Waste heat boiler

By setting up a cooling device in the inlet pipe of the waste heat boiler, the circulating cooling system of the water collection tank and the pipe bundle reduces the flue gas temperature, solving the problem of reduced anchor nail strength caused by high-temperature flue gas erosion, and extending the service life of the boiler.

CN222011961UActive Publication Date: 2024-11-15SHANGHAI QIYAO THERMAL ENERGY ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323294261.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-04
Publication Date
2024-11-15
Estimated Expiration
2033-12-04

AI Technical Summary

Technical Problem

When high-temperature flue gas enters the waste heat boiler, it causes the strength of the anchor nails to decrease and the furnace lining damage, affecting the service life of the boiler.

Method used

Design a waste heat boiler, including a cooling device in the intake pipe, including the first and second water collection tanks and multiple tube bundles, cools the flue gas through the cooling and vaporization process of liquid fluid, forms a circulating cooling system, and reduces the flue gas temperature. , protect the anchor nails.

Benefits of technology

It effectively reduces the temperature when the flue gas enters the boiler, prevents the strength of the anchor nails from falling, and extends the service life of the boiler.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222011961U_ABST
    Figure CN222011961U_ABST
Patent Text Reader

Abstract

The utility model discloses a waste heat boiler, and belongs to the technical field of waste heat recovery. The flue is arranged on the boiler body in a penetrating mode, and the flue comprises an air inlet pipe; the cooling device is arranged in the gas inlet pipe and used for cooling flue gas entering the flue, and the cooling device comprises a first water collecting tank which is configured to contain fluid for cooling; when the device is used, high-temperature flue gas entering the gas inlet pipe is cooled through the plurality of pipe bundles, so that the situation that the temperature of the flue gas just entering the flue is too high, and the strength of anchoring nails on a lining is reduced when the flue gas scours the lining in the furnace is avoided; the influence on the strength of the anchoring nail can be reduced to a certain extent, it is guaranteed that the lining cannot fall off and be damaged from the interior of the boiler due to scouring of high-temperature flue gas, and the service life of the waste heat boiler is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of waste heat recovery, and in particular relates to a waste heat boiler. Background Art

[0002] At present, coal-to-olefins have become an important supplement to petroleum olefins. In the process of preparation, high-temperature flue gas will be generated. In the process of treating the high-temperature flue gas, it is generally necessary to pass it into the waste heat boiler for waste heat recovery. After the flue gas enters the waste heat boiler through the air inlet, due to the high temperature of the flue gas, it directly scours the lining of the furnace wall. Long-term high-temperature scouring will cause the strength of the lining anchor nails to decrease, and the lining in the furnace will fall off and be damaged, thereby affecting the service life of the waste heat boiler. Utility Model Content

[0003] Purpose of the utility model: The embodiment of the present application provides a waste heat boiler, which aims to overcome the technical problem that the flue gas temperature entering the waste heat boiler through the air inlet is too high, which will cause the strength of the anchor nails to decrease.

[0004] Technical solution: A waste heat boiler described in an embodiment of the present application includes:

[0005] Boiler body;

[0006] A flue, the flue being arranged through the boiler body and comprising an air inlet pipe;

[0007] A cooling device, which is arranged inside the air inlet pipe to cool the flue gas entering the flue, and includes:

[0008] a first header tank configured to contain a fluid for cooling;

[0009] a second header tank configured to contain the cooled fluid;

[0010] A plurality of tube bundles are arranged at intervals, the tube bundle comprises a first end and a second end arranged opposite to each other, the first end is connected to the first water collecting tank, the second end is connected to the second water collecting tank, and at least a part of the tube bundle is arranged inside the air intake pipe.

[0011] In some embodiments, the cooling device has a first direction X and a second direction Y intersecting each other, the first water collecting tank and the second water collecting tank extend along the first direction X, the plurality of tube bundles extend along the second direction Y, and the plurality of tube bundles are arranged in a group along the first direction X.

