Splicing structure for new and old joint part of highway reconstruction and extension project
By adopting a multi-layer stepped splicing layer structure and embedded steel bar design in the renovation and expansion project of the expressway, the problems of insufficient strength and construction difficulties in the joints of new and old pavements in the existing technology are solved, and more stable pavement connections and more High splicing strength.
Patent Information
- Application Number
- CN202420604406.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-27
AI Technical Summary
The splicing structure of the new and old joints of the existing highway renovation and expansion projects prevents low structural strength and difficult construction, especially the insufficient bonding strength of the frame and cement and sand, which makes it difficult to stabilize the connection and easily cause cracking and damage to the road surface.
Using a multi-layer stepped splicing layer structure, alternating limit grooves and reinforcement grooves are provided on the first splicing layer and the second splicing layer, and pre-embed steel bars in the reinforcing grooves to form connection blocks to enhance connection strength and ensure new and old. Stable connection between roadbeds.
It effectively enhances the strength and stability of the connection between old and new pavements, prevents longitudinal separation, and improves the overall splicing strength and construction convenience of the splicing structure.
Smart Images

Figure CN222008508U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of new and old road surface splicing, and more specifically, particularly relates to a new and old joint splicing structure of a highway reconstruction and expansion project. Background Art
[0002] With the continuous development of society, the mileage of highways is constantly increasing, and highways are also constantly widening. However, the widening construction of highways will cause differential settlement of new and old pavements, resulting in cracking and damage to the pavement at the joints. Therefore, how to solve the problem of highway joints is a problem that needs to be solved at present. The patent with the prior art announcement number CN217351975U discloses a splicing structure of the new and old joints of a highway reconstruction and expansion project. It prevents horizontal displacement by adding a frame layer, but the above-mentioned prior art does not consider the bonding strength between the frame and cement, sand and gravel, and is relatively difficult to lay in actual use. Therefore, on this basis, a structure is needed that can reduce foreign objects, prevent low structural strength and construction difficulties, and solve the problem of splicing the new and old joints of high-speed highways. Utility Model Content
[0003] The utility model is to overcome the above-mentioned shortcomings and aims to provide a new and old joint part splicing structure of a highway reconstruction and expansion project which can solve the above-mentioned problems.
[0004] A splicing structure of the new and old joints of a highway reconstruction and expansion project, comprising an original roadbed and a spliced roadbed. A multi-layer first splicing layer is arranged at one end of the original roadbed close to the spliced roadbed, the multi-layer first splicing layer is arranged in a stepped shape, and a connecting groove is provided on the first splicing layer. A multi-layer second splicing layer is arranged at one end of the spliced roadbed close to the original roadbed, the second splicing layers correspond one-to-one to the first splicing layer, the multi-layer second splicing layers are in an inverted stepped structure, and a connecting block adapted to the connecting groove is integrally arranged at the bottom of the second splicing layer.
[0005] Furthermore, the connecting groove includes a limiting groove and a reinforcement groove, the limiting groove includes a transverse groove and a longitudinal groove connected to each other, the longitudinal groove is connected to the outside at one end close to the spliced roadbed, the reinforcement groove is a columnar structure, the connecting block includes a limiting block and a reinforcement block, and steel bars are pre-embedded in the reinforcement block.
[0006] Furthermore, the upper end of the steel bar extends into the second splicing layer.
[0007] Furthermore, the limiting grooves and the reinforcing grooves on the same first splicing layer are arranged alternately.
[0008] Furthermore, the limiting grooves and the reinforcement grooves on different first splicing layers are arranged alternately.
[0009] Furthermore, the bottom of each layer of the reinforcement groove extends to the bottom of the original roadbed.
[0010] Furthermore, the limiting groove has a T-shaped structure.
[0011] Furthermore, the limiting groove is composed of a longitudinal groove and a plurality of transverse grooves arranged at equal intervals, and the longitudinal groove runs through the middle of the transverse groove.
[0012] Furthermore, the upper surface of the first splicing layer has a serrated structure.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] The splicing structure of the new and old joint parts of the highway reconstruction and expansion project in the utility model also adopts a stepped splicing structure. The original roadbed is provided with multiple layers of first splicing layers, and the spliced roadbed is reversely provided with multiple layers of second splicing layers adapted to the first splicing layers, and a connecting groove is provided on each layer of the first splicing layer, so that a connecting block integrally formed with the second splicing layer is arranged in the connecting groove, and the same structural layers are directly used for docking, thereby effectively enhancing the connection strength of the splicing structure.
