Wall front end face formwork pulling and connecting mechanism

By designing a pulling mechanism in the wall concrete casting molding formwork system to apply tension on the front end surface of the wall, the problem of formwork expansion is solved, and the casting molding quality and construction progress are improved.

CN221989879UActive Publication Date: 2024-11-12CHENGDU NO 2 CONSTRUETION COMPDNY
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420339344.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-23
Publication Date
2024-11-12
Estimated Expiration
2034-02-23

AI Technical Summary

Technical Problem

During the casting and forming process of shear wall concrete, the front end formwork surface of the wall is narrow in width and is not easy to reinforce, resulting in the problem of the formwork expansion and impacting the casting and forming quality and construction progress.

Method used

A wall concrete casting molding formwork system is designed, including the left side formwork, the right side formwork and the front end formwork. The first and second formwork pulling mechanisms apply tension to the front end formwork, and the locking part is used. The mating connection with the pull-up piece ensures the stability of the template.

Benefits of technology

It effectively avoids the expansion of the front end formwork of the wall when pouring concrete, and improves the casting forming quality and construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989879U_ABST
    Figure CN221989879U_ABST
Patent Text Reader

Abstract

The utility model discloses a wall body front end face template tying mechanism which comprises a second template tying mechanism which comprises a plurality of second pull rods arranged between a wall body left side face template and a wall body front end face template and between a wall body right side face template and the wall body front end face template in the horizontal transverse direction. The two ends of each second pull rod are provided with a front-end pulling piece and a rear-end pulling piece through locking pieces correspondingly, the front-end pulling pieces are connected with the corresponding positions of the outer sides of the corresponding wall body front-end formwork positioning components in a matched mode, and the rear-end pulling pieces are connected with the corresponding left-side pulling pieces or the corresponding right-side pulling pieces in a matched mode. And at least two front-end tie pieces are arranged on each wall front-end template positioning component at intervals in the horizontal longitudinal direction, and are distributed on the outer side of the wall left-side template and the outer side of the wall right-side template. The second formwork tying mechanism can apply pulling force in the horizontal transverse direction to the wall front end face formwork, and the wall front end face formwork is prevented from expanding.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a wall concrete pouring and forming template system and a wall front end template pulling and connecting mechanism. Background Art

[0002] During the shear wall concrete pouring process, the front end formwork of the wall is narrow and difficult to reinforce, so the front end formwork of the wall often expands, affecting the quality of the wall concrete pouring and the construction progress. Utility Model Content

[0003] The utility model aims to provide a wall concrete casting and forming template system and a wall front end template pulling mechanism thereof, which can effectively fix the wall front end template and solve the problem of wall front end template expansion.

[0004] In a first aspect, a wall concrete casting forming formwork system is provided, comprising:

[0005] A left side wall template, the left side wall template comprising a left side wall template body and a left side wall template positioning member, the left side wall template positioning member extending in a horizontal transverse direction and abutting against the outside of the left side wall template body, the outside of the left side wall template body having at least two left side wall template positioning members arranged in an upper and lower interval;

[0006] A right side wall template, the right side wall template comprising a right side wall template body and a right side wall template positioning member, the right side wall template positioning member extending in a horizontal transverse direction and abutting against the outer side of the right side wall template body, the outer side of the right side wall template body having at least two right side wall template positioning members arranged in an upper and lower interval;

[0007] A front end face template of a wall, the front end face template of the wall comprising a front end template body of the wall and a front end template positioning member, the front end template positioning member of the wall is extended in a horizontal longitudinal direction and abuts against the outer side of the front end template body of the wall, and the outer side of the front end template body of the wall has at least two front end template positioning members arranged in an upper and lower interval;

[0008] A first template tie mechanism, the first template tie mechanism comprises a plurality of first tie rods passing through the left side template of the wall and the right side template of the wall along the horizontal longitudinal direction, the two ends of each first tie rod are respectively provided with a left tie member and a right tie member through a locking member, the left tie member is adaptively connected to the corresponding outer portion of the left side template positioning member of the corresponding wall, the right tie member is adaptively connected to the corresponding outer portion of the right side template positioning member of the corresponding wall, and at least two left tie members are arranged at intervals along the horizontal transverse direction on each left side template positioning member of the wall, and at least two right tie members are arranged at intervals along the horizontal transverse direction on each right side template positioning member of the wall;