[0012] In some embodiments, the cooling device further comprises:

[0013] A seal is configured to be disposed at the first end and / or the second end.

[0014] In some embodiments, the flue further includes an air outlet pipe, which is connected to the air inlet pipe and is used to discharge the smoke.

[0015] In some embodiments, the waste heat boiler further comprises:

[0016] An isolation piece is located on the inner side of the air inlet pipe and is used to isolate the smoke.

[0017] In some embodiments, the first header tank and the second header tank are located outside the boiler body.

[0018] In some embodiments, the temperature reduction device further comprises a steam drum configured to circulate the fluid;

[0019] The first water header tank is communicated with the steam drum, and the second water header tank is communicated with the steam drum.

[0020] In some embodiments, the waste heat boiler further comprises:

[0021] The first temperature component is arranged inside the flue, and the first temperature component is used to cool the flue gas.

[0022] In some embodiments, the first temperature component includes at least:

[0023] a first superheater, wherein the first superheater is disposed inside the flue;

[0024] a second superheater, the second superheater being in communication with the first superheater;

[0025] A third superheater is connected to the second superheater, and the third superheater is connected to the steam drum.

[0026] In some embodiments, the waste heat boiler further comprises:

[0027] The second temperature component is arranged inside the flue, and the second temperature component is used to cool the flue gas.

[0028] In some embodiments, the second temperature component includes at least:

[0029] A first temperature economizer, wherein the first temperature economizer is disposed inside the flue;

[0030] A second temperature economizer is connected to the first temperature economizer, and the second temperature economizer is connected to the steam drum.

[0031] In some embodiments, the waste heat boiler further comprises:

[0032] An ash hopper is arranged inside the boiler body, the ash hopper is communicated with the flue, and the ash hopper is located at the position of the gas outlet pipe.

[0033] Beneficial effect: The waste heat boiler of the embodiment of the present application can cool down the flue gas that has just entered the boiler body. When the high-temperature flue gas enters the interior of the flue from the air inlet pipe, it will first pass through multiple tube bundles. The interiors of the multiple tube bundles are filled with liquid fluid for cooling the flue gas. The liquid fluid vaporizes and needs to absorb the heat in the flue gas. The vaporized fluid enters the second collecting tank, enters the steam drum through the riser, is cooled in the steam drum, becomes liquid fluid again, and then enters the first collecting tank through the downcomer. The liquid fluid inside the first collecting tank replenishes the liquid fluid in the tube bundle to ensure that the liquid fluid inside the tube bundle is sufficient, thereby forming a cycle, so that the flue gas passing through the air inlet pipe can be continuously cooled down, and the flue gas temperature that has just entered the flue is prevented from being too high. When the flue gas flushes the furnace lining, the strength of the anchor nails on the lining is reduced. Since the temperature of the flue gas that has just entered the flue is reduced, the influence on the strength of the anchor nails can be reduced to a certain extent, ensuring that the lining will not fall off and be damaged from the furnace due to the flushing of the high-temperature flue gas, thereby extending the service life of the waste heat boiler. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0035] Figure 1 This is a schematic diagram of the structure of a cooling component according to an embodiment of the present application;

[0036] Figure 2 This is a schematic diagram of the structure of the waste heat boiler in an embodiment of the present application;

[0037] Figure 3 This is a schematic structural diagram of the steam cycle between the drum and the tube bundle according to an embodiment of the present application;

[0038] Figure 4 This is a structural schematic diagram of the second temperature component and the steam drum operation of an embodiment of the present application;

[0039] Figure 5 This is a structural schematic diagram of the operation of the first temperature component and the steam drum of an embodiment of the present application;

[0040] Figure 6This is a schematic diagram of the structure of the steam drum and evaporator water vapor cycle of the embodiment of the present application;