[0015] The utility model discloses a splicing structure of the new and old joints of a highway reconstruction and expansion project. The connection block is composed of a limit block and a reinforcement block. The limit groove includes a transverse groove and a longitudinal groove that are interconnected. The longitudinal groove is connected to the outside at one end near the spliced roadbed. The transverse groove strengthens the longitudinal connection strength between the new and old roadbeds, effectively preventing the longitudinal separation between the new and old roadbeds, which causes the problem of road surface damage. The columnar reinforcement block has a good supporting effect with embedded steel bars, which effectively enhances the stability of the splicing structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0017] Figure 1 It is a schematic diagram of the overall structure of the splicing structure of the new and old joints of the highway reconstruction and expansion project in Example 1.
[0018] Figure 2 It is a structural schematic diagram of the original roadbed in Example 1.
[0019] Figure 3 It is a structural schematic diagram of the spliced roadbed in Example 1.
[0020] Figure 4 It is a schematic diagram of the structure of the reinforcement block in the first embodiment.
[0021] Figure 5It is a schematic diagram of the structure of the original roadbed in the second embodiment.
[0022] Figure 6 It is a structural schematic diagram of the spliced roadbed in the second embodiment.
[0023] Figure 7 It is a structural schematic diagram of the original roadbed in Example 3.
[0024] Figure 8 It is a structural schematic diagram of the spliced roadbed in Example 3.
[0025] In the figure: 1. original roadbed; 2. spliced roadbed; 3. first splicing layer; 4. second splicing layer; 5. limiting groove; 501. transverse groove; 502. longitudinal groove; 6. reinforcement groove; 7. limiting block; 8. reinforcement block; 9. steel bar. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0027] Embodiment 1:
[0028] like Figure 1 , Figure 2 and Figure 3 As shown, the splicing structure of the new and old joints of the highway reconstruction and expansion project in this embodiment includes an original roadbed 1 with a flush upper surface and a spliced roadbed 2. A multi-layer first splicing layer 3 is arranged at one end of the original roadbed 1 close to the spliced roadbed 2. The multi-layer first splicing layer 3 is arranged in a stepped shape, and a connecting groove is opened on each first splicing layer 3. A multi-layer second splicing layer 4 is arranged at one end of the spliced roadbed 2 close to the original roadbed 1. The second splicing layers 4 are laid one by one on the first splicing layer 3. The multi-layer second splicing layers 4 are in an inverted stepped structure, and a connecting block adapted to the connecting groove is integrally arranged at the bottom of the second splicing layer 4.
[0029] In this embodiment, the connecting groove includes a limiting groove 5 and a reinforcement groove 6. The limiting groove 5 includes a transverse groove 501 and a longitudinal groove 502 which are connected to each other. The longitudinal groove 502 is connected to the outside at one end close to the splicing roadbed 2. The reinforcement groove 6 is a vertically arranged columnar structure. The connecting block includes a limiting block 7 and a reinforcement block 8 which are respectively matched with the limiting groove 5 and the reinforcement groove 6. Steel bars 9 are vertically embedded in the reinforcement block 8.
[0030] Specifically, in this embodiment, the first splicing layer 3 is provided with three layers, and the width of the first splicing layer 3 increases from top to bottom, and the thickness of the three layers of the first splicing layer 3 is the same. The limiting groove 5 is a T-shaped structure composed of a transverse groove 501 and a longitudinal groove 502, and the thickness of the limiting groove 5 on the three layers of the first splicing layer 3 is the same. The limiting block 7 is a T-shaped structure matching the limiting groove 5. The reinforcement groove 6 is a cylindrical structure, and the reinforcement block 8 is a cylindrical structure matching the reinforcement groove 6, such as Figure 4 As shown, the embedded steel bars 9 in the reinforcement block 8 are vertically distributed in a circular array and tied with annular ribs (not shown in the figure). The upper ends of the steel bars 9 extend upward into the second splicing layer 4, thereby improving the connection strength between the second splicing layer 4 and the reinforcement block 8.
[0031] In some other embodiments, the number of the first splicing layer 3 and the second splicing layer 4 can be set according to actual conditions.
[0032] In this embodiment, the limiting grooves 5 and the reinforcing grooves 6 on the same first splicing layer 3 are arranged alternately, the limiting grooves 5 on different first splicing layers 3 are arranged alternately, and the reinforcing grooves 6 on different first splicing layers 3 are also arranged alternately, so that the force is evenly distributed, and the overall splicing strength of the original roadbed 1 and the spliced roadbed 2 can be enhanced, as well as the stability of the spliced roadbed 2. In addition, the bottom of each layer of reinforcing grooves 6 extends to the bottom of the original roadbed 1, and the lower end of the corresponding reinforcing block 8 extends to the bottom of the original roadbed 1, thereby increasing the connection area as much as possible.
[0033] The working principle of the splicing structure of the new and old joints of the highway reconstruction and expansion project in this embodiment is:
[0034] During construction, first, a stepped multi-layer first splicing layer 3 is opened at the splicing end of the original roadbed 1, and a T-shaped limit groove 5 and a cylindrical reinforcement groove 6 are alternately opened on each first splicing layer 3, and then the tied steel bars 9 are placed in the reinforcement groove 6, and the limit blocks 7, reinforcement blocks 8, the second splicing layer 4 and the spliced roadbed 2 are integrally cast using roadbed materials. Later, the surface layer of the highway can be paved on the surface of the original roadbed 1 and the spliced roadbed 2.
