Integral bridge

Through the tower tension system driven by hydraulic jacks, the problem of bridge installation in karst areas is solved, and the efficient installation and safety of bridges are improved under karst geological conditions are achieved.

CN222008623UActive Publication Date: 2024-11-15ZHONGYU DESIGN CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323613131.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-28
Publication Date
2024-11-15
Estimated Expiration
2033-12-28

AI Technical Summary

Technical Problem

In the construction of bridges in karst areas, due to the influence of vehicle loads and geological conditions, cave collapse and strata deformation may damage the safety of the bridge structure, increasing the cost and difficulty of use, and the existing technology is difficult to effectively solve this problem.

Method used

A monolithic bridge is designed, using a hydraulic jack to push the support block through the piston rod, thereby pushing the limit block and support column. The tower generates tension on the bridge body through ropes, replacing the traditional bridge foundation and simplifying the installation process.

Benefits of technology

This solution can easily install the bridge body through a tower tension system driven by hydraulic jacks, improving the installation efficiency and safety of the bridge under karst geological conditions and reducing engineering costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008623U_ABST
    Figure CN222008623U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge installation, in particular to an integral bridge which comprises a bridge body, supporting assemblies are arranged on the two sides of the bridge body, bases used for installing the supporting assemblies are arranged on the lower portions of the two sides of the bridge body, and each supporting assembly comprises a tower, a supporting column, a limiting block and a rope. The supporting assembly is connected with the bridge body through a rope. A mounting cavity for mounting the limiting block is formed in the base, a hydraulic jack is fixedly connected to the inner wall of the bottom end of the mounting cavity, a supporting block is fixedly clamped to the lower end face of the limiting block, and the bottom end of the supporting column penetrates through the top end of the base and is vertically inserted into the top end of the limiting block. The hydraulic jacks can push the supporting blocks upwards through the piston rods, the supporting blocks can push the limiting blocks and the supporting columns upwards, then the tower can be pushed upwards, the tower can generate pulling force on the bridge body through the ropes, a bridge foundation can be replaced, and then the bridge body can be installed conveniently.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge installation, in particular to an integral bridge. Background Art

[0002] my country is one of the countries with the most extensive distribution of karst geology in the world. With the rapid development of highway and municipal bridge construction, it is inevitable to encounter unfavorable karst geological conditions. During the construction of bridges in karst areas, the bridge deck is affected by vehicle cyclic loads and additional road loads, which may cause cave collapse, cause stratum deformation, and damage the safety of the bridge structure, thereby adversely affecting the operation of the bridge. Karst geological conditions have a great impact on the engineering cost and safe use of the bridge foundation structure, and are not convenient for the installation of the bridge.

[0003] To this end, we propose an integral bridge. Utility Model Content

[0004] The main purpose of the utility model is to provide an integral bridge, in which the hydraulic jack can push the support block upwards through the piston rod, the support block can push the limit block and the support column upwards, and then push the tower upwards, the tower can generate tension on the bridge body through ropes, can replace the bridge foundation, and thus facilitate the installation of the bridge body, which can effectively solve the problems in the background technology.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] An integral bridge comprises a bridge body, support assemblies are arranged on both sides of the bridge body, bases for installing the support assemblies are arranged on the lower parts of both sides of the bridge body, the support assemblies comprise towers, support columns, limit blocks and ropes, the support assemblies are connected to the bridge body via ropes; an installation cavity for installing the limit blocks is arranged inside the base, a hydraulic jack is fixedly connected to the inner wall of the bottom end of the installation cavity, a support block is fixedly clamped on the lower end surface of the limit block, and the hydraulic jack is connected to the support block via a piston rod; the bottom end of the support column passes through the top end of the base and is vertically inserted into the top end of the limit block, and the limit block is slidably connected to the inner wall of the installation cavity.

[0007] By adopting the above technical solution, the hydraulic jack can push the support block upwards through the piston rod, the support block can push the limit block and the support column upwards, and then push the tower upwards, and the tower can generate tension on the bridge body through the rope.

[0008] Specifically, a limiting groove matched with the supporting column is provided on one side of the tower, the upper part of the supporting column is movably inserted into the limiting groove, and the supporting column is fixedly connected to the tower through a first bolt.

[0009] Specifically, a protective cover is fixedly sleeved on the lower part of the support column, a protective cavity is arranged inside the protective cover, a sealing gasket is fixedly glued to the inner wall of the top end of the protective cavity, and the protective cover is movably buckled on the upper part of the base.

[0010] Specifically, a sealing protrusion is provided at the center of the top end of the protective cover, and a through hole for the support column to pass through is provided in the sealing protrusion.

[0011] Specifically, a sliding block is fixedly connected to the lower portion of the inner wall of the protective cover, and four groups of the sliding blocks are relatively parallel.

[0012] Specifically, a slide groove matched with the slider is provided on the upper outer side of the base, and the slider is located in the slide groove.

[0013] Beneficial effects of the utility model:

[0014] 1. In the integrated bridge described in the utility model, the hydraulic jack can push the support block upwards through the piston rod, and the support block can push the limit block and the support column upwards, thereby pushing the tower upwards, and the tower can generate tension on the bridge body through the rope, which can replace the bridge foundation, thereby facilitating the installation of the bridge body;

[0015] 2. In the utility model, an integral bridge is provided with a protective cover fixedly mounted on the lower part of the supporting column, a protective cavity is provided inside the protective cover, a sealing gasket is fixedly glued to the inner wall of the top end of the protective cavity, and the protective cover is movably buckled on the upper part of the base, thereby being able to protect the base. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0017] Figure 1 The utility model is a structural schematic diagram of an integral bridge.