[0041] Figure markings: 10-first water collecting tank; 20-second water collecting tank; 30-tube bundle; 31-first end; 32-second end; 40-seal; 50-insulation; 60-steam drum; 70-flue; 71-inlet pipe; 72-outlet pipe; 73-ash hopper; 80-first temperature component; 81-first superheater; 82-second superheater; 83-third superheater; 90-second temperature component; 91-first temperature economizer; 92-second temperature economizer; 100-water pump; 110-pipe network; 120-evaporator; 130-boiler body; X-first direction; Y-second direction. DETAILED DESCRIPTION

[0042] The technical solutions in the embodiments of the present application will be described clearly and completely below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present application.

[0043] In the description of the present application, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more features. In the description of the present application, "plurality" means two or more, and at least one means one, two or more, unless otherwise clearly and specifically defined.

[0044] It should also be noted that in the drawings of the embodiments of the present application, the arrows marked with X and Y represent the first direction X and the second direction Y respectively. The first direction X and the second direction Y are introduced in the description of the present application in order to more clearly describe the structure and relative position relationship of each component in the waste heat boiler, wherein the first direction X and the second direction Y are two relative directions intersecting with each other. In practical applications, the first direction X can be a horizontal direction, and the second direction Y can be a setting direction of the tube bundle. Preferably, the first direction X and the second direction Y are perpendicular to each other.

[0045] One of the core technologies of coal-to-olefins is methanol-to-olefins (MTO). In recent years, China has successfully developed a number of process technology routes, among which the DMTO technology of Dalian Institute of Chemical Physics is the most widely used. In the process of preparing petroleum olefins from coal-to-olefins, renewable catalysts are particularly important in DMTO devices. In the reactor, methanol is in direct contact with the catalyst from the regenerator, and an exothermic reaction rapidly occurs on the surface of the catalyst. A large amount of coke will be produced on the surface of the catalyst after the high-temperature reaction. After the reaction, the catalyst to be regenerated with coke on the surface is stripped and then sent to the regenerator for burning. The burned regenerated catalyst is then stripped and sent back to the reactor. The high-temperature regeneration flue gas generated during the coking process contains a large amount of heat. At the same time, the regeneration flue gas also contains CO generated by incomplete combustion of coke. Conventional practice is to first pass the high-temperature flue gas into a CO incinerator for incineration, which will produce high-temperature flue gas. When treating the high-temperature flue gas, it is generally necessary to pass it into a waste heat boiler for waste heat recovery. After the flue gas enters the waste heat boiler through the air inlet, due to the high temperature of the flue gas, it directly scours the lining of the furnace wall. Long-term high-temperature scouring will cause the strength of the anchor nails on the lining to decrease, and the lining in the furnace will fall off and be damaged, thereby affecting the service life of the waste heat boiler.

[0046] In view of this, an embodiment of the present application provides a waste heat boiler to overcome at least one of the above-mentioned technical problems.

