Outer frame of building machine

By using detachable upper and lower hook mechanisms to connect the platform beam and the hanging frame beam in the building machine, the problem of inconvenient disassembly and adjustment in the existing technology where the hanging frame and platform are integrated is solved, thus achieving convenient installation and position adjustment.

CN222009543UActive Publication Date: 2024-11-15GUANGDONG NANAL CONSTR ROBOT TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323618887.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-28
Publication Date
2024-11-15
Estimated Expiration
2033-12-28

AI Technical Summary

Technical Problem

The integrated connection structure of the bracket and working platform in existing building construction machines is not convenient for disassembly and adjustment, which leads to construction difficulties.

Method used

The platform beam and the hanger beam are connected by detachable upper and lower hook mechanisms respectively, so as to realize the separate connection between the hanger and the platform, and the detachable connection is achieved through the connecting seat.

Benefits of technology

It enables convenient installation and disassembly of the bracket and platform, facilitating position adjustments during construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009543U_ABST
    Figure CN222009543U_ABST
Patent Text Reader

Abstract

The utility model discloses a building machine outer frame which comprises a platform cross beam, a hanging frame cross beam, a hanging frame device and a connecting seat, the connecting seat comprises an upper hook mechanism and a lower hook mechanism, the upper hook mechanism is connected with the platform cross beam, the lower hook mechanism is connected with the hanging frame cross beam, the upper hook mechanism is detachably connected with the lower hook mechanism, and the hanging frame cross beam is detachably connected with the hanging frame device. The platform cross beam and the hanging frame cross beam are perpendicular to each other, the upper hook mechanisms are symmetrically arranged on the two sides of the platform cross beam, each upper hook mechanism comprises a first upper abutting part and an upper connecting part, and each lower hook mechanism comprises a first connecting plate and a lower abutting part. The number of the lower abutting parts is two, and the lower abutting parts are arranged at the two ends of the lower surface of the first connecting plate respectively. According to the utility model, the hanging rack and the platform can be separately connected, and the hanging rack is convenient to mount, dismount and adjust.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction machines, in particular to an outer frame of a building construction machine. Background Art

[0002] A climbing frame or scaffolding is a traditional auxiliary tool for high-rise building construction. The existing lifting climbing frame drives the frame to rise by setting a lifting mechanism on the building wall structure, and construction workers can perform construction work on the frame. With the rapid rise in labor costs in recent years, the construction industry has adopted a solution of setting a large working platform and automatic working equipment on the top of the frame to form a building machine to save labor costs. The automatic working equipment is set on the large working platform, and the frame is directly welded to the working platform, so that the frame can move up and down at the same time as the building machine platform. However, this one-piece connection structure in which the frame and the working platform are directly welded is relatively bloated. While the construction is difficult, it is not convenient to disassemble and adjust, and it is not convenient to use overall. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide an external frame of a building construction machine, which can connect the hanging frame and the platform separately, and is convenient for installation and disassembly, and also convenient for adjustment.

[0004] In order to solve the above technical problems, the utility model provides an external frame of a building construction machine, including a platform beam, a hanging frame beam, a hanging frame device arranged below the hanging frame beam, and a connecting seat arranged between the platform beam and the hanging frame beam.

[0005] The connecting seat includes an upper hook mechanism and a lower hook mechanism, the upper hook mechanism is connected to the platform beam, the lower hook mechanism is connected to the rack beam, the upper hook mechanism and the lower hook mechanism are detachably connected, and the platform beam and the rack beam are arranged perpendicular to each other.

[0006] The hanger device comprises a connecting pole, a walkway plate and a hanger, wherein the walkway plate is horizontally connected to the connecting pole, and the hanger is arranged on the top of the connecting pole and connected to the hanger crossbeam.

[0007] As an improvement of the above scheme, the upper hook mechanism is symmetrically arranged on both sides of the platform beam, and the upper hook mechanism includes a first upper abutment portion and an upper connecting portion, the first upper abutment portion is arranged at the top of the upper connecting portion, the first upper abutment portion extends from the upper connecting portion toward the center of the platform beam, and the upper surface of the platform beam can abut against the first upper abutment portion.

[0008] As an improvement of the above scheme, the lower hook mechanism includes a first connecting plate and a lower abutting portion, the bottom of the platform beam abuts against the upper surface of the first connecting plate, the upper hook mechanism is symmetrically arranged at both ends of the upper surface of the first connecting plate, the lower abutting portion extends downward from the lower surface of the first connecting plate, and a first clamp-shaped opening is provided at the bottom of the lower abutting portion, and a first plug-in plate is provided at the upper part of the hanger beam, and the first plug-in plate can be inserted into the first clamp-shaped opening.

[0009] As an improvement of the above solution, the number of the lower abutting portions is two and they are respectively arranged at two ends of the lower surface of the first connecting plate, and the two lower abutting portions are connected to the first plug board.

