optimized and designed as a large-volume well-type drainage structure. The entire side wall and bottom can drain water, so the drainage surface is larger and the water can be quickly and effectively discharged.
[0020] 2. In the drainage well structure, a medium-coarse sand filter layer is set up, which is not only used as a filter layer, but also can be integrated with the sandless concrete pipe well structure to form a well structure. The setting of this structure makes it possible to prefabricate the sandless concrete pipe well, which is conducive to simplifying the construction process.
[0021] 3. The drainage and pressure reduction of the utility model based on the well-type drain structure can greatly reduce costs and greatly improve economic benefits compared with traditional anti-pullout bored piles.
[0022] 4. Use the intelligent pumping function of the submersible pump to collect groundwater and reduce the uplift pressure on the basement floor. At the same time, further use groundwater for greening water, highlighting the concept of green environmental protection.
[0023] 5. The application scope of the utility model is mainly to basement structures with high groundwater levels, such as high-rise and super-high-rise building structures, as well as structures where anti-floating requirements are difficult to meet or traditional anti-floating methods are too expensive, to solve the anti-floating problem of basements.
[0024] 6. The basement drainage pressure-reducing and anti-floating structure can automatically collect and discharge groundwater without manual assistance and has a high degree of automation.
[0025] 7. An inspection port is set up to regularly inspect and maintain the drain well structure.
[0026] 8. The inclined drainage pipe has a slope, which can automatically transport the accumulated water in the sandless concrete pipe well to the collection well. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is the structural schematic diagram of the basement drainage decompression and anti-floating structure.
[0028] Figure 2 for Figure 1 Enlarged view of area A.
[0029] Figure 3 Top view of the anti-floating structure for basement drainage pressure relief.
[0030] Figure 4 This is a bird's-eye view of the ring well formed by four equally divided fan-shaped rings.
[0031] Figure 5 Reason Figure 4 Main view of the sandless concrete pipe shaft with staggered overlapping ring shafts.
[0032] Figure 6 for Figure 4 A cross-sectional view of a sector ring.
[0033] Figure 7 for Figure 6 BB cross-sectional view.
[0034] Among them, 1 is a crushed stone drainage layer; 2 is a geomembrane; 3 is a plain concrete cushion layer; 4 is a reinforced concrete base plate; 5 is a decoration layer; 6 is a steel grille cover; 7 is a crushed stone cushion layer; 8 is a medium-coarse sand filter layer; 9 is a sandless concrete pipe well; 10 is a drainage pipe; 11 is a screen; 12 is a submersible pump; 13 is a water collection well; 14 is a vertical closed stirrup; 15 is a horizontal closed stirrup. DETAILED DESCRIPTION
[0035] The present invention will be further described in detail below in conjunction with specific implementation methods.
[0036] A basement drainage pressure-reducing and anti-floating structure comprises a basement structure, a drain well structure, a water collecting well structure, a water delivery structure and a drainage system; a well pit is arranged under the bottom plate of the waterproof basement structure, and a water-permeable drain well structure is arranged in the well pit; the drain well structure comprises a crushed stone cushion layer, a medium-coarse sand filter layer and a sandless concrete pipe well, the crushed stone cushion layer is laid on the bottom of the well pit, the tubular sandless concrete pipe well is placed on the crushed stone cushion layer, a medium-coarse sand filter layer is laid on the bottom of the sandless concrete pipe well, and the outer wall of the sandless concrete pipe well is wrapped by the medium-coarse sand filter layer; a water collecting well is arranged in the water collecting well structure; the water delivery structure is arranged between the sandless concrete pipe well and the water collecting well to transport the water in the sandless concrete pipe well to the water collecting well; the drainage system is connected to the water collecting well.
[0037] The upper end of the sandless concrete pipe well is connected to an inspection port, which passes through the bottom plate of the basement structure upward; the drain well structure also includes a steel grille cover plate, which is installed to cover the upper end of the inspection port.
[0038] The bottom plate of the basement structure includes a crushed stone drainage layer, a geomembrane, a plain concrete cushion layer, a reinforced concrete bottom plate, and a decoration layer, which are arranged in sequence from bottom to top.
[0039] The crushed stone drain layer extends to the well pit and wraps around the periphery of the drain well structure.
[0040] The sandless concrete pipe shaft is a prefabricated structure, including multiple ring shafts, which are arranged in sequence up and down; according to the actual hoisting conditions of the construction, the ring shaft includes four equally divided fan-shaped rings, or two equally divided semicircular rings, or one circular ring.
[0041] When the ring well is a structure of four equally divided sector rings or two semicircular rings, joints are formed between adjacent sector rings or adjacent semicircular rings, and the joints of upper and lower adjacent ring wells are staggered. Annular seams are formed between upper and lower adjacent ring wells, and the joints and annular seams are built with M7.5 cement mortar. The sandless concrete pipe well reserves a water outlet at an appropriate position according to the needs of the project. The ring well of this embodiment is composed of four equally divided sector rings, and the sandless concrete pipe well consists of 4 ring wells.
