Prefabricated assembly type pipe ditch gap connecting structure
By using the design of components such as chucks, clips, sliders, springs, etc. in prefabricated pipe trench, the problems of rust and inconvenience caused by bolts are solved, and more efficient installation and disassembly, the convenience and springs are achieved. Improved flexibility and cleanliness.
Patent Information
- Application Number
- CN202420656606.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-01
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-04-01
AI Technical Summary
The use of bolts during installation and disassembly of existing prefabricated prefabricated pipe trenches causes rust problems, which increases the difficulty and inconvenience of subsequent replacement.
A prefabricated pipe trench gap connection structure is designed, using slots and components such as card parts, sliders, springs, screws, elastic ropes and friction pads. Through sliding and rotating connection, the use of bolts is reduced, and the use of springs and elasticity is adopted. The combination of the piece adjusts the spring tension and removes rust spots.
It reduces the rust problem caused by bolt exposure, improves the convenience of dismantling of pipe trenches, improves the flexibility and cleanliness of the spring, and reduces the problem of insufficient elasticity.
Smart Images

Figure CN222008988U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of urban construction, in particular to a prefabricated assembled pipe trench gap connection structure. Background Art
[0002] Prefabricated pipe trenches are constructed using prefabricated and assembled technology. They are characterized by factory prefabrication and on-site installation. They are an efficient, environmentally friendly and energy-saving pipe trench construction method, and are often used in basements, garages and other places.
[0003] The main function of the trench is to withstand soil pressure and ground load, and to protect the cables or pipes installed inside. When using the trench, multiple trenches need to be installed side by side, and a cover is provided on the top to make it easier for workers to repair the cables or pipes inside.
[0004] Through long-term observation, it is found that multiple existing pipe trenches usually need to be installed with bolts when in use, which is too troublesome. In addition, the bolts are exposed to the outside world or buried in the soil for a long time, and are prone to rust, which causes troubles when the staff subsequently disassemble and replace some pipe trenches. Therefore, a prefabricated assembled pipe trench gap connection structure is proposed to address the above problems. Utility Model Content
[0005] In order to make up for the deficiencies of the prior art and solve at least one technical problem raised in the background technology, the utility model proposes a prefabricated assembled pipe trench gap connection structure.
[0006] The technical solution adopted by the utility model to solve its technical problems is: the prefabricated and assembled pipe trench gap connection structure described in the utility model includes a pipe trench main body; two groups of first clamping grooves are opened in the middle of the pipe trench main body; two groups of clamping members matched with the shape of the first clamping grooves are fixedly connected to the end of the pipe trench main body; two groups of clamping holes are opened in the middle of the clamping members; two groups of springs are installed on the inner wall of the pipe trench main body; a first slide plate is fixedly connected to the top of the spring; the first slide plate is slidably arranged in the middle of the pipe trench main body; a handle is fixedly connected to the top of the first slide plate; a connecting piece is fixedly connected to the end of the first slide plate; two groups of fixing pins matched with the shape of the clamping holes are fixedly connected to the middle of the connecting piece.
[0007] Preferably, two groups of second slides are slidably connected to the middle of the trench body; the bottom of the spring is fixedly connected to the top of the second slide; the middle of the second slide is rotatably connected to a screw rod; the screw rod and the middle of the trench body are threadedly connected; two groups of connecting rods are fixedly connected to the top of the spring; multiple groups of elastic ropes are fixedly connected to the middle of the connecting rod; the ends of the elastic ropes are fixedly connected to elastic sheets, and the middle of the elastic sheets are fixedly connected to the middle of the connecting rods.
[0008] Preferably, an elastic cloth is rotatably connected to the top of the pipe trench body; a buckle is fixed to the end of the elastic cloth; and two groups of second slots are provided on the top of the pipe trench body.
[0009] Preferably, a reinforcement piece is fixedly connected to the top of the first slide plate; a scraper is fixedly connected to the top of the reinforcement piece; and the scraper is arranged in contact with the inner wall of the trench body.
[0010] Preferably, two groups of weight strips are fixedly connected to the middle part of the elastic cloth.
[0011] Preferably, a plurality of groups of friction pads are fixedly connected to the middle portion of the fixing pin; the friction pads are arranged in a circular array in the middle portion of the fixing pin.
[0012] Preferably, a sponge pad is fixedly connected to the inner wall of the pipe trench body; the inner wall of the sponge pad is in contact with the middle of the screw.
[0013] The utility model is beneficial in that:
[0014] 1. The prefabricated assembled pipe trench gap connection structure described in the utility model can install and fix two groups of pipe trench bodies by cooperating with the clamps arranged at the ends of the pipe trench bodies, thereby reducing the problem of the original installation of multiple pipe trench bodies with bolts, which causes the bolts to be exposed to the outside for a long time and cause serious rust on the middle part, reduces the troublesome problem of subsequent staff replacing damaged pipe trench bodies, and improves the convenience of disassembling the pipe trench bodies.
