Water stop structure applied to vertical pipe jacking construction
By using prefabricated steel structures, including extrusion mechanism and annular scraper, the problems of reduced sealing and wear of water-stop cushion during the pipe construction are solved, and higher sealing effect and longer The life of the water-stop cushion.
Patent Information
- Application Number
- CN202420765175.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-15
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-04-15
AI Technical Summary
The sealing and firmness of the existing pipe receiving well outlet openings decrease with the construction time, resulting in a decrease in the construction quality of the pipe, and the water stop cushion layer is seriously worn when the pipe is pushed out, affecting the sealing effect.
The prefabricated steel component structure is adopted, including sleeve, outer arc and inner arc shrapnel, extrusion mechanism and annular scraper. The shrapnel is deformed and tightened through the extrusion mechanism, maintaining the sealing effect between the water-stop cushion layer and the top tube, and The wear of the water stop cushion layer by an annular scraper is reduced.
It improves the sealing effect between the top tube and the water-stop cushion layer, extends the service life of the water-stop cushion layer, reduces the wear of the top tube to the water-stop cushion layer, and stabilizes the construction quality of the top tube.
Smart Images

Figure CN221990398U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pipeline construction, and in particular to a water-stopping structure used in vertical pipe jacking construction. Background Art
[0002] Pipe jacking is a trenchless construction method, a pipeline burial construction technology with no excavation or less excavation. Pipe jacking construction is to use the jacking force generated by the jacking equipment in the working pit to overcome the friction between the pipeline and the surrounding soil, push the pipeline into the soil according to the designed slope, and transport the soil away. After one section of the pipe is pushed into the soil layer, the second section of the pipe is pushed in. The principle is to use the thrust of the main jacking cylinder and the pipeline room, relay room, etc. to push the tool pipe or tunnel boring machine from the working pit through the soil layer to the receiving pit and lift it. The pipeline follows the tool pipe or tunnel boring machine and is buried between the two pits.
[0003] The existing receiving well is mainly composed of a foundation pit, a sump at the bottom of the foundation pit, and a reserved hole on the inner wall of the foundation pit, forming a closed outlet. However, the outlet of the existing receiving well top pipe only relies on the reserved hole formed by the solidification of the reserved concrete, and its sealing and firmness will be easily damaged as the top pipe construction time goes by, affecting the laying quality of the entire sewage pipeline.
[0004] According to the patent number: CN212297912.U, the utility model relates to a reinforcement structure for the exit of a jacking receiving well, which includes a pre-buried steel ring, one end of which extends from the side wall in the receiving well, and also includes a mounting plate circumferentially arranged on the protruding end of the pre-buried steel ring, a reinforcement plate detachably connected to the mounting plate, a sleeve vertically connected to the reinforcement plate, and a water-stopping cushion layer arranged on the inner side of the sleeve, which solves the problem of poor construction quality of the jacking pipe due to the loss of drag reduction mud and the easy damage of the reserved hole when the jacking pipe is pushed out of the exit of the receiving well. The utility model has good sealing performance and a stable structure, can reduce the loss of drag reduction mud and the structure is not easy to be damaged, and has the advantage of improving the quality of jacking pipe construction.
[0005] Although the above patent uses a sleeve and a water-stopping cushion layer arranged on the inner side surface of the sleeve to prevent the drag-reducing mud from being carried away from the gap between the top pipe and the inner wall of the reserved hole when the top pipe is pushed out, mud and sand will remain on the surface of the top pipe after it is inserted into the ground and pulled out. Therefore, each time the top pipe moves in close contact with the inner circle of the water-stopping cushion layer, the water-stopping cushion layer is greatly worn, resulting in the overall thickness of the water-stopping cushion layer becoming thinner, reducing the close contact between the water-stopping cushion layer and the outer surface of the top pipe, which is easy to affect the effect of the water-stopping cushion layer.
[0006] Therefore, those skilled in the art provide a water-stop structure for use in vertical pipe jacking construction to solve the problems raised in the above-mentioned background technology. Utility Model Content
[0007] In order to solve the problems raised in the above background technology, the present application provides a water-stopping structure applied to vertical pipe jacking construction.
