Prefabricated joint of assembly type steel secondary beam

By using a combined structure of a tension spring and a limit baffle in the node device, the elastic force of the tension spring can be used to achieve internal extrusion and rapid docking of the butt screw, the problem of the docking hole position alignment in the prior art is solved, and the problem of the trouble of docking hole position alignment in the prior art is improved Assembly efficiency.

CN221989565UActive Publication Date: 2024-11-12上海杨浦建筑设计有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420551851.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-20
Publication Date
2024-11-12
Estimated Expiration
2034-03-20

AI Technical Summary

Technical Problem

The hole position alignment of existing prefabricated steel sub-beam prefabricated nodes is troublesome when docking, resulting in insufficiency of installation.

Method used

Using node device, there are slots at both ends of the top and bottom, and a perforation and docking screw are provided in the middle. The screw is equipped with a pulling spring with a pulling spring on the outside sleeve. The limit baffle is welded with the node device. The inner extrusion of the docking screw is achieved through the elastic force of the pulling spring. Connect with quick docking and with fixing nuts.

Benefits of technology

It improves the docking efficiency, simplifies the docking process, solves the problem of difficulty in alignment of holes, and realizes the rapid connection between the main beam and the secondary beam.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989565U_ABST
    Figure CN221989565U_ABST
Patent Text Reader

Abstract

The utility model discloses a prefabricated joint of an assembly type steel secondary beam, relates to the technical field of assembly type steel buildings, solves the problem that hole position alignment is troublesome when the prefabricated joint is in butt joint with mounting screw holes through screws, and comprises a main beam, a secondary beam and a joint device arranged between the main beam and the secondary beam. According to the utility model, the tension spring is sleeved outside the butt-joint screw rod, under the elastic action of the tension spring, when the main beam and the secondary beam are in butt joint, the butt-joint screw rod can be extruded inwards, only the secondary beam needs to be placed on the inner side of the main beam to slide, and when the butt-joint screw rod reaches the position of the butt-joint hole, the butt-joint screw rod can be extruded inwards. Under the elastic action of the tension spring, the butt joint screw rod can be directly pushed to penetrate into the butt joint hole, rapid butt joint of the butt joint screw rod and the butt joint hole is achieved, after the butt joint screw rod penetrates through the butt joint hole, the main beam and the secondary beam can be connected through the fixing nut, and the butt joint efficiency is improved; the problem that hole position alignment is troublesome during butt joint due to the fact that a simple bolt and screw hole structure is used is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of assembled steel buildings, in particular to a prefabricated node of an assembled steel secondary beam. Background Art

[0002] Steel secondary beam is a beam arranged horizontally in the steel structure, usually between the main beam and the plate arch. The main beam is one of the main components that bear the load of the floor slab and cantilever beam, while the plate arch plays the role of stabilizing the floor slab. The steel secondary beam plays the role of strengthening and supporting between the two. The prefabricated node of the steel secondary beam is to set the node at the intersection of the steel secondary beam to play a connecting role.

[0003] The Chinese utility model (Announcement No.: CN219411222U) discloses an installation node of a prefabricated secondary beam and a cast-in-place concrete main beam, comprising a cast-in-place concrete main beam and a prefabricated secondary beam; the two are installed by installing bolts. When the number of prefabricated secondary beams is one, the screw of the installation bolt is first buried in the cast concrete of the main beam, and then the installation screw hole on the installation plate of the prefabricated secondary beam is aligned with the screw and the nut or nut is tightened.

[0004] Since the cast-in-place concrete main beam and the prefabricated secondary beam are connected by installing bolts, and then the secondary beam mounting screw holes are aligned from the side and the screws are inserted, and the steel secondary beam is usually long, and both ends are installed using such prefabricated nodes, which makes it difficult to align the holes during docking. Therefore, a prefabricated node for assembled steel secondary beams is now proposed. Utility Model Content

[0005] In order to improve the problem that it is troublesome to align the holes when prefabricated nodes are butt-jointed by means of screw rods and screw holes, the utility model provides a prefabricated node of an assembled steel secondary beam.

