Connecting device for main frame of climbing frame

Through the design of the main frame connection device of the climbing frame, the sliding mechanism of the main slider and the secondary slider are combined with bolt fixing, the shaking problem caused by the inability to fix the pedestrian plate on the steel pipe frame is solved, and the stability and safety of the construction environment are achieved promote.

CN221989861UInactive Publication Date: 2024-11-12CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420473130.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-12
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In high-rise and super-high-rise buildings, the pedestrian board cannot be effectively fixed when constructing on steel pipe frames, causing the middle part to shake, resulting in an unsafe working environment for construction workers.

Method used

A main frame connecting device for climbing frame is designed, including the main clamping structure, the secondary clamping structure and reinforcement. The main slider and the secondary slider slide in the arc groove are used to slide together with the fixing method of bolts and nuts to realize The stable connection between the pedestrian plate and the steel pipe frame is adapted to the width changes of the installation gap.

Benefits of technology

It effectively solves the problem of shaking in the middle of the pedestrian board, provides a stable working environment, and enhances construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989861U_ABST
    Figure CN221989861U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of buildings, in particular to a climbing frame main frame connecting device which is provided with a main hooping structure, an auxiliary hooping structure and a reinforcing piece. The bottom of the main hooping structure is movably connected with the bottom of the auxiliary hooping structure. The middle part of the main hooping structure and the middle part of the auxiliary hooping structure form a first hooping area for clamping the circular tube; the upper part of the main hooping structure and the upper part of the auxiliary hooping structure form a second hooping area for clamping the plate; the reinforcing piece is inserted into the wedge-shaped groove of the auxiliary hooping structure, so that the plate is fixed in the second hooping area; a first arc-shaped groove is formed in the outer side wall of the upper portion of an arc-shaped plate in the middle of the main hooping structure, a main clamping plate and an arc-shaped main sliding plate are arranged on the upper portion of the main hooping structure, and the main sliding plate slides in the first arc-shaped groove. The bottom of the main clamping plate is fixed to the preset position of the outer surface of the main sliding plate. The walking plate of the climbing frame is fixed with the steel pipe at the corresponding bottom, so that the problem that the walking plate shakes in the middle is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of construction, and in particular relates to a climbing frame main frame connecting device. Background Art

[0002] With the continuous innovation of construction technology and the increasing maturity of technology, in the construction of high-rise and super high-rise buildings, the external protective scaffolding gradually adopts all-steel attached lifting scaffolding to replace the original I-beam cantilever scaffolding. It can be erected once and lifted and used multiple times, with good economic and social benefits.

[0003] However, when the climbing frame is being assembled and the walkway is built on the fixed steel pipe frame, most of the time the walkway is placed on the steel pipe frame and fixed at both ends and sides of the walkway by clamps, while the walkway in the middle cannot be fixed. As the walkway is too long, it will float up and down, causing the construction workers to feel unsteady during their work, which makes people feel unsafe and there are certain safety hazards. Utility Model Content

[0004] The utility model provides a climbing frame main frame connecting device to solve the above-mentioned problem.

[0005] In order to solve the above problems, the technical solution provided by the utility model is as follows: a climbing frame main frame connection device, provided with a main clamping structure, a secondary clamping structure and a reinforcement member; the bottom of the main clamping structure is movably connected with the bottom of the secondary clamping structure; the middle of the main clamping structure and the middle of the secondary clamping structure form a first clamping area for clamping a round tube; the upper part of the main clamping structure and the upper part of the secondary clamping structure form a second clamping area for clamping a plate; the reinforcement member is inserted into the wedge-shaped groove of the secondary clamping structure to fix the plate in the second clamping area; the upper outer wall of the arc plate in the middle of the main clamping structure is provided with a first arc groove, the upper part of the main clamping structure is provided with a main clamping plate and an arc-shaped main slide plate, and the main slide plate slides in the first arc groove; the bottom of the main clamping plate is fixed to a preset position on the outer surface of the main slide plate. Preferred technical solution: the bolt passes through the main screw hole at the bottom of the main clamping structure and the secondary screw hole at the bottom of the secondary clamping structure, and the bottom of the main clamping structure is fixed to the bottom of the secondary clamping structure through a nut.