[0047] Please also read Figures 1 to 3In the embodiment of the present application, the waste heat boiler includes a boiler body 130, a flue 70, and a cooling device. The flue 70 is arranged through the boiler body 130, and the flue 70 includes an air inlet pipe 71, that is, high-temperature flue gas can enter the flue 70 through the air inlet pipe 71; the cooling device is used to cool the high-temperature flue gas entering the flue 70, and the cooling device is arranged inside the air inlet pipe 71 to cool the flue gas entering the flue 70, and the cooling device includes a first water collecting tank 10, a second water collecting tank 20, and a plurality of tube bundles 30. The first water collecting tank 10 is connected to one end of the tube bundle 30, and is configured to contain a liquid fluid for cooling the high-temperature flue gas, that is, the liquid fluid can be contained in the first water collecting tank 10 before being used for flue gas cooling. During the flue gas cooling process, the liquid fluid inside the first water collecting tank 10 will enter the inside of the tube bundle 30, and is used to cool the high-temperature flue gas passing through the gaps between the multiple tube bundles 30; the second water collecting tank 20 is configured to: be used to contain a steam-water mixed fluid after cooling the high-temperature flue gas, that is, the second water collecting tank 20 is connected to the other end of the tube bundle 30, and the liquid cooling fluid in the tube bundle 30 In the process of cooling the high-temperature flue gas, the fluid will absorb the heat in the flue gas, so that the temperature of the liquid cooling fluid itself continues to rise and vaporization occurs. In the process of heat exchange between the liquid cooling fluid and the high-temperature flue gas, the vaporized gas of the liquid cooling fluid can always keep flowing along the center of the tube, and the gas flows upward, thereby entering the second water collecting tank 20. The liquid cooling fluid is attached to the inner wall of the tube, which can protect the tube bundle 30, increase the safety margin of the fluid circulation, and avoid that some parts of the inner wall of the tube are not attached with liquid cooling fluid, causing the high-temperature flue gas to damage the tube. The multiple tube bundles 30 are arranged at intervals, so that after the high-temperature flue gas enters the interior of the waste heat boiler, it can flow through the gaps between the tube bundles 30. At the same time, this interval arrangement method can also more effectively cool the high-temperature flue gas. The tube bundle 30 includes a first end 31 and a second end 32 that are arranged opposite to each other. The first end 31 is connected to the first water collecting tank 10, so that the liquid cooling fluid inside the first water collecting tank 10 can enter the interior of the tube bundle 30 body through the first end 31, and cool the high-temperature flue gas passing through the gaps between the multiple tube bundles 30. The second end 3 2 is connected to the second water collecting tank 20, so that the steam-water mixed fluid after the liquid cooling fluid absorbs heat and vaporizes enters the interior of the second water collecting tank 20 through the second end 32; both the first end 31 and the second end 32 partially penetrate to the outside of the waste heat boiler and are connected to the corresponding water collecting tank, and the penetration of the first end 31 and the second end 32 outside the waste heat boiler is sealed by welding steel plates to prevent leakage of flue gas; at the same time, at least part of the tube bundle 30 is arranged inside the air inlet pipe 71, and parts of both ends thereof penetrate to the outside of the boiler body 130 and are connected to the corresponding water collecting tank.

[0048] In some embodiments, the cooling device has a first direction X and a second direction Y intersecting each other, the first water collecting tank 10 and the second water collecting tank 20 extend along the first direction X, the plurality of tube bundles 30 extend along the second direction Y, and the plurality of tube bundles 30 are arranged in a group along the first direction X, and at least one group, that is, the plurality of tube bundles 30 are arranged perpendicular to the corresponding first water collecting tank 10 and the second water collecting tank 20, and at the same time, the first water collecting tank 10 is connected to the steam drum 60 through a downcomer, and the second water collecting tank 20 is connected to the steam drum 60 through an upcomer. (The steam drum 60 is a cylindrical pressure vessel used for steam-water separation and steam purification in the waste heat boiler, forming a water circulation loop and storing boiler water. The main function is to receive water from the economizer, separate steam and water, supply water to the circulation loop, and transport saturated steam to the superheater. A certain amount of water is stored in the steam drum 60, which has a certain amount of heat and working medium storage. When the working condition changes, the speed of steam pressure change can be slowed down, and a certain buffering effect is played when the feed water and the load are not coordinated for a short time. The steam drum 60 is equipped with an internal Device for steam-water separation); after the liquid cooling fluid inside the first water collecting tank 10 enters the main body of the tube bundle 30 through the first end 31, it absorbs the heat of the high-temperature flue gas and cools the high-temperature flue gas. After the liquid cooling fluid absorbs heat and vaporizes, the vapor enters the second water collecting tank 20 through the second end 32. The vapor inside the second water collecting tank 20 enters the steam drum 60 through the riser. After being processed by the steam drum 60, it forms a liquid cooling fluid again. The liquid cooling fluid is transported to the first water collecting tank 10 through the downcomer. Even if part of the fluid is not cooled into a liquid state, because the downcomer is arranged outside the waste heat boiler, this part of the fluid will absorb heat from the air and become liquid again during the descent process; since the density of the liquid is greater than the density of the vapor, a pressure difference will be formed. During the flow of the liquid cooling fluid, the vapor will be pushed, thereby completing the cooling cycle process, so that the temperature of the flue gas after passing through the cooling device is reduced, and the high-temperature flue gas is prevented from affecting the strength of the anchor nails on the furnace wall lining.