[0009] The second template anchoring mechanism comprises a plurality of second tie rods arranged along the horizontal transverse direction between the left side template of the wall and the front end template of the wall and between the right side template of the wall and the front end template of the wall, the two ends of each second tie rod are respectively provided with a front end anchor and a rear end anchor through a locking member, the front end anchor is adaptively connected to the corresponding outer portion of the corresponding wall front end template positioning component, the rear end anchor is adaptively connected to the corresponding left anchor or right anchor, at least two front end anchors are arranged at intervals along the horizontal longitudinal direction on each wall front end template positioning component, the at least two front end anchors are distributed on the outer side of the left side template of the wall and the outer side of the right side template of the wall.

[0010] In a second aspect, a wall front face template tie mechanism is provided, which is used for a wall concrete casting and forming template system, wherein the wall concrete casting and forming template system comprises a wall left side template, a wall right side template, a wall front face template and a first template tie mechanism;

[0011] The left side wall template comprises a left side wall template body and a left side wall template positioning member, wherein the left side wall template positioning member is extended in a horizontal transverse direction and abuts against the outer side of the left side wall template body, and the outer side of the left side wall template body has at least two left side wall template positioning members arranged in an upper and lower interval;

[0012] The right side wall template comprises a right side wall template body and a right side wall template positioning member, wherein the right side wall template positioning member is extended in a horizontal transverse direction and abuts against the outer side of the right side wall template body, and the outer side of the right side wall template body has at least two right side wall template positioning members arranged in an upper and lower interval;

[0013] The front end face template of the wall body comprises a front end template body of the wall body and a positioning member of the front end template of the wall body, wherein the positioning member of the front end template of the wall body is extended in the horizontal longitudinal direction and abuts against the outer side of the front end template body of the wall body, and the outer side of the front end template body of the wall body has at least two front end template positioning members of the wall body arranged in an upper and lower interval;

[0014] The first template tie mechanism comprises a plurality of first tie rods passing through the left side template of the wall and the right side template of the wall along the horizontal longitudinal direction, and the two ends of each first tie rod are respectively installed with a left tie member and a right tie member through a locking member, the left tie member is adaptively connected to the corresponding outer portion of the left side template positioning member of the corresponding wall, and the right tie member is adaptively connected to the corresponding outer portion of the right side template positioning member of the corresponding wall, and at least two left tie members are arranged at intervals along the horizontal transverse direction on each left side template positioning member of the wall, and at least two right tie members are arranged at intervals along the horizontal transverse direction on each right side template positioning member of the wall;

[0015] It includes:

[0016] The second template anchoring mechanism comprises a plurality of second tie rods arranged along the horizontal transverse direction between the left side template of the wall and the front end template of the wall and between the right side template of the wall and the front end template of the wall, the two ends of each second tie rod are respectively provided with a front end anchor and a rear end anchor through a locking member, the front end anchor is adaptively connected to the corresponding outer portion of the corresponding wall front end template positioning component, the rear end anchor is adaptively connected to the corresponding left anchor or right anchor, at least two front end anchors are arranged at intervals along the horizontal longitudinal direction on each wall front end template positioning component, the at least two front end anchors are distributed on the outer side of the left side template of the wall and the outer side of the right side template of the wall.

[0017] The second template tensioning mechanism can apply a pulling force in the horizontal transverse direction to the template on the front end face of the wall, thereby preventing the template on the front end face of the wall from expanding when pouring concrete.

[0018] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments. Additional aspects and advantages provided by the present invention will be partially given in the following description, partially become apparent from the following description, or be understood through practice. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The drawings constituting a part of this specification are used to assist the understanding of the present invention. The contents provided in the drawings and their related descriptions in the present invention are used to explain the present invention, but do not constitute improper limitations on the present invention.