[0042] The water supply structure includes a drainage pipe, a water outlet is opened on the side wall of the sandless concrete pipe well, a water inlet is arranged on the side wall of the water collection well, the water outlet is higher than the water inlet, the drainage pipe connects the water outlet and the water inlet, and the drainage pipe is inclined so that the drainage pipe is placed on a slope.
[0043] Screens are provided at the drain pipe ports at the water inlet and the water outlet.
[0044] The drainage system includes a submersible pump, which is located at the bottom of the sump.
[0045] The crushed stone cushion layer of the drainage well structure freely infiltrates groundwater; the medium-coarse sand filter layer further infiltrates groundwater into the sandless concrete pipe well; the crushed stone drainage layer and the medium-coarse sand filter layer can collect groundwater from different areas into the sandless concrete pipe well through infiltration. The sandless concrete pipe well has large pores and high water permeability, which is conducive to the infiltration of groundwater.
[0046] The sandless concrete pipe well is a hollow cylinder, the diameter of which is set according to the groundwater capacity, preferably φ1600mm in this embodiment, and the wall thickness is 300mm; the diameter of the steel grille cover is set according to requirements, preferably φ800mm in this embodiment. The diameter of the inspection port is not less than 800mm.
[0047] The gravel drainage layer of the basement structure is composed of gravel, and groundwater is infiltrated through the gaps between the gravel; the geomembrane and plain concrete cushion layer can prevent groundwater from corroding the steel bars of the reinforced concrete floor and protect the reinforced concrete floor structure; the decoration layer is a structural layer built according to user needs to meet the functional requirements.
[0048] The ring shaft is made of sandless concrete and steel bars. Sandless concrete is made of cement, water and coarse aggregate; the cement is 42.5 ordinary Portland cement; the coarse aggregate is 10mm-20mm single-size crushed stone, and the content of needle-like particles is strictly controlled. The ratio of cement, water and coarse aggregate is 1:0.3:6, the porosity is 15%-25%, and the permeability coefficient is 0.3cm / s. Sandless concrete needs to be stirred during production, and the stirring method is cement wrapping method, that is, all the crushed stones and 1%-3% of water are first loaded into the mixer for pre-mixing, and then cement is added to mix to form a cement slurry shell that wraps the surface of the crushed stones, and finally the remaining water is added to mix evenly. Sandless concrete should be sampled and made into test blocks, and water seepage and strength tests should be carried out after curing. The steel bars are closed stirrups, which include vertical closed stirrups and transverse closed stirrups. A fan-shaped ring includes 7 vertical C12 closed stirrups and 3 transverse C12 closed stirrups. The specific distribution of the closed stirrups is as follows Figure 6 and Figure 7 As shown in the reinforcement diagram.
[0049] The crushed stone water-repellent layer and the crushed stone cushion layer are both composed of crushed stone. The crushed stone grading ratio is: 0-5mm particle size accounts for 10%; 5-10mm particle size accounts for 30%; 10-20mm particle size accounts for 30%; 20-30mm particle size accounts for 30%. The thickness of the crushed stone water-repellent layer after compaction should not be less than 500mm.
[0050] The medium-coarse sand filter layer should be screened out to remove fine materials below 0.2 mm before use.
[0051] The water collection well is formed by hollowing out the inside of the reinforced concrete bottom plate. The cross-section of the water collection well is square, with a cross-sectional size of 1.5m×1.5m and a depth of 2.5m.
[0052] There are two submersible pumps in the water collection well. The power is determined according to the drainage requirements. The water discharge capacity of the submersible pump is not less than 20m 3 / Hour.
[0053] The diameter of the drainage pipe is selected according to the drainage requirements. In this embodiment, it is preferably φ200mm. In this embodiment, there are multiple drainage well structures. The drainage pipes are distributed in the entire basement structure to drain all groundwater in the sandless concrete pipe wells into the collection wells. The drainage pipes are PVC drainage pipes.
[0054] The basement drainage pressure-reducing and anti-floating structure also includes a water storage tank outside the building structure, and the drainage system is arranged between the water collection well and the water storage tank outside the building structure.
[0055] The groundwater pumped from the collection well can be used for garden irrigation or other secondary uses.