[0006] The utility model provides a prefabricated node of an assembled steel secondary beam, which adopts the following technical solution:

[0007] A prefabricated node of an assembled steel secondary beam, comprising a main beam, a secondary beam mounted on the main beam, and a node device arranged between the main beam and the secondary beam for docking, wherein the middle parts of the top and bottom ends of the node device are provided with a card slot, and the node device is movably connected to the end of the secondary beam through the card slot, a through hole is provided in the middle part of the node device, and a docking screw is penetrated inside the through hole, a limit baffle is fixedly welded to the front end of the docking screw, and a tension spring is welded between the limit baffle and the node device, and a fixing nut is threadedly connected to the end of the docking screw away from the limit baffle;

[0008] A docking hole is provided in the middle of the main beam, and a plug is movably provided inside the docking hole.

[0009] By adopting the above technical solution, since a tension spring is sleeved on the outside of the docking screw, under the elastic force of the tension spring, when the main beam and the secondary beam are docked, the docking screw can be squeezed inward. It is only necessary to place the secondary beam on the inside of the main beam for sliding. When the docking screw reaches the position of the docking hole, the docking screw can be directly pushed into the docking hole under the elastic action of the tension spring, thereby realizing the rapid docking of the docking screw and the docking hole. After the docking screw passes through the docking hole, the main beam and the secondary beam can be connected by the fixing nut.

[0010] Optionally, two ends of the tension spring are respectively connected to a limit baffle and a node device, and a diameter of the limit baffle is larger than a diameter of the tension spring.

[0011] By adopting the above technical solution, the elastic force of the tension spring can be used to drive the docking screw to move forward and backward, and the limit baffle is used to connect the tension spring.

[0012] Optionally, the fixing nut is located on a side of the main beam away from the secondary beam, and the docking screw penetrates the through hole and the docking hole and is threadedly connected to the fixing nut.

[0013] By adopting the above technical solution, the fixing nut can be threadedly connected with the docking screw.

[0014] Optionally, node connection holes are provided on the left and right sides of the slot of the node device, and mounting screw holes matching the node connection holes are provided on the top and bottom ends of the secondary beam.

[0015] By adopting the above technical solution, the node connection holes and the mounting screw holes can facilitate the installation of the node device on the secondary beam, and the card slot can be directly clamped on the end of the secondary beam, which is convenient for positioning the node connection holes and the mounting screw holes.

[0016] Optionally, the internal thread of the mounting screw hole is connected with a mounting bolt, the mounting bolt passes through the node connection hole and is threadedly connected to the mounting screw hole, and the secondary beam is fixedly connected to the node device through the mounting bolt.

[0017] By adopting the above technical solution, the secondary beam and the node device can be connected by installing bolts.

[0018] Optionally, the sizes of the plug and the docking hole match each other.

[0019] By adopting the above technical solution, the plug can block the docking hole, and the plug can be removed only when needed.

[0020] Optionally, the diameter of the tension spring is larger than the diameter of the through hole, and the inner diameters of the through hole and the docking hole are both larger than the outer diameter of the docking screw.

[0021] By adopting the above technical solution, it is convenient for the butt joint screw to be smoothly inserted into the inside of the through hole and the butt joint hole.

[0022] In summary, the utility model has the following beneficial effects:

[0023] The utility model arranges a tension spring on the outside of the docking screw rod. Under the elastic force of the tension spring, when the main beam and the secondary beam are docked, the docking screw rod can be squeezed inwardly. It is only necessary to place the secondary beam on the inner side of the main beam for sliding. When the docking screw reaches the position of the docking hole, the docking screw rod can be directly pushed into the docking hole under the elastic action of the tension spring, so as to realize the rapid docking of the docking screw and the docking hole. After the docking screw passes through the docking hole, the main beam and the secondary beam can be connected by a fixing nut, thereby improving the docking efficiency and solving the problem of troublesome hole alignment during docking caused by using a simple bolt and screw hole structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the overall structure of the utility model.

[0025] Figure 2 It is a structural schematic diagram of the utility model when installed.

