Wall connecting device for tying building structure and external scaffold

Through the combination of the steel pipe of the wall connecting member with a diameter of 48mm and the 200mm×200mm×4mm steel plate, the problems of difficulty in sealing holes and insufficient rigidity of traditional wall connecting parts are solved, and the stable connection between the building structure and the external scaffolding is achieved, and the construction efficiency is improved. and security.

CN222009563UActive Publication Date: 2024-11-15GUANGZHOU HENGSHENG CONSTR ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420577178.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-25
Publication Date
2024-11-15
Estimated Expiration
2034-03-25

AI Technical Summary

Technical Problem

Traditional wall connecting parts have difficulties in sealing, insufficient rigidity and inability to apply to long-distance scaffolding due to reserved holes in construction, resulting in unstable construction and safety hazards.

Method used

The steel pipe connecting the wall with a diameter of 48mm and a wall thickness of 3.5mm is combined with a steel plate of 200mm×200mm×4mm, and is placed behind the building structure and connected to the vertical pole of the external scaffolding to form a rigid bond and a right angle or rotary buckle is used. The parts achieve stable connection.

Benefits of technology

It improves construction efficiency, shortens repair period, reduces quality and safety hazards and costs, and ensures the stability and safety of the building structure and external scaffolding.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009563U_ABST
    Figure CN222009563U_ABST
Patent Text Reader

Abstract

The utility model discloses a wall connecting device for pulling and connecting a building structure and an external scaffold, one end of the wall connecting device is arranged on the building structure, the other end of the wall connecting device is arranged on a vertical rod of the external scaffold, the wall connecting device comprises a wall connecting component steel pipe, a steel plate and a fixing piece, and the steel plate is arranged on the building structure after passing through the fixing piece. One end of the wall connecting component steel pipe is connected with the steel plate, and the other end of the wall connecting component steel pipe is connected with the external scaffold vertical rod so that the building structure and the external scaffold can be connected. The wall connecting component steel pipe plays a role in bearing force with the building structure, the steel plate plays a role in being connected with the wall connecting component steel pipe, the fixing piece plays a role in fixing the steel plate, the steel plate is arranged on the building structure in a rear mode, and the steel pipe is fixed with the vertical rod of the external scaffold, so that the building structure is connected with the external scaffold. The connecting device can play a role in pulling and unloading.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building structure construction, in particular to a wall connecting device used for connecting a building structure with an external scaffolding. Background Art

[0002] During the construction of a building structure, it is usually necessary to add external scaffolding around the outer wall of the building for construction to play a protective role. In order to ensure the stability of the external scaffolding, wall ties fixed to the floor or wall columns are generally used to tie the wall to stabilize the frame. Traditional wall ties have the following problems:

[0003] 1) When pouring the floor slab, the traditional wall connection parts are pre-buried steel pipes in the slab or wall, and the ends of the steel pipes are exposed about 20cm. When setting up the external scaffolding, the vertical steel pipes of the external scaffolding are connected to the exposed steel pipes with fasteners. The connection method of the traditional wall connection parts has holes formed by the steel pipes reserved in the floor slab or wall. After cutting the steel pipes, the reserved steel pipe positions need to be blocked. If the blocking measures are insufficient or the materials are used improperly, it may cause problems such as water seepage and leakage in the external wall, and even cause damage to the wall, losing or affecting its use function;

[0004] 2) The wall ties of the external scaffolding of the external wall are usually flexible wall ties. The flexible wall ties are generally made of Φ4mm galvanized steel wire or Φ6.5mm steel bar plus steel pipe top support. The flexible wall ties use the steel bars embedded in the board or wall for flexible connection. Although the frame can be connected to the building wall to avoid the formation of difficult-to-repair holes in the board or wall, the tension bars only bear the tension, and the pressure is transmitted by the top support. The rigidity is poor, which can easily cause the external scaffolding to shake, and it is easy to be dismantled during external powder. It can only be used for external scaffolding below 24m. If the frame exceeds 24m, its overall stability cannot be guaranteed;

[0005] 3) In addition, some special buildings have no vertical slabs or reliably tied walls, so embedded parts cannot be left. Therefore, the tie points of traditional wall ties cannot be set, and the corresponding buildings cannot be connected to the external scaffolding, which leads to insufficient stability of the frame and safety hazards. Utility Model Content

[0006] The technical problem to be solved by the utility model is to provide a wall connecting device which can be placed later to tie the building structure and the external scaffolding to prevent overturning, and at the same time can be used to facilitate the later external wall sealing and repair, shorten the external wall repair period and save materials, and can quickly repair and plug leaks, which will greatly improve construction efficiency, reduce quality and safety risks caused by repairing holes, and save labor and material costs.