[0056] A method for preparing a basement drainage pressure-reducing anti-floating structure comprises the following steps:
[0057] Step 1: When constructing the basement, first use an excavator to dig out a hole-shaped well pit as a drainage well structure and a water collection well structure in the later stage;
[0058] Step 2: Before laying the gravel drainage layer, the gravel should be washed to make its mud content no more than 1%; remove the softened topsoil on the pit surface, and backfill the medium-coarse sand filter layer to the bottom elevation of the gravel drainage layer;
[0059] Step 3: Before installing the sandless concrete pipe well, first apply a crushed stone cushion layer on the bottom of the well pit to level the ground; after the positioning of the sandless concrete pipe well is completed, apply a medium-coarse sand filter layer on the inner bottom and outside the well ring of the sand concrete pipe well, and at the same time reserve a water outlet channel at the corresponding outlet of the medium-coarse sand filter layer;
[0060] Step 4: After the basement foundation is leveled and compacted, a crushed stone drainage layer is filled around the drainage well structure in the well pit; when the crushed stone drainage layer of the basement structure is constructed, drainage pipes are arranged;
[0061] Step 5: Construct the basement structure and water collection well structure. When laying the reinforced concrete base plate and the decoration layer, reserve a hole with a diameter of 800mm at the top of the sandless concrete pipe well as the inspection port of the sandless concrete pipe well; hollow out the reinforced concrete base plate to make a water collection well; connect one end of the drainage pipe to the water outlet of the sandless concrete pipe well and the other end to the water inlet of the water collection well, and install screens at the ends of the drainage pipes; install a submersible pump in the water collection well; and connect the outlet of the submersible pump to the water reservoir outside the building structure.
[0062] A drainage method for a basement drainage pressure-reducing and anti-floating structure: when the groundwater level rises, the groundwater first passes through the crushed stone cushion layer, then penetrates through the medium-coarse sand filter layer into the sandless concrete pipe well, and then when the water level rises to the bottom elevation of the drainage pipe at the outlet, the drainage pipe uses its own slope to transport the groundwater to the water collection well, and the water level in the water collection well rises. When the water level in the water collection well is higher than the bottom elevation of the drainage pipe at the water inlet, the submersible pump starts to pump water out, and when the water level in the water collection well is 0.2m high, the submersible pump stops pumping water.
[0063] The above embodiments are preferred implementation modes of the present invention, but the implementation modes of the present invention are not limited by the above embodiments. Any other changes, modifications, substitutions, combinations, and simplifications that do not deviate from the spirit and principle of the present invention should be equivalent replacement methods and are included in the protection scope of the present invention.
Claims
1. A basement drainage pressure reduction anti-floating structure, characterized by: It includes a basement structure, a drain well structure, a water collecting well structure, a water delivery structure and a drainage system; a well pit is provided under the bottom plate of the waterproof basement structure, and a permeable drain well structure is arranged in the well pit; the drain well structure includes a crushed stone cushion layer, a medium-coarse sand filter layer and a sandless concrete pipe well, the crushed stone cushion layer is laid on the bottom of the well pit, the tubular sandless concrete pipe well is placed on the crushed stone cushion layer, a medium-coarse sand filter layer is laid on the bottom of the sandless concrete pipe well, and the outer wall of the sandless concrete pipe well is wrapped by the medium-coarse sand filter layer; a water collecting well is arranged in the water collecting well structure; the water delivery structure is arranged between the sandless concrete pipe well and the water collecting well to transport the water in the sandless concrete pipe well to the water collecting well; the drainage system is connected to the water collecting well.
2. A basement drainage decompression anti-floating structure according to claim 1, characterized in that: The upper end of the sandless concrete pipe well is connected to an inspection port, which passes through the bottom plate of the basement structure upward; the drain well structure also includes a steel grille cover plate, which is installed to cover the upper end of the inspection port.
3. A basement drainage decompression anti-floating structure according to claim 1, characterized in that: The bottom plate of the basement structure includes a crushed stone drainage layer, a geomembrane, a plain concrete cushion layer, a reinforced concrete bottom plate, and a decoration layer, which are arranged in sequence from bottom to top.
4. A basement drainage decompression anti-floating structure according to claim 3, characterized in that: The crushed stone drain layer extends to the well pit and wraps around the periphery of the drain well structure.
5. A basement drainage decompression anti-floating structure according to claim 1, characterized in that: The sandless concrete pipe shaft is a prefabricated structure, including a plurality of ring shafts, each of which is arranged in sequence up and down; the ring shaft includes four equally divided fan-shaped rings, or two equally divided semicircular rings, or is a circular ring.
6. A basement drainage decompression anti-floating structure according to claim 5, characterized in that: When the ring well is a structure of four equally divided fan-shaped rings or two semicircular rings, joints are formed between adjacent fan-shaped rings or adjacent semicircular rings, and the joints of upper and lower adjacent ring wells are staggered.
7. A basement drainage decompression anti-floating structure according to claim 1, characterized in that: The water supply structure includes a drainage pipe, a water outlet is opened on the side wall of the sandless concrete pipe well, a water inlet is arranged on the side wall of the water collection well, the water outlet is higher than the water inlet, the drainage pipe connects the water outlet and the water inlet, and the drainage pipe is arranged obliquely.
8. A basement drainage pressure-reducing and anti-floating structure according to claim 7, characterized in that: Screens are provided at the drain pipe ports at the water inlet and the water outlet.
9. A basement drainage decompression anti-floating structure according to claim 1, characterized in that: The drainage system includes a submersible pump, which is located at the bottom of the sump.
10. A basement drainage pressure-reducing and anti-floating structure according to claim 1, characterized in that: It also includes an external water storage tank of the building structure, and the drainage system is arranged between the water collection well and the external water storage tank of the building structure.