[0026] Figure 3 It is a structural schematic diagram of the node device of the utility model.

[0027] Figure 4 It is a structural schematic diagram of the utility model when the plug is separated from the main beam.

[0028] Description of reference numerals:

[0029] 1. Main beam; 2. Secondary beam; 3. Node device; 4. Docking hole; 5. Fixing nut; 6. Mounting bolt; 7. Mounting screw hole; 8. Plug; 9. Slot; 10. Through hole; 11. Node connection hole; 12. Docking screw; 13. Tension spring; 14. Limit baffle. DETAILED DESCRIPTION

[0030] The following is combined with Figure 1-4 This application is described in further detail.

[0031] Please refer to Figure 1-3 A prefabricated node of an assembled steel secondary beam comprises a main beam 1, a secondary beam 2 installed on the main beam 1, and a node device 3 arranged between the main beam 1 and the secondary beam 2 for docking. A card slot 9 is provided in the middle of both ends of the top and bottom of the node device 3, and the node device 3 is movably connected to the end of the secondary beam 2 through the card slot 9. A through hole 10 is provided in the middle of the node device 3, and a docking screw 12 is penetrated inside the through hole 10. A limit baffle 14 is fixedly welded at the front end of the docking screw 12, and a tension spring 13 is welded between the limit baffle 14 and the node device 3. After the secondary beam 2 is lifted, the secondary beam 2 is inserted into the main beam 1. At this time, the docking screw 12 is retracted inwardly into the through hole 10 and abuts against the main beam 1. At this time, the node device 3 of the secondary beam 2 can slide back and forth in the main beam 1.

[0032] The two ends of the tension spring 13 are respectively connected to the limit baffle 14 and the node device 3, and the diameter of the limit baffle 14 is larger than the diameter of the tension spring 13, the diameter of the tension spring 13 is larger than the diameter of the through hole 10, and the inner diameters of the through hole 10 and the docking hole 4 are both larger than the outer diameter of the docking screw 12. When the docking screw 12 reaches the position of the docking hole 4, the docking screw 12 can be directly pushed into the docking hole 4 under the elastic action of the tension spring 13, so as to realize the rapid docking of the docking screw 12 and the docking hole 4. The end of the docking screw 12 away from the limit baffle 14 is threadedly connected with a fixing nut 5, and the fixing nut 5 is located on the side of the main beam 1 away from the secondary beam 2, and the docking screw 12 passes through the through hole 10 and the docking hole 4 and is threadedly connected with the fixing nut 5. After the docking screw 12 passes through the docking hole 4, the fixing nut 5 is screwed on the outside of the docking screw 12, thereby connecting the main beam 1 and the secondary beam 2.

[0033] Reference Figure 3-4 , node device 3 is provided with node connection holes 11 on both sides of the card slot 9, and both ends of the top and bottom of the secondary beam 2 are provided with mounting screw holes 7 that match the node connection holes 11. The internal threads of the mounting screw holes 7 are connected with mounting bolts 6. The mounting bolts 6 pass through the node connection holes 11 and are threadedly connected with the mounting screw holes 7. The secondary beam 2 is fixedly connected to the node device 3 through the mounting bolts 6. Before the secondary beam 2 is docked, the node device 3 is first installed at the end of the secondary beam 2, and the card slot 9 on the node device 3 is inserted into the end of the secondary beam 2. The card slot 9 is just located in the H-shaped secondary beam 2. After the node device 3 is close to the secondary beam 2, the mounting screw holes 7 and the node connection holes 11 are aligned with each other, and the mounting screw holes 7 and the node connection holes 11 are connected by the mounting bolts 6 to achieve the connection between the secondary beam 2 and the node device 3.

[0034] A docking hole 4 is opened in the middle of the main beam 1, and a protrusion is set on the surface of the plug 8, and the sizes of the plug 8 and the docking hole 4 are adapted to each other. Only one docking hole 4 is retained on the main beam 1, and the other docking holes 4 are blocked by the plug 8. The plug 8 is only removed from the docking hole 4 at the position where the secondary beam 2 needs to be installed.

