Rapid mounting structure for steel sheet pile enclosing purlin
Through the connection between the suspension plate and bolts of the suspension sleeve structure, the problems of low welding efficiency and safety risks in steel sheet pile support construction are solved, and rapid installation and safe and efficient steel sheet pile purlin construction are achieved.
Patent Information
- Application Number
- CN202420211936.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-29
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-01-29
AI Technical Summary
In the steel sheet pile support construction, the installation efficiency of welding cow legs, purlins and lateral support is low, the personnel safety risks are high, and there is a risk of cutting damage and fire operation during the demolition process.
The suspension sleeve structure is adopted, and the purlin is installed through suspension plates and bolt connections, which reduces welding requirements and provides a method of rapid installation and removal. The U-shaped suspension sleeve and rubber lining are used to improve the fixing firmness.
The installation speed of steel sheet pile support structure is significantly improved, the risks of workers in the grooves are reduced, fire operations and cutting damage are avoided, and construction efficiency and safety are improved.
Smart Images

Figure CN222008941U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a steel sheet pile surrounding purlin, in particular to a steel sheet pile surrounding purlin quick installation structure. Background Art
[0002] Steel sheet pile support is a common support and protection method in the current municipal construction process. For trenches exceeding a certain depth, the steel sheet pile support structure needs to add welding structures (including welded corbels, purlins, transverse supports and other structures) to form a stable support structure. In the actual construction of the steel sheet pile support structure, there are the following problems: First, the process of welding corbels, purlins and transverse supports requires manual operation in the trench, which takes a long time to weld and is inefficient, and there is a risk of long-term exposure of personnel in the trench. Second, if two layers of purlins and cross bracing structures need to be installed, if the trench on the lower excavation surface is wet with water, the welding quality will be difficult to guarantee, which is easy to affect the stability of the support structure and the risk to personnel is high. Third, when dismantling the welded structure, cutting is required, which is slow and easy to damage the steel sheet piles. In addition, hot work requires high qualifications for personnel, and hot work itself has high risks. Summary of the invention
[0003] The technical problem to be solved by the utility model is to provide a steel sheet pile surrounding purlin quick installation structure, which can improve the installation speed of the entire steel sheet pile supporting structure.
[0004] In order to solve the above technical problems, the technical solution adopted by the utility model is:
[0005] A quick installation structure for a steel sheet pile purlin comprises a hanging sleeve, which is hung on a steel sheet pile. A second fastening bolt is threadedly connected to one side of the hanging sleeve, and the second fastening bolt is screwed into the hanging sleeve and connected to a top plate. A positioning block is fixed inside the other side of the hanging sleeve, and a slot is formed between adjacent positioning blocks. The upper end of the hanging plate is placed in the slot and is locked by a first fastening bolt, and the lower end of the hanging plate extends out of the hanging sleeve and is connected to a hanging hook, and a cross-bracing purlin is hung in the hanging hook.
[0006] The device is arranged in groups on the top of the steel sheet pile.
[0007] The cross section of the suspension sleeve is U-shaped.
[0008] The appearance of the suspension sleeve is consistent with that of the steel sheet pile.
[0009] A plurality of suspension plates are installed on each suspension sleeve.
[0010] A lining plate is arranged on the inner side of the top plate, and both the lining plate and the positioning block are made of rubber.
[0011] The utility model provides a steel sheet pile surrounding purlin quick installation structure, which has the following technical effects:
[0012] 1) The method of installing the purlin by hanging and bolting has fast construction speed and high efficiency.
[0013] 2) It greatly reduces the time for workers to install and dismantle the support structure, avoids the presence of workers in the foundation pit where the support is not completed, and eliminates the risk of casualties caused by earth collapse.
[0014] 3) It avoids the risk of hot work during traditional welding installation and dismantling, and reduces the damage to steel sheet piles caused by welding and cutting. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The utility model is further described below in conjunction with the accompanying drawings and embodiments:
[0016] Figure 1 It is a schematic diagram of the partial structure of the utility model (front view).
[0017] Figure 2 It is a schematic diagram of the partial structure of the utility model (back side).
[0018] Figure 3 It is a cross-sectional view of the utility model (showing part of the structure).
[0019] In the figure: a suspension sleeve 1, a first bolt hole 2, a suspension plate 3, a suspension hook 4, a second bolt hole 5, a second fastening bolt 6, a top plate 7, a lining plate 8, a slot 9, a positioning block 10, and a first fastening bolt 11. DETAILED DESCRIPTION
[0020] like Figure 1-2 As shown, a steel sheet pile purlin quick installation structure includes a suspension sleeve 1, the cross section of the suspension sleeve 1 is U-shaped, that is, it includes a top plate and front and rear side plates. The shape of the suspension sleeve 1 is consistent with the shape of the steel sheet pile, and a length is taken. A first bolt hole 2 is opened at a suitable position on one side of the suspension sleeve 1, and a second bolt hole 5 is opened at a suitable position on the other side of the suspension sleeve 1.