[0008] The present application provides a water-stop structure for vertical pipe jacking construction using the following technical solution:
[0009] A water-stop structure used in vertical pipe jacking construction, comprising a prefabricated steel part, a sleeve installed inside the prefabricated steel part, an outer arc-shaped spring piece attached to the inner wall of the sleeve, an inner arc-shaped spring piece attached to the inner wall of the outer arc-shaped spring piece, and a water-stop cushion layer bonded to the inner walls of the outer arc-shaped spring piece and the inner arc-shaped spring piece;
[0010] Support side plates are installed on both sides of the outside of the prefabricated steel part, and both ends of the outside of the support side plates are equipped with insertion rods. One end of the outside of the insertion rod is sleeved with a roller frame, and the outsides of the two roller frames are connected with extrusion side rollers that rotate together, and the outside of the extrusion side rollers is in contact with the outside of the outer arc-shaped spring sheet, and an extrusion mechanism for cooperating with the extrusion side rollers to apply lateral pressure to the outer arc-shaped spring sheet is arranged between the outsides of the two insertion rods.
[0011] Preferably, the extrusion mechanism includes a connecting plate and a plurality of pressure springs, the two ends of the outside of the connecting plate are respectively fixed to the outside of the corresponding side roller frame, and the plurality of pressure springs are evenly spaced between the connecting plate and the outside of the supporting side plate.
[0012] Preferably, one end of the outer portion of the sleeve is equipped with a gathering port, and an annular scraper is fixedly connected to the inner ring of the gathering port.
[0013] Preferably, stabilizing plates are inserted on the upper and lower sides of the exterior of the sleeve, and the two stabilizing plates are respectively fixed to the exterior of the outer arc-shaped spring piece and the inner arc-shaped spring piece.
[0014] Preferably, a plurality of ribs are circumferentially arranged on the outer surface of the sleeve, and one end of the outer sides of the plurality of ribs are fixed to the outer side of the prefabricated steel part.
[0015] Preferably, the inner circle of the water-stop cushion layer is coated with a lubricating layer, and the lubricating layer is graphite.
[0016] In summary, this application includes the following beneficial technical effects:
[0017] 1. Through the adaptive deformation of several pressure springs in the extrusion mechanism, it is convenient to timely apply lateral pressure to the connecting plate, the roller frame and the outside of the extrusion side roller, so that the outer arc-shaped spring piece and the inner arc-shaped spring piece are deformed and tightened as a whole, and the inner diameter value of the outer arc-shaped spring piece and the inner arc-shaped spring piece is timely reduced to ensure that the consumed water-stop cushion layer can still fit tightly to the outside of the moving jacking pipe, thereby improving the sealing effect between the jacking pipe and the water-stop cushion layer.
[0018] 2. An annular scraper is fixedly connected to the inner circle of the gathering port, so that the outer part of the jacking pipe can move in close contact with the inner circle of the annular scraper, which is convenient for continuously scraping away the residual sand on the outside of the jacking pipe, effectively reducing the wear of the jacking pipe on the water-stopping cushion layer, and further improving the durability of the water-stopping cushion layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the structure of the overall first-view of the construction of the present application;
[0020] Figure 2 This application Figure 1 A schematic diagram of the structure from the first perspective on the other side;
[0021] Figure 3 It is a structural schematic diagram of the local details of the sleeve and the supporting side plate of the present application;
[0022] Figure 4 This application Figure 1 Schematic diagram of the enlarged detail connection at point A.
