Multifunctional integrated comprehensive tunneling system
By integrating equipment such as boring machines, anchor drilling rigs and water drilling rims into crawler-type self-traveling equipment, the hydraulic system is used to achieve coordinated operation, which solves the problem that the equipment cannot move forward side by side in tunnel excavation, improves efficiency and reduces risk.
Patent Information
- Application Number
- CN202420565714.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-22
AI Technical Summary
During the tunnel excavation process, multiple equipment cannot move forward side by side in a limited space at the same time, resulting in low efficiency and time-consuming and labor-intensive. In particular, the water drilling operation requires anchor drilling and a bolt drilling machine to avoid, resulting in low operating efficiency.
Integrate the tunneling machine, anchor drilling rig, hydraulic support and water probe rim into a crawler-type self-traveling equipment, and realize the coordinated operation of each device through the hydraulic system, including support devices, anchor drilling rigs, transportation devices, walking systems, and cutting The integration of devices, loading devices and water detection devices enables synchronous operation between equipment.
The coordinated operation of each equipment is achieved simultaneously, which improves the operating efficiency, reduces the number of operators, and reduces work risks.
Smart Images

Figure CN222010216U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel excavation systems, in particular to a multifunctional integrated comprehensive excavation system. Background Art
[0002] During the tunnel excavation process, a tunnel boring machine is required to excavate the tunnel, and an anchor drill is required to anchor the roof and side of the tunnel. A bracket is required to temporarily support the unanchored roof. After a certain length of excavation, a water drill is required to perform water exploration in advance on the unexcavated coal seam. Multiple devices cannot move forward in parallel within a limited space, and need to stop and avoid each other. In particular, if the water drill needs to perform water exploration, the anchor drill and tunnel boring machine need to avoid it so that it can reach the head-on working surface. Such operations are inefficient, time-consuming and labor-intensive. Utility Model Content
[0003] The purpose of the utility model is to provide a multifunctional integrated comprehensive tunneling system, which integrates the original tunneling machine, anchor drilling rig, hydraulic support for temporary support and water exploration drill into a crawler-type self-propelled equipment, which can realize the simultaneous coordinated operation of various equipment and machinery, improve the operation efficiency, and at the same time reduce the number of operators and reduce work risks.
[0004] To achieve the above-mentioned purpose, the utility model provides a multifunctional integrated comprehensive tunneling system, including a support device, an anchor drill, a transport device, a walking system, a cutting device, a loading device and a water detection device;
[0005] The support device is slidably connected to the support device slide rail of the walking system through the column;
[0006] The cutting device is slidably connected to the cutting device slide rail of the walking system through the support seat;
[0007] The loading device is fixed on one side of the traveling system, the transport device is connected to the rear of the loading device, and the transport device is fixed above the chassis of the traveling system;
[0008] The water detection device is mounted on the platform of the walking system through a lifting slide rail;
[0009] The anchor drilling rig is mounted under the support device via a sliding frame.
[0010] Preferably, the walking system includes tracks on both sides, a chassis is carried in the middle of the tracks, and platforms are carried above the tracks on both sides; a cutting device slide rail is provided on the chassis, and the cutting device can slide along the cutting device slide rail through a hydraulic system control mechanism; support device slide rails are provided on the platforms on both sides, and the support device can slide along the support device slide rails through a hydraulic system control mechanism.
[0011] Preferably, a front stabilizing device and a rear stabilizing device are provided below the platforms on both sides and in front and behind the crawlers on both sides.
[0012] Preferably, the supporting device includes a top beam, a supporting beam, a flip beam, a column, and a flip jack. The column is connected to the slide rail of the supporting device and supports the supporting beam. The supporting beam supports the top beam. A flip beam is provided at one end of the top beam. A flip jack is provided at the connection between the flip beam and the top beam. The column is provided with a hydraulic system, and the hydraulic system adjusts the height of the column.
