Climbing type boiler bottom platform of pulverized coal boiler

By designing a climbing furnace bottom platform for pulverized coal boilers, and using the combination of structural beam components and elevators, the problem of time-consuming and laborious construction of steel pipe frame working platform is solved, and efficient and safe platform installation and use is achieved.

CN222007232UActive Publication Date: 2024-11-15SHANDONG JINDAOCHENG MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420452430.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-09
Publication Date
2024-11-15
Estimated Expiration
2034-03-09

AI Technical Summary

Technical Problem

During maintenance of coal pulverized boilers for units above 300MW, building a steel pipe frame working platform is time-consuming and labor-intensive, with high safety risks, high labor costs, and high altitude construction risks.

Method used

A pulverized coal boiler climbing furnace bottom platform is designed, including structural beam assembly, elevator and platform springboard. The structural beam assembly consists of fixed cross beam, connecting beam and folding beam, and water cooling is achieved with the furnace slope surface through articulated and guide rollers. The tight contact of the wall and the smooth climbing of the elevator realizes the lifting and installation of the platform through the wire rope.

Benefits of technology

It effectively reduces the risk of building platforms at high altitudes, reduces the labor intensity of installation workers, shortens installation time, and improves safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222007232U_ABST
    Figure CN222007232U_ABST
Patent Text Reader

Abstract

The utility model discloses a climbing type boiler bottom platform of a pulverized coal boiler. The climbing type boiler bottom platform is provided with a structural beam assembly, an elevator and a walking board springboard. The structural beam assembly comprises a fixed cross beam, a connecting beam and a folding beam; at least two fixed cross beams are arranged; the connecting beams are vertically connected between the fixed cross beams in a staggered manner to form a central main body of the structural beam assembly; the folding beams are symmetrically distributed on the two sides of the fixed cross beam, the folding beam close to the fixed cross beam is hinged to the outer side of the fixed cross beam, every two adjacent folding beams are hinged end to end, and a foot plate is arranged at the position, making contact with a hearth slope water cooling wall, of the outer end of each folding beam. The elevator is fixedly connected with the structural beam assembly through the machine base, and the walking board springboard is laid on the upper end face of the structural beam assembly. Risks of high-altitude platform building are effectively reduced, labor intensity of installation workers is reduced, installation time is shortened, and safety is higher than that of a steel pipe frame working platform.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a working platform, in particular to a climbing furnace bottom platform of a pulverized coal boiler used in a thermal (thermal) power plant. Background Art

[0002] A pulverized coal boiler is an industrial boiler that generates heat by burning pulverized coal that is blown into a combustion chamber. The bottom of the pulverized coal boiler furnace is funnel-shaped and has an ash dropout port at the bottom of the furnace.

[0003] At present, when thermal (thermal) power plants overhaul the furnace of pulverized coal boilers of units above 300MW, they usually first use construction steel pipes to build scaffolding upwards on the slag scoop conveyor belt to the turning point of the water-cooled wall slope or the position of the maintenance manhole close to the operating floor elevation, and then lay a springboard on it to make a steel pipe rack working platform for the installation of the furnace maintenance lifting platform.

[0004] However, since the height difference from the conveyor belt of the slag scoop machine to the ash dropping throat is generally more than 6 meters, and the area is relatively narrow, usually about 1.4 meters wide; the elevation of the maintenance manhole on the operating floor is generally around 16 meters, and the front and rear widths of the pulverized coal boiler furnace of units above 300MW are relatively large, building a steel pipe rack working platform is not only time-consuming and labor-intensive, but also has great safety hazards and high labor costs. Utility Model Content

[0005] To this end, the embodiment of the utility model provides a climbing furnace bottom platform for a pulverized coal boiler, which solves the problem that the traditional construction of a steel pipe rack working platform is time-consuming and labor-intensive, has great safety hazards, and has high labor costs.