[0010] As an improvement of the above scheme, the hanging seat includes a second connecting plate and a second upper abutment portion, the second upper abutment portion is symmetrically arranged at both ends of the upper surface of the second connecting plate, the second upper abutment portion extends upward from the upper surface of the second connecting plate, and the top of the second upper abutment portion is provided with a second clamp-shaped opening, and the upper part of the hanging bracket cross beam is provided with a second plug-in plate, and the second plug-in plate can be inserted into the second clamp-shaped opening.

[0011] As an improvement of the above-mentioned scheme, the hanging bracket device also includes a support rod, and the support rod includes a supporting part, a reinforcing part and a fixing part. The top of the supporting part is connected to the bottom of the second connecting part. The reinforcing part is triangular. Two adjacent sides of the reinforcing part are respectively connected between the supporting part and the fixing part. The fixing part is provided with a plurality of through holes, and the connecting vertical rod is provided with a plurality of fixing holes. The positions of the through holes correspond to the positions of the fixing holes.

[0012] As an improvement of the above solution, there are multiple walkway boards, and the sides of the walkway boards are provided with connecting holes, and the positions of the connecting holes correspond to the positions of the fixing holes.

[0013] As an improvement of the above solution, the hanging bracket device also includes a grid and a pivot connector, one side of the pivot connector is connected to the side of the grid, a welding groove is provided in the middle of the pivot connector, and the connecting rod can be embedded in the welding groove.

[0014] The implementation of this utility model has the following beneficial effects:

[0015] The outer frame of the building construction machine of the utility model is provided with a platform beam, a hanging frame beam, a hanging frame device and a connecting seat, wherein the connecting seat includes an upper hook mechanism and a lower hook mechanism, the upper hook mechanism is connected to the platform beam, the lower hook mechanism is connected to the hanging frame beam, the upper hook mechanism and the lower hook mechanism are detachably connected, and the upper hook mechanism and the lower hook mechanism are connected to the platform beam and the hanging frame beam respectively by separating the upper hook mechanism and the lower hook mechanism, so that the hanging frame beam and the platform beam can be separately connected, thereby realizing the separate connection between the hanging frame and the platform, and the upper hook mechanism and the lower hook mechanism are detachably connected, which can be convenient for installation and disassembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural schematic diagram of the outer frame of the building construction machine of the utility model;

[0017] Figure 2 yes Figure 1 A partial enlarged view of middle A;

[0018] Figure 3 It is a schematic diagram of the split structure of the grid and the rotating shaft connector of the utility model. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model will be further described in detail with reference to the accompanying drawings. It is hereby stated that the directional words such as up, down, left, right, front, back, inside, outside, etc. that appear or will appear in the text of the utility model are only based on the accompanying drawings of the utility model, and are not specific limitations of the utility model.

[0020] See also Figure 1 The embodiment of the utility model discloses an external frame of a building construction machine, including a platform beam 1, a pylon beam 2, a pylon device 3 arranged below the pylon beam 2, and a connecting seat 4 arranged between the platform beam 1 and the pylon beam 2. The platform beam 1 is connected to the top working platform, the automatic working equipment is arranged on the working platform, and the pylon beam 2 is connected to the pylon below.

[0021] In order to connect the platform cross beam 1 and the rack cross beam 2 respectively, the connection seat 4 includes an upper hook mechanism 41 and a lower hook mechanism 42, the upper hook mechanism 41 is connected to the platform cross beam 1, the lower hook mechanism 42 is connected to the rack cross beam 2, and the upper hook mechanism 41 and the lower hook mechanism 42 are detachably connected, and the platform cross beam 1 and the rack cross beam 2 are arranged perpendicular to each other. During installation, the upper hook mechanism 41 can be connected to the platform cross beam 1 first, and then the lower hook mechanism 42 can be connected to the rack cross beam 2, and then the upper hook mechanism 41 and the lower hook mechanism 42 can be connected together to realize the separate connection of the platform cross beam 1 and the rack cross beam 2, and the upper hook mechanism 41 and the lower hook mechanism 42 can be detachably connected, which is convenient for installation and disassembly.

[0022] The hanging bracket device 3 includes a connecting pole 31, a walkway board 32 and a hanging seat 33. The walkway board 32 is horizontally connected to the connecting pole 31, and construction workers can walk on the walkway board 32. The walkway board 32 is connected to the hanging bracket beam 2 by means of the connecting pole 31. The hanging seat 33 is arranged on the top of the connecting pole 31 and is connected to the hanging bracket beam 2. The walkway board 32 moves synchronously with the hanging bracket through the hanging seat 33.