[0015] 2. The prefabricated assembled pipe trench gap connection structure described in the utility model can adjust the tension generated by the spring by cooperating with the screw rod arranged in the middle of the pipe trench body, thereby improving the flexibility of the spring when in use, and cooperate with the force of the elastic sheet colliding with the middle of the spring to vibrate and remove the rust spots generated in the middle of the spring, thereby improving the cleanliness of the middle of the spring and reducing the problem of insufficient elasticity caused by long-term non-use of the spring. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0017] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;
[0018] Figure 2 It is a three-dimensional cross-sectional structural schematic diagram of the utility model;
[0019] Figure 3This is a schematic diagram of the first slide structure in the utility model;
[0020] Figure 4 for Figure 3 Enlarged view of point A.
[0021] In the figure: 1. pipe trench body; 11. first slot; 12. clamping piece; 13. clamping hole; 14. spring; 15. first slide plate; 16. handle; 17. connecting piece; 18. fixing pin; 2. second slide plate; 21. screw rod; 22. connecting rod; 23. elastic rope; 24. elastic sheet; 3. elastic cloth; 31. buckle; 32. second slot; 4. reinforcement piece; 41. scraper; 5. counterweight bar; 6. friction pad; 7. sponge pad. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] like Figure 1-4As shown, the prefabricated assembled pipe trench gap connection structure comprises a pipe trench body 1; two groups of first clamping grooves 11 are opened in the middle of the pipe trench body 1; two groups of clamping members 12 with shapes matching the first clamping grooves 11 are fixedly connected to the ends of the pipe trench body 1; two groups of clamping holes 13 are opened in the middle of the clamping members 12; two groups of springs 14 are installed on the inner wall of the pipe trench body 1; a first slide plate 15 is fixedly connected to the top of the spring 14; the first slide plate 15 is slidably arranged in the middle of the pipe trench body 1; a handle 16 is fixedly connected to the top of the first slide plate 15; a connecting member 17 is fixedly connected to the end of the first slide plate 15; two groups of fixing pins 18 with shapes matching the clamping holes 13 are fixedly connected in the middle of the connecting member 17; when working, the staff needs to place multiple pipe trench bodies 1 side by side, and then the staff can use external force to pull the two groups of handles 16 upwards, so that the handles 16 will be forced to move the first slide plate 15 together The first step is to slide in the middle of the trench body 1, and the fixing pin 18 will pass over the middle of the first slot 11. At this time, the staff can clamp the other adjacent set of clamps 12 inside the first slot 11. After the positions are aligned, the staff can release the force of pulling the middle of the handle 16, and cooperate with the reaction force generated by the two sets of springs 14 being stretched, so that the first slide plate 15 can be pulled downward as a whole, and the fixing pin 18 will be stuck in the clamping hole 13 in the middle of the clamp 12, so as to install and fix the two adjacent trench bodies 1. In this step, the clamp 12 is provided at the end of the trench body 1, so that the two sets of trench bodies 1 can be installed and fixed, thereby reducing the original installation of multiple trench bodies 1 with bolts, resulting in the bolts being exposed to the outside for a long time and causing serious rust on the middle part, reducing the troublesome problems of subsequent staff replacing the damaged trench body 1, and improving the convenience of disassembling the trench body 1.
[0024] like Figure 2-4As shown, two groups of second slide plates 2 are slidably connected to the middle of the trench body 1; the bottom of the spring 14 is fixed to the top of the second slide plate 2; the middle of the second slide plate 2 is rotatably connected to a screw rod 21; the screw rod 21 is threadedly connected to the middle of the trench body 1; two groups of connecting rods 22 are fixed to the top of the spring 14; a plurality of groups of elastic ropes 23 are fixed to the middle of the connecting rod 22; an elastic sheet 24 is fixed to the end of the elastic rope 23, and the middle of the elastic sheet 24 is fixed to the middle of the connecting rod 22; during operation, a slidable second slide plate 2 is provided in the middle of the trench body 1, so that when the staff needs to adjust the tension of the spring 14, the staff can use a tool to rotate the screw rod 21 so that the screw 21 moves in and out of the middle of the trench body 1 The spring 14 is rotated, and the second slide plate 2 is squeezed downward during the rotation process, and the middle part of the spring 14 is stretched. During the movement of the spring 14 in and out of the middle part of the pipe trench main body 1, its inner wall will contact and collide with multiple elastic sheets 24, and then the deformed elastic sheet 24 will be pulled and reset by the elastic rope 23, and this is repeated. This step is combined with the screw rod 21 set in the middle part of the pipe trench main body 1 to adjust the tension generated by the spring 14, and improve the flexibility of the spring 14 when it is used. The rust spots generated in the middle part of the spring 14 can be vibrated and removed by the force of the elastic sheet 24 colliding with the middle part of the spring 14, so as to improve the cleanliness of the middle part of the spring 14 and reduce the problem of insufficient elasticity of the spring 14 when it has not been used for a long time.