[0013] Preferably, the cutting device comprises a cutting head, a connecting seat, a rotating hinge plate, a swing arm, a supporting seat and a lifting jack; the cutting head comprises a first cutting head, a second cutting head, and a middle cutting head inside the first cutting head and the second cutting head; the first cutting head and the second cutting head are controlled by a hydraulic system to realize extension and retraction on both sides, and when the first cutting head and the second cutting head are extended and retracted outward, the middle cutting head is exposed;
[0014] The connecting seat connects the cutting head and the rotating articulated disk, the rotating articulated disk is connected to the swing arm and the connecting seat, and the rotating articulated disk drives the cutting head to rotate through the control of the hydraulic system;
[0015] The swing arm is connected with the support seat and the rotating hinge plate. The support seat is divided into a left support seat and a right support seat. A lifting jack is installed between the swing arm and the left support seat and the right support seat.
[0016] The left supporting seat and the right supporting seat are respectively installed on the sliding rails of the walking and cutting device.
[0017] Preferably, the loading device includes a shovel plate and a loading pawl, and the shovel plate includes a left shovel plate, a right shovel plate, an auxiliary loading chain conveyor, and a shovel plate slide; the left shovel plate and the right shovel plate realize telescopic movement in the width direction along the shovel plate slide under the action of hydraulic power; the auxiliary loading chain conveyor is located between the left shovel plate and the right shovel plate.
[0018] Preferably, the anchor drilling rig comprises a drilling rig, a suspension device, and a sliding frame, the drilling rig is fixed on the suspension device, the suspension device is installed on the sliding frame, and the sliding frame is installed below the support beam of the supporting device.
[0019] Preferably, the water exploration device comprises a water exploration drill and a lifting slide rail, and the water exploration drill is installed on the lifting slide rail.
[0020] Preferably, the loading device comprises a scraper chain conveyor, which is arranged at the rear of the shovel board and in the middle of the crawlers on both sides of the walking system.
[0021] Therefore, the utility model adopts the above-mentioned multifunctional integrated comprehensive tunneling system, integrating the original tunneling machine, anchor drilling rig, hydraulic support for temporary support and water exploration drilling rig into a crawler-type self-propelled device, which can realize the simultaneous coordinated operation of various equipment and machines, improve work efficiency, and at the same time reduce the number of operators and reduce work risks. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the implementation or the prior art description. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0023] Figure 1 This is a schematic diagram of the overall structure of a multifunctional integrated comprehensive tunneling system of the utility model;
[0024] Figure 2 This is a side view of a multifunctional integrated comprehensive tunneling system support device of the utility model;
[0025] Figure 3 This is a front view of a multifunctional integrated comprehensive tunneling system support device of the utility model;
[0026] Figure 4 This is a side view of a walking system of a multifunctional integrated comprehensive tunneling system of the utility model;
[0027] Figure 5 This is a front view of a multifunctional integrated comprehensive tunneling system walking system of the utility model;
[0028] Figure 6 It is a side view of a multifunctional integrated comprehensive tunneling system cutting device of the utility model;
[0029] Figure 7 This is a top view of a multifunctional integrated comprehensive tunneling system cutting device of the utility model;
[0030] Figure 8 This is a side view of a multifunctional integrated comprehensive tunneling system loading device of the utility model;
[0031] Fig. 9 This is a top view of a multifunctional integrated comprehensive tunneling system loading device of the utility model;
[0032] Fig.10 This is a front view of a multifunctional integrated comprehensive tunneling system loading device of the utility model;
[0033] Fig.11 This is a top view of a multifunctional integrated comprehensive tunneling system anchor drilling rig of the utility model;
[0034] Fig.12 This is a front view of a multifunctional integrated comprehensive tunneling system anchor drilling rig of the utility model;
[0035] Fig.13 This is a side view of a multifunctional integrated water exploration device for a comprehensive tunneling system of the utility model;
[0036] Fig.14 This is a side view of a multifunctional integrated comprehensive tunneling system loading device of the utility model
[0037] Fig.15 It is a front view of a multifunctional integrated comprehensive tunneling system loading device of the utility model.