[0007] In order to solve the above technical problems, the utility model adopts the following technical solutions:

[0008] A wall connecting device for connecting a building structure to an external scaffolding, wherein one end of the wall connecting device is installed on the building structure, and the other end of the wall connecting device is installed on the vertical pole of the external scaffolding. The wall connecting device comprises a wall connecting member steel pipe, a steel plate, and a fixing piece. The steel plate is placed on the building structure through the fixing piece. One end of the wall connecting member steel pipe is connected to the steel plate, and the other end of the wall connecting member steel pipe is connected to the vertical pole of the external scaffolding so as to form a connection between the building structure and the external scaffolding.

[0009] Furthermore, the wall connecting component steel pipe is a steel pipe with a diameter of 48 mm, a wall thickness of the wall connecting component steel pipe is 3.5 mm, and a length of the wall connecting component steel pipe is 450 to 500 mm.

[0010] Furthermore, the building structure includes one of a reinforced concrete beam, a reinforced concrete column and a wall.

[0011] Furthermore, the wall connecting device includes a fastener, which is fastened at the connection between the wall connecting component steel pipe and the external scaffolding upright so as to connect the wall connecting component steel pipe and the external scaffolding.

[0012] Furthermore, the fastener is one of a right-angle fastener and a rotation fastener.

[0013] Furthermore, the plane size of the steel plate is 200mm×200mm×4mm.

[0014] Furthermore, the thickness of the steel plate is 4 mm, and a weld is provided in the middle of the steel plate. The steel plate is welded to the steel pipe of the wall component through the weld in the middle. Two fixing holes cooperating with fixing parts are also drilled on the steel plate, and the two fixing holes are respectively located on both sides of the weld. The fixing parts pass through the fixing holes of the steel plate to fix the steel plate to the building structure.

[0015] Furthermore, the external scaffolding includes a frame body and a guardrail, the guardrail is installed on the outer periphery of the frame body, and a safety net is installed on the outer side of the guardrail.

[0016] Furthermore, the frame includes a plurality of vertical poles, a plurality of horizontal cross bars, and a plurality of steel pipe fasteners. The plurality of vertical poles are spaced apart from each other along the vertical direction, and the plurality of horizontal cross bars are arranged along the horizontal direction and between two adjacent vertical poles. Both ends of each horizontal cross bar are connected between two adjacent vertical poles through two steel pipe fasteners.

[0017] Furthermore, the external scaffolding includes a steel bar grid, and the steel bar grid is tied to the horizontal crossbar of the frame body.

[0018] Compared with the prior art, the utility model has the following beneficial effects:

[0019] One end of the wall connecting device of the utility model is installed on the building structure, and the other end of the wall connecting device is installed on the vertical pole of the external scaffolding. The wall connecting device comprises a wall connecting component steel pipe, a steel plate, and a fixing piece. The steel plate is placed on the building structure through the fixing piece. One end of the wall connecting component steel pipe is connected to the steel plate, and the other end of the wall connecting component steel pipe is connected to the vertical pole of the external scaffolding so as to form a connection between the building structure and the external scaffolding. The steel pipe of the wall connecting member provided by the utility model plays a role of bearing force with the building structure, the steel plate plays a role of connecting with the steel pipe of the wall connecting member, and the fixing part plays a role of fixing the steel plate. By post-placing the steel plate on the building structure and fixing the steel pipe with the external scaffolding upright, a connection is formed between the building structure and the external scaffolding. The connection device of the utility model can play a role of pulling and unloading. Compared with the traditional wall connecting member, the post-type wall connecting device can effectively reduce the fire hazard caused by the heat treatment method of the pulling part when the wall connecting member embedded in the building structure is removed, and avoid the holes left in the construction of the building structure cannot be timely blocked, and the difficulty of repairing and plugging in the later stage can be shortened. The construction period and material saving can be realized, and the wall connecting member part can be quickly blocked, thereby solving various technical problems caused by the difficulty of blocking the holes left in the construction of the building structure at the wall connecting member part. The wall connecting device provided by the utility model is easy to install, has good rigidity, and can be reused. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a cross-sectional schematic diagram of a conventional wall connection member;

[0021] Figure 2 It is a structural schematic diagram of a wall connecting device used for connecting a building structure and an external scaffolding according to the utility model;

[0022] Figure 3 It is a cross-sectional view of the building structure of the utility model and the external scaffolding;

[0023] Figure 4 This is a schematic diagram of the structure of the wall connecting device of the utility model;

[0024] Figure 5 It is a structural schematic diagram of the fixing part of the utility model.