[0006] Preferred technical solution: the middle part of the main clamping structure is consistent with the middle part of the secondary clamping structure; arc-shaped concave parts are respectively arranged on the two side walls of the first arc-shaped groove. Preferred technical solution: convex parts matching the concave parts are arranged on the left and right sides of the main slide plate.

[0007] A preferred technical solution: a recessed position is provided on the side of the main splint facing the secondary clamping structure, and a fixing piece is provided at the recessed position; the fixing piece includes a spherical connecting ball, a connecting rod and a fixing ball; the connecting ball is nested in the recessed position, one end of the connecting rod is fixed to the part of the connecting ball exposed on the outer surface, and a designated part of the fixing ball is connected to the other end of the connecting rod.

[0008] A preferred technical solution: an adjusting thread is arranged on the surface of the other end of the connecting rod; an adjusting screw hole is arranged on the fixing ball, and the internal shape of the adjusting screw hole is the same as the shape of the other end of the connecting rod.

[0009] A preferred technical solution: a secondary clamp and a secondary slider are provided on the upper part of the secondary clamping structure; the secondary slider slides in the second arc groove of the upper outer wall of the secondary arc plate of the secondary clamping structure, the bottom of the secondary clamp is fixed to the outer surface of the secondary slider, and the top of the secondary clamp extends upward.

[0010] A preferred technical solution: the auxiliary splint is provided with a first crack, the placement groove is provided at the bottom of the first crack, and the width of the placement groove matches the width of the connecting rod.

[0011] A preferred technical solution is to provide inclined wedge-shaped grooves on both side walls of the first crack, respectively, and the wedge-shaped grooves penetrate the auxiliary clamping plate.

[0012] A preferred technical solution: the reinforcement member comprises a wedge-shaped block, a horizontal bar is arranged at the bottom of the wedge-shaped block, and the width of the horizontal bar is consistent with the width of the connecting rod.

[0013] The beneficial effect compared with the prior art is that, by adopting the above-mentioned scheme, the utility model solves the problem of the walking board not shaking during the process and in the middle by fixing the walking board of the climbing frame to the corresponding bottom steel pipe; the main slider slides in the first groove and the auxiliary slider slides in the second groove, thereby adapting to the width change between the two installation gaps of the walking board. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the technical solutions in the embodiments or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0016] Figure 2 This is a schematic diagram of the main clamping structure of the utility model;

[0017] Figure 3 This is a schematic diagram of the auxiliary clamping structure of the utility model;

[0018] Figure 4 This is a schematic diagram of the structure of the reinforcement member of the utility model. DETAILED DESCRIPTION

[0019] In order to facilitate the understanding of the present invention, the present invention is described in more detail below in conjunction with the accompanying drawings and specific embodiments. The accompanying drawings provide preferred embodiments of the present invention. However, the present invention can be implemented in many different forms and is not limited to the embodiments described in this specification. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present invention more thorough and comprehensive.

[0020] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "fixed", "integrally formed", "left", "right" and similar expressions used in this specification are for illustrative purposes only. In the drawings, units with similar structures are marked with the same reference numerals.

[0021] Unless otherwise defined, all technical and scientific terms used in this specification have the same meanings as those commonly understood by technicians in the technical field of the utility model. The terms used in this specification are only for the purpose of describing specific embodiments and are not used to limit the utility model.

[0022] like Figure 1-4 As shown, one embodiment of the utility model is: set a position on the surface of the pedestrian board in advance, reserve a corresponding number of installation gaps, then place the pedestrian board on the constructed steel pipe bracket, and fix the pedestrian board and the steel pipe bracket through the climbing frame main frame connecting device.

[0023] A climbing frame main frame connection device is provided with a main clamping structure 1, a secondary clamping structure 2 and a reinforcement member 3; the bottom of the main clamping structure 1 is movably connected to the bottom of the secondary clamping structure 2; the middle part of the main clamping structure 1 and the middle part of the secondary clamping structure 2 form a first clamping area 4 for clamping a round tube; the upper part of the main clamping structure 1 and the upper part of the secondary clamping structure 2 form a second clamping area 5 for clamping a plate; the reinforcement member 3 is inserted into the wedge-shaped groove 21 of the secondary clamping structure 2 to fix the plate in the second clamping area 5; the upper outer side wall of the arc plate in the middle of the main clamping structure 1 is provided with a first arc groove 22, and the upper part of the main clamping structure 1 is provided with a main clamping plate 11 and an arc-shaped main slide plate, and the main slide plate slides in the first arc groove 22; the bottom of the main clamping plate 11 is fixed at a preset position on the outer surface of the main slide plate.