[0038] Reference numerals
[0039] 1. Support device; 2. Anchor drilling rig; 3. Transport device; 4. Travel system; 5. Cutting device; 6. Loading device; 7. Water detection device;
[0040] 101, top beam; 102, supporting beam; 103, turning beam; 104, column; 105, turning jack;
[0041] 201, drilling rig; 202, suspension device; 203, sliding frame; 301, scraper chain conveyor;
[0042] 401, crawler; 402, chassis; 403, platform; 404, cutting device slide rail; 405, supporting device slide rail; 406, front stabilizing device; 407, rear stabilizing device;
[0043] 501, cutting head; 502, connecting seat; 503, rotating hinge plate; 504, swing arm; 505, lifting jack; 506, left supporting seat; 507, right supporting seat;
[0044] 601, shovel board; 602, loading pawl; 603, auxiliary loading chain conveyor; 604, shovel board slide;
[0045] 701. Water exploration drilling rig; 702. Lifting slide rail. DETAILED DESCRIPTION
[0046] The technical solution of the utility model is further described below through the accompanying drawings and embodiments.
[0047] Unless otherwise defined, the technical terms or scientific terms used in the present invention shall have the usual meanings understood by persons with ordinary skills in the field to which the present invention belongs. The words "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. Words such as "include" or "comprise" and the like mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Words such as "connect" or "connected" and the like are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0048] Embodiment 1
[0049] A multifunctional integrated tunneling system, such as Figure 1 As shown, it includes a supporting device 1, an anchor drilling rig 2, a transport device 3, a walking system 4, a cutting device 5, a loading device 6 and a water detecting device 7.
[0050] Support device 1 Figure 2 , Figure 3 As shown, the support device 1 is mounted on the platform of the walking system 4. The walking system 4 is as shown in FIG. Figure 4 , 5 shown.
[0051] The walking system 4 includes tracks 401 , which are used to carry the entire equipment to move forward or backward. A chassis 402 is mounted between the tracks 401 on the left and right sides, and a platform 403 is mounted above the tracks 401 .
[0052] The chassis 402 is provided with a cutting device slide rail 404, and the cutting device 5 can be moved forward or backward along the cutting device slide rail 404 through the hydraulic system control mechanism. The left and right platforms 403 are provided with a supporting device slide rail 405, and the supporting device 1 can be moved forward or backward along the supporting device slide rail 405 through the hydraulic system control mechanism.
[0053] A front stabilizer 406 and a rear stabilizer 407 are provided below the platform 403 and in front and behind the crawler track 401 to ensure that the equipment is in a stable and reliable state when working.
[0054] The support device 1 includes a top beam 101 , a supporting beam 102 , a flip beam 103 , a column 104 , and a flip jack 105 . The components are connected to each other and play a temporary support role under the hydraulic support of the column 104 .
[0055] The top beam 101 is directly connected to the top, mainly providing temporary support for the top plate. After one or several cycles of excavation, the top beam 11 can be lowered and moved forward along the support device slide rail 405 or along with the walking system 4 to start new support.
[0056] Under the action of the turning jack 105, the turning beam 103 can realize a turning operation at a certain angle to assist in laying the net.
[0057] The joist 102 is an indirect top support, the upper part of which is connected to the top beam 101 , and the lower part has a column 104 . Under the supporting force of the column 104 , the top plate is supported by the top beam 101 .
[0058] The column 104 is mainly the power source for support, and plays a major supporting role through the power provided by the hydraulic system and the pump station.
[0059] The support device 1 can realize rectangular, arched, trapezoidal and other external structures according to different tunnel cross-sections; for tunnels with good roof conditions, the support device 1 can be raised and lowered at the same time; for tunnels with poor roof conditions, the top beam 101 and the support beam 102 of the support device can be made into two groups of combined structures A / B to achieve single-group lifting, that is, group A is lowered and moved forward, and group B is still connected to the top for support, thereby improving the safety factor.
[0060] The structure of the cutting device 5 is as follows: Figure 6 , 7 As shown, it includes a cutting head 501, a connecting seat 502, a rotating hinge plate 503, a swing arm 504, a supporting seat and a lifting jack 505.