[0049] Preferably, the liquid cooling fluid can be liquid water. The liquid water is contained in the interior of the first water collecting tank 10. After entering the interior of the main body of the tube bundle 30 through the first end 31, it absorbs the heat of the high-temperature flue gas and cools the high-temperature flue gas. After absorbing heat, the liquid water turns into water vapor. The water vapor can always keep flowing along the center of the tube. The water vapor flows upward and enters the interior of the second water collecting tank 20 through the second end 32. The liquid water is attached to the inner wall of the tube, which can protect the tube bundle 30. The water vapor then enters the interior of the steam drum 60 through the riser, and steam-water separation is performed inside the steam drum 60. The liquid water then enters the interior of the first water collecting tank 10 through the downcomer, thereby completing the cooling cycle process.

[0050] In some embodiments, the cooling device also includes a seal 40, which is configured to be arranged at the first end 31 and / or the second end 32. Preferably, the seal 40 can be a refractory fiber belt. The first end 31 and the second end 32 of the tube bundle 30 both penetrate the furnace wall of the waste heat boiler and are connected to the corresponding water collecting tank. The refractory fiber belt is coated on the penetration between the first end 31 and the furnace wall, and / or the refractory fiber belt is coated on the penetration between the second end 32 and the furnace wall. When the high-temperature flue gas passes through the tube bundle 30, the catalyst powder and condensed water entrained in the high-temperature flue gas will fall and accumulate at the bottom of the furnace, and the refractory fiber belt can block the catalyst powder and condensed water to prevent them from accumulating at the bottom of the furnace and corroding the furnace wall and pipeline at the pipe penetration point.

[0051] In some embodiments, the flue 70 also includes an outlet pipe 72, which is connected to the inlet pipe 71. The outlet pipe 72 is used to discharge the flue gas. The cooling device is located in the inlet pipe 71. The temperature of the high-temperature flue gas when entering the inlet pipe 71 is as high as 900-1200°C. This temperature is too high. When the flue gas circulates and flushes inside the flue 70, the strength of the anchor nails on the inner wall of the boiler will be reduced, thereby causing damage to the interior of the boiler. Therefore, the cooling device is set at the inlet pipe 71. The high-temperature flue gas entering the boiler is first cooled by the cooling device, so that the temperature of the flue gas drops below 900°C. When the flue gas at this temperature circulates and flushes inside the flue 70, the strength of the anchor nails on the inner wall of the boiler will not be reduced, thereby playing a certain protective role on the inner wall of the boiler. Finally, the flue gas after a series of treatments is discharged from the outlet pipe 72.

[0052] In some embodiments, the waste heat boiler also includes an isolation member 50, which is located on the inner side of the boiler body 130. Specifically, the isolation member 50 is located between the tube bundle 30 and the boiler body 130. Preferably, the isolation member 50 can be a high-aluminum refractory castable, which is generally arranged at the position of the flue gas inlet pipe 71. Since the temperature at the position of the flue gas just entering the air inlet pipe 71 is still relatively high, the isolation member 50 with the same shape as the air inlet pipe 71 is arranged on the inner wall of the boiler body 130. The isolation member 50 can provide a certain degree of protection for the furnace wall at the position of the air inlet pipe 71. At the same time, the first end 31 and the second end 32 of the tube bundle 30 both penetrate the isolation member 50, and the penetration point of the first end 31 and the second end 32 with the isolation member 50 is also covered with a sealing member 40, which is also used to block catalyst powder and condensed water to prevent them from accumulating at the bottom of the furnace and corroding the isolation member 50 and the pipeline at the pipe penetration point.