[0024] The bolts penetrate the main screw holes at the bottom of the main clamping structure 1 and the secondary screw holes at the bottom of the secondary clamping structure 2, and the bottom of the main clamping structure 1 and the bottom of the secondary clamping structure 2 are fixed by nuts.

[0025] The middle part of the main clamping structure 1 is consistent with the middle part of the secondary clamping structure 2; arc-shaped recessed parts are respectively arranged on both side walls of the first arc-shaped groove 22.

[0026] The left and right sides of the main sliding plate are provided with convex parts matching with the concave parts.

[0027] A recessed position is provided on the side of the main splint 11 toward the secondary clamping structure 2, and a fixing member is provided at the recessed position; the fixing member includes a spherical connecting ball 12, a connecting rod 13 and a fixing ball 14; the connecting ball 12 is nested in the recessed position, one end of the connecting rod 13 is fixed to the portion of the connecting ball 12 exposed on the outer surface, and a designated portion of the fixing ball 14 is connected to the other end of the connecting rod 13.

[0028] The surface of the other end of the connecting rod 13 is provided with an adjusting thread; the fixing ball 14 is provided with an adjusting screw hole, and the inner shape of the adjusting screw hole is the same as the shape of the other end of the connecting rod 13 .

[0029] A secondary clamping plate and a secondary slider are provided on the upper part of the secondary clamping structure 2; the secondary slider slides in the second arc groove of the upper outer wall of the secondary arc plate of the secondary clamping structure 2, the bottom of the secondary clamping plate is fixed to the outer surface of the secondary slider, and the top of the secondary clamping plate extends upward.

[0030] The auxiliary splint is provided with a first crack, and the placement groove 23 is provided at the bottom of the first crack. The width of the placement groove 23 matches the width of the connecting rod 13 .

[0031] Inclined wedge-shaped grooves 21 are respectively provided on both side walls of the first crack, and the wedge-shaped grooves 21 penetrate the auxiliary clamping plate.

[0032] The reinforcement member 3 includes a wedge-shaped block 31 , and a horizontal bar 32 is arranged at the bottom of the wedge-shaped block 31 . The width of the horizontal bar 32 is consistent with the width of the connecting rod 13 .

[0033] The following are the fixed processes:

[0034] First, the main screw hole at the bottom of the main clamping structure 1 and the secondary screw hole at the bottom of the secondary clamping structure 2 are penetrated by bolts to connect the bottom of the main clamping structure 1 and the bottom of the secondary clamping structure 2; the nut is installed at the end of the bolt to fix it;

[0035] Then, the middle arc plate of the main clamping structure 1 and the middle arc plate of the secondary clamping structure 2 form a first clamping area 4, and the first clamping area 4 clamps the steel pipe below the installation gap of the pedestrian board;

[0036] Secondly, the main plate 11 on the upper part of the main clamping structure 1 passes through one installation gap, and the secondary main plate on the upper part of the secondary clamping structure 2 passes through the second installation gap; lift the connecting rod 13, so that the other end of the connecting rod 13 falls into the placement groove 23; rotate the fixing ball 14, so that the adjusting screw hole in the fixing ball 14 is sleeved on the other end of the connecting rod 13, and because the adjusting screw hole cooperates with the adjusting thread, the fixing ball 14 moves toward the connecting ball 12. When the fixing ball 14 fits with the secondary plate, it means that the main plate 11 and the secondary plate are fixed in the horizontal direction and cannot move;

[0037] Finally, the wedge block 31 is inserted into the wedge groove 21, and the horizontal bar 32 at the bottom of the wedge block 31 is stuck in the placement groove 23 and fits with the upper surface of the other end of the connecting rod 13, indicating that the other end of the connecting rod 13 can no longer move vertically up and down in the first crack, thereby achieving vertical fixation;

[0038] The pedestrian board is completely fixed and clamped by horizontally fixing the main clamping plate 11 and the auxiliary clamping plate and vertically fixing the connecting rod 13.