[0025] like Figure 2 and 3 As shown, the top of the trench body 1 is rotatably connected with an elastic cloth 3; the end of the elastic cloth 3 is fixedly connected with a buckle 31; the top of the trench body 1 is provided with two groups of second slots 32; during operation, by arranging the elastic cloth 3 on the top of the trench body 1, after the staff completes the installation of multiple trench bodies 1, the staff can pull the buckle 31, so that the middle of the elastic cloth 3 will be deformed and elongated after being stressed. At this time, the staff can clamp the buckle 31 in the middle of the second slot 32 for fixing. This step is combined with the elastic cloth 3 arranged on the top of the first slide 15, and the elastic cloth 3 covering the top of the first slide 15, which can block some impurities and other garbage, and reduce the problem that large pieces of garbage are stuck at the sliding shaft of the first slide 15, which makes it troublesome to remove the trench body 1 later.
[0026] like Figure 4As shown, a reinforcement 4 is fixedly connected to the top of the first slide 15; a scraper 41 is fixedly connected to the top of the reinforcement 4; the scraper 41 is arranged in contact with the inner wall of the trench body 1; when working, by arranging the scraper 41 on the top of the first slide 15, when the first slide 15 is moving, the scraper 41 will scrape off part of the impurities in the sliding groove by using the cut surface, and the two groups of reinforcements 4 will shake in and out up and down after being squeezed, and transfer the impurities accumulated on the top of the scraper 41 to the outside world. This step, combined with the scraper 41 that is arranged in contact with the sliding groove of the trench body 1, can reduce the jamming phenomenon of the first slide 15 when working, and at the same time, combined with the reinforcement 4 with elastic force, can reduce the attachment time of impurities in the middle part of the scraper 41.
[0027] like Figure 3 As shown, two groups of counterweight strips 5 are fixedly connected to the middle of the elastic cloth 3; when working, by arranging the counterweight strip 5 in the middle of the buckle 31, the working position of the elastic cloth 3 can be reinforced with the downward gravity of the counterweight strip 5. This step, together with the counterweight strip 5, can reduce the problem of the middle of the elastic cloth 3 flying due to strong wind when the trench body 1 is used in the outside world, and reduce the phenomenon of falling off between the buckle 31 and the second slot 32.
[0028] like Figure 3 As shown, a plurality of groups of friction pads 6 are fixedly connected to the middle of the fixing pin 18; the friction pads 6 are arranged in a circular array in the middle of the fixing pin 18; when working, by arranging a plurality of groups of friction pads 6 made of soft materials in the middle of the fixing pin 18, when the fixing pin 18 is stuck in the middle of the card 12, the friction pads 6 will be squeezed during the movement. This step, together with the squeezed friction pads 6, can improve the stability of the fixing pin 18 and the card 12 when they are closed, and reduce the problem of shaking when the two are connected and fixed in and out.
[0029] like Figure 3 As shown, a sponge pad 7 is fixedly connected to the inner wall of the trench body 1; the inner wall of the sponge pad 7 is arranged in contact with the middle part of the screw 21; during operation, by arranging the sponge pad 7 on the inner wall of the trench body 1, the sponge pad 7 can remove some impurities and moisture in the middle part of the screw 21. This step cooperates with the sponge pad 7 to reduce the problem of more impurities or corroded rust spots in the middle part of the screw 21, resulting in greater resistance after the in-and-out thread rotation with the trench body 1.