[0023] Explanation of the reference numerals in the accompanying drawings: 1. Prefabricated steel parts; 2. Sleeve; 3. Rib; 4. Stabilizing plate; 5. Support side plate; 6. Gathering port; 7. Annular scraper; 8. Extrusion side roller; 9. Roller frame; 10. Insert rod; 11. Pressure spring; 12. Connecting plate; 13. Water-stop cushion; 14. Outer arc spring; 15. Inner arc spring; 16. Lubricating layer. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] Example 1
[0026] like Figure 1-Figure 4 As shown, the present application discloses a water-stop structure used for vertical pipe jacking construction, including a prefabricated steel part 1, a sleeve 2 is installed inside the prefabricated steel part 1, and the prefabricated steel part 1 is a receiving well, wherein the sleeve 2 is cast at the receiving hole of the prefabricated steel part 1, and the inner wall of the sleeve 2 is fitted with an outer arc-shaped spring piece 14, and the inner wall of the outer arc-shaped spring piece 14 is fitted with an inner arc-shaped spring piece 15, wherein the outer arc-shaped spring piece 14 and the arc-shaped spring piece 15 are both made of stainless steel, and the inner walls of the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15 are both bonded with a water-stop cushion layer 13, so that the inner diameter values of the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15 can be adaptively changed under the action of external force, and cooperate with the water-stop cushion layer 13 to achieve a continuous sealing effect;
[0027] At the same time, support side plates 5 are installed on both sides of the outside of the prefabricated steel part 1, and both ends of the outside of the support side plates 5 are equipped with plug rods 10. One end of the outside of the plug rod 10 is sleeved with a roller frame 9, so that the inside of the roller frame 9 can move outside the plug rod 10 to avoid deformation and dislocation of the pressure spring 11. The outsides of the two roller frames 9 are connected to the extrusion side rollers 8 for common rotation. At the same time, notches are opened on both sides of the inside of the sleeve 2, so that the outside of the extrusion side rollers 8 fits with the outside of the outer arc spring piece 14, which is convenient for applying lateral pressure to the outside of the outer arc spring piece 14, causing the outer arc spring piece 14 and the inner arc spring piece 15 to deform;
[0028] At the same time, the extrusion side roller 8 can roll outside the outer arc spring piece 14 to avoid affecting the deformation of the outer arc spring piece 14. An extrusion mechanism is provided between the outsides of the two insertion rods 10 for cooperating with the extrusion side roller 8 to apply lateral pressure to the outer arc spring piece 14. The extrusion mechanism facilitates the real-time deformation of the outer arc spring piece 14 and the inner arc spring piece 15.
[0029] like Figure 1-Figure 3 As shown, the extrusion mechanism includes a connecting plate 12 and a plurality of pressure springs 11. The two ends of the outside of the connecting plate 12 are respectively fixed to the outside of the corresponding side roller frame 9. A plurality of pressure springs 11 are evenly distributed between the connecting plate 12 and the outside of the supporting side plate 5. Through the plurality of pressure springs 11, the connecting plate 12 and the roller frame 9 are elastically connected to one side of the outside of the supporting side plate 5, so as to provide the connecting plate 12 and the roller frame 9 with the force required for movement.
[0030] like Figure 1 and Figure 2 As shown, one end of the outer part of the sleeve 2 is equipped with a gathering port 6, which makes it easier for the jacking pipe to enter the interior of the sleeve 2 more accurately through the gathering port 6. At the same time, an annular scraper 7 is fixedly connected to the inner circle of the gathering port 6. The annular scraper 7 and the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15 initially have the same inner diameter value, so that when the jacking pipe enters the interior of the sleeve 2, the outer part of the jacking pipe can move in contact with the inner circle of the annular scraper 7, so as to continuously scrape off the residual mud and sand on the outside of the jacking pipe, effectively reduce the wear of the jacking pipe on the water-stop cushion layer 13, and further improve the durability of the water-stop cushion layer 13.
[0031] like Figure 1 and Figure 2 as well as Figure 4 As shown, stabilizing plates 4 are inserted at the upper and lower parts of the outside of the sleeve 2, and the two stabilizing plates 4 are respectively fixed to the outside of the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15, which can ensure the stability of the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15 inside the sleeve 2 without affecting the deformation of the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15.
[0032] like Figure 1 and Figure 2 As shown, a plurality of ribs 3 are circumferentially arranged on the outer surface of the sleeve 2, and one end of the outer side of the plurality of ribs 3 is fixed to the outer side of the prefabricated steel part 1. The plurality of ribs 3 further improve the overall support of the sleeve 2 to ensure the stability of the jacking pipe when it moves inside the sleeve 2.
[0033] like Figure 4 As shown, the inner circle of the water-stopping cushion layer 13 is coated with a lubricating layer 16, and the lubricating layer 16 is graphite, which improves the lubrication effect of the contact surface between the water-stopping cushion layer 13 of the outer arc-shaped spring piece 14 and the inner arc-shaped spring piece 15, and facilitates the contraction and movement of the inner arc-shaped spring piece 15 in the inner circle of the water-stopping cushion layer 13.
[0034] The standard parts used in the utility model can all be purchased from the market, and special-shaped parts can be customized according to the instructions and the drawings. The specific connection methods of each part adopt the conventional means such as mature bolts, rivets, welding, etc. in the existing technology. The machinery, parts and equipment all adopt the conventional models in the existing technology, and the circuit connection adopts the conventional connection method in the existing technology, which will not be described in detail here.