[0061] The cutting head 501 includes a first cutting head, a second cutting head, and a middle cutting head inside the first cutting head and the second cutting head. The first cutting head and the second cutting head can be controlled by a hydraulic system to achieve left and right extension, thereby widening the cutting head 501 as a whole; when the first cutting head and the second cutting head are extended and retracted, the middle cutting head is exposed, thereby achieving simultaneous cutting operation with the first cutting head and the second cutting head.
[0062] The connection seat 502 is used to connect the cutting head 501 and the rotating hinged disc 503, and the rotating hinged disc 503 is connected to the swing arm 504 and the connection seat 502. The rotating hinged disc 503 can be controlled by the hydraulic system to realize the rotation function, thereby driving the cutting head 501 to rotate, so that the cutting head 501 can cut in the horizontal direction or at a certain angle to the horizontal, so as to meet the excavation of flat-top or inclined-top tunnels.
[0063] The swing arm 504 is connected with the support seat and the rotating hinge plate 503. The support seat is divided into a left support seat 506 and a right support seat 507. A lifting jack 505 is installed between the swing arm 504 and the left support seat 506 and the right support seat 507. Under the control of the hydraulic system, the lifting jack 505 drives the swing arm 504 to move up and down, thereby realizing the tunnel high and low direction excavation operation. The left support seat 506 and the right support seat 507 are respectively installed on the walking cutting device slide rail 404, and can move forward and backward along the cutting device slide rail 404 to realize the cutting head 501 in the forward direction of excavation operation.
[0064] Loading device 6 Figure 8 , 9 As shown in Figure 10, it includes a shovel board 601 and a loading pawl 602. The shovel board 601 includes: a left shovel board, a right shovel board, an auxiliary loading chain conveyor 603, and a shovel board slideway 604. The left shovel board and the right shovel board can realize the telescopic movement in the width direction along the shovel board slideway 604 under the action of hydraulic power to meet the excavation and relocation requirements of tunnels of different widths. The shovel board slideway 603 provides a predetermined track for the width extension of the left and right shovel boards to ensure the extension along the predetermined track. After the shovel board 601 is extended and widened, the auxiliary loading chain conveyor 603 loads the floating coal in the widened middle part to meet the loading requirements.
[0065] Anchor Drilling Machine 2 Fig.11 , 12 As shown, it includes a drilling rig 201, a suspension device 202, and a sliding frame 203. The drilling rig 201 is fixed on the suspension device 202 and can realize rotation operation to realize anchor drilling operation on the top plate and the side wall; the suspension device 202 is installed on the sliding frame 203 and can slide forward and backward and left and rear along the sliding frame 203 to complete anchoring operations at different positions. The sliding frame 203 is installed under the support beam 102 of the support device 1, so that the anchor drilling rig 2 can move forward simultaneously with the support device 1.
[0066] Water detection device 7 Fig.13 As shown, it includes a water exploration drilling rig 701 and a lifting rail 702. The water exploration drilling rig 701 is installed on the lifting rail 702 and can move along the lifting rail 702 to achieve water exploration operations at different heights.
[0067] The water exploration drilling rig 701 is slidably connected with the lifting rail 702, so that the water exploration drilling rig 701 can realize the up and down angle adjustment on the lifting rail 702, and the water exploration drilling rig 701 can also rotate in situ to perform horizontal or inclined water exploration operations in different directions. The lifting rail 702 is installed on the walking system 4, and can realize the overall movement of the equipment.
[0068] Loading device 3 Fig.14 , 15As shown, the main structure is a scraper chain conveyor 301, which is arranged at the rear of the shovel plate 601 and between the two tracks of the walking system 4, and is used to transfer the fallen coal generated during the excavation process to the conveying equipment and transport the coal out of the mine.
[0069] Therefore, the utility model adopts the above-mentioned multifunctional integrated comprehensive tunneling system, integrating the original tunneling machine, anchor drilling rig, hydraulic support for temporary support and water exploration drilling rig into a crawler-type self-propelled device, which can realize the simultaneous coordinated operation of various equipment and machines, improve work efficiency, and at the same time reduce the number of operators and reduce work risks.