[0025] In the figure: wall connecting device 1, wall connecting member steel pipe 11, steel plate 12, fixing parts 13, fasteners 14, building structure 2, external scaffolding 3, frame body 31, vertical pole 311, horizontal cross bar 312, guardrail 32, safety net 33, steel bar grid 34. DETAILED DESCRIPTION

[0026] The present invention is described in detail below in conjunction with the accompanying drawings, which are part of this specification and illustrate the principle of the present invention through embodiments. Other aspects, features and advantages of the present invention will become clear through the detailed description. In the drawings referred to, the same or similar parts in different figures are represented by the same reference numerals.

[0027] like Figure 1-5 As shown, the first embodiment of the utility model provides a wall connecting device 1 for connecting a building structure 2 and an external scaffolding 3. One end of the wall connecting device 1 is installed on the building structure 2, and the other end of the wall connecting device 1 is installed on the vertical pole 311 of the external scaffolding 3. The wall connecting device 1 includes a wall connecting member steel pipe 11, a steel plate 12, and a fixing member 13. The steel plate 12 is placed on the building structure 2 through the fixing member 13. One end of the wall connecting member steel pipe 11 is connected to the steel plate 12, and the other end of the wall connecting member steel pipe 11 is connected to the vertical pole 311 of the external scaffolding 3 so as to form a connection between the building structure 2 and the external scaffolding 3. The wall-connecting steel pipe 11 provided in the utility model plays a role of bearing force with the building structure 2, the steel plate 12 plays a role of connecting with the wall-connecting steel pipe 11, and the fixing piece 13 plays a role of fixing the steel plate 12. By post-placing the steel plate 12 on the building structure 2 and fixing it with the steel pipe and the vertical pole 311 of the external scaffolding 3, a connection is formed between the building structure 2 and the external scaffolding 3. The connection device of the utility model can shorten the repair period of the building structure 2 and save materials, and can quickly repair the leak-proof and sealed structure, which will greatly improve the construction efficiency, reduce the quality and safety hazards caused by repairing holes, and save labor and material costs. It improves the problem of loose installation caused by changing the connection method of the existing external scaffolding 3 due to the construction process requirements, and solves the quality problems caused by the retained holes in the subsequent construction.

[0028] When the utility model is implemented specifically, the wall connecting member steel pipe 11 is a steel pipe with a diameter of 48 mm, a wall thickness of 3.5 mm, a length of 450 to 500 mm, and the wall connecting member steel pipe 11 is used to form a rigid tie between the external scaffolding 3 and the building structure 2 to play a role in unloading.

[0029] The building structure 2 of the utility model includes one of a reinforced concrete beam, a reinforced concrete column and a wall.

[0030] In specific implementation, the wall connection device 1 includes a fastener 14, which is fastened at the connection between the wall component steel pipe 11 and the vertical pole 311 of the external scaffolding 3 so as to connect the wall component steel pipe 11 with the external scaffolding 3. The fastener 14 is one of a right-angle fastener and a rotating fastener. The right-angle fastener is a right-angle fastener for construction and is made of cast iron. The rotating fastener is a rotating fastener for construction and is made of cast iron. The plane size of the steel plate 12 is 200mm×200mm×4mm. The steel plate 12 is used to fix the wall component steel pipe 11 to form a connection. The thickness of the steel plate 12 is 4 mm. A weld is provided in the middle of the steel plate 12. The steel plate 12 is welded to the wall component steel pipe 11 through the weld in the middle. Two fixing holes matching with the fixing parts 13 are drilled on the steel plate 12. The two fixing holes are respectively located on both sides of the weld. The fixing parts 13 pass through the fixing holes of the steel plate 12 to fix the steel plate 12 on the building structure 2. The fixing parts 13 can be expansion screws.

[0031] In other embodiments, the fixing member 13 of the present invention may be configured as a screw.