[0020] Figure 1 It is a structural schematic diagram of a wall concrete pouring and forming formwork system according to an embodiment of the utility model.

[0021] Figure 2 This is a structural diagram of the rear end anchor member in the wall concrete casting and forming formwork system of the embodiment of the utility model. DETAILED DESCRIPTION

[0022] The utility model is described clearly and completely below in conjunction with the accompanying drawings. A person skilled in the art will be able to implement the utility model based on these descriptions. Before describing the utility model in conjunction with the accompanying drawings, it should be particularly noted that:

[0023] The technical solutions and technical features provided in each section, including the following description, can be combined with each other without conflict. In addition, where possible, these technical solutions, technical features and related combinations can be assigned specific technical themes and protected by relevant patents.

[0024] The embodiments of the utility model involved in the following description are usually only a part of the embodiments rather than all the embodiments. Based on these embodiments, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of patent protection.

[0025] The terms "include", "comprises", "have" and any variations thereof in this utility model and the corresponding claims and related parts are intended to cover non-exclusive inclusions. Other related terms and units can be reasonably interpreted based on the relevant content provided in this utility model.

[0026] Figure 1 This is a schematic diagram of the structure of the wall concrete casting and forming template system of the utility model embodiment. Figure 1 As shown, the wall concrete casting and forming formwork system is used for shear wall concrete casting and forming, which includes: a wall left side formwork 1, a wall right side formwork 2, a wall front end formwork 3, a first formwork tensioning mechanism 4 and a second formwork tensioning mechanism 5.

[0027] The left side wall formwork 1 comprises a left side wall formwork body 11 and a left side wall formwork positioning member 12, wherein the left side wall formwork positioning member 12 is extended in a horizontal transverse direction and abuts against the outside of the left side wall formwork body 11, and the outside of the left side wall formwork body 11 has at least two left side wall formwork positioning members 12 arranged in an upper and lower interval;

[0028] The wall right side template 2 comprises a wall right side template body 21 and a wall right side template positioning member, wherein the wall right side template positioning member is extended in a horizontal transverse direction and abuts against the outer side of the wall right side template body 21, and the outer side of the wall right side template body 21 has at least two wall right side template positioning members arranged in an upper and lower interval;

[0029] The wall front face template 3 comprises a wall front template body 31 and a wall front template positioning member 32, wherein the wall front template positioning member 32 is extended in the horizontal longitudinal direction and abuts against the outer side of the wall front template body 31, and the outer side of the wall front template body 31 has at least two wall front template positioning members 32 arranged in an upper and lower interval;

[0030] The first template tie mechanism 4 comprises a plurality of first tie rods 41 passing through the left wall template 1 and the right wall template 2 along the horizontal longitudinal direction, and the two ends of each first tie rod 41 are respectively provided with a left tie member 42 and a right tie member through a locking member, the left tie member 41 is adaptively connected to the corresponding outer portion of the corresponding left wall template positioning member 12, and the right tie member is adaptively connected to the corresponding outer portion of the corresponding right wall template positioning member, and at least two left tie members 42 are arranged at intervals along the horizontal transverse direction on each wall template positioning member 12, and at least two right tie members are arranged at intervals along the horizontal transverse direction on each wall template positioning member;

[0031] The second template anchoring mechanism 5 includes a plurality of second tie rods 51 arranged along the horizontal transverse direction between the left side template 1 of the wall and the front end template 3 of the wall and between the right side template 2 of the wall and the front end template 3 of the wall. The two ends of each second tie rod 51 are respectively provided with a front end anchor 52 and a rear end anchor 53 through locking members. The front end anchor 52 is adaptively connected to the corresponding outer portion of the corresponding wall front end template positioning member 32, and the rear end anchor 53 is adaptively connected to the corresponding left side anchor 42 or the right side anchor. At least two front end anchors 52 are arranged at intervals along the horizontal longitudinal direction on each wall front end template positioning member 32, and the at least two front end anchors 52 are distributed on the outer side of the left side template 1 of the wall and the outer side of the right side template 2 of the wall.