[0021] Positioning blocks 10 are fixed on the left and right sides of the inner side of the suspension sleeve 1 located on one side of the first bolt hole 2, and a slot 9 is formed between the two positioning blocks 10. The upper end of the suspension plate 3 is located in the slot 9, and the first fastening bolt 11 is screwed into the first bolt hole 2 and the threaded hole of the suspension plate 3 to be locked, so as to realize the connection between the suspension plate 3 and the suspension sleeve 1. A suspension hook 4 is provided at the bottom end of the suspension plate 3, and the suspension hook 4 is used to place the horizontal bracing purlin.
[0022] The second bolt hole 5 is threadedly connected to the second fastening bolt 6, and the end of the second fastening bolt 6 is connected to the top plate 7. By rotating the second fastening bolt 6, the top plate 7 can be pushed forward and the steel sheet pile can be clamped between the top plate 7 and the positioning block 10, thereby achieving the fixation of the device.
[0023] Preferably, the length of the suspension plate 3 in the present device can be customized and adjusted. When only a single-layer transverse bracing purlin needs to be installed, the length of all the suspension plates 3 is the same. When a double-layer transverse bracing purlin needs to be installed, two suspension plates 3 of different lengths are set. The upper transverse bracing purlin is horizontally placed on the suspension hook 4 of the short suspension plate 3, and the lower transverse bracing purlin is horizontally placed on the suspension hook 4 of the long suspension plate 3.
[0024] Preferably, in order to ensure reliability, a threaded hole is opened on the outer plate of the suspension hook 4, and a bolt is screwed in to tighten the surrounding purlin against the vertical end surface of the suspension plate 3.
[0025] Preferably, the lining plate 8 and the positioning block 10 are both made of rubber, which increases the friction of the contact surface to a certain extent.
[0026] Working principle and process:
[0027] 1) After continuous injection of steel sheet piles, they are inserted into the deep soil layer. The plates of the steel sheet piles are interlocked with each other and remain stable and firm as a whole. The surface soil in the area surrounded by the steel sheet piles is excavated to a certain depth, and then the surrounding purlins are installed.
[0028] 2) If a single-layer horizontal bracing purlin support is installed, first hang the hanging sleeve 1 on the upper end of the steel sheet pile, and by rotating the second fastening bolt 6, the top plate 7 and the lining plate 8 are moved closer to the side wall of the steel sheet pile, and finally the steel sheet pile is pressed against the end face of the positioning block 10; thereby, the hanging sleeve 1 is fixed to the upper end of the steel sheet pile.
[0029] 3) Then vertically insert the suspension plate 3 into the slot 9, screw the first fastening bolt 11 through the first bolt hole 2, and finally fix the suspension plate 3 on the suspension sleeve 1.
[0030] 4) Repeat the above steps 2)-3) and install the device on the top of the steel sheet pile in multiple pieces.
[0031] 5) If you only want to install a single-layer purlin, you can directly place the horizontal bracing purlin horizontally in the hanging hook 4, and then install the vertical bracing purlin. If you want to install a double-layer purlin, you can Figure 1-2 , two kinds of suspension plates 3 of different lengths are installed, so that after multiple devices are installed, two rows of suspension hooks 4 are formed, the upper row is used to hang the upper horizontal bracing purlin, and the lower row is used to hang the lower horizontal bracing purlin. The installation method of the longitudinal bracing purlin is the same as the previous single-layer purlin.
Claims
1. A steel sheet pile purlin quick installation structure, characterized in that: The invention comprises a suspension sleeve (1), wherein the suspension sleeve (1) is hung on a steel sheet pile, one side of the suspension sleeve (1) is threadedly connected with a second fastening bolt (6), the second fastening bolt (6) is screwed into the suspension sleeve (1) and connected to a top plate (7), a positioning block (10) is fixed inside the other side of the suspension sleeve (1), a slot (9) is formed between adjacent positioning blocks (10), the upper end of the suspension plate (3) is placed in the slot (9) and is locked by a first fastening bolt (11), the lower end of the suspension plate (3) extends out of the suspension sleeve (1) and is connected to a suspension hook (4), and a cross brace purlin is hung in the suspension hook (4).
2. The steel sheet pile purlin quick installation structure according to claim 1 is characterized by: The steel sheet pile purlin quick installation structure comprises multiple groups, which are arranged on the top of the steel sheet piles.
3. The steel sheet pile purlin quick installation structure according to claim 1 is characterized in that: The cross section of the suspension sleeve (1) is U-shaped.
4. The steel sheet pile purlin quick installation structure according to claim 3 is characterized by: The appearance of the suspension sleeve (1) is consistent with that of the steel sheet pile.
5. The steel sheet pile purlin quick installation structure according to claim 4 is characterized in that: A plurality of groups of suspension plates (3) are mounted on each suspension sleeve (1).
6. The steel sheet pile purlin quick installation structure according to claim 1 is characterized by: A lining plate (8) is provided on the inner side of the top plate (7), and the lining plate (8) and the positioning block (10) are both made of rubber.