[0006] In order to achieve the above-mentioned purpose, the embodiment of the utility model provides the following technical solutions: a climbing furnace bottom platform of a pulverized coal boiler, comprising a structural beam assembly, a hoist and a platform springboard;

[0007] The structural beam assembly includes a fixed beam, a connecting beam and a folding beam; at least two fixed beams are provided; the connecting beams are vertically staggered and connected between the fixed beams to form the central body of the structural beam assembly; the folding beams are symmetrically distributed on both sides of the fixed beams, the folding beams close to the fixed beams are hinged on the outside of the fixed beams, the two adjacent folding beams are hinged to each other end to end, and a foot plate is provided at the position where the outer end of each folding beam contacts the water-cooled wall of the slope surface of the furnace;

[0008] The hoist is fixedly connected to the structural beam assembly via a machine base, and the platform ramp is laid on the upper end surface of the structural beam assembly.

[0009] As a preferred solution for the climbing furnace bottom platform of the pulverized coal boiler, the foot plate is arranged at the end where the folding beam of the front road contacts the water-cooled wall on the slope surface of the furnace, and the foot plate is installed near the contact between the lower hinge seat and the water-cooled wall on the slope surface of the furnace;

[0010] The foot plate is also arranged at one end of the last folding beam in contact with the water-cooled wall on the slope surface of the furnace, and the foot plate is directly mounted on several ends of the folding beam in contact with the water-cooled wall on the slope surface of the furnace;

[0011] The inclination angle of the foot plate is the same as the inclination angle of the water-cooled wall of the furnace slope surface.

[0012] As a preferred solution for the climbing furnace bottom platform of a pulverized coal boiler, a guide roller is provided under the foot plate. During the climbing process, the outer end of the folding beam contacts the water-cooled wall of the sloped surface of the furnace through the guide roller for climbing guidance.

[0013] As a preferred solution for the climbing furnace bottom platform of the pulverized coal boiler, the folding beam and the upper part of the fixed beam, and the folding beam of the rear track and the upper part of the folding beam of the front track are hinged through an upper hinge seat;

[0014] When the folding beam and the fixed beam are in a horizontal state, the lower parts of the folding beam and the fixed beam are hinged via a lower hinge seat;

[0015] When the folding beam of the rear track and the folding beam of the front track are in a horizontal state, the lower parts of the folding beams of the front and rear tracks are hinged through the lower hinge seat.

[0016] As a preferred solution for the climbing furnace bottom platform of a pulverized coal boiler, the hoist is connected to the steel wire rope introduced into the furnace from the steel wire rope hole on the furnace top.

[0017] As a preferred solution for the climbing furnace bottom platform of the pulverized coal boiler, the platform springboard adopts a steel plate mesh working surface structure or a metal plate structure welded into a frame by metal materials;

[0018] The lower end of the platform springboard is placed on the folding beams adjacent to the left and right through a hook or an ear fork.

[0019] As a preferred solution for the climbing furnace bottom platform of the pulverized coal boiler, the structural beam assembly is provided with two groups of lifting points, the first group of lifting points is distributed at the upper ends of the fixed cross beam and the connecting beam; the second group of lifting points is distributed at the upper end of the folding beam in the front road;

[0020] Each group of lifting points is provided with four or more;

[0021] The hoist is connected to the structural beam assembly at the hoisting point through a machine base.

[0022] As a preferred solution for the climbing furnace bottom platform of the pulverized coal boiler, an ash cover plate auxiliary platform is provided below the structural beam assembly, and the ash cover plate auxiliary platform is built at the throat position of the ash outlet of the furnace.

[0023] The beneficial effects of the utility model are that it is provided with a structural beam assembly, a hoist and a platform springboard; the structural beam assembly includes a fixed beam, a connecting beam and a folding beam; there are at least two fixed beams; the connecting beams are vertically staggered and connected between the fixed beams to form the central body of the structural beam assembly; the folding beams are symmetrically distributed on both sides of the fixed beams, the folding beams close to the fixed beams are hinged on the outside of the fixed beams, the two adjacent folding beams are hinged to each other end to end, and the outer end of each folding beam is provided with a foot plate at the position where the water-cooled wall of the slope surface of the furnace is contacted; the hoist is fixedly connected to the structural beam assembly through the machine base, and the platform springboard is laid on the upper end surface of the structural beam assembly. The utility model effectively reduces the risk of building a platform at high altitude, reduces the labor intensity of the installation workers, shortens the installation time, and is safer than using a steel pipe rack work platform. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the implementation or the prior art description. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.

