Stranded rope controller of pipeline dredging device
By designing a winch controller for a pipe dredging device, the position of the winch is adjusted using guide wheels and limit pins, which solves the problem of poor dredging effect of existing devices, achieves the stability of the winch in the center of the pipe, and improves dredging efficiency.
Patent Information
- Application Number
- CN202420928646.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-30
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-04-30
AI Technical Summary
Existing pipe dredging devices cannot ensure that the cable is centered in the pipe when using steel cable to pull the dredging disc, resulting in poor dredging effect.
A winch controller for a pipe dredging device was designed, including a positioning frame, a locking frame, an assembly pole, a guide wheel, and a limit pin. By adjusting the position of the guide wheel, the winch can be aligned with the center of the pipe, and the limit pin is used to prevent the winch from detaching.
This design ensures the rope remains centered in the pipe, improving the effectiveness of pipe dredging and making it particularly suitable for dredging urban sewer pipes of different diameters.
Smart Images

Figure CN221989540U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a twisted rope controller for a pipeline dredging device, belonging to the technical field of pipeline dredging equipment. Background Art
[0002] In the field of municipal engineering, urban pipelines, especially sewer pipes, need to be frequently unblocked to ensure smooth flow of the pipelines. There are many existing municipal pipeline dredging equipment, such as the commonly used pipeline dredging equipment, such as a mechanical traction dredging machine disclosed in the utility model patent with the authorization announcement number CN216865422U, which uses a steel cable to pull the dredging disc from the inside of the pipeline to complete the pipeline dredging work. Although the existing pipeline dredging equipment can meet the needs of municipal pipeline dredging to a certain extent, due to the characteristics of different diameters of urban dredging pipelines, when the existing dredging device moves forward by pulling the dredging disc with a steel cable, the steel cable cannot ensure that it is in the center of the pipeline, which leads to the problem of poor dredging effect when the existing pipeline dredging device is used for pipeline dredging. Therefore, it is necessary to develop a new rope controller to solve the above problems of the existing dredging device. Summary of the invention
[0003] The purpose of the utility model is to provide a rope controller for a pipeline dredging device which has a compact structure and an ingenious design so as to solve the problem of poor dredging effect of the existing pipeline dredging devices.
[0004] The technical solution of the utility model is:
[0005] A rope controller for a pipeline dredging device, comprising a positioning frame, a locking frame, an assembly pole, a guide wheel and a limit pin; the characteristics are: the positioning frame is equipped with an assembly pole; the lower end of the assembly pole is provided with a mounting fork; the mounting fork is equipped with a guide wheel; the mounting fork below the guide wheel is equipped with a limit pin; the locking frame is equipped on the assembly pole above the guide wheel.
[0006] The positioning frame comprises a tripod, a sliding sleeve, an intermediate crossbar and a locking screw; the middle of the tripod is fixedly provided with the intermediate crossbar; the center of the intermediate crossbar is fixedly provided with the sliding sleeve; and a locking screw is provided on one side of the sliding sleeve.
[0007] The tripod is an equilateral triangle structure.
[0008] The locking frame includes a sliding sleeve, a supporting sleeve, a telescopic rod, a locking screw and an adjusting screw; the sliding sleeve is installed on the assembly vertical rod; the locking screw is installed on the surface of the sliding sleeve; the supporting sleeves are symmetrically fixed on both sides of the sliding sleeve; the telescopic rod is slidably installed in the supporting sleeve; and the adjusting screw is installed on the supporting sleeve.
[0009] The advantages of the utility model are:
[0010] The rope controller of the pipe dredging device has a compact structure and ingenious design. It can adjust the position of the guide wheel so that the rope of the pipe dredging device can correspond to the center of the pipe after passing through the guide wheel, thereby solving the problem of poor dredging effect of existing pipe dredging devices and is particularly suitable for the needs of pipe dredging. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a structural schematic diagram of the utility model;
[0012] Figure 2 This is a schematic diagram of the structure of the positioning frame of the utility model;
[0013] Figure 3 for Figure 1 A schematic diagram of the enlarged structure at A in the middle;
[0014] Figure 4 for Figure 3 Schematic diagram of the left view structure;
[0015] Figure 5 It is a schematic diagram of the working state structure of the utility model.
[0016] In the figure: 1. Positioning frame; 2. Assembly pole; 3. Installation fork; 4. Guide wheel; 5. Limit pin; 6. Locking frame; 7. Tripod; 8. Middle cross bar; 9. Sliding sleeve; 10. Locking screw; 11. Sliding sleeve; 12. Locking screw; 13. Support sleeve; 14. Telescopic rod; 15. Adjustment screw; 16. Well ring. DETAILED DESCRIPTION
[0017] The rope controller of the pipeline dredging device includes a positioning frame 1, a locking frame 6, an assembly pole 2, a guide wheel 4 and a limit pin 5 (see the attached manual). Figure 1 ).
[0018] The positioning frame 1 includes a tripod 7, a sliding sleeve 9, an intermediate crossbar 8 and a locking screw 10; the middle of the tripod 7 is fixedly mounted with the intermediate crossbar 8; the center of the intermediate crossbar 8 is fixedly mounted with the sliding sleeve 9; one side of the sliding sleeve 9 is equipped with a locking screw 10 (see the attached manual Figure 2 ). The tripod 7 is an equilateral triangle structure (see the attached Figure 2 ).
