Step-shaped roof precast beam with window

By designing the prefabricated beams on the stepped roof with windows and using upper and lower chords and truss structures, the problem of the position and strength of the steel beams when the long lighting window is installed is solved, and the beauty, load bearing performance and construction efficiency are improved.

CN222009359UActive Publication Date: 2024-11-15SIPPR ENG GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420622940.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-28
Publication Date
2024-11-15
Estimated Expiration
2034-03-28

AI Technical Summary

Technical Problem

When installing existing long lighting windows, the location of the steel beams causes the extension below the roof panel to affect the beauty, or the window hole is too long to weaken the strength of the steel beams and cannot bear large loads.

Method used

Design a stepped-shaped prefabricated beam with window roof, including an upper and lower chord arranged in parallel, a finished window installation position is set in the middle, and there are truss structures on both sides. The load-bearing performance is improved by using rectangular steel pipes and reinforcement rods, and reinforcement is strengthened by welding connection of steel plates. Overall structure.

Benefits of technology

It achieves beautiful shape, lightweight, small overall deflection and excellent load-bearing performance, meeting the bearing requirements of roof beams, while taking into account the beauty, simplifying the construction process and shortening the construction cycle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009359U_ABST
    Figure CN222009359U_ABST
Patent Text Reader

Abstract

The utility model discloses a stepped roof precast beam with a window, which is arranged between adjacent step surfaces and comprises an upper chord member and a lower chord member which are arranged in parallel, the top surface of the upper chord member is flush with the upper step surface, the bottom surface of the lower chord member is flush with the lower step surface, and two ends of the upper chord member and two ends of the lower chord member are used for connecting roof longitudinal beams. Finished window mounting positions are arranged in the middles of the upper chord and the lower chord, and truss structures located between the upper chord and the lower chord are arranged on the two sides of each finished window mounting position. The step-level roof beam is attractive in appearance, light, ingenious, small in overall deflection, excellent in bearing performance and convenient and fast to install, can meet the force bearing requirement of the step-level roof beam, meanwhile, meets the overall attractive requirement after a window is installed on a roof in a step mode, materials are easy to obtain, overall component production can be completed in a factory, then on-site installation is conducted, and production cost is reduced. The construction process is optimized, and the construction period is greatly shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of large-span civil building steel structures, in particular to a stepped prefabricated roof beam with windows. Background Art

[0002] Some modern-style civil buildings, such as exhibition halls, sales offices, art centers, and hotels, will use a stepped roof structure to enhance the sense of lines and rhythm of the architectural shape. The span of this type of building is generally in the range of 8 to 18 meters, and the height of each stepped step is 500 to 1000 mm. In order to enhance the brightness and transparency of the interior, a long flat lighting window with a length of 4 to 8 meters and a height of 200 to 500 mm will be set in the stepped shape. When installing existing lighting windows, the following problems will be encountered: 1) When the steel beam under the lighting window is a solid-web steel beam, the steel beam must be lower than the bottom of the next step, resulting in a misalignment, resulting in partial view of the steel beam extending from under the roof panel indoors (see Figure 6 1) If the steel beam is placed close to the top of the next step for the sake of aesthetics, the web height of the steel beam will be sharply compressed to 300-500mm. At this time, the bearing capacity of the steel beam cannot meet the load of the roof panel, equipment on the board and windows. 2) If a whole H-shaped steel beam is used, a 4-8m window hole needs to be opened on the web of the steel beam to install windows (see Figure 6 As shown in the middle part b), due to the long window opening, the web strength of the steel beam and the overall bending bearing capacity of the steel beam will be weakened too much, resulting in the inability to bear large loads. Summary of the invention

[0003] In order to solve the above problems, the utility model provides a stepped prefabricated roof beam with windows, which can specifically adopt the following technical solutions:

[0004] The stepped prefabricated roof beam with windows described in the utility model is arranged between adjacent step surfaces, and includes an upper chord and a lower chord arranged in parallel, the top surface of the upper chord is flush with the upper step surface, and the bottom surface of the lower chord is flush with the next step surface, the two ends of the upper chord and the lower chord are used to connect the roof longitudinal beams, and a finished window installation position is arranged in the middle of the upper chord and the lower chord, and a truss structure located between the upper chord and the lower chord is arranged on both sides of the finished window installation position.

[0005] The finished window installation position is formed by an upper chord rod, a lower chord rod, and a vertical rod arranged between the upper chord rod and the lower chord rod.

[0006] A pair of vertical rods are symmetrically arranged along the central axis of the upper chord rod and the lower chord rod, and a reinforcing rod connected to the upper chord rod and the lower chord rod is also arranged between the vertical rods.

[0007] The reinforcing rod is arranged along the central axis of the upper chord rod and the lower chord rod and is located at the rear side of the finished window.