[0023] The beneficial effects of the embodiments of the utility model are as follows:

[0024] The external frame of the building machine of the utility model embodiment is provided with a platform beam 1, a hanging frame beam 2, a hanging frame device 3 and a connecting seat 4, wherein the connecting seat 4 includes an upper hook mechanism 41 and a lower hook mechanism 42, the upper hook mechanism 41 is connected to the platform beam 1, and the lower hook mechanism 42 is connected to the hanging frame beam 2, the upper hook mechanism 41 and the lower hook mechanism 42 are detachably connected, and the upper hook mechanism 41 and the lower hook mechanism 42 are connected to the platform beam 1 and the hanging frame beam 2 respectively by separating the upper hook mechanism 41 and the lower hook mechanism 42, so that the hanging frame beam 2 and the platform beam 1 can be separately connected, thereby realizing the separate connection between the hanging frame and the platform, and the upper hook mechanism 41 and the lower hook mechanism 42 are detachably connected, which can facilitate installation and disassembly, and the platform beam 1 and the hanging frame beam 2 are arranged perpendicular to each other, and can adjust their positions to each other for easy adjustment.

[0025] Specifically, see Figure 2There are two upper hook mechanisms 41 and they are symmetrically arranged on both sides of the platform beam 1. The upper hook mechanism 41 includes a first upper abutting portion 411 and an upper connecting portion 412. The first upper abutting portion 411 is arranged at the top of the upper connecting portion 412. The first upper abutting portion 411 extends from the upper connecting portion 412 toward the center of the platform beam 1 to hook the platform beam 1. The upper surface of the platform beam 1 can abut against the first upper abutting portion 411. The first upper abutting portion 411 can limit the up and down movement of the platform beam 1. The upper connecting portions 412 are respectively arranged on both sides of the platform beam 1, so as to limit the left and right movement of the platform beam 1. At the same time, the first upper abutting portion 411 is in contact connection with the platform beam 1, and the movement of the platform beam 1 in its length direction is not restricted.

[0026] The lower hook mechanism 42 includes a first connecting plate 421 and a lower abutting portion 422. The upper hook mechanism 41 is symmetrically arranged at the two ends of the upper surface of the first connecting plate 421. The bottom of the platform beam 1 abuts against the upper surface of the first connecting plate 421. The first connecting plate 421 supports the platform beam 1. The lower abutting portion 422 extends downward from the lower surface of the first connecting plate 421. The bottom of the lower abutting portion 422 is provided with a first clamp-shaped opening 423. The upper part of the hanger beam 2 is provided with a first plug-in board 21. When installed, the first plug-in board 21 can be inserted into the first clamp-shaped opening 423. The first clamp-shaped opening 423 has the function of left and right limit and upper and lower limit for the first plug-in board 21. The number of the lower abutting portions 422 is two and they are respectively arranged at the two ends of the lower surface of the first connecting plate 421 to form two limit positions for the first plug-in board 21, so that the connection is stable. The two lower abutment portions 422 are connected to the first plug-in plate 21, and the lower abutment portions 422 are contact-connected to the first plug-in plate 21. The movement of the bracket beam 2 in the length direction is not restricted. Since the platform beam 1 and the bracket beam 2 are arranged perpendicular to each other, and the movement of the platform beam 1 in the length direction is not restricted, the bracket beam 2 and the platform beam 1 can move relative to each other along their respective length directions, so the position between the bracket beam 2 and the platform beam 1 can be adjusted.

[0027] When connecting the hanger device 3, the hanger seat 33 includes a second connecting plate 331 and a second upper abutting portion 332. The bottom of the hanger beam 2 abuts on the second connecting plate 331, and the second connecting plate 331 supports the hanger beam 2. The second upper abutting portions 332 are symmetrically arranged at the two ends of the upper surface of the second connecting plate 331 to limit the two positions of the second connecting plate 331 to make the connection stable. The second upper abutting portion 332 extends upward from the upper surface of the second connecting plate 331, and a second clamp-shaped opening 333 is provided on the top of the second upper abutting portion 332. A second plug-in plate 22 is provided on the upper part of the hanger beam 2, and the second plug-in plate 22 can be inserted into the second clamp-shaped opening 333. The second clamp-shaped opening 333 can limit the movement of the second plug-in plate 22 in the left and right directions and the up and down directions, while not limiting the movement of the second plug-in plate 22 in its length direction for easy adjustment.