[0032] Generally speaking, each wall front end template positioning component 32 is placed on the corresponding wall left side template positioning component 12 and the wall right side template positioning component.

[0033] Specifically, threads are provided at both ends of the first pull rod 41 , and the locking members at both ends of the first pull rod 41 are nuts.

[0034] Specifically, threads are provided at both ends of the second pull rod 51 , and the locking members at both ends of the second pull rod 51 are nuts.

[0035] Specifically, the left formwork positioning member 12 is composed of a pair of steel pipes, and the left anchor 42 is a claw that is compatible with the pair of steel pipes.

[0036] Specifically, the right side template positioning component is composed of a pair of steel pipes, and the right side anchor is a claw that is compatible with the pair of steel pipes at the same time.

[0037] Specifically, the front end template positioning member 32 of the wall body is made of steel bars, and the front end anchor 52 is a hook that matches the steel bars.

[0038] Specifically, the rear end anchor 53 is a clamp that matches the corresponding steel pipe, and the clamp and the corresponding claw are pressed against each other (such as Figure 1 shown).

[0039] As an improvement to the clamp, Figure 2 As shown, the clamp includes a left half ring 61 and a right half ring 62, and second tie rod axial mounting through holes 63 matching the corresponding second tie rods 51 are respectively provided above the left half ring 61 and above the right half ring 62, and the second tie rods 51 corresponding to these second tie rod axial mounting through holes 63 pass through these second tie rod axial mounting through holes 63 and are connected to the corresponding locking pieces, and the bottom of the left half ring 61 is connected to the bottom of the right half ring 63 via a locking structure.

[0040] Specifically, a plurality of latch holes 64 are arranged at intervals in the circumferential direction below the left half ring 61 and below the right half ring 62. Each latch hole 64 below the left half ring 61 corresponds to each latch hole 64 below the right half ring 62 and can be matched with the latch 65 at the same time. By selecting the latch hole 64 that the latch 65 is adapted to, the size of the inner hole of the clamp can be adjusted so that the clamp can better match the corresponding left wall template positioning member 12 or the corresponding right wall template positioning member.

[0041] The above-mentioned wall concrete casting and forming template system can apply a pulling force (in the horizontal direction) to the front end template 3 of the wall through the second template tensioning mechanism. Figure 1 In the situation shown, the pulling force is in the horizontal and backward direction), thereby preventing the front face formwork 3 of the wall from expanding when pouring concrete.

[0042] When the rear end anchor 53 adopts a clamp that is compatible with the corresponding steel pipe and the clamp and the corresponding claw are pressed against each other, it is equivalent to using the left anchor 42 (specifically the claw) or the right anchor (specifically the claw) to withstand the pressure in the horizontal lateral direction applied by the rear end anchor 53, thereby cleverly utilizing the force-bearing capacity of the left anchor 42 and the right anchor, simplifying the structure of the second template anchor mechanism 5 and ensuring the stability of the second template anchor mechanism 5.

[0043] The above is a description of the relevant contents of the utility model. A person skilled in the art will be able to implement the utility model based on these descriptions. Based on the above contents of this specification, all other embodiments obtained by a person skilled in the art without making any creative work shall fall within the scope of the utility model.