[0018] Figure 2 The utility model is an integral bridge Figure 1 Enlarged view of point A in the middle.

[0019] Figure 3 It is a three-dimensional diagram of a protective cover of an integral bridge of the utility model.

[0020] In the figure: 1. Bridge body; 2. Support assembly; 3. Base; 4. Protective cover; 5. Slide; 6. Tower; 7. Support column; 8. Limit block; 9. Limit groove; 10. Rope; 11. Protective cavity; 12. Sealing gasket; 13. Slider; 14. Installation cavity; 15. Hydraulic jack; 16. Support block; 17. Through hole; 18. Sealing protrusion. DETAILED DESCRIPTION

[0021] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0022] like Figure 1-3 As shown, an integral bridge comprises a bridge body 1, support assemblies 2 are provided on both sides of the bridge body 1, bases 3 for installing the support assemblies 2 are provided on the lower parts of both sides of the bridge body 1, the support assemblies 2 comprise towers 6, support columns 7, limit blocks 8 and ropes 10, and the support assemblies 2 are connected to the bridge body 1 via ropes 10; an installation cavity 14 for installing the limit blocks 8 is provided inside the base 3, a hydraulic jack 15 is fixedly connected to the inner wall of the bottom end of the installation cavity 14, a support block 16 is fixedly clamped on the lower end surface of the limit block 8, and the hydraulic jack 15 is connected to the support block 16 via a piston rod; the bottom end of the support column 7 passes through the top end of the base 3 and is vertically inserted into the top end of the limit block 8, and the limit block 8 is slidably connected to the inner wall of the installation cavity 14.

[0023] As an embodiment of the utility model, a limiting groove 9 matched with the support column 7 is provided on one side of the tower 6, and the upper part of the support column 7 is movably inserted in the limiting groove 9, and the support column 7 is fixedly connected to the tower 6 by a first bolt; a protective cover 4 is fixedly sleeved on the lower part of the support column 7, and a protective cavity 11 is provided in the protective cover 4, and a sealing gasket 12 is fixedly glued to the inner wall of the top end of the protective cavity 11, and the protective cover 4 is movably buckled on the upper part of the base 3; a sealing protrusion 18 is provided at the center of the top end of the protective cover 4, and a through hole 17 for the support column 7 to pass through is provided in the sealing protrusion 18; a slider 13 is fixedly connected to the lower part of the inner wall of the protective cover 4, and four groups of sliders 13 are relatively parallel; a slide groove 5 matched with the slider 13 is provided on the upper outer side of the base 3, and the slider 13 is located in the slide groove 5, so that the protective cover 4 can slide on the upper part of the base 3.

[0024] It should be noted that the utility model is an integral bridge, with support assemblies 2 provided on both sides of the bridge body 1, and bases 3 for installing the support assemblies 2 provided on the lower parts of both sides of the bridge body 1. The support assemblies 2 are connected to the bridge body 1 through ropes 10. When the height of the tower 6 needs to be adjusted, the hydraulic jack 15 can push the support block 16 upward through the piston rod, and the support block 16 can push the limit block 8 and the support column 7 upward, thereby pushing the tower 6 upward, and the tower 6 can generate tension on the bridge body 1 through the ropes 10.

[0025] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. An integral bridge, It is characterized in that The invention comprises a bridge body (1), support assemblies (2) are arranged on both sides of the bridge body (1), bases (3) for installing the support assemblies (2) are arranged at the lower parts of both sides of the bridge body (1), the support assemblies (2) comprise a tower (6), a support column (7), a limit block (8) and a rope (10), and the support assemblies (2) are connected to the bridge body (1) via the rope (10); The base (3) is provided with an installation cavity (14) for installing a limit block (8), a hydraulic jack (15) is fixedly connected to the inner wall of the bottom end of the installation cavity (14), a support block (16) is fixedly clamped on the lower end surface of the limit block (8), and the hydraulic jack (15) is connected to the support block (16) via a piston rod; The bottom end of the support column (7) passes through the top end of the base (3) and is vertically inserted into the top end of the limit block (8), and the limit block (8) is slidably connected to the inner wall of the installation cavity (14).

2. An integral bridge according to claim 1, Features: A limiting groove (9) matched with the support column (7) is provided on one side of the tower frame (6); the upper portion of the support column (7) is movably inserted into the limiting groove (9); and the support column (7) is fixedly connected to the tower frame (6) via a first bolt.

3. The integrated bridge according to claim 1, Features: A protective cover (4) is fixedly sleeved on the lower part of the support column (7), a protective cavity (11) is provided in the protective cover (4), a sealing gasket (12) is fixedly glued to the inner wall of the top end of the protective cavity (11), and the protective cover (4) is movably buckled on the upper part of the base (3).

4. An integral bridge according to claim 3, Features: A sealing protrusion (18) is provided at the center of the top end of the protective cover (4), and a through hole (17) is provided in the sealing protrusion (18) for the support column (7) to pass through.

5. An integral bridge according to claim 4, Features: A slider (13) is fixedly connected to the lower portion of the inner wall of the protective cover (4), and four groups of the sliders (13) are arranged in parallel with each other.

6. The integrated bridge according to claim 1, Features: A slide groove (5) adapted to the slide block (13) is provided on the upper outer side of the base (3), and the slide block (13) is located in the slide groove (5).