[0035] The splicing structure of the new and old joints of the highway reconstruction and expansion project in this embodiment also adopts a stepped splicing structure. The original roadbed 1 is provided with multiple layers of first splicing layers 3, and the spliced roadbed 2 is reversely provided with multiple layers of second splicing layers 4 adapted to the first splicing layers 3, and each layer of the first splicing layer 3 is provided with a limiting groove 5 and a reinforcement groove 6, so that a limiting block 7 and a reinforcement block 8 integrally formed with the second splicing layer 4 are arranged in the limiting groove 5 and the reinforcement groove 6, and the same structural layers are directly used for docking, so as to effectively enhance the connection strength of the splicing structure.
[0036] Embodiment 2:
[0037] The splicing structure of the new and old joints of the highway reconstruction and expansion project in this embodiment is a further improvement based on the first embodiment.
[0038] Specifically, Figure 5 , Figure 6 As shown, the limit groove 5 in this embodiment is composed of a longitudinal groove 502 and a plurality of transverse grooves 501 arranged at equal intervals. The longitudinal groove 502 runs through the middle of the transverse groove 501. Correspondingly, the limit block 7 is adapted to the limit groove 5. The limit block 7 is composed of a longitudinal block and a number of transverse blocks corresponding to the transverse groove 501. By increasing the number of transverse blocks and transverse grooves 501, the splicing area between the limit block 7 and the first splicing layer 3 is increased, thereby further enhancing the splicing strength between the original roadbed 1 and the spliced roadbed 2.
[0039] Embodiment three:
[0040] The splicing structure of the new and old joints of the highway reconstruction and expansion project in this embodiment is a further improvement based on the first embodiment.
[0041] Specifically, Figure 7 , Figure 8 As shown, in this embodiment, the upper surface of the first splicing layer 3 is a sawtooth structure, and the corresponding lower surface of the second splicing layer 4 is a sawtooth structure that fits the upper surface of the first splicing layer 3. By setting the upper surface of the first splicing layer 3 and the lower surface of the second splicing layer 4 to a sawtooth structure, the connection area between the upper surface of the first splicing layer 3 and the lower surface of the second splicing layer 4 is effectively increased, thereby further enhancing the splicing strength between the original roadbed 1 and the spliced roadbed 2.
[0042] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A splicing structure of the new and old joints of a highway reconstruction and expansion project, characterized in that: It includes the original roadbed (1) and the spliced roadbed (2); A multi-layer first splicing layer (3) is arranged at one end of the original roadbed (1) close to the spliced roadbed (2), the multi-layer first splicing layer (3) is arranged in a stepped shape, and a connecting groove is opened on the first splicing layer (3); The spliced roadbed (2) is provided with a plurality of second splicing layers (4) at one end close to the original roadbed (1), the second splicing layers (4) correspond one-to-one to the first splicing layers (3), and a connecting block adapted to the connecting groove is integrally provided at the bottom of the second splicing layer (4).
2. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 1 is characterized in that: The connection groove comprises a limit groove (5) and a reinforcement groove (6); the limit groove (5) comprises a transverse groove (501) and a longitudinal groove (502) which are connected to each other; one end of the longitudinal groove (502) close to the spliced roadbed (2) is connected to the outside; the reinforcement groove (6) is a columnar structure; the connection block comprises a limit block (7) and a reinforcement block (8); and a steel bar (9) is pre-embedded in the reinforcement block (8).
3. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 2 is characterized in that: The upper end of the steel bar (9) extends into the second splicing layer (4).
4. The splicing structure of the new and old joints of the highway reconstruction and expansion project according to claim 2 or 3 is characterized in that: The limiting grooves (5) and the reinforcing grooves (6) on the same first splicing layer (3) are arranged alternately.
5. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 4 is characterized in that: The limiting grooves (5) and the reinforcing grooves (6) on the different first splicing layers (3) are arranged in an alternating manner.
6. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 5 is characterized in that: The bottom of each layer of the reinforcement groove (6) extends to the bottom of the original roadbed (1).
7. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 6 is characterized in that: The limiting groove (5) is in a T-shaped structure.
8. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 6 is characterized in that: The limiting groove (5) is composed of a longitudinal groove (502) and a plurality of transverse grooves (501) arranged at equal intervals, and the longitudinal groove (502) runs through the middle of the transverse groove (501).
9. The splicing structure of the new and old joint parts of the highway reconstruction and expansion project according to claim 1 is characterized in that: The upper surface of the first splicing layer (3) has a sawtooth structure.