[0025] The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification so as to facilitate understanding and reading by persons familiar with the technology. They are not used to limit the conditions under which the present invention can be implemented, and therefore have no substantial technical significance. Any structural modification, change in proportion or adjustment in size shall still fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention.

[0026] Figure 1 It is a schematic diagram of the state of the climbing furnace bottom platform of the pulverized coal boiler provided in the embodiment of the utility model at the ash falling throat of the furnace;

[0027] Figure 2 It is a schematic diagram of the unfolded state of the first folding beam of the climbing furnace bottom platform of the pulverized coal boiler provided in the embodiment of the utility model;

[0028] Figure 3 It is a schematic diagram of the fully unfolded state of the folding beams of the climbing furnace bottom platform of the pulverized coal boiler provided in the embodiment of the utility model;

[0029] Figure 4A schematic diagram of the state change of the climbing process of the climbing furnace bottom platform of a pulverized coal boiler provided in an embodiment of the utility model;

[0030] Figure 5 It is a schematic diagram of a top view of the folding beams of the climbing furnace bottom platform of a pulverized coal boiler provided in an embodiment of the utility model after they are fully unfolded.

[0031] In the figure: 1. Structural beam assembly; 2. Hoist; 3. Walkway springboard; 4. Fixed crossbeam; 5. Connecting beam; 6. Folding beam; 7. Machine base; 8. Water-cooled wall; 9. Footboard; 10. Guide roller; 11. Upper hinge seat; 12. Lower hinge seat; 13. Wire rope; 14. Lifting point; 15. Gray cast cover auxiliary platform; 16. Throat. DETAILED DESCRIPTION

[0032] The following is a specific embodiment of the present invention. People familiar with the technology can easily understand the other advantages and functions of the present invention from the contents disclosed in this specification. Obviously, the described embodiment is a part of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0033] See also Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 The utility model embodiment provides a climbing furnace bottom platform of a pulverized coal boiler, including a structural beam assembly 1, a hoist 2 and a platform springboard 3;

[0034] The structural beam assembly 1 includes a fixed beam 4, a connecting beam 5 and a folding beam 6; the fixed beam 4, the connecting beam 5 and the folding beam 6 of the structural beam assembly 1 are welded into a sheet-type or polygonal structural frame using metal profiles, at least two fixed beams 4 are provided, and the number of fixed beams 4 can be increased as needed, and the connecting beams 5 are vertically staggered and connected between the fixed beams 4 to form the central body of the structural beam assembly 1; the folding beams 6 are symmetrically distributed on both sides of the fixed beam 4, the folding beams 6 close to the fixed beam 4 are hinged on the outside of the fixed beam 4, and the two adjacent folding beams 6 are hinged to each other end to end, and a foot plate 9 is provided at the position where the outer end of each folding beam 6 contacts the water-cooled wall 8 on the slope surface of the furnace;

[0035] The hoist 2 is fixedly connected to the structural beam assembly 1 through the machine base 7, the platform springboard 3 is laid on the upper end surface of the structural beam assembly 1, and the platform springboard 3 adopts a steel plate mesh working surface structure or a metal plate structure welded into a frame by metal materials; the lower end of the platform springboard 3 is placed on the left and right adjacent folding beams 6 through a hook or ear fork;

[0036] Among them, an ash cover auxiliary platform 15 is provided below the structural beam assembly 1. The ash cover auxiliary platform 15 is built at the throat 16 of the ash outlet of the furnace. The ash cover auxiliary platform 15 serves as a basic working platform for assembling the climbing furnace bottom platform of the pulverized coal boiler.

[0037] Since the front-to-back width of the furnace of the pulverized coal boiler of units above 300MW is relatively large, the climbing furnace bottom platform of the pulverized coal boiler of this embodiment can be assembled at the ash throat 16 of the boiler furnace, and the climbing hoist 2 is used to realize the overall lifting and installation, and the structural beam assembly 1 is divided into two or more folding modes for unfolding, which changes the dilemma of difficult installation and difficult unfolding due to the long structural beam assembly 1. When assembling at the ash throat 16 for the first time, the first folding beam 6 is installed first, and when it rises to the specified position, the first folding beam 6 is unfolded and the platform springboard 3 is laid; then the second folding beam 6 is connected, and when it rises to the preset installation position, the second folding beam 6 is unfolded and the remaining platform springboard 3 is laid; the third folding beam 6 can also be installed in sequence as needed until it rises to the final installation position.