[0008] The truss structure is composed of vertical web members and diagonal web members. The diagonal web members are arranged between adjacent vertical web members, and the diagonal web members are continuous diagonal web member structures or parallel diagonal web member structures.

[0009] The upper chord rod and the lower chord rod are both rectangular steel pipe structures, and sealing plates are arranged at the ends of the upper chord rod and the lower chord rod.

[0010] When the roof longitudinal beam is a hot-rolled H-shaped steel or a welded H-shaped steel structure, coaxially arranged vertical grooves are opened at the ends of the upper chord and the lower chord, and vertical connecting steel plates are arranged in the vertical grooves. A stiffening rib located between the upper chord and the lower chord is welded on the left and right sides of the vertical connecting steel plate, and the stiffening rib and the vertical connecting steel plate are welded to the web of the roof longitudinal beam.

[0011] The utility model provides a stepped prefabricated roof beam with windows, which is beautiful in shape, light and clever, has a small overall deflection, excellent bearing performance, and is easy and quick to install. It can meet the bearing requirements of stepped roof beams while taking into account the overall aesthetic requirements of the roof after the windows are installed. The utility model is easy to obtain materials, and the production of the overall components can be completed in the factory, and then installed on site, which optimizes the construction process and greatly shortens the construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a schematic diagram of the structure of the utility model Figure 1 .

[0013] Figure 2 This is a schematic diagram of the structure of the utility model Figure 2 .

[0014] Figure 3 It is a schematic diagram of the connection structure of the utility model and the hot-rolled H-shaped steel or welded H-shaped steel structure roof longitudinal beam.

[0015] Figure 4 yes Figure 3 Schematic diagram of the slotted structure of the upper / lower chord.

[0016] Figure 5 It is a schematic diagram of the connection structure between the utility model and the longitudinal beam of the rectangular tube structure roof.

[0017] Figure 6 It is a structural diagram of a stepped window roof using different structural beams to install windows. DETAILED DESCRIPTION

[0018] The following is a detailed description of an embodiment of the utility model in conjunction with the accompanying drawings. This embodiment is implemented on the premise of the technical solution of the utility model, and a detailed implementation method and a specific operation process are given, but the protection scope of the utility model is not limited to the following embodiment.

[0019] like Figure 1 , Figure 2 , Figure 6 As shown in part c, the stepped window roof prefabricated beam described in the utility model is arranged between adjacent step surfaces, including an upper chord 1 and a lower chord 2 arranged in parallel, wherein the top surface of the upper chord 1 is flush with the upper step surface, and the bottom surface of the lower chord 2 is flush with the next step surface, and the total height is within the range of 800-1000mm, the front-to-back width is 150-200mm, and the span is 8-18m, which meets the height requirements of the stepped shape of the building. In order to reduce the weight of the steel beam and meet the lightness requirements, the upper chord 1 and the lower chord 2 are selected to be rectangular steel pipe structures, and welded rectangular pipes or cold-bent thin-walled finished rectangular pipes can be used, and the thickness is preferably 6-12mm. Furthermore, steel plates are welded at the ends of the upper chord 1 and the lower chord 2 as sealing plates 11.

[0020] The ends of the upper chord 1 and the lower chord 2 are connected to the roof longitudinal beam M. When the roof longitudinal beam M is a hot-rolled H-shaped steel or welded H-shaped steel structure, the ends of the upper chord 1 and the lower chord 2 are provided with coaxially arranged vertical grooves 12 (see Figure 4 ), the vertical groove 12 passes through the sealing plate 11, and a vertical connecting steel plate 13 is arranged in the vertical groove 12. The vertical connecting steel plate 13 is welded with the upper chord rod 1, the lower chord rod 2 and the sealing plate 11 at the intersection using double-sided fillet welds or single-sided groove welding technology. After that, a stiffening rib 14 located between the upper chord rod 1 and the lower chord rod 2 is welded on the left and right sides of the vertical connecting steel plate 13. The vertical connecting steel plate 13 and the stiffening rib 14 constitute a support (see Figure 3 ), can be welded to the roof longitudinal beam M to improve the connection firmness. When the roof longitudinal beam M is a beam or column in the form of a rectangular tube structure (see Figure 5 ), the upper chord 1 and the lower chord 2 can be directly welded to the side of the rectangular tube by groove welding or surrounding fillet welds.

[0021] A finished window installation position 3 is provided in the middle of the upper chord bar 1 and the lower chord bar 2. The finished window installation position 3 has a height of 200-500 mm and a length of 4-8 m. One or two finished aluminum alloy windows can be installed. The windows can be fixed or openable. The finished window installation position 3 is surrounded by the upper chord bar 1, the lower chord bar 2, and a pair of vertical bars 4 welded between the upper chord bar 1 and the lower chord bar 2. The two vertical bars 4 are also made of welded rectangular tubes or cold-bent thin-walled finished rectangular tubes, and are symmetrically arranged along the central axis of the upper chord bar 1 and the lower chord bar 2.