[0053] In some embodiments, the first water collecting tank 10 and the second water collecting tank 20 are located on the outside of the boiler body 130. Preferably, the first water collecting tank 10 is arranged on the outside of the boiler body 130 at a bottom position relative to the tube bundle 30, and the second water collecting tank 20 is arranged on the outside of the boiler body 130 at a top position relative to the tube bundle 30. The first water collecting tank 10 and the second water collecting tank 20 are both connected to the boiler body 130 through a steel structure frame, and the steel structure frame supports the first water collecting tank 10 and the second water collecting tank 20.

[0054] Please also read Figures 1 to 5 In some embodiments, the waste heat boiler also includes a first temperature component 80, which is arranged inside the flue 70, and the first temperature component 80 is used to cool the flue gas; the flue 70 includes a front vertical section and a rear vertical section. After the flue gas passes through the air inlet pipe 71 from the horizontal direction, it enters the front vertical section, and the first temperature component 80 is also located inside the front vertical section. During the flow of the flue gas, the flue gas can be cooled.

[0055] In some embodiments, the first temperature component 80 includes at least a first superheater 81, a second superheater 82, and a third superheater 83. The first superheater 81 is arranged inside the flue 70 and is located in the front vertical section. The second superheater 82 is connected to the first superheater 81 through a pipeline and is also located in the front vertical section. The third superheater 83 is connected to the second superheater 82 through a pipeline and is also located in the front vertical section, and is connected to the steam drum 60; specifically, the first superheater 81, the second superheater 82, and the third superheater 83 are all arranged inside the front vertical section of the flue 70, and the flue gas passes through each superheater tube bundle for heat exchange in the flue 70. The pipeline connecting the second superheater 82 and the first superheater 81 and the pipeline connecting the third superheater 83 and the second superheater 82 are all arranged outside the flue, and the pipeline is used for the circulation of water vapor.

[0056] In some embodiments, the waste heat boiler also includes a second temperature component 90, which is arranged inside the flue 70 and located in the rear vertical section. The second temperature component 90 is used to cool the flue gas entering the rear vertical section. When the flue gas enters the interior of the rear vertical section from the front vertical section, the second temperature component 90 can further cool the flue gas.

[0057] In some embodiments, the second temperature component 90 includes at least a first temperature economizer 91 and a second temperature economizer 92. The first temperature economizer 91 is arranged inside the flue 70 and is located inside the rear vertical section. The second temperature economizer 92 is connected to the first temperature economizer 91 through a pipeline, is also located inside the rear vertical section, and is connected to the steam drum 60; specifically, the first temperature economizer 91 and the second temperature economizer 92 are both arranged inside the rear vertical section of the flue 70, and the flue gas passes through the tube bundles of each temperature economizer in the flue 70 for heat exchange. The pipelines connecting the first temperature economizer 91 and the second temperature economizer 92 are also arranged outside the flue, and the pipelines are used for the circulation of liquid water.