[0038] Assistance Figure 1 and Figure 2 In this embodiment, a foot plate 9 is provided at the contact point between the folding beam 6 and the furnace slope surface water-cooled wall 8, wherein a foot plate 9 is provided at the end of the preceding folding beam 6 that contacts the furnace slope surface water-cooled wall 8, and the foot plate 9 at the preceding folding beam 6 is installed at the position of contact with the furnace slope surface water-cooled wall 8 near the lower hinge seat 12; in addition, a foot plate 9 is also provided at the end of the last folding beam 6 that contacts the furnace slope surface water-cooled wall 8, and the foot plate 9 at the last folding beam 6 is directly installed at several end positions where the folding beam 6 contacts the furnace slope surface water-cooled wall 8. Moreover, the angle of the foot plate 9 is the same as the slope angle of the furnace slope surface water-cooled wall 8, so that the furnace slope surface water-cooled wall 8 can stably support the folding beam 6 through the foot plate 9.

[0039] During the climbing process, the outer end of the folding beam 6 contacts the furnace slope water-cooled wall 8 through the guide roller 10 for climbing guidance. The guide roller 10 allows the structural beam assembly 1 to crawl along the furnace slope water-cooled wall 8 to prevent the furnace slope water-cooled wall 8 from being scratched during the lifting process, thereby achieving slow and smooth lifting.

[0040] Assistance Figure 1 and Figure 4In this embodiment, the folding beam 6 is installed at both ends of the fixed beam 4, and the folding beam 6 and the upper part of the fixed beam 4, as well as the upper part of the rear folding beam 6 and the upper part of the front folding beam 6 are hinged through the upper hinge seat 11; when the folding beam 6 and the fixed beam 4 are in a horizontal state, the folding beam 6 and the lower part of the fixed beam 4 are hinged through the lower hinge seat 12; when the rear folding beam 6 and the front folding beam 6 are in a horizontal state, the lower parts of the front and rear folding beams 6 are hinged through the lower hinge seat 12, and after the hinge, the locking pin (existing structure) is inserted to achieve a firm connection.

[0041] Assistance Figure 5 In this embodiment, the structural beam assembly 1 is provided with two groups of lifting points 14, the first group of lifting points 14 is distributed at the upper ends of the fixed cross beam 4 and the connecting beam 5; the second group of lifting points 14 is distributed at the upper ends of the front folding beam 6; each group of lifting points 14 is provided with more than four; the base 7 of the hoist 2 is connected to the structural beam assembly 1 through the lifting points 14, and the hoist 2 is provided with more than four; the hoist 2 is connected to the wire rope 13 introduced into the furnace from the wire rope hole on the furnace top, and the entire structural beam assembly 1 is driven to rise and fall slowly and smoothly by controlling the hoist 2, thereby realizing the installation and disassembly of the furnace bottom platform.

[0042] The process of building the climbing furnace bottom platform of the pulverized coal boiler in this embodiment is as follows:

[0043] First, an ash cover auxiliary platform 15 is built at the throat 16 of the ash outlet of the pulverized coal boiler. The ash cover auxiliary platform 15 serves as the basic working platform for assembling the climbing furnace bottom platform of the pulverized coal boiler. A hoist 2 is brought in from the slag scooping machine below the ash outlet at the bottom of the furnace. The hoist 2 is used to lift the parts of the ash cover auxiliary platform 15 to the throat 16 of the ash outlet and install them one by one.