[0019] The purpose of arranging the tripod 7 in this way is to enable the sharp corner of the tripod 7 to be just engaged with the well ring 16 of the sewer well mouth during operation.
[0020] The assembly pole 2 is slidably mounted on the positioning frame 1 through the sliding sleeve 9; when the locking screw 10 is tightened, the locking screw 10 can fix the sliding sleeve 9 and the assembly pole 2 into a whole. When the locking screw 10 is loosened, the assembly pole 2 can maintain a sliding connection with the sliding sleeve 9, and the purpose of adjusting the height of the assembly pole 2 can be achieved.
[0021] The lower end of the assembly pole 2 is provided with an installation fork 3; a guide wheel 4 is installed in the installation fork 3; a limit pin 5 is installed in the installation fork 3 below the guide wheel 4 (see the attached manual). Figure 3 and 4 The purpose of setting the guide wheel 4 and the limit pin 5 is to enable the rope of the pipeline dredging device to move under the guidance of the guide wheel 4 during operation. During this process, the limit pin 5 will limit the rope to prevent the rope from escaping from the installation fork 3.
[0022] A locking frame 6 is mounted on the assembly pole 2 above the guide wheel 4 (see the attached manual). Figure 1 The locking frame 6 includes a sliding sleeve 11, a supporting sleeve 13, a telescopic rod 14, a locking screw 12 and an adjusting screw 15 (see the attached manual). Figure 1 ).
[0023] A sliding sleeve 11 is mounted on the assembly pole 2. The sliding sleeve 11 is slidably connected to the assembly pole 2. A locking screw 12 is mounted on the surface of the sliding sleeve 11; when the locking screw 12 is tightened, the sliding sleeve 11 and the assembly pole 2 can be fixedly connected.
[0024] The two sides of the sliding sleeve 11 are symmetrically fixed with support sleeves 13; a telescopic rod 14 is slidably installed in the support sleeve 13; an adjustment screw 15 is installed on the support sleeve 13 (see the attached manual Figure 1 ). When the adjusting screw 15 is tightened, the support sleeve 13 and the adjusting screw 15 can be kept fixedly connected.
[0025] When the rope controller of the pipeline dredging device is working, the positioning frame 1 is first placed on the well ring 16 of the water well head (see the attached manual). Figure 5 ). Then loosen the locking screw 10 and adjust the assembly pole 2; when the lower edge of the guide wheel 4 is in the same straight line with the center of the urban pipeline, tighten the locking screw 10.
[0026] After the above work is completed, loosen the locking screw 12 and then adjust the locking frame 6 to a suitable position. Then loosen the adjustment screw 15, and then pull the telescopic rod 14 out of the inside of the support sleeve 13 for a distance, so that the telescopic rod 14 contacts the wall of the sewer, and then lock the adjustment screw 15. At this time, under the action of the locking frame 6, the assembly stand 2 will maintain a fixed position with the sewer, so that the rope controller can be fixed inside the sewer. Then, pass the rope of the pipeline dredging device from the bottom of the guide wheel 4 and connect it to the dredging disk in the pipeline. In this way, the rope controller can always control the rope of the pipeline dredging device at the center of the pipeline, thereby solving the problem of poor dredging effect of the existing pipeline dredging device.
[0027] The rope controller of the pipe clearing device has a compact structure and ingenious design. It can adjust the position of the guide wheel 4 so that the rope of the pipe clearing device can correspond to the center of the pipe after passing through the guide wheel 4, thereby solving the problem of poor clearing effect of the existing pipe clearing device and being particularly suitable for the needs of pipe clearing.
Claims
1. A rope controller for a pipeline dredging device, comprising a positioning frame (1), a locking frame (6), an assembly pole (2), a guide wheel (4) and a limit pin (5); characterized in that: The positioning frame (1) is provided with an assembly pole (2); a mounting fork (3) is provided at the lower end of the assembly pole (2); a guide wheel (4) is installed in the mounting fork (3); a limit pin (5) is installed in the mounting fork (3) below the guide wheel (4); and a locking frame (6) is installed on the assembly pole (2) above the guide wheel (4).
2. A rope controller for a pipeline dredging device according to claim 1, characterized in that: The positioning frame (1) comprises a tripod (7), a sliding sleeve (9), an intermediate crossbar (8) and a locking screw (10); the middle of the tripod (7) is fixedly mounted with the intermediate crossbar (8); the center of the intermediate crossbar (8) is fixedly mounted with the sliding sleeve (9); and the locking screw (10) is mounted on one side of the sliding sleeve (9).
3. A rope controller for a pipeline dredging device according to claim 2, characterized in that: The tripod (7) is in the form of an equilateral triangle.
4. A rope controller for a pipeline dredging device according to claim 2, characterized in that: The locking frame (6) comprises a sliding sleeve (11), a supporting sleeve (13), a telescopic rod (14), a locking screw (12) and an adjusting screw (15); the sliding sleeve (11) is mounted on the assembly vertical rod (2); the locking screw (12) is mounted on the surface of the sliding sleeve (11); the supporting sleeves (13) are symmetrically fixed on both sides of the sliding sleeve (11); the telescopic rod (14) is slidably mounted in the supporting sleeve (13); and the adjusting screw (15) is mounted on the supporting sleeve (13).