[0032] When the utility model is implemented, the external scaffolding 3 includes a frame body 31 and a guardrail 32, the guardrail 32 is installed on the outer periphery of the frame body 31, and a safety net 33 is installed on the outer side of the guardrail 32. Among them, the frame body 31 includes a plurality of vertical poles 311, a plurality of horizontal cross bars 312, and a plurality of steel pipe fasteners, the plurality of vertical poles 311 are spaced apart from each other along the vertical direction, the plurality of horizontal cross bars 312 are arranged along the horizontal direction and between two adjacent vertical poles 311, and the two ends of each horizontal cross bar 312 are connected between two adjacent vertical poles 311 through two steel pipe fasteners.

[0033] In other embodiments, the safety net 33 of the utility model also includes a fixed frame, ropes, and buffers. The fixed frame is provided with a plurality of threading holes, and the ropes pass through the threading holes on the fixed frame to be woven into a grid of the safety net 33. The buffers are installed at the intersections of the grid of the safety net 33 formed by the ropes, and a buffer is provided at each intersection.

[0034] The external scaffolding 3 of the utility model comprises a steel bar grid 34 , and the steel bar grid 34 is tied to the horizontal cross bar 312 of the frame body 31 .

[0035] The above description has been a detailed description of the present invention. The above description is only a preferred embodiment of the present invention and should not limit the scope of implementation of the present application. That is, all equivalent changes and modifications made within the scope of the present application should still fall within the scope of the present invention.

Claims

1. A wall connection device for connecting a building structure with an external scaffolding. Features: One end of the wall connecting device is installed on the building structure, and the other end of the wall connecting device is installed on the vertical pole of the external scaffolding. The wall connecting device includes a wall connecting component steel pipe, a steel plate, and a fixing piece. The steel plate is placed on the building structure through the fixing piece. One end of the wall connecting component steel pipe is connected to the steel plate, and the other end of the wall connecting component steel pipe is connected to the vertical pole of the external scaffolding so as to form a connection between the building structure and the external scaffolding.

2. The wall connecting device for connecting the building structure and the external scaffolding according to claim 1, Features: The wall connecting component steel pipe is a steel pipe with a diameter of 48 mm, a wall thickness of 3.5 mm, and a length of 450 to 500 mm.

3. The wall connecting device for connecting the building structure and the external scaffolding according to claim 2, Features: The building structure includes one of a reinforced concrete beam, a reinforced concrete column and a wall.

4. The wall connecting device for connecting the building structure and the external scaffolding according to claim 1, Features: The wall connecting device comprises a fastener, which is fastened at the connection between the wall connecting component steel pipe and the external scaffolding upright so as to connect the wall connecting component steel pipe with the external scaffolding.

5. The wall connecting device for connecting the building structure and the external scaffolding according to claim 1, Features: The plane size of the steel plate is 200mm×200mm×4mm.

6. The wall connecting device for connecting the building structure and the external scaffolding according to claim 1, Features: The thickness of the steel plate is 4 mm. A weld is provided in the middle of the steel plate. The steel plate is welded to the steel pipe of the wall component through the weld in the middle. Two fixing holes matching with the fixing parts are also drilled on the steel plate. The two fixing holes are respectively located on both sides of the weld. The fixing parts pass through the fixing holes of the steel plate to fix the steel plate to the building structure.

7. The wall connecting device for connecting the building structure and the external scaffolding according to claim 4, Features: The fastener is one of a right-angle fastener and a rotating fastener.

8. The wall connecting device for connecting the building structure and the external scaffolding according to claim 1, Features: The external scaffolding comprises a frame body and a guardrail. The guardrail is installed on the outer periphery of the frame body, and a safety net is installed on the outer side of the guardrail.

9. The wall connecting device for connecting the building structure and the external scaffolding according to claim 8, Features: The frame includes a plurality of vertical poles, a plurality of horizontal cross bars, and a plurality of steel pipe fasteners. The plurality of vertical poles are spaced apart from each other along the vertical direction, and the plurality of horizontal cross bars are arranged along the horizontal direction and between two adjacent vertical poles. The two ends of each horizontal cross bar are connected between two adjacent vertical poles through two steel pipe fasteners.

10. The wall connecting device for connecting the building structure and the external scaffolding according to claim 8, Features: The external scaffolding comprises a steel bar grid, and the steel bar grid is tied to the horizontal crossbar of the frame body.