[0044] Then, the fixed beam 4 and the connecting beam 5 are lifted to the gray cover auxiliary platform 15 by the hoist 2. The split parts of the connecting beam 5 are connected end to end to form a long connecting beam 5 with the same width direction as the left and right sides of the furnace; all the fixed beams 4 are placed at the installation position between the two long connecting beams 5, vertically staggered and firmly connected with bolts or pins to form the central body of the structural beam assembly 1. The first folding beam 6 corresponds to the ends of the fixed beam 4 one by one, and is respectively installed on the outside of the two ends of the fixed beam 4, and is hinged through the upper hinge seat 11. The first folding beam 6 is placed obliquely on the water-cooled wall 8 on the slope surface of the furnace through the guide roller 10.

[0045] Then install the base 7 of the hoist 2 on a group of lifting points 14 inside the central body of the structural beam assembly 1, install the hoist 2, connect the wire rope 13 introduced from the wire rope hole on the furnace roof to the hoist 2, and operate the hoist 2 to drive the structural beam assembly 1 to rise slowly and steadily. When it rises to a horizontal state, the first folding beam 6 is hinged with the lower hinge seat 12 of the fixed crossbeam 4, and then the lock pin is inserted to connect firmly, and the folding beam 6 is adjusted so that all the footboards 9 are firmly in contact with the water-cooled wall 8 on the slope surface of the furnace. The platform springboard 3 is laid outward from both sides of the connecting beam 5 until it is laid close to the water-cooled wall 8 on the slope surface of the furnace.

[0046] Then move all the machine bases 7 together with the hoist 2 to a group of lifting points 14 outside the first folding beam 6 near the outer end of the water-cooled wall 8 on the slope surface of the furnace, and prepare for the second lifting installation; connect the second or last folding beam 6 to the outer end of the first folding beam 6, and the last folding beam 6 corresponds to the end of the previous folding beam 6 one by one, and is hinged through the upper hinge seat 11. The last folding beam 6 is placed obliquely on the water-cooled wall 8 on the slope surface of the furnace through the guide roller 10 at the end. Operate the hoist 2 to drive the structural beam assembly 1 to rise slowly and steadily. When the last folding beam 6 is in a horizontal state, after the last folding beam 6 is hinged with the lower hinge seat 12 of the previous folding beam 6, insert the locking pin to connect it firmly, and adjust the foot plate 9 of the end folding beam 6 until it is firmly in contact with the water-cooled wall 8 on the slope surface of the furnace; then spread the last folding beam 6 outward to cover the walkway ramp 3. The lower end of the platform springboard 3 is placed and fixed on the adjacent folding beams 6 on the left and right through a hook or ear fork and a matching positioning block. Finally, the connecting piece of the machine base 7 and the folding beam 6 is separated, and the hoist 2 is controlled to be retracted upward to separate the machine base 7 from the furnace bottom platform.

[0047] In summary, the utility model is provided with a structural beam assembly 1, a hoist 2 and a platform springboard 3; the structural beam assembly 1 includes a fixed beam 4, a connecting beam 5 and a folding beam 6; at least two fixed beams 4 are provided; the connecting beams 5 are vertically staggered and connected between the fixed beams 4 to form the central body of the structural beam assembly 1; the folding beams 6 are symmetrically distributed on both sides of the fixed beam 4, the folding beams 6 close to the fixed beam 4 are hinged on the outside of the fixed beam 4, the two adjacent folding beams 6 are hinged to each other at the head and tail, and a foot plate 9 is provided at the position where the outer end of each folding beam 6 contacts the water-cooled wall 8 of the slope surface of the furnace; the hoist 2 is fixedly connected to the structural beam assembly 1 through the machine base 7, and the platform springboard 3 is laid on the upper end surface of the structural beam assembly 1. The utility model can be assembled at the ash drop throat 16 of the boiler furnace, and the climbing hoist 2 is used to realize the overall lifting and installation, and the structural beam assembly 1 is divided into two or more folding ways to unfold, changing the dilemma of difficult installation and difficult unfolding due to the long structural beam assembly 1. When assembling at the ash throat 16 for the first time, first install the first folding beam 6, and when it rises to the specified position, unfold the first folding beam 6 and lay the platform springboard 3; then connect the second folding beam 6, and when it rises to the preset installation position, unfold the second folding beam 6 and lay the remaining platform springboard 3; the third folding beam 6 can also be installed in sequence as needed until it rises to the final installation position. The utility model effectively reduces the risk of high-altitude construction platforms, reduces the labor intensity of installation workers, shortens installation time, and is safer than using a steel pipe frame work platform.