[0022] In order to ensure that the deflection of the middle steel beam meets the requirements, a reinforcing rod 5 connected to the upper chord rod 1 and the lower chord rod 2 is also provided at the center of the two vertical rods 4. The front-to-back width of the reinforcing rod 5 is 50-100 mm less than that of the upper chord rod 1 / lower chord rod 2, and is located at the rear side of the finished window to meet the full length requirements of the flat and long window.

[0023] The two sides of the finished window installation position 3 are also provided with a truss structure welded to the upper chord 1 and the lower chord 2. Specifically, the truss structure is composed of vertical web members 6 and diagonal web members 7. The vertical web members 6 are evenly spaced between the upper chord 1 and the lower chord 2, and the diagonal web members 7 are arranged between adjacent vertical web members 6. The diagonal web members 7 are continuous diagonal web member structures (see Figure 1 ) or parallel diagonal brace structure (see Figure 2 ).

[0024] It can be seen that the stepped window roof prefabricated beam described in the utility model is an end truss + middle hollow window body composed of upper and lower chords and various webs. Since there are fewer webs in the middle of the window, the self-weight of the component can be effectively reduced. The truss-like form adopted at the end can effectively strengthen the bending rigidity of the entire steel beam. The middle part adopts a reinforcing rod to connect the upper and lower chords, which does not affect the effect of the building's exterior windows, while enhancing the integrity of the upper and lower chords, effectively reducing the deflection deformation of the steel beam in the span, and at the same time, it is convenient for the installation and fixation of the flat long aluminum alloy finished window. It can be processed and formed in the factory, effectively ensuring the welding quality, high component precision and excellent quality; after the factory is completed, it can be transported to the site for direct installation, reducing the on-site assembly procedures, thereby saving construction time. The utility model has many excellent characteristics such as light weight, low steel consumption, reasonable structure, beam-window integration, etc., which can effectively solve the problem that the traditional large-span stepped window roof beam cannot take into account the load-bearing, lighting and aesthetics when setting, and has great industry promotion value.

[0025] It should be noted that, in the description of the present invention, terms indicating orientation or positional relationships, such as "front", "rear", "left", "right", "vertical", "horizontal", "inside", "outside", etc., are based on the orientation or positional relationships shown in the drawings and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

Claims

1. A stepped prefabricated roof beam with windows, arranged between adjacent step surfaces, characterized in that: It includes an upper chord and a lower chord arranged in parallel, the top surface of the upper chord is flush with the upper step surface, and the bottom surface of the lower chord is flush with the next step surface, the two ends of the upper chord and the lower chord are used to connect the roof longitudinal beams, and a finished window installation position is arranged in the middle of the upper chord and the lower chord, and a truss structure located between the upper chord and the lower chord is arranged on both sides of the finished window installation position.

2. The stepped prefabricated roof beam with windows according to claim 1, characterized in that: The finished window installation position is formed by an upper chord rod, a lower chord rod, and a vertical rod arranged between the upper chord rod and the lower chord rod.

3. The stepped prefabricated roof beam with windows according to claim 2 is characterized in that: A pair of vertical rods are symmetrically arranged along the central axis of the upper chord rod and the lower chord rod, and a reinforcing rod connected to the upper chord rod and the lower chord rod is also arranged between the vertical rods.

4. The stepped prefabricated roof beam with windows according to claim 3 is characterized in that: The reinforcing rod is arranged along the central axis of the upper chord rod and the lower chord rod and is located at the rear side of the finished window.

5. The stepped prefabricated roof beam with windows according to claim 1, characterized in that: The truss structure is composed of vertical web members and diagonal web members. The diagonal web members are arranged between adjacent vertical web members, and the diagonal web members are continuous diagonal web member structures or parallel diagonal web member structures.

6. The stepped prefabricated roof beam with windows according to claim 1, characterized in that: The upper chord rod and the lower chord rod are both rectangular steel pipe structures, and sealing plates are arranged at the ends of the upper chord rod and the lower chord rod.

7. The stepped prefabricated roof beam with windows according to claim 6, characterized in that: When the roof longitudinal beam is a hot-rolled H-shaped steel or a welded H-shaped steel structure, coaxially arranged vertical grooves are opened at the ends of the upper chord and the lower chord, and vertical connecting steel plates are arranged in the vertical grooves. A stiffening rib located between the upper chord and the lower chord is welded on the left and right sides of the vertical connecting steel plate, and the stiffening rib and the vertical connecting steel plate are welded to the web of the roof longitudinal beam.