[0070] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in this field should understand that they can still modify or replace the technical solution of the utility model with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the utility model.
Claims
1. A multifunctional integrated tunneling system, Features: It includes support device, anchor drilling machine, transport device, walking system, cutting device, loading device and water exploration device; The support device is slidably connected to the support device slide rail of the walking system through the column; The cutting device is slidably connected to the cutting device slide rail of the walking system through the support seat; The loading device is fixed on one side of the traveling system, the transport device is connected to the rear of the loading device, and the transport device is fixed above the chassis of the traveling system; The water detection device is mounted on the platform of the walking system through a lifting slide rail; The anchor drilling rig is mounted under the support device via a sliding frame.
2. A multifunctional integrated tunneling system according to claim 1, Features: The walking system includes crawlers on both sides, a chassis is carried in the middle of the crawlers on both sides, and platforms are carried above the crawlers on both sides respectively; a cutting device slide rail is provided on the chassis, and the cutting device can slide along the cutting device slide rail through the hydraulic system control mechanism; supporting device slide rails are provided on the platforms on both sides, and the supporting device can slide along the supporting device slide rails through the hydraulic system control mechanism.
3. A multifunctional integrated comprehensive tunneling system according to claim 2, Features: A front stabilizing device and a rear stabilizing device are arranged under the platforms on both sides and in front and behind the crawlers on both sides.
4. A multifunctional integrated comprehensive tunneling system according to claim 3, Features: The supporting device includes a top beam, a supporting beam, a flip beam, a column, and a flip jack. The column is connected to the slide rail of the supporting device and supports the supporting beam. The supporting beam supports the top beam. A flip beam is provided at one end of the top beam. A flip jack is provided at the connection between the flip beam and the top beam. The column is provided with a hydraulic system, and the hydraulic system adjusts the height of the column.
5. A multifunctional integrated comprehensive tunneling system according to claim 4, Features: The cutting device includes a cutting head, a connecting seat, a rotating hinge plate, a swing arm, a supporting seat and a lifting jack; the cutting head includes a first cutting head, a second cutting head, and a middle cutting head inside the first cutting head and the second cutting head; the first cutting head and the second cutting head are controlled by a hydraulic system to realize extension and retraction on both sides, and when the first cutting head and the second cutting head are extended and retracted, the middle cutting head is exposed; The connecting seat connects the cutting head and the rotating articulated disk, the rotating articulated disk is connected to the swing arm and the connecting seat, and the rotating articulated disk drives the cutting head to rotate through the control of the hydraulic system; The swing arm is connected with the support seat and the rotating hinge plate. The support seat is divided into a left support seat and a right support seat. A lifting jack is installed between the swing arm and the left support seat and the right support seat. The left supporting seat and the right supporting seat are respectively installed on the sliding rails of the walking and cutting device.
6. A multifunctional integrated comprehensive tunneling system according to claim 5, Features: The loading device includes a shovel plate and a loading pawl. The shovel plate includes a left shovel plate, a right shovel plate, an auxiliary loading chain conveyor, and a shovel plate slideway. The left shovel plate and the right shovel plate realize widthwise telescopic movement along the shovel plate slideway under the action of hydraulic power. The auxiliary loading chain conveyor is located between the left shovel plate and the right shovel plate.
7. A multifunctional integrated comprehensive tunneling system according to claim 6, Features: The anchor drilling rig comprises a drilling rig, a hanging device and a sliding frame. The drilling rig is fixed on the hanging device, the hanging device is installed on the sliding frame, and the sliding frame is installed under the support beam of the supporting device.
8. A multifunctional integrated comprehensive tunneling system according to claim 7, Features: The water exploration device comprises a water exploration drill and a lifting slide rail. The water exploration drill is installed on the lifting slide rail and is slidably connected with the lifting slide rail.
9. A multifunctional integrated comprehensive tunneling system according to claim 8, Features: The loading device comprises a scraper chain conveyor, which is arranged at the rear of the shovel and between the crawlers on both sides of the walking system.