[0028] The hanger device 3 also includes a support rod 34, and the support rod 34 includes a support portion 341, a reinforcement portion 342 and a fixing portion 343. The top of the support portion 341 is connected to the bottom of the second connection portion. The reinforcement portion 342 is triangular, and the two adjacent sides of the reinforcement portion 342 are respectively connected between the support portion 341 and the fixing portion 343, so the reinforcement portion 342 plays a role of strengthening and fixing. The fixing portion 343 is arranged on the outer side of the support rod 34, and a plurality of through holes 344 are arranged on the fixing portion 343. The connecting vertical rod 31 is provided with a plurality of fixing holes 311. The positions of the through holes 344 correspond to the positions of the fixing holes 311. The through holes 344 can be connected to the fixing holes 311 by fasteners such as bolts, thereby connecting the fixing portion 343 and the connecting vertical rod 31. There are multiple walkway boards 32, and a connecting hole 321 is provided on the side of the walkway board 32. The position of the connecting hole 321 corresponds to the position of the fixing hole 311. The connecting hole 321 can be connected to the fixing hole 311 by fasteners such as bolts, thereby connecting the walkway board 32 and the connecting pole 31.

[0029] See also Figure 3 The hanger device 3 further includes a grid frame 35 and a shaft connector 36. The grid frame 35 plays a protective role to protect workers. One side of the shaft connector 36 is connected to the side of the grid frame 35. A welding groove 361 is provided in the middle of the shaft connector 36. During installation, the connecting rod 31 can be embedded in the welding groove 361, and then the connecting rod 31 and the shaft connector 36 can be welded together.

[0030] The above are preferred implementations of the present utility model. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present utility model. These improvements and modifications are also considered to be within the protection scope of the present utility model.

Claims

1. A building construction machine external frame, characterized in that: It includes a platform beam, a pylon beam, a pylon device arranged below the pylon beam, and a connecting seat arranged between the platform beam and the pylon beam; The connecting seat comprises an upper hook mechanism and a lower hook mechanism, the upper hook mechanism is connected to the platform beam, the lower hook mechanism is connected to the rack beam, the upper hook mechanism and the lower hook mechanism are detachably connected, and the platform beam and the rack beam are arranged perpendicular to each other; The hanger device comprises a connecting pole, a walkway plate and a hanger, wherein the walkway plate is horizontally connected to the connecting pole, and the hanger is arranged on the top of the connecting pole and connected to the hanger crossbeam.

2. The outer frame of the building construction machine according to claim 1, characterized in that: The upper hook mechanism is symmetrically arranged on both sides of the platform beam, and the upper hook mechanism includes a first upper abutment portion and an upper connecting portion. The first upper abutment portion is arranged at the top of the upper connecting portion, and the first upper abutment portion extends from the upper connecting portion toward the center of the platform beam. The upper surface of the platform beam can abut against the first upper abutment portion.

3. The outer frame of the building construction machine according to claim 2, characterized in that: The lower hook mechanism includes a first connecting plate and a lower abutting portion. The bottom of the platform beam abuts against the upper surface of the first connecting plate. The upper hook mechanism is symmetrically arranged at both ends of the upper surface of the first connecting plate. The lower abutting portion extends downward from the lower surface of the first connecting plate. A first clamp-shaped opening is provided at the bottom of the lower abutting portion. A first plug-in plate is provided at the upper part of the bracket beam, and the first plug-in plate can be inserted into the first clamp-shaped opening.

4. The outer frame of the building construction machine according to claim 3 is characterized in that: The number of the lower abutting portions is two and they are respectively arranged at two ends of the lower surface of the first connecting plate, and the two lower abutting portions are connected to the first plug board.

5. The outer frame of the building construction machine according to claim 1, characterized in that: The hanging seat includes a second connecting plate and a second upper abutment portion, the second upper abutment portion is symmetrically arranged at both ends of the upper surface of the second connecting plate, the second upper abutment portion extends upward from the upper surface of the second connecting plate, a second clamp-shaped opening is provided on the top of the second upper abutment portion, and a second plug-in plate is provided on the upper part of the hanging bracket cross beam, and the second plug-in plate can be inserted into the second clamp-shaped opening.

6. The outer frame of the building construction machine according to claim 5, characterized in that: The hanging bracket device also includes a support rod, which includes a supporting part, a reinforcing part and a fixing part. The top of the supporting part is connected to the bottom of the second connecting plate. The reinforcing part is triangular. Two adjacent sides of the reinforcing part are respectively connected between the supporting part and the fixing part. The fixing part is provided with a plurality of through holes, and the connecting vertical rod is provided with a plurality of fixing holes. The positions of the through holes correspond to the positions of the fixing holes.

7. The outer frame of the building construction machine according to claim 6, characterized in that: There are multiple walkway boards, and the sides of the walkway boards are provided with connection holes, and the positions of the connection holes correspond to the positions of the fixing holes.

8. The outer frame of the building construction machine according to claim 1, characterized in that: The hanging rack device also includes a grid and a rotating shaft connector, one side of the rotating shaft connector is connected to the side of the grid, a welding groove is provided in the middle of the rotating shaft connector, and the connecting rod can be embedded in the welding groove.

Citation Information

Cited By

  • Hanging frame structure of building machine

    CN223937595U