[0030] The working principle is that multiple trench bodies 1 are placed side by side, and then the staff can use external force to pull the two groups of handles 16 upward, so that the handles 16 will cause the first slide plate 15 to slide synchronously in the middle of the trench body 1 after being stressed, and the fixing pin 18 will pass over the middle of the first slot 11. At this time, the staff can clamp another group of adjacent clamps 12 inside the first slot 11, and after aligning the positions, the staff can release the force of pulling the middle of the handle 16, and cooperate with the reaction force generated by the two groups of springs 14 being stretched, so that the first slide plate 15 can be pulled downward as a whole, and at the same time When the fixing pin 18 is stuck in the clamping hole 13 in the middle of the clamping member 12, the two sets of adjacent trench bodies 1 are installed and fixed. By providing a slidable second slide plate 2 in the middle of the trench body 1, when the staff needs to adjust the tension of the spring 14, the staff can use a tool to rotate the screw rod 21 so that the screw rod 21 can move in and out of the middle of the trench body 1. At the same time, the second slide plate 2 is pressed downward during the rotation process, and the middle of the spring 14 is stretched. In the process of the spring 14 moving in and out of the middle of the trench body 1, the inner wall of the spring 14 is in contact with the multiple elastic sheets 24. The elastic sheet 24 is then pulled back to its original position by the elastic rope 23, and the process is repeated. The elastic cloth 3 is arranged on the top of the pipe trench body 1, so that after the staff has installed a plurality of pipe trench bodies 1, the staff can pull the buckle 31, so that the elastic cloth 3 is deformed and stretched in the middle after being stressed. At this time, the staff can clamp the buckle 31 in the middle of the second clamping groove 32 for fixing. The scraper 41 is arranged on the top of the first slide plate 15, so that when the first slide plate 15 is moving, the scraper 41 can remove some impurities in the sliding groove by cutting. The scraper 41 is scraped out, and the two groups of reinforcement members 4 will swing up and down when subjected to the extrusion force, and transfer the impurities accumulated on the top of the scraper 41 to the outside world. A counterweight bar 5 is provided in the middle of the buckle 31, and the working position of the elastic cloth 3 can be reinforced by the downward gravity of the counterweight bar 5. Multiple groups of friction pads 6 made of soft materials are provided in the middle of the fixing pin 18, so that when the fixing pin 18 is stuck in the middle of the clamp 12, the friction pad 6 will be squeezed during the movement. A sponge pad 7 is provided on the inner wall of the trench body 1, so that the sponge pad 7 can remove some impurities and moisture in the middle of the screw 21.
[0031] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.
Claims
1. A prefabricated assembled pipe trench gap connection structure, comprising a pipe trench body (1); two groups of first slots (11) are provided in the middle of the pipe trench body (1); the characteristics are: Two groups of clamping members (12) whose shapes match those of the first clamping slot (11) are fixedly connected to the end of the pipe trench body (1); two groups of clamping holes (13) are opened in the middle of the clamping members (12); two groups of springs (14) are installed on the inner wall of the pipe trench body (1); a first slide plate (15) is fixedly connected to the top of the spring (14); the first slide plate (15) is slidably arranged in the middle of the pipe trench body (1); a handle (16) is fixedly connected to the top of the first slide plate (15); a connecting member (17) is fixedly connected to the end of the first slide plate (15); and two groups of fixing pins (18) whose shapes match those of the clamping holes (13) are fixedly connected in the middle of the connecting member (17).
2. The prefabricated assembled trench gap connection structure according to claim 1, characterized in that: The middle of the pipe trench body (1) is slidably connected to two groups of second slide plates (2); the bottom of the spring (14) is fixedly connected to the top of the second slide plate (2); the middle of the second slide plate (2) is rotatably connected to a screw rod (21); the screw rod (21) and the middle of the pipe trench body (1) are threadedly connected; the top of the spring (14) is fixedly connected to two groups of connecting rods (22); the middle of the connecting rod (22) is fixedly connected to multiple groups of elastic ropes (23); the end of the elastic rope (23) is fixedly connected to an elastic sheet (24), and the middle of the elastic sheet (24) is fixedly connected to the middle of the connecting rod (22).
3. The prefabricated assembled trench gap connection structure according to claim 1 is characterized in that: The top of the pipe trench body (1) is rotatably connected to an elastic cloth (3); the end of the elastic cloth (3) is fixedly connected to a buckle (31); and two groups of second clamping grooves (32) are provided on the top of the pipe trench body (1).
4. The prefabricated assembled trench gap connection structure according to claim 1, characterized in that: A reinforcing member (4) is fixedly connected to the top of the first slide plate (15); a scraper (41) is fixedly connected to the top of the reinforcing member (4); and the scraper (41) is arranged in contact with the inner wall of the trench body (1).
5. The prefabricated assembled trench gap connection structure according to claim 3 is characterized in that: Two groups of weight bars (5) are fixedly connected to the middle of the elastic cloth (3).
6. The prefabricated assembled trench gap connection structure according to claim 1, characterized in that: A plurality of groups of friction pads (6) are fixedly connected to the middle of the fixing pin (18); the friction pads (6) are arranged in a circular array in the middle of the fixing pin (18).
7. The prefabricated assembled trench gap connection structure according to claim 1, characterized in that: A sponge pad (7) is fixedly connected to the inner wall of the pipe trench body (1); the inner wall of the sponge pad (7) is arranged in contact with the middle of the screw rod (21).