[0058] Please also read Figures 1 to 5 Specifically, when the high-temperature flue gas passes through the rear vertical section, liquid water is introduced into the first temperature economizer 91 through the water pump 100 outside the boiler. When the flue gas circulates inside the flue 70, it will pass through the first temperature economizer 91, thereby exchanging heat with the liquid water inside the first temperature economizer 91, the temperature of the liquid water increases, and the temperature of the flue gas decreases; under the action of the water pump 100, the liquid water inside the first temperature economizer 91 flows to the second temperature economizer 92 through the pipeline, and when the flue gas passes through the second temperature economizer 92, it exchanges heat with the liquid water inside it, the temperature of the liquid water increases, and the temperature of the flue gas decreases; under the action of the water pump 100, the liquid water in the second temperature economizer 92 enters the steam drum 60; in this process, the flow direction of the liquid water is the same as that of the flue gas. The flow direction of the steam in the drum 60 is opposite to that of the flue gas; in the front vertical section, the steam in the drum 60 enters the interior of the third superheater 83 through the pipeline, and performs heat exchange with the flue gas passing through the third superheater 83, the temperature of the steam increases, and the temperature of the flue gas decreases; the steam in the third superheater 83 enters the interior of the second superheater 82 through the pipeline, and performs heat exchange with the flue gas passing through the second superheater 82, the temperature of the steam increases, and the temperature of the flue gas decreases; the steam in the second superheater 82 enters the interior of the first superheater 81 through the pipeline, and performs heat exchange with the flue gas passing through the first superheater 81, the temperature of the steam increases, and the temperature of the flue gas decreases, and finally the heated superheated water steam flows into the external pipe network 110; in this process, the flow direction of the water steam is opposite to that of the flue gas;

[0059] See also Figure 6 In the rear vertical section of the flue 70, an evaporator 120 is also provided. The evaporator 120 is also connected to the steam drum 60 through a pipe. The liquid water inside the steam drum 60 enters the evaporator 120 through one of the pipes. The evaporator 120 cools the high-temperature flue gas flowing inside the flue 70. The liquid water inside the evaporator 120 absorbs the heat in the flue gas and turns into water vapor. The water vapor enters the steam drum 60 through another pipe, thereby forming a steam-water cycle.

[0060] Specifically, the first superheater 81 may be a high-temperature superheater, the second superheater 82 may be a medium-temperature superheater, the third superheater 83 may be a low-temperature superheater, the second temperature economizer 92 may be a high-temperature economizer, and the first temperature economizer 91 may be a low-temperature economizer.

[0061] Among them, the flue gas temperature at the inlet of the first superheater 81 is 800-950°C, the flue gas temperature at the inlet of the second superheater 82 is 650-750°C, the flue gas temperature at the inlet of the third superheater 83 is 550-600°C, the flue gas temperature at the inlet of the second temperature economizer 92 is 450-500°C, and the flue gas temperature at the inlet of the first temperature economizer 91 is 250-300°C.

[0062] In some embodiments, the waste heat boiler further includes an ash hopper 73, which is disposed inside the boiler body 130, is connected to the flue 70, and is located at the position of the exhaust pipe 72. During the process of the flue gas circulating inside the flue 70, some dust and impurities will be entrained in the flue gas. The flue gas enters from the air inlet pipe 71, circulates inside the flue 70, and is discharged from the exhaust pipe 72. Since the direction of the flue gas changes by 90 degrees at the exhaust pipe 72 of the flue 70, some dust and impurities will be discharged under the action of gravity and inertia. The dust and impurities will fall into the ash hopper 73 and be collected by the ash hopper 73 for unified treatment. Some of the dust and impurities in the flue gas will adhere to the tube bundle 30, the first temperature component 80 and the second temperature component 90. By arranging soot blowers on the tube bundle 30, the first superheater 81, the second superheater 82, the third superheater 83, the first temperature economizer 91 and the second temperature economizer 92, the dust and impurities attached to these structures can be blown off, so that the dust and impurities fall into the ash hopper 73 with the flow of the flue gas.

[0063] In some embodiments, a plurality of metal expansion joints are spaced apart on the boiler body 130 , and the thermal expansion of the boiler body 130 is absorbed by the metal expansion joints.

[0064] In some embodiments, the boiler body 130 is arranged in a π shape, which increases the overall height difference of the boiler, improves the water circulation power, increases the reliability of boiler operation, and also saves a lot of floor space.