[0035] The implementation principle of the utility model is: before the secondary beam 2 is butt-jointed, the node device 3 is first installed at the end of the secondary beam 2, and the slot 9 on the node device 3 is inserted into the end of the secondary beam 2, the slot 9 is just located in the H-shaped secondary beam 2, and after the node device 3 is close to the secondary beam 2, the installation screw hole 7 and the node connection hole 11 are aligned with each other, and the installation screw hole 7 and the node connection hole 11 are connected by the installation bolt 6 to realize the connection between the secondary beam 2 and the node device 3.

[0036] After the secondary beam 2 is subsequently hoisted, the secondary beam 2 is inserted into the main beam 1. At this time, the docking screw 12 is retracted inwardly into the through hole 10 and abuts against the main beam 1. At this time, the node device 3 of the secondary beam 2 can slide back and forth in the main beam 1 until the docking screw 12 reaches the designated docking hole 4 position. Only one docking hole 4 is retained on the main beam 1, and the other docking holes 4 are blocked by the plug 8. The plug 8 is removed only from the docking hole 4 at the position where the secondary beam 2 needs to be installed.

[0037] When the docking screw 12 reaches the position of the docking hole 4, the docking screw 12 can be directly pushed into the docking hole 4 under the elastic action of the tension spring 13, thereby realizing the rapid docking of the docking screw 12 and the docking hole 4. After the docking screw 12 passes through the docking hole 4, the fixing nut 5 is screwed on the outside of the docking screw 12, thereby connecting the main beam 1 and the secondary beam 2.

[0038] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.

Claims

1. A prefabricated node of an assembled steel secondary beam, comprising a main beam (1), a secondary beam (2) mounted on the main beam (1), and a node device (3) arranged between the main beam (1) and the secondary beam (2) for butt connection, characterized in that: A slot (9) is provided in the middle of both the top and bottom ends of the node device (3), and the node device (3) is movably connected to the end of the secondary beam (2) through the slot (9); a through hole (10) is provided in the middle of the node device (3), and a docking screw (12) is passed through the through hole (10); a limit baffle (14) is fixedly welded to the front end of the docking screw (12), and a tension spring (13) is welded between the limit baffle (14) and the node device (3); and a fixing nut (5) is threadedly connected to one end of the docking screw (12) away from the limit baffle (14); A docking hole (4) is provided in the middle of the main beam (1), and a plug (8) is movably provided inside the docking hole (4).

2. The prefabricated node of an assembled steel secondary beam according to claim 1, characterized in that: The two ends of the tension spring (13) are respectively connected to a limit baffle (14) and a node device (3), and the diameter of the limit baffle (14) is greater than the diameter of the tension spring (13).

3. The prefabricated node of an assembled steel secondary beam according to claim 1, characterized in that: The fixing nut (5) is located on a side of the main beam (1) away from the secondary beam (2), and the docking screw rod (12) is threadedly connected to the fixing nut (5) after passing through the through hole (10) and the docking hole (4).

4. The prefabricated node of an assembled steel secondary beam according to claim 1, characterized in that: The node device (3) is provided with node connection holes (11) on both left and right sides of the slot (9), and the secondary beam (2) is provided with mounting screw holes (7) matching the node connection holes (11) at both top and bottom ends.

5. The prefabricated node of the assembled steel secondary beam according to claim 4, characterized in that: The internal thread of the mounting screw hole (7) is connected to a mounting bolt (6), the mounting bolt (6) passes through the node connection hole (11) and is threadedly connected to the mounting screw hole (7), and the secondary beam (2) is fixedly connected to the node device (3) via the mounting bolt (6).

6. The prefabricated node of an assembled steel secondary beam according to claim 1, characterized in that: The sizes of the plug (8) and the docking hole (4) are adapted to each other.

7. The prefabricated node of an assembled steel secondary beam according to claim 1, characterized in that: The diameter of the tension spring (13) is greater than the diameter of the through hole (10), and the inner diameters of the through hole (10) and the docking hole (4) are both greater than the outer diameter of the docking screw (12).