[0048] Although the utility model has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the utility model. Therefore, these modifications or improvements made without departing from the spirit of the utility model are within the scope of protection claimed by the utility model.

Claims

1. A climbing furnace bottom platform for a pulverized coal boiler, characterized in that: It comprises a structural beam assembly (1), a hoist (2) and a platform springboard (3); The structural beam assembly (1) comprises a fixed crossbeam (4), a connecting beam (5) and a folding beam (6); the connecting beam (5) is vertically staggered and connected between the fixed crossbeams (4) to form a central body of the structural beam assembly (1); the folding beams (6) are symmetrically distributed on both sides of the fixed crossbeam (4), the folding beams (6) close to the fixed crossbeam (4) are hinged on the outside of the fixed crossbeam (4), the two adjacent folding beams (6) are hinged to each other end to end, and a foot plate (9) is provided at the position where the outer end of each folding beam (6) contacts the furnace slope surface water-cooled wall (8); The hoist (2) is fixedly connected to the structural beam assembly (1) via a machine base (7), and the platform springboard (3) is laid on the upper end surface of the structural beam assembly (1).

2. The climbing furnace bottom platform of a pulverized coal boiler according to claim 1, characterized in that: The foot plate (9) is arranged at one end of the front folding beam (6) that contacts the furnace slope surface water-cooled wall (8), and the foot plate (9) is installed near the lower hinge seat (12) where it contacts the furnace slope surface water-cooled wall (8); The foot plate (9) is also arranged at one end of the last folding beam (6) in contact with the furnace slope surface water-cooled wall (8), and the foot plate (9) is directly mounted on a plurality of ends of the folding beam (6) in contact with the furnace slope surface water-cooled wall (8); The inclination angle of the foot plate (9) is the same as the inclination angle of the furnace slope surface water-cooled wall (8).

3. The climbing furnace bottom platform of a pulverized coal boiler according to claim 2, characterized in that: A guide roller (10) is provided below the foot plate (9), and during the climbing process, the outer end of the folding beam (6) contacts the furnace slope water-cooled wall (8) through the guide roller (10) to guide the climbing.

4. The climbing furnace bottom platform of a pulverized coal boiler according to claim 3, characterized in that: The folding beam (6) and the upper part of the fixed crossbeam (4), as well as the folding beam (6) of the rear track and the upper part of the folding beam (6) of the front track are all hingedly connected via an upper hinge seat (11); When the folding beam (6) and the fixed crossbeam (4) are in a horizontal state, the folding beam (6) and the lower part of the fixed crossbeam (4) are hingedly connected via a lower hinge seat (12); When the rear folding beam (6) and the front folding beam (6) are in a horizontal state, the lower parts of the front and rear folding beams (6) are hingedly connected via the lower hinge seat (12).

5. The climbing furnace bottom platform of a pulverized coal boiler according to claim 1, characterized in that: The hoist (2) is connected to a steel wire rope (13) introduced into the furnace from a steel wire rope hole at the furnace top.

6. The climbing furnace bottom platform of a pulverized coal boiler according to claim 1, characterized in that: The walkway ramp (3) is a steel plate mesh working surface structure or a metal plate structure welded into a frame by metal materials; The lower end of the platform springboard (3) is placed on the folding beams (6) adjacent to the left and right through a hook or an ear fork.

7. The climbing furnace bottom platform of a pulverized coal boiler according to claim 1, characterized in that: The structural beam assembly (1) is provided with two groups of lifting points (14), the first group of lifting points (14) being distributed at the upper ends of the fixed cross beam (4) and the connecting beam (5); the second group of lifting points (14) being distributed at the upper end of the front folding beam (6); Each group of lifting points (14) is provided with four or more; The hoist (2) is connected to the structural beam assembly (1) at the hoisting point (14) via a machine base (7).

8. The climbing furnace bottom platform of a pulverized coal boiler according to claim 1, characterized in that: A ash cover plate auxiliary platform (15) is provided below the structural beam assembly (1), and the ash cover plate auxiliary platform (15) is built at the throat (16) of the ash outlet of the furnace.