Claims

1. The front end template of the wall is connected by a mechanism, characterized by: A wall concrete casting and forming template system, the wall concrete casting and forming template system comprising a wall left side template, a wall right side template, a wall front end template and a first template tie mechanism; The left side wall template comprises a left side wall template body and a left side wall template positioning member, wherein the left side wall template positioning member is extended in a horizontal transverse direction and abuts against the outer side of the left side wall template body, and the outer side of the left side wall template body has at least two left side wall template positioning members arranged in an upper and lower interval; The right side wall template comprises a right side wall template body and a right side wall template positioning member, wherein the right side wall template positioning member is extended in a horizontal transverse direction and abuts against the outer side of the right side wall template body, and the outer side of the right side wall template body has at least two right side wall template positioning members arranged in an upper and lower interval; The front end face template of the wall body comprises a front end template body of the wall body and a positioning member of the front end template of the wall body, wherein the positioning member of the front end template of the wall body is extended in the horizontal longitudinal direction and abuts against the outer side of the front end template body of the wall body, and the outer side of the front end template body of the wall body has at least two front end template positioning members of the wall body arranged in an upper and lower interval; The first template tie mechanism comprises a plurality of first tie rods passing through the left side template of the wall and the right side template of the wall along the horizontal longitudinal direction, and the two ends of each first tie rod are respectively installed with a left tie member and a right tie member through a locking member, the left tie member is adaptively connected to the corresponding outer portion of the left side template positioning member of the corresponding wall, and the right tie member is adaptively connected to the corresponding outer portion of the right side template positioning member of the corresponding wall, and at least two left tie members are arranged at intervals along the horizontal transverse direction on each left side template positioning member of the wall, and at least two right tie members are arranged at intervals along the horizontal transverse direction on each right side template positioning member of the wall; It includes: The second template anchoring mechanism comprises a plurality of second tie rods arranged along the horizontal transverse direction between the left side template of the wall and the front end template of the wall and between the right side template of the wall and the front end template of the wall, the two ends of each second tie rod are respectively provided with a front end anchor and a rear end anchor through a locking member, the front end anchor is adaptively connected to the corresponding outer portion of the corresponding wall front end template positioning component, the rear end anchor is adaptively connected to the corresponding left anchor or right anchor, at least two front end anchors are arranged at intervals along the horizontal longitudinal direction on each wall front end template positioning component, the at least two front end anchors are distributed on the outer side of the left side template of the wall and the outer side of the right side template of the wall.

2. The wall front end template tie mechanism according to claim 1, characterized in that: Both ends of the first pull rod are provided with threads, and the locking members at both ends of the first pull rod are nuts.

3. The wall front end template tie mechanism according to claim 1, characterized in that: Both ends of the second pull rod are provided with threads, and the locking members at both ends of the second pull rod are nuts.

4. The wall front end template tie mechanism according to claim 1, characterized in that: The left-side formwork positioning member is composed of a pair of steel pipes, and the left-side anchor is a claw that is simultaneously compatible with the pair of steel pipes; and / or, the right-side formwork positioning member is composed of a pair of steel pipes, and the right-side anchor is a claw that is simultaneously compatible with the pair of steel pipes.

5. The wall front end template tie mechanism according to claim 1, characterized in that: The front end template positioning component of the wall body is made of steel bars, and the front end anchor is a hook matched with the steel bars.

6. The wall front end template tie mechanism according to claim 1, characterized in that: The left-side template positioning component includes a steel pipe, and the left-side anchor is a claw that matches the steel pipe; the right-side template positioning component includes a steel pipe, and the right-side anchor is a claw that matches the steel pipe; the rear-end anchor adopts a clamp that matches the corresponding steel pipe, and the clamp and the corresponding claw are pressed against each other.

7. The wall front end template tie mechanism according to claim 6, characterized in that: The clamp includes a left half ring and a right half ring, and second tie rod axial mounting through holes matching the corresponding second tie rods are respectively arranged above the left half ring and above the right half ring, and the second tie rods corresponding to these second tie rod axial mounting through holes pass through these second tie rod axial mounting through holes and are connected to the corresponding locking pieces, and the bottom of the left half ring is connected to the bottom of the right half ring through a locking structure.

8. The wall front end template tie mechanism according to claim 7, characterized in that: A plurality of latch holes are arranged circumferentially at intervals below the left half ring and the right half ring. Each latch hole below the left half ring corresponds to each latch hole below the right half ring one by one and can cooperate with the latch at the same time.

9. The wall front end template tie mechanism according to claim 1, characterized in that: The wall concrete casting and forming formwork system is used for concrete casting and forming of shear walls.

10. The wall front end template tie mechanism according to claim 1, characterized in that: Each front end template positioning component of the wall is placed on the corresponding left side template positioning component of the wall and the right side template positioning component of the wall.