[0065] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0066] The waste heat boiler provided in the embodiment of the present application is introduced in detail above, and the principle and implementation mode of the present application are explained by applying specific examples. The description of the above embodiments is only used to help understand the technical solution and core idea of ​​the present application; ordinary technicians in this field should understand that: they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some of the technical features therein with equivalents; and these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the present application.

Claims

1. A waste heat boiler, It is characterized in that include: Boiler body (130); A flue (70), the flue (70) being arranged through the boiler body (130), the flue (70) comprising an air inlet pipe (71); A cooling device, the cooling device being arranged inside the air inlet pipe (71) to cool the flue gas entering the flue (70), the cooling device comprising: A first header tank (10), the first header tank (10) being configured to contain a fluid for cooling; a second water collecting tank (20), the second water collecting tank (20) being configured to contain the cooled fluid; A plurality of tube bundles (30) are arranged at intervals, the tube bundle (30) comprising a first end (31) and a second end (32) arranged opposite to each other, the first end (31) being connected to the first water collecting tank (10), the second end (32) being connected to the second water collecting tank (20), and at least a portion of the tube bundle (30) being arranged inside the air inlet pipe (71).

2. The waste heat boiler according to claim 1, It is characterized in that The cooling device has a first direction (X) and a second direction (Y) intersecting each other, the first water collecting tank (10) and the second water collecting tank (20) extend along the first direction (X), the plurality of tube bundles (30) extend along the second direction (Y), and the plurality of tube bundles (30) are arranged in a group along the first direction (X).

3. The waste heat boiler according to claim 1, It is characterized in that The cooling device also includes: A sealing member (40) is configured to be disposed at the first end (31) and / or the second end (32).

4. The waste heat boiler according to claim 1, It is characterized in that The flue (70) further comprises an air outlet pipe (72), wherein the air outlet pipe (72) is in communication with the air inlet pipe (71), and the air outlet pipe (72) is used to discharge the smoke.

5. The waste heat boiler according to claim 1, It is characterized in that The waste heat boiler also includes: An isolation member (50), the isolation member (50) is located on the inner side of the air inlet pipe (71) and is used to isolate the smoke.

6. The waste heat boiler according to claim 1, It is characterized in that The first water collecting tank (10) and the second water collecting tank (20) are located outside the boiler body (130).

7. The waste heat boiler according to claim 1, It is characterized in that The temperature reduction device further comprises a steam drum (60), wherein the steam drum (60) is configured to circulate the fluid; The first water collecting tank (10) is in communication with the steam drum (60), and the second water collecting tank (20) is in communication with the steam drum (60).

8. The waste heat boiler according to claim 7, It is characterized in that The waste heat boiler also includes: A first temperature component (80), the first temperature component (80) is arranged inside the flue (70), and the first temperature component (80) is used to cool the flue gas.

9. The waste heat boiler according to claim 8, It is characterized in that The first temperature component (80) comprises at least: a first superheater (81), the first superheater (81) being arranged inside the flue (70); a second superheater (82), the second superheater (82) being in communication with the first superheater (81); A third superheater (83), the third superheater (83) is connected to the second superheater (82), and the third superheater (83) is connected to the steam drum (60).

10. The waste heat boiler according to claim 7, It is characterized in that The waste heat boiler also includes: A second temperature component (90), the second temperature component (90) is arranged inside the flue (70), and the second temperature component (90) is used to cool the flue gas.

11. The waste heat boiler according to claim 10, It is characterized in that The second temperature component (90) comprises at least: a first temperature economizer (91), the first temperature economizer (91) being arranged inside the flue (70); A second temperature economizer (92), the second temperature economizer (92) is connected to the first temperature economizer (91), and the second temperature economizer (92) is connected to the steam drum (60).

12. The waste heat boiler according to claim 4, It is characterized in that The waste heat boiler also includes: An ash hopper (73) is disposed inside the boiler body (130), the ash hopper (73) is communicated with the flue (70), and the ash hopper (73) is located at the position of the gas outlet pipe (72).