[0035] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0036] The implementation principle of a water-stop structure used in vertical pipe jacking construction in the embodiment of the present application is as follows: during operation, the construction personnel apply external force to the connecting plates 12 on both sides in advance to overcome the reverse force of the plurality of pressure springs 11, and drive the connecting plates 12 and the roller frame 9 and the extrusion side rollers 8 to move, so that the extrusion side rollers 8 on both sides do not contact the outside of the outer arc-shaped spring pieces 14, so that the outer arc-shaped spring pieces 14 and the inner arc-shaped spring pieces 15 can be stretched naturally, so that the pipe jacking can enter the inside of the sleeve 2 through the gathering port 6, so that the outer surface of the pipe jacking can be attached to the outside of the outer arc-shaped spring pieces 14 and the inner arc-shaped spring pieces 15, and at the same time, the water-stop cushion layer 13 is squeezed to achieve a sealing effect on the pipe jacking when it moves;
[0037] Then the construction personnel may lose control of the connecting plate 12, and under the influence of the reverse force of several pressure springs 11, the connecting plate 12, the roller frame 9 and the extrusion side roller 8 are driven to reset and move, so that the extrusion side roller 8 can fit the outer surface of the outer arc spring piece 14. As the top pipe moves inside the sleeve 2, the surface of the top pipe frictionally consumes the surface of the water-stop cushion layer 13 and the inner arc spring piece 15 bonded to the outside of the water-stop cushion layer 13, and several pressure springs 11 in the extrusion mechanism are stretched accordingly, and lateral pressure is continuously applied to the outside of the connecting plate 12, the roller frame 9 and the extrusion side roller 8, so that the outer arc spring piece 14 and the inner arc spring piece 15 are deformed and tightened as a whole, and the inner diameter value of the outer arc spring piece 14 and the inner arc spring piece 15 is reduced in time to ensure that the consumed water-stop cushion layer 13 can still fit tightly to the outside of the moving top pipe, thereby improving the sealing effect between the top pipe and the water-stop cushion layer 13.
[0038] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the utility model and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.
Claims
1. A water-stop structure used in vertical pipe jacking construction, comprising a prefabricated steel part (1), wherein a sleeve (2) is installed inside the prefabricated steel part (1), characterized in that: The inner wall of the sleeve (2) is fitted with an outer arc-shaped spring piece (14), the inner wall of the outer arc-shaped spring piece (14) is fitted with an inner arc-shaped spring piece (15), and the inner walls of the outer arc-shaped spring piece (14) and the inner arc-shaped spring piece (15) are both bonded with a water-stop cushion layer (13); Support side plates (5) are installed on both sides of the exterior of the prefabricated steel part (1), and both ends of the exterior of the support side plates (5) are equipped with insertion rods (10), and one end of the exterior of the insertion rod (10) is sleeved with a roller frame (9), and an extrusion side roller (8) is rotatably connected between the exteriors of the two roller frames (9), and the exterior of the extrusion side roller (8) is in contact with the exterior of the outer arc-shaped spring sheet (14), and an extrusion mechanism is provided between the exteriors of the two insertion rods (10) for cooperating with the extrusion side roller (8) to apply lateral pressure to the outer arc-shaped spring sheet (14).
2. A water-stop structure for vertical pipe jacking construction according to claim 1, characterized in that: The extrusion mechanism comprises a connecting plate (12) and a plurality of pressure springs (11), the two ends of the outside of the connecting plate (12) are respectively fixed to the outside of the corresponding side roller frame (9), and a plurality of pressure springs (11) are evenly spaced between the connecting plate (12) and the outside of the supporting side plate (5).
3. A water-stop structure for vertical pipe jacking construction according to claim 2, characterized in that: One end of the outer portion of the sleeve (2) is equipped with a gathering port (6), and the inner ring of the gathering port (6) is fixedly connected with an annular scraper (7).
4. A water-stop structure for vertical pipe jacking construction according to claim 3, characterized in that: The outer part of the sleeve (2) is interspersed with stabilizing plates (4) at the upper and lower parts, and the two stabilizing plates (4) are respectively fixed to the outer parts of the outer arc-shaped spring piece (14) and the inner arc-shaped spring piece (15).
5. A water-stop structure for vertical pipe jacking construction according to claim 4, characterized in that: A plurality of ribs (3) are circumferentially arranged on the outer surface of the sleeve (2), and one end of the outer sides of the plurality of ribs (3) are fixed to the outer side of the prefabricated steel part (1).
6. The water-stop structure used in vertical pipe jacking construction according to claim 1, characterized in that: The inner circle of the water-stop cushion layer (13) is coated with a lubricating layer (16), and the lubricating layer (16) is graphite.