[0039] Embodiment 2: In order to adapt to the width change between the two installation gaps of the pedestrian board, a first arc groove 22 is set in the arc plate in the middle of the main clamping structure 1, and a second arc groove is set in the arc plate in the middle of the secondary clamping structure 2. The main slider slides in the first arc groove 22 to cause the main splint 11 to move up and down and fine-tune left and right. Similarly, the secondary slider slides in the second arc groove to cause the secondary splint to move up and down and fine-tune left and right. The width change between the installation gaps is adapted by fine-tuning the main splint 11 and the secondary splint up and down and left and right.

[0040] It should be noted that the above-mentioned technical features are further combined with each other to form various embodiments not listed above, which are all deemed to be within the scope of the present utility model specification; and, for ordinary technicians in this field, they can be improved or transformed according to the above description, and all these improvements and transformations should fall within the scope of protection of the claims attached to the present utility model.

Claims

1. A climbing frame main frame connecting device, characterized in that; A main clamping structure, a secondary clamping structure and a reinforcement member are provided; the bottom of the main clamping structure is movably connected with the bottom of the secondary clamping structure; the middle of the main clamping structure and the middle of the secondary clamping structure form a first clamping area for clamping the round tube; The upper part of the main clamping structure and the upper part of the secondary clamping structure form a second clamping area for plate-shaped clamping; the reinforcement piece is inserted into the wedge-shaped groove of the secondary clamping structure to fix the plate in the second clamping area; the upper outer wall of the arc-shaped plate in the middle part of the main clamping structure is provided with a first arc groove, and the upper part of the main clamping structure is provided with a main clamping plate and an arc-shaped main slide plate, and the main slide plate slides in the first arc groove; the bottom of the main clamping plate is fixed at a preset position on the outer surface of the main slide plate.

2. A climbing frame main frame connection device according to claim 1, characterized in that; The bolt passes through the main screw hole at the bottom of the main clamping structure and the secondary screw hole at the bottom of the secondary clamping structure, and the bottom of the main clamping structure and the bottom of the secondary clamping structure are fixed by a nut.

3. A climbing frame main frame connection device according to claim 1, characterized in that; The middle part of the main clamping structure is consistent with the middle part of the secondary clamping structure; arc-shaped recessed parts are respectively arranged on both side walls of the first arc-shaped groove.

4. A climbing frame main frame connection device according to claim 3, characterized in that; The left and right sides of the main sliding plate are provided with convex parts matching with the concave parts.

5. A climbing frame main frame connection device according to claim 1, characterized in that; A recessed position is provided on the side of the main splint toward the secondary clamping structure, and a fixing piece is provided at the recessed position; the fixing piece includes a spherical connecting ball, a connecting rod and a fixing ball; the connecting ball is nested in the recessed position, one end of the connecting rod is fixed to the part of the connecting ball exposed on the outer surface, and a designated part of the fixing ball is connected to the other end of the connecting rod.

6. A climbing frame main frame connection device according to claim 5, characterized in that; The surface of the other end of the connecting rod is provided with an adjusting thread; the fixing ball is provided with an adjusting screw hole, and the inner shape of the adjusting screw hole is the same as the shape of the other end of the connecting rod.

7. A climbing frame main frame connection device according to claim 6, characterized in that; A secondary clamping plate and a secondary slider are provided on the upper part of the secondary clamping structure; the secondary slider slides in the second arc groove of the upper outer wall of the secondary arc plate of the secondary clamping structure, the bottom of the secondary clamping plate is fixed to the outer surface of the secondary slider, and the top of the secondary clamping plate extends upward.

8. A climbing frame main frame connection device according to claim 7, characterized in that; The auxiliary splint is provided with a first crack, a placement groove is provided at the bottom of the first crack, and the width of the placement groove matches the width of the connecting rod.

9. A climbing frame main frame connection device according to claim 8, characterized in that; Inclined wedge-shaped grooves are respectively arranged on both side walls of the first crack, and the wedge-shaped grooves penetrate through the auxiliary clamping plate.

10. A climbing frame main frame connection device according to claim 9, characterized in that; The reinforcing member comprises a wedge-shaped block, a horizontal bar is arranged at the bottom of the wedge-shaped block, and the width of the horizontal bar is consistent with the width of the connecting rod.